标识号 Task Complete Duration Start Finish 前置任务 2020年第2季度 2020年第3季度 2020年第4季度

Percent 2 3 4 5 6 7 8 9 10
1 SCHEDULLE_TUCANCIPA TANKS "6 CCT +2 BBT + 1 DAW - 0301 0% 200 days 2020/2/19 2020/10/8
2 LOI confirmation 100% 1 day 2020/2/19 2020/2/19
3 Signed contract -abi 0% 1 day 2020/3/25 2020/3/25 22SS-30 days
4 Civil ready for site construction-abi 0% 1 day 2020/5/25 2020/5/25 48SS-2 days
5 Civil ready for tank location-abi 0% 1 day 2020/2/19 2020/2/19
6 PREPARATION IN LEHUI WORKSHOP 0% 174 days 2020/2/20 2020/9/9
7 6 CCT 4800hl + 2 BBT 3600hl + 1 DAW 0% 130 days 2020/2/20 2020/7/20
8 Design and confirmation 0% 8 days 2020/2/20 2020/2/28
9 Drawing design 0% 6 days 2020/2/20 2020/2/26 2
10 Drawing confirmation 0% 3 days 2020/2/27 2020/2/29 9
11 Drawing dispatch (ERP+WPS+ITP) 0% 25 days 2020/3/2 2020/6/13 10
12 Procument 0% 153 days 2020/2/27 2020/8/22
13 Main materials 0% 10 days 2020/2/27 2020/3/9 9
14 Piping 0% 30 days 2020/6/15 2020/7/18 11
15 Fittings 0% 60 days 2020/6/15 2020/8/22 11
16 Manufacturing 0% 63 days 2020/2/27 2020/5/9
17 Vessel manufacturing 0% 57 days 2020/2/27 2020/5/2 9
18 Factory Acceptance Test 0% 3 days 2020/5/4 2020/5/6 17
19 Package and cleaning before shipping 0% 3 days 2020/5/7 2020/5/9 18
20 Transportation 0% 131 days 2020/4/10 2020/9/9
21 1st batch(2 CCTs in pieces) 0% 53 days 2020/4/10 2020/6/10
22 FOB China port 0% 2 days 2020/4/10 2020/4/11
23 CIF 0% 45 days 2020/4/13 2020/6/3 22
24 Custom clearance(by customer) 0% 3 days 2020/6/4 2020/6/6 23
25 DAP site 0% 3 days 2020/6/8 2020/6/10 24
26 2nd batch(4 CCT&2 BBT break bulk) 0% 53 days 2020/5/11 2020/7/10
27 FOB China port 0% 2 days 2020/5/11 2020/5/12
28 CIF 0% 45 days 2020/5/13 2020/7/3 27
29 Custom clearance(by customer) 0% 3 days 2020/7/4 2020/7/7 28
30 DAP site 0% 3 days 2020/7/8 2020/7/10 29
31 3rd batch(PIR) 0% 53 days 2020/5/20 2020/7/20
32 FOB China port 0% 2 days 2020/5/20 2020/5/21
33 CIF 0% 45 days 2020/5/22 2020/7/13 32
34 Custom clearance(by customer) 0% 3 days 2020/7/14 2020/7/16 33
35 DAP site 0% 3 days 2020/7/17 2020/7/20 34
36 4th batch(steel structure) 0% 53 days 2020/5/30 2020/7/30
37 FOB China port 0% 2 days 2020/5/30 2020/6/1
38 CIF 0% 45 days 2020/6/2 2020/7/23 37
39 Custom clearance(by customer) 0% 3 days 2020/7/24 2020/7/27 38
40 DAP site 0% 3 days 2020/7/28 2020/7/30 39
41 5th batch(1 DAW in one whole part) 0% 53 days 2020/7/10 2020/9/9
42 FOB China port 0% 2 days 2020/7/10 2020/7/11
43 CIF 0% 45 days 2020/7/13 2020/9/2 42
44 Custom clearance(by customer) 0% 3 days 2020/9/3 2020/9/5 43
45 DAP site 0% 3 days 2020/9/7 2020/9/9 44
46 MECHANICAL ASSEMBLY ON SITE 0% 116 days 2020/5/27 2020/10/8
47 Mobilization / Preparing the Assembly Area 0% 10 days 2020/5/27 2020/6/6
