Sie sind auf Seite 1von 8

SITE TESTING & COMMISSIONING PROCEDURE

LINE IMPEDANCE PARAMETERS MEASUREMENT

Page 1/8
The Site Test Procedures as per the Site Inspection & Test Plan to Measure Line
Impedance Parameters designated (STP- LINE IMPEDANCE PARAMETERS
MEASUREMENT) is as follows:

Responsible:
Commissioning Manager is responsible for the content of this instruction and
the Commissioning Engineer for its implementation.

Purpose:

To measure line impedance for power cable or overhead line conductor.

Test equipment:
 CPC 100
 CPCU1
 CPGB1

Reference documentation:
Refer to Approved Drawing & Cable or conductor Manufacturer DATA sheet.

Characteristics, method of inspections


1. Precaution.
2. Line Impedance Measurement
 Phase to Ground Measurement.
 Phase to Phase Measurement.
 3 Phase to Ground Measurement.
3. OHL Line Test
 Insulation Test
 Phasing Test
 Phase Sequence Test
 Conductivity Test
 Susceptance Test

1. Precaution:

 Measurement only applies to single circuit line where no mutual coupling to parallel
lines.

 Ground the power lines on both ends, using an installed ground switch or manmade
grounding cables.

 Make sure that the connection to ground at the far end of the line is not removed
during the complete test procedure.

Page 2/8
 Open the near grounding switch to measure circular current which is flowing
through the conductor.

 Check user safety as per manufacturer recommendation,

2. Line Impedance Measurement:

 Phase to Ground Measurement.

 Make the connection as per below diagram

Page 3/8
 Use the preprogrammed templates from CPC 100.

Templates  Cables & Transmission Line  Line Impedance

 Choose template matching with selected current range for measurements.

 In this template, can find Schema test card and sequencer card.
o Schema test card – These cards are comments of test card. Which show how
to connect the clamps to the CP GB1.
o Sequencer test card – These cards are used for measurements.

 Check user safety as per manufacturer recommendation.

 Resistive part of the impedance can be corrected by means of temperature for


Aluminum or Copper.

 Once everything is ready, press I/O button on the CPC 100’s front panel to start
measurement after you have connected the clamps which is comes from line to the
CP GB1.

 The Measurement stopped automatically after the sequence card has terminated.

 Ground the line immediately after the measurement.

 Change the connections of CP GB1 according to Phase to Phase measurement


and 3 Phase Measurement and continue the test.

 Phase to Phase Measurement.

 Make the connection as per below diagram

Page 4/8
 3 Phase Measurement

3. OHL Line Test

Insulation Resistance Test:


1. Connect the circuit as shown.
2. Keep the line open at both the ends.
3. Using Megger, check the insulation resistance between phases
and between each phases and ground.

Page 5/8
Phasing Test:
1. Isolate the three phases from both ends and connect the circuit as shown.
2. Ground one phase from Remote end and connect the local end with
insulation tester (Megger) between the phase to ground.
3. Repeat for remaining phases.

Phase Sequence Test:

1. Connect the circuit as shown.


2. Connect 3ph 220V or 380V AC Voltage supply (Generator) to the line.
3. Connect phase sequence meter to both end of the line.
4. Read the phase sequence at sending and receiving ends.

Page 6/8
Conductivity Test:
1. Connect the circuit as shown.
2. Short the three phases together from other end.
3. Using Insulation tester (Megger), Apply 1kV DC between Phase R and Y
and observe the reading in the megger.
4. Repeat the same for Phase Y and B.

Susecptance Test:
(1) Connect the circuit as shown
(2) Isolate the three phases from both ends.
(3) Connect 1-phase 220 V AC supply voltage source (Generator) between
phase R and Y.
(4) Connect Ammeter and Voltmeter as shown in the figure.
(5) Apply voltage and observe the reading of the Ammeter and Voltmeter.
(6) Calculate phase to phase susceptance as per the formula below
(7) Repeat for both phase Y-B and B-R. Fill the result in the test record.

X= 2V/I IN OHM.
B= 1/ (-JX) IN Moh or siemens.

Page 7/8
Page 8/8