CHECKLIST 402  Equipment Name: 

Foundation-Transformer/Inverter/HT Panel  Equipment Weight: 


 
Date: PROJECT Details -   Equipment Rating: 
 
Time :  Reference Doc: 
Sr.No  ITEM CRITERION APPROVAL (✓/ ☓)  REMARKS 

1  Excavation   Check whether Excavation is done as per approved drawing.     
2  Levelling  Ensure the levelling of excavated soil before PCC.     
3  PCC  Ensure PCC Grade and PCC concrete level as per drawing.     
4  Excavated soil  Excavated soil should be at distance of 1 meter from excavated pit.     
Check the Reinforcement (Steel bar) dimensions, size, quantity and position as per drw.     
Reinforcement  Check Reinforcement arrangement, overlapping, winding, Spacing, straighten etc. 

check before RCC  Cover block (50X50 mm) must be provided between PCC level and Reinforcement. 
Ensure Reinforcement should not be touch to PCC level. 
Shuttering box size should be as per design or as per foundation size.     
Shuttering box fixing/connection should be done by nut‐bolts. Connections of boxes by 
Form 
6  Armour/steel wire not allowed.  
Boxes/Shuttering  
Light coat of oil should be done inside of form boxes to avoid honeycomb or repairing. 
No any reinforcement should be touch to shuttering box. (Maintain a required gap) 
Whether the RCC Grade is as per design.      
7  RCC Mixture 
Ensure mixing of Cement, Aggregate/Gravel, Sand with designated proportion. 
Check concrete workability or water‐cement ratio by slump test.     
8  Slump Test  Is the light coat of oil and tamping rod is used during test? 
Slump value should be as per material grade. 
Ensure whether the cube mould (150x150 mm) is filled with Freshly made concrete for testing     
purpose.  
Ensure tamping rod while cube sample filling concrete and light coat of oil to inner surface of 
9  Cube sample 
cube mould before filling. 
After making cube sample, mention the date, foundation name and signature of site 
representative from client side. 
Concrete     
10  During RCC work, make sure the vibrator is using for concrete compaction. 
Compaction 
Check fixing of channel, plate, Jacking pad if any     
Channel Fixing in 
11  Check centre to centre distance of jacking pad in case of transformer. 
RCC 
Check channel, plate dimensions and fixing position.  
12  Dimensions   Check all the dimensions given in drawing before and after concreting.     
Check visual defect after finishing concrete work Like:     
13  Concrete defect  Cracks, Honeycomb, Repairs, foundation shape, reinforcement exposed etc. If any then do the 
additional repairing by using cement plaster. 
14  Curing  Is curing done after concreting. Gunny bags to be used for curing.     
INSPECTED BY‐  APPROVED BY‐  Checklist No‐ SSE‐QC‐ELE‐402 Rev0 
Sheet No‐ 1 OF 2 

INT/SIGN  INT/SIGN  Page size‐ A4 


 