Beruflich Dokumente
Kultur Dokumente
ON
FAILURE OF TRNSFORMERS
AT
WAZIRABAD, MEHRAULI AND LODHI ROAD
SUBSTATIONS
OF
DELHI TRANSMISSION COMPANY LTD. (DTL)
JANUARY 2007
Report on failure of 220kV/66kV-33kV/11kV, 100MVA
Transformer (NGEF make) at Wazirabad substation;
220kV/66kV/11kV, 100MVA Transformer (CGL make) at
Mehrauli substation and 220kV/66kV-33kV/11kV, 100MVA
Transformer (CGL make) at Lodhi Road substation of DTL on
25-08-2006, 20-09-2006 and 06-11-2006 respectively
----------------------------------------------------------------------------------------------------------------
--
1.0 INTRODUCTION
A Standing Committee has been constituted to assess the cause of failure and rate of
failure of various substation equipment of 220kV and above voltage class and to
suggest remedial measures so as to minimise / avert such failures in future. As part of
such activity, Shri K.K. Arya, Director and S.K.Ray Mohapatra, Dy. Director of
SE&TD Division of CEA visited the site of failure of transformer at Wazirabad on
September 13, 2006. Dr. S. Mukhopadhyay,Chief Engineeer, K.K. Arya, Director and
S.K.Ray Mohapatra, Dy. Director of SE&TD Division of CEA visited the site of
failure of transformer at Mehrauli on September 29, 2006. Shri S.K.Ray Mohapatra,
Dy. Director and Ashok Kumar, Asstt. Director of SE&TD Division of CEA visited
the site of failure of transformer at Lodhi Road on November 28, 2006.
During the visits, the respective teams had meetings with DTL officials and discussed
in detail with the operation and maintenance staff of substation about the sequence of
events leading to failure of transformer. The results of various tests conducted on the
transformer before and after failure including DGA and other relevant information
were also collected. The assessment / analysis of failure of transformers is discussed
below.
1
1.1 FAILURE OF TRANSFORMER AT 220kV/66kV WAZIRABAD
SUBSTATION
1.1.1 Observations
2
(o) At the time of failure the OLTC was at normal tap (No.9)
(p) The 220kVdouble bus bar system was operating with bus coupler closed.
(q) At the time of site visit various repairing activity and fitting of various
accessories were going on. All gaskets of transformer tank were replaced.
Equaliser pipe of B-phase HV bushing found broken giving way for oil to come out.
No other damage to the neighbouring equipment was reported due to the failure of
transformer.
The transformer was commissioned in 1999 after about two years of manufacture
(1997). The Insulation Resistance(IR) measurement, magnetising current, magnetic
balance test, turns ratio test, measurement of BDV & other parameters (water content,
neutralisation value, % of sediment & sludge, dielectric dissipation factor, specific
resistance, interfacial tension, and flash point) of oil, cleaning of bushings, tightness
of clamps, connectors, nuts and bolts, thermal scanning using infrared camera,
3
checking of oil leakage are being carried out by DTL as part of the routine
maintenance checks.
The measurement of capacitance and tandelta of bushings and windings was carried
out only once on January 17, 2005 since its commissioning. No major repair work of
transformer was carried out except filteration of oil and replacement of damaged
pumps.
(a) The failed autotransformer is of NGEF make with unloaded tertiary winding
and was commissioned during 1999 after about two (2) years from date of
manufacture (1997). The transformer failed on 25-08-2006 after serving for
only about seven years. The average loading on the transformer has rarely
exceeded 50% of its rated capacity and has never been overloaded beyond its
maximum capacity during its service life. The load current of the transformer
prior to failure was only 79A against rated current of 262.4 A.
(b) The DGA was conducted after failure at DTL’s laboratory on 26-08-2006 and
at New Delhi on 28-08-2006. There is wide variation in both reports.
However, presence of high content of Acetylene (C2H2) is observed in both
the reports. This implies high energy arcing which could be due to insulation
breakdown between windings or between coils or between coils and earth.
(c) Tertiary winding is the potential cause of failure of many transformers. The
failed transformer had a peculiar feature. External reactor was used in series
with tertiary winding of the transformer. This was an old practice of limiting
the short circuit current in the tertiary winding. The external reactor of tertiary
winding had failed. The burning of cellulose insulation over copper conductor
leading to exposure of copper conductor of one of the coils of B-phase of
external reactor was clearly visible.
(d) There was clear indication of flashover / arcing marks on clamping rods
(metallic) and base of the core of the external reactor of the transformer,
which could be between bare conductor and clamping rods (metallic) / base of
the core of coil. DGA conducted after failure also supports such arcing.
(e) The reports of Sweep Frequency Response Analysis (SFRA) and exciting
current test conducted by PGCIL does not mention any abnormality.
