Beruflich Dokumente
Kultur Dokumente
Construction Management
Site Management
1. Roles of Consultant and Contractor at Site (Covered
CE403 – Construction under Life of a Project – Construction Management
Introduction)
Management
2. Documents, Records and Meetings
(Slides Set No. 3)
3. Progress Monitoring and Control
4. Site Supervision
By
5. Cash flow management
Dr. Pujitha B. G. Dissanayake 6. Introductionto Material and Construction
Department of Civil Engineering Equipment Management.
Faculty of Engineering
University of Peradeniya
1 CE403 - Construction Management 2
1
6/26/2019
2
6/26/2019
3
6/26/2019
4
6/26/2019
5
6/26/2019
6
6/26/2019
7
6/26/2019
Construction Management
Cash Flow Analysis
Exercise 2: (Cont.)
(i) Using the above data prepare a cash-flow statement
for the above contract. State any assumptions made.
(ii) If the contractor needs to borrow money from the
bank at an interest rate of 3% per month, what would
be the minimum total finance charge incurred by the
contractor to maintain positive cash flow.