Pilot Pile Work

Work Status
Pile
Bridge Boring Casting End
SI. No. Pile Id Chainage Length Time
Name Start Date Date
(m)
1 BR-03 Near A1 0+308.000 38.00 8/15/2018 6:20 AM 8/16/2018
2 BR-04 Near P6 0+576.630 43.00 9/18/2018 8:45 PM 9/19/2018
3 BR-15 Near A1 8+138.470 38.00 11/3/2018 7:50 AM 11/4/2018
4 BR-13 Near A1 6+503.640 32.00 2/11/2019 8:30 AM 2/12/2019

5 BR-18 Near A1 11+505.660 25.00 3/2/2019 9:00 AM 3/3/2019

6 BR-37 Near A2 24+788.500 25.00 3/9/2019 12:55 PM 3/9/2019


7 BR-22 Near A2 14+800 35.00 4/19/2019 7:15 PM 4/23/2019
8 BR-27 Near A1 18+335.680 30.00 5/5/2019 12:15 PM 5/7/2019
9 BR-30 Near A2 20+463.77 30.00 5/28/2019 4:45 PM 6/1/2019
10

296.00
Total Piling Length (m) Concrete Volume (Cum)
Pilot Pile Work

Work Status
Concrete Reinforcem Design Applied
Time Volume ent QTY PIT Date Date of Loading Load Load
(cum) (Ton) (Ton) (Ton)
1:25 AM 45.00 10.757 9/21/2018 10/1/2018 270 675
8:30 PM 60.00 10.435 10/19/2018 11/3/2018 400 1000
1:00 AM 45.00 10.413 11/22/2018 12/6/2018 300 750
2:15 AM 38.00 6.522 2/20/2019 3/11/2019 320 800

7:26 AM 34.50 5.493 3/12/2019 4/7/2019 250 625

11:45 PM 31.00 5.493 3/18/2019 4/20/2019 250 625


5:00 PM 40.00 6.976 4/30/2019 6/23/2019
5:20 PM 36.00 6.295 5/23/2019 7/27/2019
6:50 PM 36.50 6.295 6/30/2019

366.000 68.679
Concrete Volume (Cum) Reinforcement QTY (Ton)
Remarks

Test load failed

Test load failed

Test load failed


Bridge No: 03 (Sangu River)

Working Pile Status


Concrete Reinforcem
Pile Boring Start Casting
SI. No. Name Pile Id Chainage Time Time Volume ent QTY PIT Date Remarks
Length Date End Date
(cum) (Ton)
1 Wp1 38.50 18-Dec-18 6:30 AM 19/Dec/18 12:10 AM 47.00 11.660
2 Wp2 38.50 13-Dec-18 6:15 AM 14/Dec/18 12:54 PM 46.00 11.660
3 Wp3 38.50 9-Dec-18 6:30 AM 10/Dec/18 2:30 AM 48.00 11.660
A1 0+316.850 12/Feb/19
4 Wp4 34.399 12-Dec-18 6:00 AM 13/Dec/18 3:40 AM 38.00 10.660
5 Wp5 38.50 10-Dec-18 9:00 AM 11/Dec/18 3:00 AM 45.00 11.660
6 Wp6 38.50 15-Dec-18 6:00 AM 16/Dec/18 1:00 AM 51.00 11.660
7 Wpa 43.00 20-Mar-19 6:00 PM 21/Mar/19 2:30 PM 50.00 12.932
8 Wpb 43.00 18-Mar-19 6:00 PM 19/Mar/19 6:15 PM 50.00 12.932
9 Wpc 43.00 22-Mar-19 9:15 PM 23/Mar/19 4:00 PM 50.00 12.932
P1 0+357.375 30/Apr/19
10 Wpd 43.00 13-Mar-19 12:30 PM 14/Mar/19 11:20 AM 53.00 12.932
11 Wpe 43.00 25-Mar-19 8:00 PM 26/Mar/19 1:35 PM 50.00 12.932
12 Wpf 43.00 3-Mar-19 12:45 PM 4/Mar/19 12:40 PM 53.00 12.932
13 Wp-1 43.00 28-Jan-19 6:20 AM 29/Jan/19 4:20 AM 48.00 10.855
14 Wp-2 43.00 31-Jan-19 6:40 AM 1/Feb/19 1:00 AM 53.50 10.043
15 Wp-3 43.00 25-Jan-19 6:20 AM 26/Jan/19 7:00 AM 52.00 10.855
P2 0+399.650 12/Mar/19
16 Wp-4 43.00 29-Jan-19 6:40 AM 31/Jan/19 1:40 AM 50.00 10.043
17 Wp-5 43.00 26-Jan-19 6:30 AM 27/Jan/19 5:30 PM 48.00 10.855
18 Wp-6 43.00 1-Feb-19 6:40 AM 1/Feb/19 11:24 PM 50.00 10.043
19 Wp1 43.00 6-Feb-19 4:00 PM 7/Mar/19 6:30 AM 51.00 10.043
20 Wp2 43.00 16-Feb-19 6:40 AM 17/Feb/19 1:30 AM 49.00 10.043
21 Wp3 43.00 9-Feb-19 6:25 AM 10/Feb/19 1:30 AM 50.00 10.043
P3 0+441.925 12/Mar/19
22 Wp4 43.00 13-Feb-19 10:10 PM 14/Feb/19 3:40 PM 50.00 10.043
23 Wp5 43.00 8-Feb-19 6:20 AM 9/Feb/19 1:50 AM 50.00 10.043
24 Wp6 43.00 12-Feb-19 6:20 AM 13/Feb/19 12:30 AM 52.00 10.043
25 Wp1 43.00 10-Feb-19 6:20 AM 10/Feb/19 11:50 PM 50.50 10.043
26 Wp2 43.00 17-Feb-19 12:00 AM 17/Feb/19 4:10 PM 50.00 10.043
27 Wp3 43.00 11-Feb-19 12:48 AM 11/Feb/19 8:40 PM 50.00 10.043
P4 0+484.200 12/Mar/19
28 Wp4 43.00 15-Feb-19 7:30 AM 16/Feb/19 1:10 PM 49.00 10.043
29 Wp5 43.00 13-Feb-19 12:50 AM 13/Feb/19 7:40 PM 51.00 10.043
30 Wp6 43.00 18-Feb-19 6:30 AM 19/Feb/19 2:40 AM 52.00 10.043
31 Wp1 43.00 7-Feb-19 11:50 AM 8/Feb/19 3:00 AM 51.00 10.043
32 Wp2 43.00 16-Jan-19 7:00 AM 17/Jan/19 5:53 AM 50.00 10.876
33 Wp3 43.00 24-Jan-19 1:00 AM 24/Jan/19 11:00 PM 52.00 10.855
P5 0+526.475 12/Feb/19
34 Wp4 43.00 15-Jan-19 12:10 PM 16/Jan/19 12:40 PM 55.00 10.876
35 Wp5 43.00 5-Feb-19 10:00 AM 6/Feb/19 4:00 AM 53.00 10.043
36 Wp6 43.00 22-Jan-19 6:20 AM 23/Jan/19 5:05 AM 51.00 10.855
Bridge No: 03 (Sangu River)

Working Pile Status


Concrete Reinforcem
Pile Boring Start Casting
SI. No. Name Pile Id Chainage Time Time Volume ent QTY PIT Date Remarks
Length Date End Date
(cum) (Ton)
37 Wp1 43.00 23-Jan-19 6:30 AM 24/Jan/19 3:05 AM 51.00 10.855
38 Wp2 43.00 17-Jan-19 12:30 PM 18/Jan/19 8:45 AM 52.00 10.876
39 Wp3 43.00 13-Jan-19 6:20 AM 14/Jan/19 2:55 AM 47.00 10.876
P6 0+568.750 12/Feb/19
40 Wp4 43.00 27-Jan-19 6:20 AM 28/Jan/19 2:30 AM 50.00 10.855
41 Wp5 43.00 14-Jan-19 6:25 AM 15/Jan/19 3:00 AM 58.00 10.876
42 Wp6 43.00 21-Jan-19 6:20 AM 22/Jan/19 3:00 AM 51.00 10.855
43 Wp1 38.50 26-Dec-19 6:15 AM 26/Dec/19 9:05 PM 46.00 11.660
44 Wp2 38.50 8-Jan-19 6:20 AM 8/Jan/19 9:55 PM 46.00 11.660 20/Feb/19
45 Wp3 38.50 6-Jan-19 6:40 AM 6/Jan/19 10:00 PM 47.00 11.660
A2 0+610.500
46 Wp4 38.50 9-Jan-19 6:20 AM 9/Jan/19 9:35 AM 46.00 11.660 20/Jan/19 Load Test
47 Wp5 38.50 2-Jan-19 6:15 AM 2/Jan/19 11:00 PM 51.00 11.660
20/Feb/19
48 Wp6 38.50 5-Jan-19 6:20 AM 5/Jan/19 11:45 AM 51.50 11.660
Total Piling Length= 2005.90 m 2395.500 528.463 554.886
Concrete Volume (Cum) Reinforcement QTY (Ton)

Pile Cap to Pier Cap work Status

Abutment/ Abutment/ Abutment/ Abutment/ Abutment/ Abutment/ Abutment/ Abutment/Pie


Pile Cap Pile Cap Pile Cap
Pier 1st lift Pier 2st lift Pier 3rd lift Pier Pier Pier Cap Pier Cap r Cap
SI. No. Name Chainage PCC Date PCC QTY Concreting Concreting Reinforcem Dirt wall
Casting Date Casting Date Casting Concreting Reinforceme Concreting Concreting Reinforcemen
Date Volume ent QTY
& QTY & QTY Date & QTY Total Volume nt QTY Date Volume t QTY

1 A1 0+316.850 9-Feb-19 5.00 20-Feb-19 98 15.015 10-03-19(15) 31-07-2019(15) - 30 - 8/6/2019 28 13.144


2 P1 0+357.375 28-Apr-19 14.00 24-May-19 85 20.315 26-05-19(15.5) 28-05-19 (15) 15.0+15.0+13.5 74 13.646

3 P2 0+399.650 18-Mar-19 8.00 28-Mar-19 87 20.315 3-4-19(15.5) 05-04-19(14.0) 15.0+7.0 51.5 10..880 5/18/2019 112 12.631

4 P3 0+441.925 10-Mar-19 8.00 23-Mar-19 87 20.315 29-3-19(8) 02-04-19(8.0) 11-04-19(8.5) 24.5 10.285 5/16/2019 43 6.014
5 P4 0+484.200 7-Mar-19 8.00 17-Mar-19 85 20.315 22-3-19(15.5) 29-3-19(15) 01-04-19(12) 42.5 9.517

6 P5 0+526.475 13-Feb-19 4.50 8-Mar-19 89 20.315 12-03-19(8) 17-03-19(8) 26-03-19(5) 21 9.263 4/20/2019 42 6.014

7 P6 0+568.750 7-Feb-19 5.00 27-Feb-19 85 20.315 06-03-19(15) 11-03-19(14) - 29 8.153 10/7/2019 110 12.631

8 A2 0+610.500 19-Feb-19 5.00 5-Mar-19 99 10.301 19-03-19(15) 21-04-19(15) - 30 - 9/17/2019 28

Total QTY= 57.500 715.000 147.206 302.500 50.864 363.000 50.434

Total QTY M15 = 57.500 Cum

Total QTY M35 = 1380.500 Cum

Total QTY Re-bar = 248.504 Ton


Bridge No: 07 (Canal)

Working Pile Status


Concrete Reinforcem
Pile Boring Start Casting
SI. No. Name Pile Id Chainage Time Time Volume ent QTY
Length Date End Date
(cum) (Ton)
1 Wp1
2 Wp2
3 Wp3
A1 3+424.475
4 Wp4
5 Wp5
6 Wp6
7 Wp1
8 Wp2
9 Wp3
P1 3+450.000
10 Wp4
11 Wp5
12 Wp6
43 Wp1
44 Wp2
45 Wp3
A2 3+475.525
46 Wp4
47 Wp5
48 Wp6
Bridge No: 07 (Canal)

Working Pile Status

PIT Date Remarks


Bridge No: 13

Working Pile Status


Concrete Reinforcem
Pile Boring Start Casting
SI. No. Name Pile Id Chainage Time Time Volume ent QTY
Length Date End Date
(cum) (Ton)
1 Wp1 40.00 11-Apr-19 11:30 AM 12/Apr/19 8:31 PM 48.00 7.749
2 Wp2 40.00 19-Apr-19 11:25 AM 20/Apr/19 2:42 AM 46.50 7.749
3 Wp3 40.00 17-Apr-19 8:00 AM 17/Apr/19 10:30 PM 47.00 7.749
A1 6+512
4 Wp4 40.00 20-Apr-19 9:30 PM 21/Apr/19 10:17 AM 47.00 7.749
5 Wp5 40.00 13-Apr-19 11:40 AM 14/Apr/19 12:05 AM 45.00 7.749
6 Wp6 40.00 18-Apr-19 11:30 AM 19/Apr/19 12:34 AM 46.00 7.749
43 Wp1 34.50 22-Apr-19 9:30 PM 23/Apr/19 4:19 PM 53.00 6.984
44 Wp2 34.50 29-Apr-19 12:50 PM 30/Apr/19 6:41 AM 46.00 6.984
45 Wp3 34.50 27-Apr-19 1:00 AM 27/Apr/19 2:40 AM 42.00 6.984
A2 6+552
46 Wp4 34.50 30-Apr-19 4:45 PM 1/May/19 5:09 AM 45.00 6.984
47 Wp5 34.50 24-Apr-19 10:35 AM 25/Apr/19 12:16 PM 48.00 6.984
48 Wp6 34.50 28-Apr-19 10:50 AM 28/Apr/19 11:09 PM 41.00 6.984
Bridge No: 13

Working Pile Status

PIT Date Remarks

30/Apr/19

23/May/19

load Test
Bridge No: 17 (Canal)

Working Pile Status


Concrete Reinforcem
Pile Boring Start Casting
SI. No. Name Pile Id Chainage Time Time Volume ent QTY
Length Date End Date
(cum) (Ton)
1 Wp1 32.00 26-Mar-19 11:50 AM 27/Mar/19 12:02 PM 36.00 6.522
2 Wp2 32.00 30-Mar-19 2:20 AM 31/Mar/19 5:25 AM 36.50 6.522
3 Wp3 32.00 14-Mar-19 8:00 PM 16/Mar/19 12:02 AM 38.50 6.522
A1 9+804.475
4 Wp4 32.00 28-Mar-19 7:20 PM 29/Mar/19 2:18 PM 36.00 6.522
5 Wp5 32.00 22-Mar-19 12:50 PM 23/Mar/19 1:35 PM 35.00 6.522
6 Wp6 32.00 1-Apr-19 1:00 AM 2/Apr/19 4:30 AM 36.00 6.522
7 Wp1 27.50 2-May-19 1:00 AM 3/May/19 12:30 AM 39.00 5.177
8 Wp2 27.50 9-May-19 10:30 PM 9/May/19 7:30 PM 32.00 5.177
9 Wp3 27.50 11-Apr-19 5:20 PM 13/Apr/19 12:58 AM 31.00 5.177
P1 9+830.000
10 Wp4 27.50 5-May-19 2:00 PM 6/May/19 12:30 PM 32.00 5.177
11 Wp5 27.50 17-Apr-19 10:30 PM 18/Apr/19 9:25 PM 31.00 5.177
12 Wp6 27.50 11-May-19 8:00 PM 12/May/19 5:40 PM 32.00 5.177
43 Wp1 32.00 15-Apr-19 6:40 PM 16/Apr/19 7:20 PM 36.00 6.563
44 Wp2 32.00 7-May-19 1:00 AM 8/May/19 1:15 PM 36.00 6.563
45 Wp3 32.00 22-Apr-19 3:10 PM 24/Apr/19 6:35 AM 36.00 6.563
A2 9+855.525
46 Wp4 32.00 3-May-19 2:00 AM 4/May/19 1:30 AM 36.00 6.563
47 Wp5 32.00 22-Apr-19 3:10 PM 24/Apr/19 6:35 AM 36.00 6.563
48 Wp6 32.00 10-May-19 3:00 AM 11/May/19 1:30 PM 36.00 6.536
Bridge No: 17 (Canal)

