SS0838- Daily Erection Report

Date:24-10-2015 EDR#3
Attendance:
Indict No. Direct No. Equipment No
Construction Manager Foreman 1 Crane 70 ton 1
Project Site Manager 1 Crane Operator 1 Man-lift 41m 1
QC Engineer 1 Manlift Operator 2 Crane 60 ton 1
Supervisor 1 Forklift Operator Trailers 2
Store Keeper 1 Rigger3 1
Driver (Other) 1 Erectors 6
Safety Manager 1 Helpers 3
Welders
Fabricators
Painters
Safety Officer 2

Total:

Building Name: Process Building E&F


Mark# Qty Unit Weight,kg Total Weight, kg Mark# Qty Unit Weight,kg Total Weight, kg
Q5-1 3 31.241 93.723
Q8-1 7 11.242 78.694

Total Quantity=10pcs Total weight=172.417kg Delivered weight up to 25-oct=3444.85605ton


Area of concern:
S.N. Issue detail Date Action by
1- Through bolts are still not fixed with grout at E-portion at level +112m. DGC
2- There is no safe access to install level +105m. DGC
E-Portion at process building still arenot clear and ready for structural work. DGC
3-

4- ZAMIL-SICC require the packing list of bolts which were delivered by DGC. DGC
Prepared by: Eng Moayyad Alhoyan.
Check by: Eng Omar Alhassan.
Approved by: