(1) Objective:
The purpose of this procedure is to describe the required resources and procedure for
the erection of the Stack#1- 7th & 8th shell.
(1) Field Application:
This procedure applies to the erection of the Stack#1-7th & 8th shell. However, it may vary
depending on available resources & site conditions. The same shall be revised as per
necessity.
(2) Resources:
A) Manpower
The workforce planned for this operation would include:
Section Engineer/Supervisor 1
Rigger Foreman 1
HSE Supervisor 1
Riggers 8
1 of 6
(4) Equipment and tools and tackles required:-
Crane boom length and radius will be decided as per crane load
chart.
2 of 6
6. Safety Control:
During the erection process, all necessary safety guidelines will be
maintained during all the lifting operations.
3 of 6
When wind speed (sustained or gusts) exceeds 20 mph then lifting
operation must not begin (or, if already in progress, must be terminated
4 of 6
5 of 6
6 of 6