Beruflich Dokumente
Kultur Dokumente
EPC Package 2 –
Utilities and Offsites
Contract No. CNT-1100-1000-007
Revision History
Related Documents
Holds
Term Comment
CONTENTS
1. SCOPE ......................................................................................................................................4
2. REFERENCES ..........................................................................................................................5
3. DEFINITIONS ............................................................................................................................6
4. DESIGN - GENERAL .................................................................................................................7
5. DESIGN - PIPING INSULATION ...............................................................................................8
6. DESIGN - EQUIPMENT .............................................................................................................9
7. DESIGN – HFSO PIPELINE .................................................................................................... 10
8. MATERIALS - GENERAL ........................................................................................................ 17
9. MATERIAL - THERMAL INSULATION .................................................................................... 18
10. MATERIAL - WEATHERPROOF JACKET ............................................................................... 19
11. MATERIALS - ANCILLARIES .................................................................................................. 20
12. APPLICATION - GENERAL ..................................................................................................... 21
13. APPLICATION - PIPING .......................................................................................................... 22
14. APPLICATION - EQUIPMENT ................................................................................................. 26
15. APPLICATION - TANKS .......................................................................................................... 29
16. INSPECTION AND TESTING .................................................................................................. 29
17. HANDLING, PRESERVATION AND STORAGE ...................................................................... 30
18. FIGURES................................................................................................................................. 32
1. SCOPE
1.1 This specification covers the use of thermal insulation for above ground, external
insulation of piping and equipment operating between Ambient Temperature and 540°C,
for the purpose of Heat Conservation, Process Stabilisation, Temperature Maintenance,
and Personnel Protection for the Duqm Refinery in Duqm, Sultanate of Oman. For
services operating in excess of 540°C, process licensor shall recommend a suitable
insulation system and advise required insulation thickness.
1.2 The insulation requirements of this specification are suitable for use in both indoor and
outdoor service with normal process plant atmospheres. Alternative designs and
materials shall be considered if necessary for highly corrosive atmospheres or potential
leaks and spills of chemicals.
1.3 This specification is intended to cover piping, pressure vessels and circular ducting, heat
exchangers and mechanical equipment.
1.4 This specification does not cover cold service insulation. Cold service insulation is
covered by specification DRP001- OUF-SPE-W-000-011.
1.5 This specification does not cover acoustic attenuation insulation. Acoustic Insulation is
covered by specification DRP001- OUF-SPE-W-000-012.
1.6 This specification does not cover Vendor designed insulation for Boiler or Fired Heater
packages including Airheaters, Economisers, Gas Flues and Air Ducting. The
specification is intended to cover Contractor supplied insulation for parts of such
packages except for rectangular ducting.
1.7 This specification does not cover Daily Service Tanks, Process or Large Product
Storage Tankage nor insulated underground lines. For any tanks which require
insulation for the prevention of heat loss, the Vendor shall submit a suitable insulation
system and required insulation thickness complete with detail of heat preservation
calculations to Contractor for review and approval.
1.8 Piping and equipment requiring insulation shall be specified on the following project
documents:
2. REFERENCES
ASTM C585 Standard Practice for Inner and Outer Diameters of Thermal
Insulation for Nominal Sizes of Pipe and Tubing
ASTM C592 Standard Specification for Mineral Fiber Blanket Insulation and
Blanket-Type Pipe Insulation
ASTM C612 Standard Specification for Mineral Fiber Block and Board
Thermal Insulation
3. DEFINITIONS
Company Duqm Refinery & Petrochemical Industries Company
4. DESIGN - GENERAL
4.1 In this specification, insulation for the prevention of heat loss is designed for the
following conditions:
4.2 In this specification, insulation for personnel protection is designed for the following
conditions:
4.3 Insulation comprises a layer (or layers) of heat resisting fibre material enclosed within
protective metal sheeting sealed against the ingress of moisture and designed to allow
differential expansion.
4.4 Internally refractory lined piping and equipment shall not be insulated. Over these areas
personnel protection shall be achieved by the use of stood-off metal guards.
4.5 Insulation is not necessary for piping and equipment for which heat loss is desired -
other than for acoustic attenuation, personnel protection or to avoid thermal stress
problems.
4.6 The purpose for which insulation is required is identified by the applicable symbols in
Table 1. Piping and Equipment to be insulated shall be identified by these symbols on
Piping and Instrumentation Diagrams and Line Lists.
4.7 Instruments and associated piping subject to operating flow and/or temperature
conditions approximating those in the piping or equipment to which they are connected,
shall be insulated to the same requirements as that piping or equipment. The insulation
requirements shall be classified by symbols in accordance with Table 1.
4.8 All insulated austenitic stainless steel, Carbon steel and low alloy piping and equipment
shall be protected against corrosion by painting in accordance with Painting of New
Equipment and Piping Doc. No. DRP001- OUF-SPE-W-000-008.
4.9 All insulated austenitic stainless steel piping and equipment shall be protected against
chloride attack with a 0.15 mm thick, sacrificial aluminium foil system. The foil shall be
applied with 50 mm overlaps and secured with stainless steel wire or bands.
The aluminium foil shall have a chemical composition of 98% minimum aluminium and
shall not have an adhesive backing.
Stainless steel foil shall be used for operating temperatures in excess of 500°C.
4.10 To assist corrosion prevention insulation materials shall be of the correct chemical
nature and shall include the following requirements
4.11 Personnel protection shall be applied in accordance with Table 4 to all exposed surfaces
operating above 65°C and located within 600mm horizontally or 2100mm vertically of a
normal access walkway or work area.
Pipe and Equipment designated for personnel protection (“PP” or “PG”) shall be fully
painted in accordance with specification DRP001- OUF-SPE-W-000-008.
4.12 The Material for stand off metal guards used in personnel protection shall be as follows:
BS EN 485-NS3-H6
ASTM B209 Alloy 3003 – H14 of H16
316 stainless steel in fire hazard areas or in case personnel protection is applied
on 300 series stainless steels or Ni-Based Alloys. The material shall comply with
BS 10088-2 or ASTM A240.
The minimum standoff distance shall be in accordance with Figure 7 to prevent
deliberate or accidental contact.
5.1 Insulated piping systems shall have straight pipe, bends, tees and non-flanged pipe
fittings completely insulated.
5.2 All valves and flanged joints shall be insulated only in the following services:
1. Steam services
2. Trace heated or jacketed services
3. Closed Condensate services.
4. Other special services when agreed with Company
5.3 Bucket and Float type steam traps shall be traced and insulated together with the inlet
piping.
5.4 Insulation on inlet piping to Thermostatic and Thermodynamic steam traps shall
terminate a minimum of 450mm from the trap leaving the remainder of piping and the
trap uninsulated.
5.5 Steam trap outlet piping shall not be insulated except for Personnel Protection
considerations.
5.6 Insulation shall not be applied to the following unless otherwise specified for Acoustic
Attenuation, Personnel Protection or other special reasons.
1. Piping which becomes hot intermittently, such as relief valves, vents, steam-
out and snuffing steam systems, flare and blowdown systems and by-
passes at control valves.
5.7 Piping shall be designed to provide an absolute minimum clearance of 25mm between
the outside surface of any insulation finishing material and adjacent surfaces.
5.8 Where insulated horizontal piping is supported on steel shoes, the height of the shoe
shall be such that the underside of the insulation finishing material is clear of the
supporting structure upon which the shoe rests by 25mm minimum.
5.9 Vertical piping insulation shall be supported by bolted collars at intervals (see figure 6,
together with figure 1, section18). Collars shall be supplied, fabricated, and fitted by the
Insulation Applicator.
6. DESIGN - EQUIPMENT
6.1 Support skirts of insulated vertical vessels greater than 1200mm diameter shall be
insulated both internally and externally for a minimum distance of 600mm below the
bottom tangent line. On skirts which do not require fireproofing the insulation shall
terminate not less than 300mm above the support concrete or steelwork. Where
support skirts are to be fireproofed the insulation shall extend to the top of the
fireproofed areas and stainless steel finishing material shall be used to protect the area
of skirt insulation below the bottom tangent line.
6.2 Support skirts of insulated vertical vessels of 1200mm diameter and less shall be
insulated externally only, as described in paragraph 6.1 above.
6.3 Bottom heads of insulated vertical vessels fully enclosed by a support skirt shall be
insulated without weatherproof jacket finishing material and shall be insulated only when
the vessel outside diameter is greater than 1200mm.
6.4 Liquid ends of positive displacement pumps and casings of centrifugal pumps shall be
insulated only when heat traced or jacketed.
6.5 Insulation shall not be applied to the following unless otherwise specified for Acoustic
Attenuation, and Personnel Protection or other special reasons.
1. Pumps with operating temperatures below 200oC unless pumped fluid has a
pour point above minimum design ambient temperatures.
6.6 Insulation for vessels and similar equipment shall be adequately supported or
suspended, dependent on insulation material form, with clips and support lugs, welded
on at intervals around the equipment item and positioned by the Equipment fabricator in
accordance with Standard Detail Drawings specification DRP001-OUF-SPE-V-000-003.