(f) Magnetising current test results and magnetic balance test and ratio tests
conducted after failure does not show any abnormality. IR test results
conducted after tripping show the Dielectric absorption ratio (IR after 60
secs./IR after 15Sec.) for LV-E,MV-LV and HV-LV are 1.0, 1.2,1.2
respectively which are below normal requirement of at least 1.3. IR after 600
sec. has not been measured.
(g) The reason for low oil level alarm, low oil flow alarm and fan & pump fail
indication is not understood.
(h) The fault gases developed inside the transformer due to severe arcing might
have resulted in sudden pressure rise leading to operation of PRD.
4
Transformer oil tested after failure indicated low BDV of oil i.e 49kV. The
transformer at Wazirabad substation has been reenergised after filteration of oil and
replacement of damaged reactor of tertiary winding by another reactor of similar
design.
1.2.1 Observations
No other damage to the neighbouring equipment was reported due to the failure of
transformer.
5
(b) Before tripping, the transformer was running in parallel with another 100MVA
transformer (No.-II) of CGL make. The third transformer(BHEL make) was
running independently on Bus-1. The peak load on transformer No.-1&2 was
92MVA on 30-05-2006.
(d) After failure of transformer, all LT tests on the transformer were carried out
by DTL in presence of CGL Engineer. SFRA test was conducted by PGCIL.
DGA was also conducted after failure of transformer.
(e) It is also reported that , physical inspection (after draining of oil) carried out
by DTL in presence of service Enginner of CGL shows no abnormality.
(a) The failed transformer is of CGL make with unloaded tertiary winding and
was commissioned in the substation during 1999. The year of manufacture of
transformer is 1982. The transformer failed on 20-09-2006 after serving for
about twenty four (24) years.
(d) After failure of transformer, SFRA test was conducted by PGCIL and it was
reported that significant deformation has taken place in Y –phase of IV
winding (66kV) and minor deformation in HV and LV(Tertiary) winding.
(e) Dissolved Gas Analysis shows high concentration of Acetylene and Hydrogen
which clearly indicate low as well as high enegy discharge.
6
(f) Furan analysi was conducted for the said transformer on 21-09-2004 by CPRI.
The test result shows high content of 2-Furfuraldehyde(2535ppb). Such high
level of furan content indicates that significant damage to paper insulation has
occurred due to heat.
(g) Considering the present life of transformer (about 24 years) and Furan
analysis, it is obvious that the cellulose insulation of transformer has
undergone excessive aging. The complete replacement of winding of
transformer might be required. The advice of manufacturer in this
regard may sought before going ahead with any major repair work which
may not be cost effective considering the condition of insulation of
transformer.
1.3.1 Observations
(a) The substation is fed at 220kV level through tapping from the nearby 220kV
line. There is no bus bar system at 220kV level. The nearby line has been
tapped and feeding directly to two transformers through Surge arrester, CVT,
CT, isolators and Circuit breaker.
(b) No oil leakage from OIP bushings was not observed.
(c) No external deformation was observed with the transformer and main tank
was intact.
(d) Factory test report, site test reports not available with the operating and
maintenance staff.
7
1.3.2 Consequential Damages
No other damage to the neighbouring equipment was reported due to the failure of
transformer.
(b) Before tripping, the transformer was running in parallel with another 100MVA
transformer. The peak load on transformer No.-1&2 was 92MVA on 30-05-
2006.
(e) The 33kV outgoing feeder tripped with heavy jerk. The 33kV cable of BSES
was checked and found dead short circuit between two phases. One such two
phase cable fault had also occurred earlier.
(f) After failure of transformer, all LT tests on the transformer were carried out
by DTL in presence of CGL Engineer. SFRA test was conducted by PGCIL.
DGA was also conducted from NTPC after failure of transformer.
(g) It is also reported that internal inspection of winding (after draining of oil)
carried out by DTL in presence of service Enginner of CGL.
The past Operation and maintenance history is not avialable. The capacitance and
tandelta of bushings and windings was carried out during January 2005 as well as on
03-11-2006 prior to failure which did not show any abnormality. DGA for the failed
transformer is being carried out by DTL since 2004.
(a) Since its commissioning in the substation two cable faults have been reported.
(b) Low IR value observed for HV to Earth and LV to earth( i.e ratio of IR value
after 60 sec. to IR value after 10 Sec.).
(c) The failed transformer is of CGL make with unloaded tertiary winding and
was commissioned in the substation during 2004. The year of manufacture of
8
transformer is 2003/2004. The transformer failed on 06-11-2006 after serving
for about two (2) years.
(f) After failure of transformer, SFRA test was conducted by PGCIL and it was
reported that significant deformation has taken place in Y-phase of HV
winding and R & B-phases of IV winding (66kV). Tertiary(LV) winding has
also been affected.
