Sie sind auf Seite 1von 3

GENERAL SPECIFICATION

PIPELINES - RISERS

Installation of steel pipeline by horizontal


directional drilling
Contents

1. Scope ....................................................................................................................... 3

2. Reference documents............................................................................................. 3

3. General..................................................................................................................... 4
3.1 Definitions ..........................................................................................................................4
3.2 Local Authorities ................................................................................................................5

4. Performance of the Work........................................................................................ 5


4.1 Management......................................................................................................................5
4.2 Engineering........................................................................................................................6
4.3 Survey..............................................................................................................................11
4.4 Site preparation ...............................................................................................................11
4.5 Drilling..............................................................................................................................12
4.6 Reaming ..........................................................................................................................12
4.7 Pipe pulling ......................................................................................................................13
4.8 Pipe pre-commissioning ..................................................................................................14
4.9 Reinstatement..................................................................................................................14
4.10 As-built.............................................................................................................................14

5. Equipment/Material ............................................................................................... 15

6. Safety ..................................................................................................................... 16
6.1 Safety assessment ..........................................................................................................16
6.2 Implementation on site.....................................................................................................16

7. QA/QC .................................................................................................................... 16
7.1 General ............................................................................................................................16
7.2 Inspection ........................................................................................................................17

8. Documentation ...................................................................................................... 17

Appendix 1 Sketch of HDD ...................................................................................... 18

Appendix 2 Content of daily reports and logs ....................................................... 19


1. Scope
This specification covers the minimum requirements for the installation of pipelines by
Horizontal Directional Drilling technique. This specification excludes the fabrication of the pipe
string (covered by an other specification).
This general specification shall be considered as a framework stating the technical guidelines of
the COMPANY and may be completed by a particular specification detailing specific aspects of
the works.
While remaining within the requirements of the specification, alternative methods and drawings,
other than those specified here, may be proposed. These alternatives must be properly justified
(preferably based on previous experience) and will be subject to approval by the COMPANY.

2. Reference documents
The reference documents listed below form an integral part of this General Specification. Unless
otherwise stipulated, the applicable version of these documents, including relevant appendices
and supplements, is the latest revision published at the EFFECTIVE DATE of the CONTRACT.
Pipeline installed by HDD may be considered as submerged and consequently offshore
code/specification may apply.
Detail design and construction work shall be carried out in accordance with one the following
Standard, unless otherwise specified by COMPANY and in accordance with appropriate
sections of the specifications and standards listed below.
Differences that could occur between this general specification and the references shall be
brought to the COMPANY’s notice for clarification.

Standards

Reference Title
API RP 1111 Design, Construction, Operation, and Maintenance of Offshore
Hydrocarbon Pipelines
API 5L Specification for Line Pipe
API 5LW Recommended Practice for Transportation of Line Pipe on Barges
and Marine Vessels.
API 1104 Standard for Welding Pipelines and Related Facilities
BS 4515 Process of Welding of steel pipelines on land and offshore
ISO 9001
ISO 9002

Professional Documents

Reference Title
DnV 81 Rules for Submarine Pipeline Systems, 1981

Das könnte Ihnen auch gefallen