Beruflich Dokumente
Kultur Dokumente
Quick Changeover/
Shorter LT
Smaller WIP
Set Up Time Reduction Fewer defects
Greater scheduling flexibility
But, more handling and changeovers (setups)
Changeover of equipment
or a process: to go from
making thing to another,
or to go from doing one
kind of task to doing
another.
1
Setup/changeover improvement:
Examples usually neglected
Cost. Less time; no need for specialists. RETAD: Rapid Exchange of Tools and Dies.
Quality. Fewer setup mistakes, Goals
Flexibility. Easier to switch over. SMED: Single Minute Exchange of Dies
Utilization. Reduced idle time from setup. OTED: One-Touch Exchange of Dies
2
SMED Procedure
SMED applies not only to the changeover of dies
but to changeovers in all kinds of processes and industries.
3
Changeover Analysis Worksheet
Step #1. Study Existing Method (cont’d)
Distinguish Internal Tasks from External Tasks
Internal (online)
Must be done while machine is stopped
(attaching, mounting, detaching dies, parts, fixtures;
adjusting height, pressure, location; etc.)
External (offline)
Can be done while machine is running
(e.g., fetching and adjusting materials, tools, fixtures,
etc.)
Unnecessary
Setup
Internal
Person
1 2 3 4 6 7 External
Idle zzzzzz
7 Operator Zzzzzzzzzzzzzzzzzzzzzzz zzzzzzzzzzzzzzzzzzzzzzzzz
zzzzzzzzz
5
7
10
109 70 Minutes
98
Stop Machine Start Machine
15
8
15
14
14
21
21
84
4
Step # 2. Convert Internal to External Setup procedure worksheet; distinguish
external and internal
Convert any activity that can be done
safely while machine is running to External
Searching for tools, parts, etc.
Waiting for materials, instructions, tools, etc.
Adjustments to tools and fixtures (calibration)
44 40
44
Setup
Internal
Person
1 2 2 3 4 6 7 External
Idle zzzzzz
Operator Zzzzzzzzzzzzzzzzzzzzzzzzz---------------- zzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzzz
5
Setup Person
3 6 7
70 Minutes
44 minutes
5
Step # 3b. Improve Every Task in the
Step # 3a. Improve Internal Steps Setup Procedure
Reduce attachment-detachment times
Reduce # bolts
Reduce # threads • If the goal is small-batch production with frequent
Reduce of eliminate adjustments changeovers, then short internal setup is not enough
A setup that takes 2 hrs might actually take 10
• Both internal and external time—the total setup time—
hrs (8 hrs for adjustments!)
must be short.
Shortening internal steps has immediate
impact on reducing downtime
Step # 3b. Improve Every Task in the Step # 3b. Improve Every Task in the
Setup Procedure Setup Procedure
Example, assume: • Ultimate Goal: total setup time should be so short that it
• 450-minute day no longer matters—where the number of setups or the
• Desired: 10 batches batch size required to meet demand can be accommodated
• If each batch requires 10 minutes, processing time = 100 min without even thinking about the setup time.
• Total time remaining for setup = 450-100 = 350 • Rule of thumb #1: no setup takes longer than 10
• Current time per setup = 45 minutes minutes.
• Rule of thumb #2: for operations where the work pace
• Therefore, maximum number of batches produced must conform to takt time (planned time per unit), the
= (350 min/day)/45 min/setup = 7.78 setups/day. changeover time should not exceed the takt time.
• Ideal setup procedure: involves no more than one
• 45 min/setup is too long. To produce 10 batches/day, simple task. Shingo called this OTED for one-touch
total setup time (both external and internal) must be exchange of dies.
reduced to a maximum of 350/10 = 35 minutes
6
External Steps Quick-change fasteners
External setup time must be shortened
whenever it exceeds batch production time.
Most external setup time is spent getting,
looking for, or transporting things
Methods to improve:
Use kits and carts for tools and fixtures
Store needed items nearby
Use improved methods and correct-height carts
Keep everything arranged, organized, clearly
marked
7
Material handling equipment No Adjustments: One-touch
Changeover!
Adjustment time
(Scrap samples)
Begin
production
Setup Run
Begin
production
Steps
8
Step # 4. Abolish the Setup Step # 4. Abolish the Setup
1. Redesign products/parts to eliminate 3. Use less versatile (but less expensive) kinds of
machines, and dedicate each machine to one
changeover kind of product/part
2. Use machines that can produce more
than one kind of part at the same time With one versatile machine, many setups
Honda: presses that make left and right door A setup B setup C setup A setup B
panels simultaneously With dedicated machines, no setups
A A A
B B
C C
40
30
Load/unload
Alignment and Adjustment
20
Secure
10
Goal = 10 min
0
July Aug Sept Oct Nov Dec Jan Feb Mar
9
Quick Changeover: CT Scans
Many of these steps can be performed while the scan machine
Example: events to complete a CT scan C/O is being used for another patient
1. Scan ends; turn off machine (E = External steps)
2. Remove IV from patient 1. Scan ends; turn off machine
3. Remove patient from scan bed 2. Remove IV from patient E
4. Take patient out of scan room 3. Remove patient from scan bed
5. Bring next patient into scan room 4. Take patient out of scan room
6. Verify patient ID 5. Bring next patient into scan room
7. Explain procedure to patient 6. Verify patient ID E
8. Verify physician orders 7. Explain procedure to patient E
9. Start IV on patient 8. Verify physician orders E
10. Place patient on scan bed 9. Start IV on patient E
11. Turn of CT scan machine 10. Place patient on scan bed
11. Turn on CT scan machine
New procedure
Scans ends; turn off machine
Remove patient from scan bed
Take patient out of scan room
Bring next patient into scan room
Place patient on scan bed
Turn on CT scan machine
Results
Number of internal steps cut by almost 50%
Changeover time is reduced to the time it takes
to do the internal steps (reduction of 82%)
This allowed twice as many scans/day, eliminated
backlogs, and increased revenues from scans.
10