Sie sind auf Seite 1von 6

PT.

SUCI ENERGI SOLUSI INDONESIA (SEISO INDONESIA)


Jl. Raya Berlian Biru No. 20, Pondok Permata Suci Manyar - Gresik 61151
Telp: 031-39924654, Fax : 031-39924654

Prepared for:
Attention: Mr. Agus Salim Date: 4/30/2020
Company: PT. Gresik Power Indonesia Quotation Number: QO-2020-011 R5
Address: Jl. Raya Roomo, Kecamatan Manyar Customer ID: GPI
Gresik, East Java 61151
Telp: Prepared by: GANES PUTRA ANGGARA
Fax: Telp: +62 821 4334 6075
E-mail: Agus.Salim@Linde.com E-mail: ganes.seiso@gmail.com

Unit Rate Unit Price Sub Total Total Price


No. Description
Qty Unit IDR IDR IDR

Tank cleaning, Inspection, Coating, and Repair

1 Tank Cleaning ( Follow API 2016 ) 1 LOT 125,000,000 125,000,000 125,000,000


Diameter : 12.4 meter
Height : 12.1 meter
Scope of work :
1. Transfer remaining product
2. Desludging - remove sludge
3. Closed loop cleaning
4. Wall wash test
2 Waste Disposal completed with manifest 20 m3 3,500,000 70,000,000 70,000,000

3 Tank Inspection ( Follow API 653 ) 1 LOT 120,000,000 120,000,000 120,000,000


- NDT : thickness, PT, MPI
- Vacuum Box Test
- Magnetic Flux Leakage (MFL)

4 Internal Tank Surface Coating


Area: 180 cm elevation from bottom plate section
- Sand Blasting Application (SSPC-SP 10) Near White Metal 212.64 m2 466,785 99,257,162 99,257,162
Blast Cleaning
- Paint Material 212.64 m2 753,250 160,171,080 160,171,080
- Abrassive Material 212.64 m2 277,150 58,933,176 58,933,176
- Scaffolding 1 Lot 5,750,000 5,750,000 5,750,000
- Manpower 1 Lot 6,900,000 6,900,000 6,900,000
SUB TOTAL 331,011,418

5 Tank Repair
- External based plate sealant / sika 1 Ls 22,243,760 22,243,760 22,243,760
- External based concrete repair 1 Ls 30,585,170 30,585,170 30,585,170
- Rubber sealing on concrete groove 1 Ls 39,149,018 39,149,018 39,149,018
- Provide a tubing hole at breather nozzle for N2 blanket
1 Ls 7,392,000 7,392,000 7,392,000
feeding, 1" ANSI 150
SUB TOTAL 99,369,948

TOTAL IDR 745,381,366

Costumer scope of work :


- Water for cleaning - Plant air
- Electrical supply (generator) - Crane/forklift

Contractor scope of work :


- Tank cleaning - Manpower - Scaffolding
- Tank Inspection - PPE & consumable
- Tank coating - Chemical

- Paint material : By International Paint


- Application : By Spray and/or Roller
- Paint Specification :
Coat No
No. Surface Preparation Generic Type Product Name Total (DFT)
Internal Tank
1 Primer Coat SSPC - SP10 (Near White Metal Blast Cleaning) Epoxy Phenolic (1x500µ) Interline984
1000µ
2 Top Coat SSPC - SP2 (Hand Tool Cleaning) Epoxy Phenolic (1x500µ) Interline984

Remarks:
- Term of Payment :
Down Payment : 30% IDR 223,614,410 (After PO Released)
Payment 2 : 70% IDR 521,766,956 (After Work Completed)
IDR 745,381,366
- Work Duration : 16 days
- Validity : 30 days

Term and Condition:


1 This price is exclude VAT 10%
2 Payment: follow remarks above
3 Acceptance: This quotation can be used as an official purchased order, if desired. Simply sign below to agree to all pricing,
terms and condition, and send completed form to fax: +62 31 9924654 or e-mail: marketing.seiso@yahoo.com

