B.

SITE MATERIALS REQUIREMENT CHART


PROJECT TITLE: CONSTRUCTION OF 3 STOREYS RESIDENTIAL APARTMENT IN
GACULIRO, GASABO DISTRICT
ITEM SITE MATERIALS
No ACTIVITY DESCRIPTION QTY
office furniture ls
site store & offices ls
provision of plants & equipment
concrete mixers 4
1 PRELIMINARY WORK
provision of site sanitation ls
provision of first aid post

provision of water and power to site


Provision of directional signs and sign
boards.

TOTAL 
SHEET No 001

JOB: SITE PREPARATION


MATERIALS
unit RATE AMOUNT

23,500,000
B. SITE MATERIALS REQUIREMENT CHART
PROJECT TITLE: CONSTRUCTION OF 3 STOREYS RESIDENTIAL APARTMENT
IN GACULIRO, GASABO DISTRICT
SITE MATERIALS
ITEM No ACTIVITY DESCRIPTION QTY
cement 519
reinforcement
 Aggregates 85
 sand 55
2 STRUCTURE WORK  rubble 69
 scaffolds 400
DPC 350
DPM 444

TOTAL 
SHEET No 002

JOB: CONCRETE STUCTURE


SITE MATERIALS
unit RATE AMOUNT
bags 10500 5,449,500
SM 600000 0
CM 40000 3,400,000
CM 16000 880,000
CM 25000 1,725,000
SM 7500 3,000,000
CM 800 280,000
SM 1000 444,000

 67,682,500
B. SITE MATERIALS REQUIREMENT CHART
PROJECT TITLE: CONSTRUCTION OF 3 STOREYS RESIDENTIAL
APARTMENT IN GACULIRO, GASABO DISTRICT
SITE MATERIALS
ITEM No ACTIVITY DESCRIPTION
cement
reinforcement
 Aggregates
2 STRUCTURE WORK
 sand
 scaffolds

TOTAL 
B. SITE MATERIALS REQUIREMENT CHART
SHEET No 003 PROJECT TITLE: CONSTRUCTION OF 3 STORE
REYS RESIDENTIAL RESIDENTIAL APARTMENT IN GACULIRO, GAS
BO DISTRICT JOB: CONCRETE STRUCTURE DISTRICT
SITE MATERIALS
QTY unit RATE AMOUNT ITEM No ACTIVITY
448 bags 10500 4,704,000
ton 600000 0
72 CM 40000 2,880,000
2 STRUCTURE WORK
45 CM 16000 720,000
420 SM 12500 5,250,000

AL   67,682,500 TOTAL 


QUIREMENT CHART
CONSTRUCTION OF 3 STOREYS SHEET No
RTMENT IN GACULIRO, GASABO
DISTRICT JOB
SITE MATERIALS
DESCRIPTION QTY unit RATE AMOUNT
cement 448 bags 10500 4,704,000
reinforcement ton 600000 0
 Aggregates 72 CM 40000 2,880,000
 sand 45 CM 16000 720,000
 scaffolds 420 SM 12500 5,250,000

TOTAL   67,682,500
B. SITE MATERIALS REQUIREMENT CHART
PROJECT TITLE: CONSTRUCTION OF 3 STOREYS SHEET No
RESIDENTIAL APARTMENT IN GACULIRO, GASABO
DISTRICT JOB
SITE MATERIALS
ITEM No ACTIVITY DESCRIPTION QTY unit RATE AMOUNT
cement 448 bags 10500 4,704,000
reinforcement ton 600000 0
 Aggregates 72 CM 40000 2,880,000
2 STRUCTURE WORK
 sand 45 CM 16000 720,000
 scaffolds 420 SM 12500 5,250,000

TOTAL   67,682,500
B. SITE MATERIALS REQUIREMENT CHART
PROJECT TITLE: CONSTRUCTION OF 3 STOREYS SHEET No
RESIDENTIAL APARTMENT IN GACULIRO, GASABO
DISTRICT JOB
SITE MATERIALS
ITEM No ACTIVITY DESCRIPTION QTY unit RATE
cement 448 bags 10500
reinforcement ton 600000
 Aggregates 72 CM 40000
2 STRUCTURE WORK  sand 45 CM 16000
 scaffolds 420 SM 12500

TOTAL 
LS
AMOUNT
4,704,000
0
2,880,000
720,000
5,250,000

 67,682,500
A.    LABOUR RECRUITMENT CHART
PROJECT: CONSTRUCTION OF 4 STOREYS RESIDENTIAL APARTMENT IN GACULIRO, GASABO DISTRICT
HEADMAN CRAFTSMEN
QTY RATE
ITEM ACTVITY QTY RATE AMOUNT day AMOUNT
1 Excavation 2 7000 14,000  - -  -
Structure work 6 7000 42,000 40 5000 200000
foreman 1 10000 10,000 0
ART SHEET No……………………
LIRO, GASABO DISTRICT JOB……………………………
CASUAL LABOURERS ESP No
TOTAL
QTY RATE DAILY Days GRAND
day AMOUNT COST TOTAL
40 2500 100000 114,000 25 2850000
80 2500 200000 442,000 100  7,450,000
 -  -  - 10,000 125 1250000

4100000
project:
date: labour
item activity type qty dura- unit rate amount
# tion RWF RWF
Site organization
,,
,,
1 ,,
,,
,,
,, -
2 Escavation work foreman 1 25 day 10,000 250,000
,, kapitas 2 25 day 7,000 350,000
,, craftsmen 0 25 day 5,000 -
,, casual 40 25 day 2,500 2,500,000
4 Structure work foreman 1 100 day 10,000 1,000,000
,, kapitas 6 100 day 7,000 4,200,000
,, craftsmen 40 100 day 5,000 20,000,000
,, casual 80 100 day 2,500 20,000,000
,, -
,, -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
labour total 48,300,000
subject:
materials equipment
descripyion qty unit rate amount description qty duration
RWF RWF
workshop
First aid kit
safety
tools 1 ls 23,000,000 23,000,000
acilities
power&water
site stores&office
- truck to carry soil 3 20.0
- compactor 1 2.0
- excavator 1 80.0
- concrete mixers 4_
cement 2325 bag 10,500 24,412,500 scaffolds 400 5.0
reinforcement ton 600,000 - formwork (2) 420 1
aggregates 380 m3 40,000 15,200,000 formwork (3rd) 420 1
sand 240 m3 16,000 3,840,000 formwork (4th) 420 1
Rubble stones 75 m3 25,000 1,875,000 formwork (5th) 420 1

-
-
-
-
-
-
-
-
-
-
-
-
-
materials total 45,327,500 equipment
sheet#:
equipment subcon-
unit rate amount tracting
RWF total
RWF RWF RWF

23,000,000

day 120,000 7,200,000 7,450,000


day 75,000 150,000 500,000
hrs 200,000 16,000,000 16,000,000
lp 2,500,000 10,000,000 12,500,000
month 7,500 15,000,000 40,412,500
m2 12,500 5,250,000 9,450,000
m2 12,500 5,250,000 40,450,000
m2 12,500 5,250,000 29,090,000
m2 12,500 5,250,000 7,125,000
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
equipment total 69,350,000 - 185,977,500
Grand Total 185,977,500