A. Dechter
Chapter 6 - Solutions
Problem 1:
b. The mean of the sampling distribution is the average of the sample means
x = Mean = (5.95+6+5.95+5.975)/4 = 5.97
The standard deviation of the sampling distribution is computed as . The population
n
standard deviation can be estimated from the 4 samples using the equation:
n
(x
i 1
i x) 2
, where n = 16, and X = 5.97, therefore = 0.1138
n 1
(Note: that in this case the standard deviation is not given, but estimated from the data
collected. We did not cover this method in the class so if the standard deviation is not
given use the alternative method.)
The standard deviation of the sampling distribution of the sample means is equal to
0.0569 which is estimated using , where = 0.1138, and n = 4 (i.e., the number of
n
observations in each sample).
1
SOM 306 – Operations Management
A. Dechter
Problem 4:
Sample
Sample 1 2 3 4 Mean Range
1 16.40 16.11 15.90 15.78 16.05 0.62
2 15.97 16.10 16.20 15.81 16.02 0.39
3 15.91 16.00 16.04 15.92 15.97 0.13
4 16.20 16.21 15.93 15.95 16.07 0.28
5 15.87 16.21 16.34 16.43 16.21 0.56
6 15.43 15.49 15.55 15.92 15.60 0.49
7 16.43 16.21 15.99 16.00 16.16 0.44
8 15.50 15.92 16.12 16.02 15.89 0.62
9 16.13 16.21 16.05 16.01 16.10 0.20
10 15.68 16.43 16.20 15.97 16.07 0.75
X-bar Chart
16.40
16.20
16.00
15.80
15.60
15.40
15.20
1 2 3 4 5 6 7 8 9 10
Sample Number
2
SOM 306 – Operations Management
A. Dechter
R-Chart
1.20
1.00
0.80
0.60
0.40
0.20
0.00
1 2 3 4 5 6 7 8 9 10
Sample Number
b. The process is not capable of meeting the design standards. Design standards dictate that
fill levels range between 16.3 ounces and 15.7. There are nine observations that do not
fall in this range.
Problem 6:
X-bar Chart
12.4
12.2
12
11.8
11.6
11.4
11.2
11
1 2 3 4 5
Sample Number
3
SOM 306 – Operations Management
A. Dechter
R-Chart
1.4
1.2
1
0.8
0.6
0.4
0.2
0
1 2 3 4 5
Sample Number
R-Chart is in control, but since X-bar chart is not in control, then the process is not in control.
Problem 7:
6
CL = P = = 0.06
100
0.06(1 0.06)
UCL = 0.06 +3 = 0.22
20
0.06(1 0.06)
LCL = 0.06 -3 = 0 (rounded to zero since the LCL value is negative)
20
Problem 8:
18
a. CL = p = = 0.09
200
(0.09)(0.91)
p= = 0.064
20
UCL = 0.09 + 3(0.064) = 0.282
LCL = 0.09 – 3(0.064) = - 1.02 = 0
4
SOM 306 – Operations Management
A. Dechter
b.
P-Chart
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
1 2 3 4
Sample Number
Problem 10: