Sr. No. Contents Page

01 Scope of work 3

02 References 3

03 Definitions 3

04 Responsibilities/ Supervision 3

05 Description of Work 4

06 Plant Requirement 5

07 Manpower Requirement 6

Temporary works to be designed and


08 6
Installed

09 Health and Safety Requirements 6

10 Environment requirements 6

11 Security arrangements 6

Special Contractual
12 7
Arrangements
13 Records to be produced 7

14 Attachments 7
Project: WORLD TRADE CENTER DOHA QATAR
Method Statement for the
Title of the
Installation of Alarm Check
Document
Valve
Reference No. Revision No Date Page No.
QC-MS-FF-006 00 08 OCT 2010 3 of 7

1.0. Scope & Objective


This method statement covers the detailed procedure for installation of Breeching Inlets & Cabinet.
This procedure defines the method used to ensure that the installation of Breeching Inlet is carried as
per the contract specification requirements and the approved drawings of Qatar World Trade Center

2.0. References
Contract Documents:
• Specification : 15310, 2.08 (A)

• NFPA 13, 2007 Edition Standard for the Installation of Sprinkler System

• The Local Fire Authority, Qatar Civil Defence Directorate

• Shop Drawings: Marked “ISSUED FOR CONSTRUCTION”

3.0. Definitions
Fire Protection System. Any fire alarm device or system or fire extinguishing device or
system, or their combination, that is designed and installed for detecting, controlling, or
extinguishing a fire or otherwise alerting occupants, or the fire department, or both, that a fire
has occurred
Automatic Sprinkler. A fire suppression or control device that operates automatically
when its heat-activated element is heated to its thermal rating or above, allowing water to
discharge over a specified area.

4.0. Responsibilities/ Supervision


4.1 Project Manager shall have the overall responsibility of the project for execution, quality
and safety. He shall maintain the planning progress and co-ordination of works with
main contractor.
4.2 Project/ Site Mechanical Engineer(s) shall be responsible for monitoring of
the day-to-day activities on site, for materials, drawings, allocation of resources to
work areas on site and testing & commissioning. He shall report to the Project
Manager.
4.3 Supervisor/ Charge Hand shall be directly responsible for the day-to-day job
at site, for coordinating of work with Technicians or any other staff assigned his area.
4.4 QA/QC Department will be overseeing the quality requirements and quality control
measures for the project in coordination with Project/Site Engineer(s).
4.5 Safety Officer shall be responsible for the health & safety aspects on site as per the
ARABTEC/EFECO safety Manual.
Project: WORLD TRADE CENTER DOHA QATAR
Method Statement for the
Title of the
Installation of Alarm Check
Document
Valve
Reference No. Revision No Date Page No.
QC-MS-FF-006 00 08 OCT 2010 4 of 7

5.0 Description of works


5.1 Pre Installation Check
5.1.1 Ensure that all safety requirements are in place in accordance with project
safety plan
5.1.2 Ensure that the latest revision of the approved working drawing is being
used.
5.1.3 On receipt of material on site, QA/QC engineer/ Site Engineer shall inspect
the material internally and inspection shall be offered to the engineer for approval in
MIR ( Material inspection request form)
5.1.4 Ensure that the all materials used have passed receiving inspection in
accordance with QA procedures and are not damaged or defective. Any non-
conforming materials must be labeled by store keeper and returned to quarantine
area in accordance with procedure.
5.1.5 Ensure that all the pipe fitters and helpers are aware of the correct materials
handling and installation procedure to ensure that best quality of workmanship.
Training shall be provided by site engineers / Supervisor as and when required.
5.1.6 Ensure space & access for installation is available and at correct location as
per the approved drawing and site conditions.
5.1.7 Check the tools required to install the Alarm Check valve.
5.1.8 Supervisor shall ensure that correct tools and Alarm check valve with trim kit
are available for installation and to achieve compliance with contract requirement.