Working Pile Status

PIT Date Remarks

30/Apr/19

23/May/19 For Load Test

19/May/19
Bridge No: 36 (Culvert)
Bridge No: 36 (Culvert)
Bridge No: 37 (Canal)

Working Pile Status


Concrete Reinforcem
Pile Boring Start Casting
SI. No. Name Pile Id Chainage Time Time Volume ent QTY PIT Date Remarks
Length Date End Date
(cum) (Ton)
1 Wp1 25.00 29-May-19 4:45 AM 29/May/19 4:20 PM 37.50 5.823
2 Wp2 25.00 18-Jun-19 5:00 AM 18/Jun/19 4:00 PM 30.00 5.722
3 Wp3 25.00 30-May-19 5:05 AM 30/May/19 2:55 PM 30.50 5.722
A1 24+798.155 17/Sep/19
4 Wp4 25.00 20-Jun-19 7:00 AM 20/Jun/19 5:35 PM 30.00 5.722
5 Wp5 25.00 16-Jul-19 10:50 AM 17/Jul/19 1:45 AM 30.00 5.722
6 Wp6 25.00 16-Jun-19 9:45 AM 16/Jun/19 10:35 AM 31.00 5.722
7 Wp1
8 Wp2
9 Wp3
P1 24+818.680
10 Wp4
11 Wp5
12 Wp6
43 Wp1 25.00 19-Jul-19 3:30 PM 20/Jul/19 12:20 AM 30.00 5.722
44 Wp2 25.00 21-Jul-19 5:00 AM 21/Jul/19 1:50 AM 28.00 5.823
45 Wp3 25.00 5-Jul-19 5:00 AM 5/Jul/19 2:45 PM 30.00 5.722
A2 24+839.205 17/Sep/19
46 Wp4 25.00 19-Jul-19 4:55 AM 19/Jul/19 2:20 PM 30.00 5.823
47 Wp5 25.00 17-Jul-19 11:30 AM 17/Jul/19 12:00 PM 30.00 5.722
48 Wp6 25.00 22-Jul-19 7:00 AM 22/Jul/19 7:10 PM 30.00 5.823
Total Piling Length= 300.00 m 367.000 69.068
Concrete Volume (Cum) Reinforcement QTY (Ton)
Bridge No: 03 (Sangu River)