6.7 External vacuum stiffening rings on equipment shall be fully and independently
insulated. The insulation finishing metal sheeting shall be sealed and allow for
differential expansion. The sheeting shall be shaped to shed water.
7.1 The HFSO Pipeline from refinery to jetty complete with Skin Effect Heat tracing shall be
insulated. See Pipeline Mechanical Basis of Design (DRP001-OUF-SPE-Y-650-011) for
design conditions of the Pipeline. The insulation type shall be either shop-applied,
sprayed PIR insulation or a traditional shop or field applied insulation system, based on
the final design of the skin effect tracing. Contractor will confirm insulation requirements
with heat tracing manufacturer and verify the most cost-effective method of insulation
installation. A high density foam insulation with a high-strength cladding material such
as FRP shall be used local to the pipeline clamp supports.
DESIGN - TABLE 1
NOTE* The intent of Piping and Instrumentation Diagrams, Line Classification lists, Insulation
Summaries etc. which designate insulation for types PP and PG is to call attention only to
the eligibility of such service. The actual extent of such insulation shall be determined
using the criteria defined in paragraph 4.11.
DESIGN - Table 2
* Note: FOR INSULATION IN FIRE HAZARD ZONES STAINLESS STEEL SHEETING SHALL BE
USED.
DESIGN - Table 3
DESIGN - Table 4
8. MATERIALS - GENERAL
8.1 All material shall be as described in the following paragraphs, and shall be of high
quality and good appearance.
8.2 Insulation materials shall be of low chloride content, chemically inert, non-sulphurous,
rot proof, vermin proof, impervious to hot water and steam, non-injurious to health and
non-corrosive to steel or aluminium, (even if soaked with water at ambient temperatures
for extended periods). Insulation material must be CFC free, designed with the
guidelines of Montreal Protocol,1987, for protection of Ozone layer as per Environmental
Design Basis DRP001-OUF-DCR-Z-000-018.
8.4 Insulation materials containing ASBESTOS in any form are not permitted.
8.5 Insulation and jacketing materials backed with paper or other flammable material are not
acceptable.
8.6 Zinc bearing materials shall not be used on stainless steel pipe and/or equipment.
8.7 Material shall have low smoke emission and shall not melt or drip in fire as per BS 476
and relevant ASTM standard.
9.1 Rigid insulating material shall be Fibrous Preformed (Mineral Fibre with resin binder)
Insulation and shall be of long fibred rock material processed from a molten state into
fibrous form and bonded with a binder suitable for the intended operational temperature
range.
9.1.1 Preformed materials shall satisfy the minimum requirements of quality standard in
accordance with BS 3958 (Parts 4 and 5), ASTM C547 and ASTM C612.
9.1.2 The insulation material shall be supplied plain faced in Manufacturer's Standard sizes
and the average measured length, width and thickness shall not differ from the standard
dimensions specified by more than plus or minus 3mm.
9.2 Flexible insulation shall be layers of a long fibred mineral material, made from rock
processed from a molten state into fibrous form, and be without binder. It shall be
stitched through with heat resistant ties (galvanised wire) to galvanised wire netting on
one side (ties and netting shall be stainless for stainless steel surfaces).
9.2.1 Flexible materials shall satisfy the minimum requirements of quality standard in
accordance with ASTM C592 or ASTM C553.
9.2.3 In addition the insulation shall have the following physical properties:-
10.1 The selection of Aluminium material in both coil and flat sheeting form for use as the
thermal insulation protective metal cover shall take precedent over other metallic
coverings with the exception of insulation in fire hazard zones where stainless steel
covering shall be used.
10.2 Aluminium jacketing shall be flat mill finished commercial grade of alloy ALMn which
shall comply with BS EN 485 or ASTM B209 under the following material designations:
BS EN 485 - NS 3 - H6
Stainless steel jacketing required in case of fire hazard areas shall be flat mill
finished grade 2B of steel to comply with BS 10088-2 or ASTM A240. Stainless
Steels Grade shall be SS 304 or SS 316.
10.3 Aluminium metal jacketing shall be supplied with factory applied protective barrier
coating of polysurlyn applied to one side which shall comply with BS 476 Class 1
(Surface Spread of Flame). The backing shall be directly laminated to the aluminium
without use of adhesives or glue.
10.4 Alternative jacketing such as coated mild steels/ Aluminized steel can also be used for
weather proofing after approval of COMPANY and CONTRACTOR.
11.1 Binding and tie wire used where indicated to secure insulation materials and sacrificial
foil over stainless steel surfaces shall be 18% Cr - 8% Ni stainless steel wire having a
minimum diameter of 1.22mm. The wire shall be fully annealed.
11.2 Banding for use over insulation and over metallic finishing jacket shall be in handable
coils ready to be cut to required lengths at site. Bands shall be as shown in Table 2 of
this specification 20mm or 12mm wide x 0.5mm thick - fully annealed 18% Cr – 8% Ni
stainless steel.
Expansion sections of banding where required to cater for differential expansion shall be
of the same size and material as the flat bands and shall be of the 'Expand-R-Strap' type
or 'Techalloy' Breather spring type or an approved equivalent.
11.3 Banding clips for use with securing bands shall be of the same stainless steel material
as the banding and shall be of the 'Butterfly' type similar to 'Band-it-Valstrap Clips'.
11.4 Rivets required for metal jacket fabrication shall be the expanding Monel 'pop' blind eye
type, 9.5mm long x 5mm diameter.
11.5 Screws required for metal jacket fabrication shall be stainless steel slotted pan head
self-tapping type A No. 8 dia. x 12mm long to BS 4174 complete with neoprene washers
under the head.
1. 'S' and 'J' clips - Formed from 20mm wide stainless steel banding.
5. Sacrificial foil - Use as a barrier material between stainless steel piping and
equipment surfaces and insulation material shall be 0.06mm thick
aluminium foil for operating temperatures of 500oC and below, and
stainless steel foil at operating temperatures in excess of 500oC.
11.7 Sealing compound for use as metal sealant, sealing overlaps of metal jacketing shall be
a suitable flexible non-setting compound having properties which render materials
waterproof, weatherproof, chemically resistant and fire resistant.
12.1 The requirements of application, given in this Specification in no way absolve the
Applicator from responsibilities of applying an insulating system that will give a
satisfactory operational performance and the requirements given herein shall be
regarded as directives and guidelines for the acceptable minimum. The Applicator shall
carry out the work in accordance with the best practices of insulation application with the
minimum of waste and debris and the final job shall present a neat, efficient, and
workmanlike appearance.
12.2 All hydrostatic tests on piping and equipment, including steam tracing systems, shall be
carried out before insulating material is applied. The Insulation Applicator shall only
insulate those sections of the plant that have been specifically released by an authorised
agent of the Contractor for such work. If however, it has been planned and decided to
insulate prior to other trades work and before tests have been completed, insulation
shall terminate a suitable distance before and after welded and flanged joints, and
sealed against water ingress and also protected from mechanical damage which may be
caused by other trades and during subsequent testing.
12.3 Surfaces to be insulated shall be clean, dry and free from loose rust scale. It shall be
the Insulation Applicator's responsibility to remove the loosely adhering scale and dirt by
an appropriate method which does not scar, scour or damage the metal surface.
12.4 Insulated stainless steel, carbon and low alloy steel piping and equipment require
protective coatings as specified in specification of Painting of New Equipment and
Piping Doc. No. DRP001- OUF-SPE-W-000-008.
Where coatings are applied, repairs if necessary, shall be carried out by the appointed
Painting Contractor and the coatings shall be the subject of inspection by an authorised
agent of the Contractor prior to the commencement of insulation application.
12.5 Insulated stainless steel piping and equipment shall be wrapped with sacrificial foil prior
to insulation application. The foil shall be secured with stainless steel tie-wires at
sufficient intervals to ensure the foil remains in place throughout the service life of the
insulation. The supply and application of foil shall be the responsibility of the Insulation
Applicator.
12.6 The Insulation Applicator shall NOT carry out any welding or drilling on piping or
equipment, Applicator shall however be responsible to carry out a check and confirm
that all insulation supports, as indicated on fabrication drawings, have been installed and
welded into position. The Insulation Applicator shall also confirm that a sufficient and
satisfactory number of supports have been provided.
12.7 Insulation shall be finished, sealed and weatherproofed at all terminal points including
either side of temporary shop supports, lifting lugs, testing points etc. At these positions
on shop insulated items closure pieces shall be designed and fabricated, to fit exactly at
a later date on site, without impairing the weatherproofing. The Insulation Applicator
shall remain totally responsible for the finished insulation.
12.8 Equipment nameplates shall remain visible after insulation has been applied. The
surrounding edges shall be efficiently sealed against water ingress.
12.9 The application of the insulation shall take into account expansion movements of piping,
and equipment at normal operating temperatures and include provision within the
insulating system for any differential expansion anticipated. Shop applied insulation
shall take into account not only thermal expansion and contraction movements but also
movements of flexing and vibration created by on-off loading and transportation. The
anticipated scope of these movements shall be outlined to the Insulation Applicator by
the item Shop Fabricator.
12.10 Thermowell bosses, pressure tappings and weep hole nipples shall not be insulated but
left accessible, the surrounding edges of insulation shall be positively sealed against
water ingress.
12.11 Double layer construction shall be required when operating temperatures are over
300°C and/or the insulation thickness is greater than 100mm. Insulation installed in two
or more layers shall be staggered joint construction and each layer shall be adequately
secured in place.
12.12 Insulation shall be applied in large regular pieces cut to size where necessary and firmly
butted together to minimise voids, and to keep edges of material under compression.
Circumferential joints shall be staggered by one half sections.
12.13 Wet or damaged insulation shall not be used under any circumstances. Installed
material awaiting its protective cover shall be adequately protected from damage, rain,
and contamination by other trades such as oils, spent welding rods, paint etc.
12.14 A minimum clearance of 25mm between the outside surface of any insulation finish and
adjacent equipment, pipe or structural members shall be maintained. Care shall be
taken where insulation is shop applied to ensure this minimum clearance.
12.15 Where voids occur in the insulation they shall be filled with suitable fibrous loose fill
material. Loose fill used for shop applications shall be protected from possible damage
during subsequent lifting and transporting.
12.16 Where installed, expansion joints shall comprise of compressible mineral fibre of
sufficient density and composition to operate efficiently as both insulant and expansion
facility at the given operating temperatures.
12.17 Insulation supports shall not project proud of the insulation outer surface and shall be
given sufficient coverage of insulating material to avoid hot spots on the insulation
metallic weatherproof cover at support positions.
12.18 Weatherproof jacket shall be designed and installed to shed water at ALL times. Flat
horizontal surfaces are not acceptable. It shall be borne in mind throughout shop
application that sloping planes in shop conditions may possibly become flat surfaces
when finally positioned at site and continuous care shall be taken to ensure that final
orientation is known by the Insulation Applicator.
13.1 Preformed insulation shall be applied, supported and secured to straight length single
pipe runs using two half sections up to the maximum manufactured sizes, above this
size piping shall be insulated with the minimum number of cut segments.
13.2 Insulating material shall be applied to fit snugly against the contours presented to the
applicator and neatly cut and shaped only where necessary to achieve this requirement.
The insulation shall be carried out with the least number of material pieces as possible
and all unavoidable gaps, cavities, and voids shall be suitably filled with compatible
13.3 Shop fabricated piping shall be amply supported and positioned in such a manner that
allows complete all-round uninterrupted access to the work piece. At temporary support
points during shop fabrication, insulation shall be terminated and sealed and closure
pieces fabricated for later installation at site.
13.4 The insulation materials shall be secured to the pipes by means of circumferential tie
wires or bands in accordance with the following:
Pipe 250mm (10”) to 500mm (20”) NB – 12mm wide diameter stainless steel
bands
Pipe above 500mm (20”) NB and Equipment Shells – 20mm wide diameter
stainless steel bands
Tie wires or bands shall be positioned sufficient to provide three ties or securing
positions for each length of pipe insulation section. Ends of tie wires shall be turned into
the insulation material.
13.5 Each layer of insulation on piping requiring two or more layers shall be secured in
exactly the same method as required by paragraph 13.4 above. Joints of each layer
shall be offset by staggering.
13.6 Where necessary the insulation on vertical or near vertical piping (i.e. greater than 45o
angle from horizontal) shall be supported by bolted-on metal clips provided and installed
by the Insulation Applicator who shall assume responsibility of adequate pipe insulation
support. Support positions shall be at no greater distance apart than the following:
oC mm
Up to 370 4500
Where multilayer insulation is used, supports shall be extended to provide for each
layer. If support positions are used to create expansion joints, care shall be taken to
ensure that expansion joints in each layer shall be offset at least 150mm from each
other.
13.7 Over pipe bends and elbows the insulation shall be correctly sized mitre cut pipe
sections or segments to suit the contour of the bends without gaps and ill-fitting pieces.
The mitred pieces shall be secured in place with at least two ties per complete mitred
collar of insulation.
13.8 Preformed pipe sections or segments of insulation shall be carefully cut and shaped
around 'tee' junctions and the insulating material of the tangential pipe shall be carefully
and neatly cut to mate up to the material applied to the parent pipe without the creation
of voids or gaps at the junction.
13.9 Insulation shall be stopped short of flanged joints and unions by a sufficient distance to
permit easy removal of the flange nuts and bolts or breaking of the unions to take place
without disturbance to and damage of the insulating material. At these positions the
insulation shall be straight edged and sealed against water ingress with a metal closure.
13.10 Insulation at solid welded or clamped pipe supports shall be cut and shaped to fit around
the support and tied securely to enable the insulation to be carried with the pipe
movement. Pipe supports designed to allow the pipe to move independently shall be
insulated to allow movement to take place without damage to the insulating material.
13.11 Traced pipe and fittings shall be insulated with oversized insulating sections to allow
accommodation of both parent pipe and tracer without damage or deformation of the
insulation. Traced instrument lines and fittings shall be totally enclosed by the insulation
in a similar manner and the designed warm air annulus shall be maintained throughout
the traced pipe length.
13.12 Where specified, valves and flanged joints shall be insulated with lined removable
covers held into position with 12mm wide stainless steel bands or quick release toggle
clips. Designs of these covers shall be submitted to Contractor for approval prior to
fabrication. Insulated valves shall be completely covered, but the insulation shall be cut
and shaped around the valve stem and kept clear of the stuffing-box gland. Insulation
covers shall overlap and totally enclose the sealed ends of piping insulation.
13.13 The piping insulation protective metal sheeting finish shall provide a weatherproofed and
mechanical damage resistant covering over the whole of the insulated areas and be
applied and fitted in such a manner as to provide a close fitting assembly without gaps.
13.14 Straight pipe shall have metal jacketing cut and machine rolled (approx. 1-metre-long)
wrapped around, with 50mm minimum overlaps on both longitudinal and circumferential
overlaps. All laps shall be arranged to shed water.
13.15 A single ball swage shall be made on all circumferential overlaps. Longitudinal overlaps
shall be 'cracked' with a 45° angle inward turn of the overlapping edge to ensure a tight
metal to metal contact.
13.16 At all operating temperatures the seams at overlap positions shall be rendered
watertight by the use of a metal seam sealer which shall be applied between
overlapping metal edges in sufficient quantity and care to ensure that insulation remains
dry and unwetted whether the possible water impingement is from rain, hose, or fire
sprinklers.
13.17 The metal covering shall be secured tightly around the insulated pipe and held in place
with 12mm wide stainless steel bands on a maximum of 300mm centres. One band
shall be located on each circumferential lap and the distance between laps divided at
equal band spacings. The band securing seals shall be kept neatly in line and
positioned away from viewing angles as much as is possible.
13.18 Vertical overlaps on vertical or near vertical piping shall be staggered to provide
overlaps at 'North' and 'South' positions in alternate sections of covering.
13.19 Each section of metal covering on vertical piping with insulation OD's larger than 250mm
shall be supported from the next lower section with two 'S' clips fabricated from banding
material. The 'S' clips shall be of sufficient length to allow the minimum overlap of
50mm.
13.20 On vertical piping with insulation OD's of 600mm and larger, the securing bands shall be
supported by 'J' clips fabricated from banding material. The 'J' clip spacing shall be a
minimum of two per band. All 'J' clips shall be screwed into position and secured.
13.21 Insulated bends and elbows in piping 80mm and larger, shall be metalled with 'lobster
back' segments using 10mm minimum ball swage to assist shaping. The metal bands
shall be screwed with self-tapping screws and include metal sealants to provide a
completely waterproofed arrangement.
13.22 Insulated bends and elbows in piping smaller than 80 mm may use complete pressed
humped back flat metal elbows or fabricated 'stove pipe' elbows but these fitments shall
be completely and positively waterproofed.
14.1 The insulation over equipment shall be supported by rings, bars, clips etc., welded and
fitted to the metal surfaces by the equipment fabricators. Maximum use shall be made
of these provisions by the Insulation Applicator.
14.2 Sections and slabs shall be cut and shaped to fit the equipment contours using the
minimum number of insulating pieces.
14.3 With the exception of vertical vessel bottom heads as specified in section 6.3, the heads
of equipment shall be insulated with preformed material of a form best suited to the
curvature of the equipment.
14.4 Insulating material shall be secured to equipment items by means of 20mm wide
stainless steel bands at 300mm maximum centres. Bands shall be machine stretched
and tensioned to take out slack only.
14.5 The bottom heads of vertical vessels shall be insulated with flexible wire-backed
mattress. These shall be fixed by wires to the support clips provided on the vessel head
and radial bands.
14.6 Insulation securing bands on equipment larger than 2135mm outside diameter shall be
provided with expansion sections at 7620mm maximum spacing.
14.8 Expansion gaps shall be provided on horizontal equipment with mineral fibre as
described in paragraph 14.7 above being compressed between joints of the equipment
insulation at 3660mm maximum intervals.