48 Mobilization / Preparing the Assembly Area 0% 10 days 2020/5/27 2020/6/6 25SS-10 days
49 1st fabrication: TANKS 2 CCT 4800 hl - TUCANCIPA 0% 79 days 2020/6/11 2020/9/10
50 Assemble cones 0% 4 days 2020/6/11 2020/6/15 25
51 Assemble dish head 0% 4 days 2020/6/16 2020/6/19 50
52 Assemble shells 0% 20 days 2020/6/20 2020/7/13 51
53 Erection 0% 1 day 2020/7/14 2020/7/14 52
54 Erect DAW 0% 1 day 2020/9/10 2020/9/10 45
55 HYDRO - TEST 0% 2 days 2020/7/15 2020/7/16
56 CCT TQ 001# 0% 1 day 2020/7/15 2020/7/15 53
57 CCT TQ 002# 0% 1 day 2020/7/16 2020/7/16 56
58 INSULATION 0% 16 days 2020/7/20 2020/8/6
59 CCT TQ 001# 0% 3 days 2020/7/20 2020/8/3 56FS+3 days
60 CCT TQ 002# 0% 3 days 2020/8/4 2020/8/6 59
61 2nd fabrication: TANKS 4 CCT 4800 hl + 2 BBT 3600hl 0% 72 days 2020/6/11 2020/9/2
62 Assemble cones 0% 6 days 2020/6/11 2020/6/17 25
63 Assemble dish head 0% 6 days 2020/7/11 2020/7/17 62 LEHUI
64 Assemble shells 0% 35 days 2020/7/18 2020/8/27 63
65 Erection 0% 3 days 2020/8/28 2020/8/31 64
66 Install steel structure 0% 2 days 2020/9/1 2020/9/2 65
67 HYDRO - TEST 0% 6 days 2020/9/3 2020/9/9
68 CCT TQ 003# 0% 1 day 2020/9/3 2020/9/3 66
69 CCT TQ 004# 0% 1 day 2020/9/4 2020/9/4 68
70 CCT TQ 005# 0% 1 day 2020/9/5 2020/9/5 69
71 CCT TQ 006# 0% 1 day 2020/9/7 2020/9/7 70
72 BBT TQ 001# 0% 1 day 2020/9/8 2020/9/8 71
73 BBT TQ 002# 0% 1 day 2020/9/9 2020/9/9 72
74 INSULATION 0% 25 days 2020/9/8 2020/10/6
75 CCT TQ 003# 0% 3 days 2020/9/8 2020/9/22 68FS+3 days
76 CCT TQ 004# 0% 3 days 2020/9/23 2020/9/25 75
77 CCT TQ 005# 0% 2 days 2020/9/26 2020/9/28 76
78 CCT TQ 006# 0% 3 days 2020/9/29 2020/10/1 77
79 BBT TQ 001# 0% 3 days 2020/10/2 2020/10/5 78
80 BBT TQ 002# 0% 1 day 2020/10/6 2020/10/6 79
81 INSTALL VLAVE GROUP 0% 56 days 2020/8/4 2020/10/7
82 CCT TQ 001# 0% 1 day 2020/8/4 2020/8/15 59
83 CCT TQ 002# 0% 1 day 2020/8/7 2020/8/7 60
84 CCT TQ 003# 0% 1 day 2020/9/23 2020/9/23 75
85 CCT TQ 004# 0% 1 day 2020/9/26 2020/9/26 76
86 CCT TQ 005# 0% 1 day 2020/9/29 2020/9/29 77
87 CCT TQ 006# 0% 1 day 2020/9/22 2020/9/22 78 LEHUI
88 BBT TQ 001# 0% 1 day 2020/10/6 2020/10/6 79
89 BBT TQ 002# 0% 1 day 2020/10/7 2020/10/7 80
90 HANDOVER TO ABI PIPING CONTRACTOR 0% 53 days 2020/8/8 2020/10/8
91 CCT TQ 001# 0% 1 day 2020/8/17 2020/8/17 82
92 CCT TQ 002# 0% 1 day 2020/8/8 2020/8/8 83

LEHUI
标识号 Task Complete Duration Start Finish 前置任务 2020年第2季度 2020年第3季度 2020年第4季度
Percent 2 3 4 5 6 7 8 9 10
93 CCT TQ 003# 0% 1 day 2020/9/24 2020/9/24 84
94 CCT TQ 004# 0% 1 day 2020/9/28 2020/9/28 85
95 CCT TQ 005# 0% 1 day 2020/9/30 2020/9/30 86
96 CCT TQ 006# 0% 1 day 2020/9/23 2020/9/23 87
97 BBT TQ 001# 0% 1 day 2020/10/7 2020/10/7 88
98 BBT TQ 002# 0% 1 day 2020/10/8 2020/10/8 89