Beruflich Dokumente
Kultur Dokumente
ASU
SHEET 1 OF 20
SITE MANAGEMENT PLAN
TSK PHASE II
CONSTRUCTION SITE MANAGEMENT PLAN
OF
ASU
CONFIDENTIALITY
The information contained in this document is confidential to Tata Steel. Accordingly, copyright of
this document is retained with Tata Steel and no copying in any format of this document is permitted
without the written permission from the approver of this document.
Page 2 of 20
Manage Schedule
12 May 2014
INDEX
To complete the civil work of ASU in 9 months. The objective of preparing construction
methodology to ensure that there should be the strategy to start the construction
activities smoothly on site. This project is being driven based on following construction
philosophies (6 KPI’s):
Discipline
Quality
Safety
Benchmark level of productivity.
Cost
Time
Page 4 of 20
Manage Schedule
12 May 2014
2. Scope of Work
S. No. Description
1 Air Filter
2 MAC
3 BAC
4 Common Silencer
5 IA Comp Foundation
6 MP / LP Cold Box, Exchange cold, Argon cold box foundation,
7 Pump Casting Foundation
8 Turbine Casing Foundation
9 Air Purification Vessel Foundation
10 Water Chiller Tower ( E 60 )
11 Gox Barrier
12 Reactivation Heater Foundation
13 Water Chiller Pump Foundation
14 Liquid Disposal System Foundation
15 Booster after Cooler
16 LAR Storage Tank
17 LOX Storage Tank
18 LIN Storage Tank
19 LIN Storage Tank Pump
20 LOX Atmospheric Vaporizer Foundation
21 LIN Atmospheric Vaporizer Foundation
22 LAR Atmospheric Vaporizer Foundation
23 Compressor Shelter Steel Column Foundation
24 Pipe Racks Steel Column Foundation
25 Pipe Cable Tray & Platform Steel supporting Foundation
26 Cooling Tower
27 ECR, Office and Sub – Station Building
Page 5 of 20
Manage Schedule
12 May 2014
28 Cable Trenches
29 Paving, Road & Drain works
Site Infrastructure:
Fabrication yard
Vehicle Parking Zone
Office vehicles
Equipment’s i.e. excavator, boom placer
Assembly Point – at site
Workmen Rest shed & Toilet Block
Labour Camp at Plot 2
Training Centre at Plot 2
Canteen – At Labour Camp
Batching Plant centralized at Plot 1
QC Lab – Centralized at Plot 1
Page 7 of 20
Manage Schedule
12 May 2014
Power Requirement:
Organization Chart
Attached separately
Communication Method:
All communication will be addressed to Mr J. L. N. Murty – Project Director ( TPL)
related to project and method will be:
Culture Building:
Project will be executed with” ZERO” harm goal and TATA culture 6
KPI’s will be developed among all the site team, workmen at site by
the thru following activities:
Skill Assessment
Safety Training
Tool Box Talk
First AID Training at site
Routine health check-up
Gate pass for ASU Area
Displaying signage at work place
Utilizing Modular formwork
Page 9 of 20
Manage Schedule
12 May 2014
Mechanized work thru Auto rebar cut & bend plant, cranes,
boom placer etc.
DON’Ts :
As per TSK guidelines workmen must be following instructions during
working at site:
Never enter work place without PPE.
Workers must not enter in swinging area of the equipment
without prior & prior communication to operator.
No workmen should enter in the equipment’s working area.
Workers must not touch with bare hand any equipment’s or
reinforcement steel.
No workers should enter into guarded area without safety
harness or suitable PPE’s.
Without wearing gloves no workers should be allowed for
concreting process to avoid chemical attack.
Never take rest under / around the equipment’s even if it is
stopped or in breakdown condition
Mobile phone should not be used during operation at work
site
Page 10 of 20
Manage Schedule
12 May 2014
5. Amenities
Transportation of TPL staff : By Bus / LMV
Transportation of Workmen & Operator : By Bus
Pick & drop of workmen Lunch at site : By Bus
Pick & drop of lunch box : ASU site
Equipment’s planned for the execution of ASU structures are mentioned below
with two shift operators:
Needle- 10 nos
Excavators - 2 nos
Hywa- 8 nos
Hydra- 1 no
Trailer- 1 nos
Note: Excavator, Hywa, Transit mixer, rock breaker, Boom Placer etc
available at site and can be deployed as per requirement.