14.9 Where specified; pump casing, turbines, compressors, equipment flanges, nozzles,
channel covers, manway and handhole flanged covers shall be insulated with lined
removable prefabricated covers secured with 20mm wide stainless steel bands or quick
release toggle clips. Design to be approved by Contractor as in 14.12 below.
14.10 Insulation shall be stopped short of uninsulated flanges and nozzles etc., a sufficient
distance to permit withdrawal of bolts without disturbing the remainder of the insulation.
Insulation shall be weatherproofed and sealed at these positions.
14.11 Insulated bottom heads of shop insulated vertical equipment with fully enclosed support
skirt, shall be provided with temporary weather resistant protection which shall efficiently
prevent the ingress of water and weather during transportation, storage and lifting.
14.12 The insulation over pumps, compressors and turbines shall be in the form of lined
removable metal covers. Design of the covers shall be submitted and approved by
Contractor prior to fabrication. Removable covers shall be fabricated by the Insulation
Applicator and be made up in sizeable pieces designed to be quickly and easily taken
apart and reassembled. In the fully assembled state lined covers shall represent an
efficient, weatherproof, waterproof and sound resistant covering.
14.13 The protective metal weatherproof jacket over vertical vessel shells shall be constructed
of rectangular sheet metal panels applied in a "wallpaper" pattern with the short width of
panel in a circumferential direction parallel to the equipment insulation support rings and
the longer length of panel in a parallel direction to the vessel centre line. The weight of
the panel shall be taken on the equipment insulation support rings, via angle brackets
bolted to the panel in accordance with Fig 3. There shall be a minimum of two brackets
per panel. Shop applied insulation shall ensure that angle brackets remain in contact
with support rings. The short width of panel shall be rolled to suit the outside curvature
of the vessel insulation. The long side of panel shall be cut to suit the distance between
insulation support rings.
14.14 The panels shall be applied commencing at the bottom of the vessel. Each
circumferential ring of panels shall be tensioned by means of temporary tensioning
bands until the final joint is screwed tight. 'S' clips shall be used as sheeting support at
unscrewed circumferential overlaps. 'S' clips shall be riveted into position on shop
applied systems, to prevent slippage during transportation.
14.15 The panels shall be held tight over the vessel insulation by means of circumferential
20mm wide stainless steel bands and seals. The bands shall be positioned on all
horizontal overlaps and at 450mm centres. Bands shall be held in their relative
positions with 'J' clips and be machine stretched and sealed to remove slack only.
14.16 The panels shall have a minimum overlap of 80mm on both horizontal and vertical
edges. The overlaps shall be arranged to shed water at all times.
14.17 The vertical overlaps shall be secured with self tapping screws at 75mm pitch, these
shall be constructed with a 150mm overlap. All overlaps shall be rendered watertight by
use of a metal sealant positioned between overlapping metal edges.
14.18 All equipment projections such as nozzles, shall have the metal jacketing sealed using a
metal flashing cut to fit the projection and extend over the jacket by at least 75mm. The
seal between the flashing and jacket shall be made water tight by use of self tapping
screws and metal sealing mastic.
14.19 Horizontal cylindrical equipment shall be finished with flat metal jacket arranged in
circumferential bands with the edge of the sheets with the longer dimension applied
around the circumference of the equipment insulation.
14.20 The panels shall have a minimum of 75mm overlap on both longitudinal and
circumferential edges, both overlaps being finished with a simple ball swage and
rendered water tight with a metal seam sealer applied between overlapping metal
edges.
14.21 Horizontal overlaps shall be secured with No. 8 x 15mm long, self tapping screws set in
the overlap at 75mm intervals, and shall be so arranged that staggered bands of
panelling encircle the equipment. Vertical overlaps shall not be screwed.
14.22 The metal protective finish shall be banded and sealed at 450mm centres ensuring that
one band is set over each vertical overlap.
14.23 The insulated heads of vertical and horizontal equipment shall be fabricated from flat
metal in an "orange peel" construction with all radial seams overlapping a minimum of
50mm and secured with self tapping screws at 75mm centres. All overlaps shall be ball
swaged and be rendered water tight by the use of metal seam sealer between metal
overlaps.
14.24 Projections from the heads shall be sealed using metal flashings neatly cut to fit around
the projections and extending over the jacket for a minimum of 75mm. The seal
between flashing and jacket shall be weatherproofed with self tapping screws and seam
sealing mastics.
14.25 Insulation on bottom heads of fully skirted equipment does not require weatherproofing.
(See para. 14.11 re-temporary shop insulated covering).
14.26 Heads of equipment 550mm OD and smaller shall be finished and waterproofed with
square ended fabricated covers.
14.27 On shop insulated items at temporary shop supports, the insulating system shall be
terminated and sealed, and closure pieces shall be designed and fabricated to fit the
open positions. Designs of closure pieces shall take into account the insulating
requirements together with support and securement and the necessity of maintaining
waterproofing and weatherproofing after closures are in place. Design proposals shall
be approved by Contractor before fabrication of closures commences. Closure pieces
shall be fitted at site by the site appointed Insulation Applicator.
15.1 Method of installing insulation of tanks shall be similar to the vertical equipment
insulation with the following exceptions:
15.2 The lower 300mm (minimum) of the shell from foundation to top shall be insulated with
cellular glass and the remainder of the shell shall be insulated with mineral fibre blanket
or board type insulation. Cellular glass material shall in accordance with ASTM C552.
15.3 Vertical (pencil) rods used to secure the insulation and jacketing material shall be
installed by the tank fabricator. Bands used to secure insulation and weatherproofing
jacket shall be secure to vertical rods.
15.4 The insulation gaps over the pencil rods shall be completely filled with blanket type
insulation and a strip of weatherproofing jacket shall be installed over the insulation and
held in place with the screws spaced on 150mm centres on the adjacent insulation
weatherproofing. The minimum overlap of the strip on the adjacent jacket shall be
150mm on both vertical sides. Strips shall overlap each other a minimum of 150mm and
shall be arranged to shed water.
15.5 Only closed (crimp type) seals shall be used for bands. Wing type seals are not
allowed. The maximum distance between bands shall not exceed 300mm. Expansion
(breather) springs shall be provided with angle cleats bolted to the stainless steel bands
to allow for the thermal movements of the tank. The expansion spring spacing shall be
calculated based on operating conditions of each tank, but shall be a minimum of 2 per
band and/or every 9m maximum.
15.6 Shop fabricated tank insulation panels may be used subject to the Contractor/Company
approval. Details of the panels shall be submitted for Contractor and Company’s
approval prior to sue. If roof insulation is required the Applicator shall submit proposals
based on the size, shape and flex, operating temperature and roof stiffeners of each
tank requiring insulation to be agreed upon by Contractor.
The Applicator shall submit to Contractor for approval, his proposed quality control and
testing procedures for all factory and/or field manufactured insulation
materials/components.
The Inspection and Test Plan shall reference all test procedures, witness points,
acceptance/rejection criteria, frequency of testing and how control of quality is measured
and maintained.
Where appropriate, results shall be plotted on statistical control charts showing upper
and lower limits of acceptance.
Manufacturers of all materials shall supply test certificates indicating all test results of
the applicable tests required by this specification.
16.2 Inspection
The Applicator shall advise Contractor and allow ample notice before commencing
specific insulation applications.
The Contractor’s Inspector shall be afforded all reasonable facilities for carrying out his
duties in verifying that the insulation is executed in accordance with the specified
requirements.
The Contractor’s Inspector shall have the right to inspect and test the insulation and
cladding at all stages, including any subsequent repairs; and to reject any and all tools,
instruments, materials, staging, equipment or work which does not conform to the
specification.
The Applicator shall be responsible for the repair of any minor defects or localised
replacement of insulation and cladding, where this becomes necessary in the course of
inspection by the Contractor.
Prior to final acceptance of completed work, a joint inspection shall be made by the
Applicator and Contractor and an agreed inspection report signed by both parties.
In the case of major defects, rectification shall involve more extensive removal and
replacement of the insulation system, at the discretion of Contractor’s Inspector.
Where the insulation and/or cladding has sustained damage attributable to the
Applicator, the affected areas shall be removed and replaced.
materials should not be unpacked from their containers until required for use at the job-
site. Packaging should be marked with type of material, size, thickness, quality and
quantity.
Packaging should allow for materials to be handled such that the risk of mechanical
damage is minimized. Stacking heights of material shall be limited to avoid crushing of
lower layers.
17.2 Storage
All forms of insulation must be kept dry and protected from damage and shall be stored
in dry weatherproof stores. Manufacture and storage methods used shall be adequate
to protect the insulation materials and accessories from degradation for at least 12
months.
18. FIGURES
Figure 1: PIPING (1 OF 4)
Figure 1: PIPING (2 OF 4)
Figure 1: PIPING (3 OF 4)
Figure 1: PIPING (4 OF 4)
up to 8 inch 50
> 8 inch or flat surfaces 100