5.2 INSTALLATION OF ALARM CHECK VALVE


5.2.1 The Alarm Check Valve must be installed in an area not subject to freezing
temperatures or physical damage. The Alarm Check Valve may be installed in the vertical
position with direction of flow up, or in the horizontal position with the access cover up.
5.2.2 Verify that the appropriate trim chart and technical data for the Alarm Check Valve
and associated equipment are available.

5.2.3 Remove all plastic thread protectors from the openings of the Alarm Check Valve.

5.2.4 Apply a small amount of pipe-joint compound or tape to the external threads of all
pipe connections required. Take care not to allow any compound, tape, or other foreign matter
inside any nipples or openings of the valve or trim components. Trim the Alarm Check Valve in
accordance trim chart provided along with the alarm check valve

5.2.5 Install the Alarm Check Valve and trim according to current Trim Charts for the valve
used. Trim charts are provided with trim package and available with the project engineer or
Technical Engineer. After installing the alarm check valve, please unpack the water motor
gong and follow the instructions below to install as per the requirement.
Project: WORLD TRADE CENTER DOHA QATAR
Method Statement for the
Title of the
Installation of Alarm Check
Document
Valve
Reference No. Revision No Date Page No.
QC-MS-FF-006 00 08 OCT 2010 5 of 7

5.2.6 For installation of water motor gong mark the through-wall locations for the
centerlines of the Sleeve and Drain Outlet. The Drain Outlet must be located at least 10 inches
(250mm)

5.2.7 Make 1-1/2 inch (38 mm) diameter holes straight through the wall at both locations.

5.2.8 Cut the non-threaded end of the Sleeve to a length equal to that of the wall thickness
plus 0 to 1/8 inch (0 to 3 mm). Thread the cut end to ¾ inch NPT per ANSI B1.20.1.

5.2.9 Install the alarm line piping up to and including the union half. Use thread sealant
sparingly on male threads only.

5.2.10 Prior to initiating installation of the Water Motor Alarm, mount the Drain Trim (less the
Wall Plate and 45° Elbow), as well as the balance of alarm line piping (including other union
half) to the Water Motor.

5.2.11 Tighten the NPT threaded end of the Sleeve into the Body hand tight plus 1/8 turn.

5.2.12 Slip the Support Washer over the Sleeve and place the assembly in position against
the wall.

5.2.13 Tighten the 3/4 inch Union. Install the Wall Plate and tighten the 45° Elbow.

5.2.14 Apply pressure against the outside edge of the Water Motor Body and verify
that the Body and Support

5.2.15 Washer sit square against the wall. If not, adjust the alarm line and/or drain piping to
suit.

5.2.16 From the outside wall, insert the Drive Shaft through the Sleeve and fully insert it into
the Impeller. (When fully inserted, the Shaft should protrude beyond the face of the wall by
approximately 20" minus 2" minus wall thickness.) Mark the Drive Shaft at a point of
approximately 1/8 to 1/4 inch inside the face of the wall; remove the Shaft; cut the Shaft where
previously marked; file off burrs from the cut end of the Drive Shaft; and, re-insert the Drive
Shaft through the Sleeve and fully insert it into the Impeller.

5.2.17 Hold the Gong Mount in position against the wall, engage the Coupling with
the Drive Shaft and then carefully thread the Striker Shaft Bearing onto the Sleeve. Securely
tighten the Striker Shaft Bearing using a pair of channel locks on the 1-1/2 inch (38 mm) hex
end.

5.2.18 Spin the Striker by hand and verify that it spins freely (without any sign of binding). If
not, make the necessary adjustments.

5.2.19 Install the gong and securely tighten the Cap Nut. The identification sign
lettering must be orientated horizontally.
Project: WORLD TRADE CENTER DOHA QATAR
Method Statement for the
Title of the
Installation of Alarm Check
Document
Valve
Reference No. Revision No Date Page No.
QC-MS-FF-006 00 08 OCT 2010 6 of 7

5.2.20 After installation, the alarm check valve must be tested in accordance with
the recognized installation standards. If a thread leak occurs or the groove joints leak, normally
the unit must be removed and the joints should be done again. This is due to the fact that
when the joint seal leaks, the sealing compound or tape is washed out of the joint or the
groove of the pipe might more or the groove fittings gasket might be damaged.

5.2.21 Ensure the alarm check valve is installed as per the procedure and the trim
connections are installed as per the trim chart.

5.2.22 Verify that all system components are rated for the water working pressure of the
system.

5.2.23 Final touch up of painting is to be done if required

6.0 PLANT REQUIREMENT

• Special Wrench
• Wrench
• General tools
Protective clothing / equipment
• Engaged personnel on site will wear or use the following safety equipment as
appropriate:
• Hard hats, safety boots, overalls / work wear, high visibility clothing, safety
goggles, gloves and Masks.

7.0 MANPOWER REQUIREMENT


Manpower requirement like Site Engineer, Supervisor/ Foreman, and pipe fitters
depends upon the planning organization chart and site progress of works.

8.0. TEMPORARY WORKS TO BE DESIGNED & INSTALLTED


All the Safe Working Scaffolding Platforms will be installed in compliance to safety
standard requirements.

9.0. HEALTH AND SAFET REQUIREMENTS


Implementation of Health & Safety mechanisms and checks shall be done as
per contract agreement and the approved EFECO safety manual. The safety officer
shall carryout the necessary routine inspections.
Project: WORLD TRADE CENTER DOHA QATAR
Method Statement for the
Title of the
Installation of Alarm Check
Document
Valve
Reference No. Revision No Date Page No.
QC-MS-FF-006 00 08 OCT 2010 7 of 7

Safety Lighting : Safety lights will be used in case of power failure ensuring good
illumination for the personnel. Green color safety jacket shall be worn on site for all personnel who
are in site.
Task Lighting : Adequate lighting will be provided ensuring the good illumination of
the working area. Task Lighting will be connected to the nearest site distribution board which is
RCD protected.
Emergency Arrangements : Site general safety procedure will be followed. In
case of emergency, the safety officer will stop the work. He will put in to action the emergency
arrangements as described in EFECO safety Manual.

Risk Control : Risk Assessment and their controls are carried out for the
following activity / hazard and enclosed with this method statement.
• Using Hand Tools
• Disposal of Waste Material
• Temporary Site Electrical Supply
The safety officer has the right to stop all the fire fighting works activity, if he is not satisfied
with the safety arrangement on site during installation and testing process.

10.0 ENVIRONMENTAL REQUIREMENTS


All remedial measures to control all the operations within the environmental legal limits
for Information and record.

11.0 SECURITY ARRANGEMENTS


No additional security arrangements over and above those already in place at the site,
restricted access to the job site and the maintaining of the boundary fence security guards will be
posted on all entrance points being used by vehicles during the camping out of this item of work to
control and coordinate traffic movements.

12.0 SPECIFIC CONTRACTUAL OBLIGATIONS


We are executing all the works by following the Project Specifications Section No. 15310
and the related issued “For Construction” drawings.

13. RECORDS TO BE PRODUCED


The following Form(s) / Checklist(s) shall be prepared and raised to verify the above
activity to ensure that the activity is carried out as per the contract requirements.
•Inspection Request (IR’s) – Revision 0 shall be raised along with QC checklist for
alarm check valve installations
• QC Checklist for Installation of Alarm check valve
14. ATTACHMENTS
Project: WORLD TRADE CENTER DOHA QATAR
Method Statement for the
Title of the
Installation of Alarm Check
Document
Valve
Reference No. Revision No Date Page No.
QC-MS-FF-006 00 08 OCT 2010 8 of 7

The following documents are enclosed with this method statement:


• Form ITP–F-03-Inspection and Test plan for Installation of Fire Alarm check
Valve
• QC Checklist for Installation of Alarm check valve
• Risk Assessment Form – Using Hand Tools ( QC-RAF-01 )
• Risk assessment Form – Disposal of Waste Materials ( QC-RAF-02 )
• Risk assessment Form – Temporary Site Electrical Supply ( QC-RAF-03 )
******************************