(g) The joint internal inspection by DTL and service engineer of CGL has repoted
physical damage and distortion to winding. It is also reported that the repair
works can not be under taken at site for which transformer has to be
transported to manufacturer’s works.
(h) Dissolved Gas Analysis is being carried out regularly since 2004. DGA was
conducted during September 2004, January 2005, May 2005, October 2005,
September 2006 and November 2006. CO2 content is continuosly increasing
since 2004. The DGA conducted during November 2006 shows high
concentration of Acetylene, Hydrogen, CO and CO2 which clearly indicate
low as well as high energy discharge.
(i) Heavy short circuit and interturn insulation failure could be the reason of
failure of the transformer. The deformation in winding observed during
internal inspcetion might be due to flow of heavy short circuit current for
a longer duration.
The failed transformer is to be moved out of the station for repair and a healthy
transformer is likely to replace the faulty one to meet the load demand.
2.0 RECOMMENDATIONS
2.1 Design of transformer with such external reactor in series with tertiary winding of
transformer (as in case of NGEF make transformer at Wazirabad) is no more a
9
conventional practice. Such design of tertiary winding with series reactor may be
avoided in future.
2.2 Factory test report and pre-commissioning test reports of each transformer, which are
considered to be the base results, should be made available to the operation and
maintenance staff of the substation so that subsequent measured results can be
compared with the base value to find out any abnormal change. The trend analysis
(relative change in test result and rate of change) will provide valuable information to
O&M staff for taking early action so that any major failure can be avoided.
2.3 In addition to other tests being conducted by DTL, it is recommended to conduct core
to ground insulation resistance measurement, DC resistance measurement and
determination of Polarization Index (PI) corresponding to 60secs. and 600 secs.,
Recovery Voltage measurement, SFRA etc. may also form part of maintenance
activity. PI corresponding to 60secs. and 600 secs., might provide additional
information and help in assessing condition of transformer. The periodicity of the
tests is to be decided.
2.4 Complete data base of previous test results starting from factory test, pre-
commissioning tests etc. and history of the transformer may be maintained properly
which would help in proper evaluation of results. Periodicity of tests to be conducted
on transformer needs to be decided based on condition assessment and relative change
in test results with respect to time (trend analysis) rather than conventional scheduled
time based.
2.5 DGA is being carried out by DTL since 2003. But the rising trend of various fault
gases need to be monitored to plan future action. It is suggested that DTL may
procure on line portable DGA equipment which can cater to number of substations for
condition monitoring of transformers. In the process dependency on outside agency
would not be there and measurements can be carried out as and when required. DGA
based on the results of same equipment used at different times would provide better
information for analysis / interpretation.
2.6 Non-operation of Pressure Relieve Device (PRD) has caused serious damages to
transformers in number of cases as in recent past in DTL’s system also. So far no site
tests are being conducted to assess healthiness of PRD whose operation is very much
required to save transformer from serious damages. Therefore, it is required to check
healthiness of PRD at site at regular interval of time. The manufacturer may be
consulted to find out the method of checking healthiness of PRD of transformer at
site.
2.7 Since oil surge relay, Buchholz of OLTC has also operated, the OLTC assembly may
also be checked in case of transformer at Mehrauli substation.
2.9 Field test results (conducted after failure) may be verified during major repair work at
manufacturer works / at site for which the concerned person associated with operation
10
& maintenance activities may be deputed to manufacturer’s works for the purpose to
have better insight and understanding of cause of failure which would help in future.
2.10 In all three cases, failure of transformer is attributed to insulation failure (interturn
isulation failure) and / deformation in windings. The deformation in winding
indicates flow of high short circuit current for longer duration. There is no
Disturbance Recorder at 220kV substations to record such system faults and its
duration. The replacement of conventional Electro-mechanical / static relay by
modern numerical relay could help in getting such valuable information. As such the
short circuit withstand level of transformer is being verified by emperical
calculations. No short circuit test is being conducted on the transformer due to non-
availability of indigenous testing facility. Therefore, such failures raise serious
question about the short circuit withstand capability of transformers being
manufactured in the country. The fault clearing time of protective system needs to be
reviewed. Adequate measures need to be taken to protect the transformer from severe
short circuit condition.
2.11 It is observed that SFRA is being carried out by DTL only after failure of
transformers. If base / reference signature would have been available, it would have
provided better insight into cause of failure. Two out of three failures of transformer
reported above shows deformation in winding. Similar observations were also made
in case of failure of transformers of DTL in the past. Therfore, it is advisable to
conduct SFRA for healthy transformers also as and when required, may be at least
once in two years.
Submitted by
(Dr. S. Mukhopadhyay)
Chief Engineer (SE&TD) and
Chairman, Standing Committee
to investigate the failure of equipment
at 220kV & above sub-station
11