Working Pile Status


Concrete Reinforcem
Pile Boring Start Casting
SI. No. Name Pile Id Chainage Time Time Volume ent QTY PIT Date Remarks
Length Date End Date
(cum) (Ton)
1 Wp1 26.70 11-Apr-19 5:00 PM 12/Apr/19 4:45 AM 33.50 6.050
2 Wp2 26.70 2-Apr-19 12:40 PM 2/Apr/19 11:00 PM 32.50 6.050
3 Wp3 26.70 12-Apr-19 3:30 PM 13/Apr/19 4:45 AM 32.50 6.050
A1 0+316.850 30/Apr/19
4 Wp4 26.70 3-Apr-19 11:30 PM 4/Apr/19 2:25 PM 32.50 6.050
5 Wp5 26.70 13-Apr-19 4:00 PM 14/Apr/19 4:30 AM 32.50 6.050
6 Wp6 26.70 1-Apr-19 6:00 AM 1/Apr/19 9:20 PM 32.50 6.050 Load Test
7 Wp1 26.70 16-Apr-19 9:00 AM 16/Apr/19 11:30 PM 32.50 5.300
8 Wp2 26.70 27-Apr-19 5:10 AM 27/Apr/19 5:50 PM 32.50 5.300
9 Wp3 26.70 17-Apr-19 3:45 PM 18/Apr/19 1:40 AM 32.50 5.300
P1 0+357.375
10 Wp4 26.70 29-Apr-19 3:30 AM 29/Apr/19 3:20 PM 32.50 5.300
11 Wp5 26.70 21-Apr-19 3:50 AM 21/Apr/19 7:00 PM 33.50 5.300
12 Wp6 26.70 3-May-19 4:30 AM 3/May/19 7:45 PM 32.50 5.300
13 Wp-1 26.70 28-Apr-19 4:20 AM 28/Apr/19 7:30 PM 32.50 5.300
14 Wp-2 26.70 2-May-19 11:35 AM 2/May/19 2:30 PM 32.50 5.300
15 Wp-3 26.70 20-Apr-19 3:00 AM 20/Apr/19 3:30 PM 32.50 5.300
P2 0+399.650
16 Wp-4 26.70 30-Apr-19 3:30 AM 30/Apr/19 3:50 PM 32.50 5.300
17 Wp-5 26.70 23-Apr-19 8:00 AM 23/Apr/19 8:40 PM 32.50 5.300
18 Wp-6 26.70 18-Apr-19 12:30 PM 19/Apr/19 4:15 AM 32.50 5.300
43 Wp1 26.70 5-May-19 5:00 AM 5/May/19 5:00 PM 32.50 6.050
44 Wp2 26.70 12-May-19 9:00 AM 16/May/19 6:25 PM 32.50 6.050
45 Wp3 26.70 9-May-19 10:00 AM 10/May/19 3:20 PM 32.50 6.050
A2 0+610.500 23/May/19
46 Wp4 26.70 17-May-19 7:00 AM 17/May/19 11:15 PM 32.50 6.050
47 Wp5 26.70 6-May-19 11:30 AM 7/May/19 7:45 PM 32.50 6.050
48 Wp6 26.70 11-May-19 7:00 AM 11/May/19 7:40 PM 32.50 6.050
Total Piling Length= 640.80 m 782.000 136.200 143.010
Concrete Volume (Cum) Reinforcement QTY (Ton)

Pile Cap to Pier Cap work Status

Abutment/ Abutment/ Abutment/ Abutment/ Abutment/


Pile Cap Pile Cap Pile Cap Pier Cap Pier Cap Pier Cap
Pier 1st lift Pier 2st lift Pier 3rd lift Pier Pier
SI. No. Name Chainage PCC Date PCC QTY Concreting Concreting Reinforcem Concreting Concreting Reinforcement Dirt wall
Casting Date Casting Date Casting Concreting Reinforceme
Date Volume ent QTY Date Volume QTY
& QTY & QTY Date & QTY Total Volume nt QTY

05-10-2019
1 A1 0+316.850 28-Jun-19 5.50 30-Jul-19 89 13.211 22.50
(22.50)

2 P1 0+357.375

3 P2 0+399.650

8 A2 0+610.500

Total QTY= 5.500 89.000 13.211 22.500 0.000 0.000 0.000

Total QTY M15 = 5.500 Cum

Total QTY M35 = 111.500 Cum

Total QTY Re-bar = 13.211 Ton


Bridge No: 36 (Culvert)
Bridge No: 36 (Culvert)