7. Administrative Issues
Grievance redressal – Level I – Section In-charge – 3 days for resolution
Grievance redressal – Level II – RCM – 3 days for resolution
Grievance redressal – Level III – Head Admin – 3 days for resolution
Grievance redressal – Level IV – Project Director – 3 days for resolution
8. Statutory Compliance
Approach road,
Water & Power point
Page 13 of 20
Manage Schedule
12 May 2014
Construction Preparedness:
For excavation and disposal of earth Construction methodology document
No. TSL/TSK/Civil/Standard/01 shall be followed. refer to doc
TSL/TSK/civil/methodology/03 in annexure This standard cover following
aspects.
production.
Availability Remarks/
Scope of Intermediate
Sl. Description Source before Proposed
Supply storage at
activity Control
within 07
Contractor's days of
Raw structural External
7 TSK machining and issuing
steel Purchase
fabrication yard construction
drawings
Foundation Bolts Fabrication Contractor's site
8 TPL 24 Hrs.
and embedment Yard store
MS inserts and Fabrication Contractor's site
9 TSK 24 Hrs.
Embedment Yard store
Shuttering raw External Contractor's
10 TPL 07 days
Materials Purchase shuttering yard
Contractor's
Contractor's site
11 Shuttering boards TPL shuttering 03 day
yard
yard
Scaffolding External Contractor's site
12 TPL 05 Days
Material Purchase yard
Non Shrink
External Contractor's site
13 Grouting TPL 04 days
Purchase yard
Material.
Concrete External
14 TPL Batching plant 07 days
Admixtures Purchase
5.2 Machinery
5.3 Manpower
Workforce
S. No. Discipline Work Description Skill Level
1 Rod fitter Rebar cutting, Bending, Cage making Skilled
2 Helper Muck cleaning, Helpers for fitters and riggers Skilled
3 Mason Concrete pouring Skilled
Cage & tremie pipe lifting, placing, loading and Skilled
4 Rigger
unloading
5 Mechanic For Equipment repair Skilled
6 Supervisor For supervision of all jobs being executed at site. Skilled
2 Piling TSL/TSK/Civil/Methodology/02
3 Excavation TSL/TSK/Civil/Methodology/03
4 Shuttering TSL/TSK/Civil/Methodology/04
5 Reinforcement TSL/TSK/Civil/Methodology/05
6 Inserts and embedment TSL/TSK/Civil/Methodology/06
7 Concrete TSL/TSK/Civil/Methodology/07
8 Curing TSL/TSK/Civil/Methodology/08
9 Backfilling TSL/TSK/Civil/Methodology/09
10 Brickwork TSL/TSK/Civil/Methodology/10
11 Plaster TSL/TSK/Civil/Methodology/11
12 Painting TSL/TSK/Civil/Methodology/12
13 Grouting TSL/TSK/Civil/Methodology/13
14 Floor finish TSL/TSK/Civil/Methodology/14
15 False ceiling TSL/TSK/Civil/Methodology/15
16 Sanitary & Plumbing TSL/TSK/Civil/Methodology/16
17 Waterproofing TSL/TSK/Civil/Methodology/17
18 Scaffolding TSL/TSK/Civil/Methodology/18
19 Road work TSL/TSK/Civil/Methodology/19
S. No. Code of Practice Doc. No.
1 Earthwork TSL/TSK/Civil/Standard/01
2 Concrete TSL/TSK/Civil/Standard/02
3 Road Construction TSL/TSK/Civil/Standard/03
4 Storage TSL/TSK/Civil/Standard/04
5 Plastering TSL/TSK/Civil/Standard/05
6 Painting TSL/TSK/Civil/Standard/06
7 Brickwork TSL/TSK/Civil/Standard/07
8 Survey TSL/TSK/Civil/Standard/08
9 Formwork TSL/TSK/Civil/Standard/09
10 Reinforcement TSL/TSK/Civil/Standard/10
1
TSL/TSK/QSR/Civil/0
2 Concrete site work 2
TSL/TSK/QSR/Civil/0
3 Design mix of concrete 3
TSL/TSK/QSR/Civil/0
4 Concrete batching plants 4
TSL/TSK/QSR/Civil/0
5 Reinforcement work 5
TSL/TSK/QSR/Civil/0
6 formwork 6
TSL/TSK/QSR/Civil/0
7 Masonary work 7
TSL/TSK/QSR/Civil/0
8 Plastering work 8
TSL/TSK/QSR/Civil/0
9 Painting work 9
TSL/TSK/QSR/Civil/1
10 False ceiling work 0
TSL/TSK/QSR/Civil/1
11 Ceramic & vitrified tile work 1
TSL/TSK/QSR/Civil/1
12 Road work 2
TSL/TSK/QSR/Civil/1
13 Railway formation 3
TSL/TSK/QSR/Civil/1
14 Piling work 4
………..END………….