Acceptance of Quotation: Prepared by: Approved by:

Name:
Position: Ganes Putra A. A. Zainul Abidin
date: Cost Estimator Director
PT. SUCI ENERGI SOLUSI INDONESIA (SEISO INDONESIA)
Jl. Raya Berlian Biru No. 20, Pondok Permata Suci Manyar - Gresik 61151
Telp: 031-39924654, Fax : 031-39924654

Prepared for:
Attention: Mr. Agus Salim Date: 4/30/2020
Company: PT. Gresik Power Indonesia Quotation Number: QO-2020-011 R4
Address: Jl. Raya Roomo, Kecamatan Manyar Customer ID: GPI
Gresik, East Java 61151
Telp: Prepared by: GANES PUTRA ANGGARA
Fax: Telp: +62 821 4334 6075
E-mail: Agus.Salim@Linde.com E-mail: ganes.seiso@gmail.com

Unit Rate Unit Price Sub Total Total Price


No. Description
Qty Unit IDR IDR IDR

Tank cleaning, Inspection, Coating, and Repair

1 Tank Cleaning ( Follow API 2016 ) 1 LOT 125,000,000 125,000,000 125,000,000


Diameter : 12.4 meter
Height : 12.1 meter
Scope of work :
1. Transfer remaining product
2. Desludging - remove sludge
3. Closed loop cleaning
4. Wall wash test
2 Waste Disposal completed with manifest 20 m3 3,500,000 70,000,000 70,000,000

3 Tank Inspection ( Follow API 653 ) 1 LOT 120,000,000 120,000,000 120,000,000


- NDT : thickness, PT, MPI
- Vacuum Box Test
- Magnetic Flux Leakage (MFL)

4 Internal Tank Surface Coating


Area: 180 cm elevation from bottom plate section
- Sand Blasting Application (SSPC-SP 10) Near White Metal 212.64 m2 466,785 99,257,162 99,257,162
Blast Cleaning
- Paint Material 212.64 m2 753,250 160,171,080 160,171,080
- Abrassive Material 212.64 m2 277,150 58,933,176 58,933,176
- Scaffolding 1 Lot 5,750,000 5,750,000 5,750,000
- Manpower 1 Lot 6,900,000 6,900,000 6,900,000
SUB TOTAL 331,011,418

5 Tank Repair
- External based plate sealant / sika 1 Ls 27,804,700 27,804,700 27,804,700
- External based concrete repair 1 Ls 47,267,990 47,267,990 47,267,990
- Rubber sealing on concrete groove 1 Ls 73,404,408 73,404,408 73,404,408
- Provide a tubing hole at breather nozzle for N2 blanket
1 Ls 30,800,000 30,800,000 30,800,000
feeding, 1" ANSI 150
SUB TOTAL 179,277,098

TOTAL IDR 825,288,516

Costumer scope of work :


- Water for cleaning - Plant air
- Electrical supply (generator) - Crane/forklift

Contractor scope of work :


- Tank cleaning - Manpower - Scaffolding
- Tank Inspection - PPE & consumable
- Tank coating - Chemical

- Paint material : By International Paint


- Application : By Spray and/or Roller
- Paint Specification :
Coat No
No. Surface Preparation Generic Type Product Name Total (DFT)
Internal Tank
1 Primer Coat SSPC - SP10 (Near White Metal Blast Cleaning) Epoxy Phenolic (1x500µ) Interline984
1000µ
2 Top Coat SSPC - SP2 (Hand Tool Cleaning) Epoxy Phenolic (1x500µ) Interline984

Remarks:
- Term of Payment :
Down Payment : 30% IDR 247,586,555 (After PO Released)
Payment 2 : 70% IDR 577,701,961 (After Work Completed)
IDR 825,288,516
- Work Duration : 16 days
- Validity : 30 days

Term and Condition:


1 This price is exclude VAT 10%
2 Payment: follow remarks above
3 Acceptance: This quotation can be used as an official purchased order, if desired. Simply sign below to agree to all pricing,
terms and condition, and send completed form to fax: +62 31 9924654 or e-mail: marketing.seiso@yahoo.com

Acceptance of Quotation: Prepared by: Approved by:

Name:
Position: Ganes Putra A. A. Zainul Abidin
date: Cost Estimator Director
PT. SUCI ENERGI SOLUSI INDONESIA (SEISO INDONESIA)
Jl. Raya Berlian Biru No. 20, Pondok Permata Suci Manyar - Gresik 61151
Telp: 031-39924654, Fax : 031-39924654

Prepared for:
Attention: Mr. Agus Salim Date: 4/30/2020
Company: PT. Gresik Power Indonesia Quotation Number: QO-2020-011 R3
Address: Jl. Raya Roomo, Kecamatan Manyar Customer ID: GPI
Gresik, East Java 61151
Telp: Prepared by: GANES PUTRA ANGGARA
Fax: Telp: +62 821 4334 6075
E-mail: Agus.Salim@Linde.com E-mail: ganes.seiso@gmail.com

Unit Rate Unit Price Sub Total Total Price


No. Description
Qty Unit IDR IDR IDR

Tank cleaning, Inspection, Coating, and Repair

1 Tank Cleaning ( Follow API 2016 ) 1 LOT 125,000,000 125,000,000 125,000,000


Diameter : 12.4 meter
Height : 12.1 meter
Scope of work :
1. Transfer remaining product
2. Desludging - remove sludge
3. Closed loop cleaning
4. Wall wash test
2 Waste Disposal completed with manifest 20 m3 3,500,000 70,000,000 70,000,000

3 Tank Inspection ( Follow API 653 ) 1 LOT 130,000,000 130,000,000 130,000,000


- NDT : thickness, PT, MPI
- Vacuum Box Test
- Magnetic Flux Leakage (MFL)

4 Internal Tank Surface Coating


Area: 180 cm elevation from bottom plate section
- Sand Blasting Application (SSPC-SP 10) Near White Metal 212.64 m2 527,670 112,203,749 112,203,749
Blast Cleaning
- Paint Material 212.64 m2 851,500 181,062,960 181,062,960
- Abrassive Material 212.64 m2 313,300 66,620,112 66,620,112
- Scaffolding 1 Lot 6,500,000 6,500,000 6,500,000
- Manpower 1 Lot 7,800,000 7,800,000 7,800,000
SUB TOTAL 374,186,821

5 Tank Repair
- External based plate sealant / sika 1 Ls 32,860,100 32,860,100 32,860,100
- External based concrete repair 1 Ls 55,862,170 55,862,170 55,862,170
- Rubber sealing on concrete groove 1 Ls 86,750,664 86,750,664 86,750,664
- Provide a tubing hole at breather nozzle for N2 blanket
1 Ls 36,400,000 36,400,000 36,400,000
feeding, 1" ANSI 150
SUB TOTAL 211,872,934

TOTAL IDR 911,059,755

Costumer scope of work :


- Water for cleaning - Plant air
- Electrical supply (generator)
- Crane/forklift

Contractor scope of work :


- Tank cleaning - Manpower - Scaffolding
- Tank Inspection - PPE & consumable
- Tank coating - Chemical

- Paint material : By International Paint


- Application : By Spray and/or Roller
- Paint Specification :
Coat No
No. Surface Preparation Generic Type Product Name Total (DFT)
Internal Tank
1 Primer Coat SSPC - SP10 (Near White Metal Blast Cleaning) Epoxy Phenolic (1x500µ) Interline984
1000µ
2 Top Coat SSPC - SP2 (Hand Tool Cleaning) Epoxy Phenolic (1x500µ) Interline984

Remarks:
- Term of Payment :
Down Payment : 50% IDR 455,529,877 (After PO Released)
Payment 2 : 50% IDR 455,529,877 (After Work Completed)
IDR 911,059,755
- Work Duration : 10 days
- Validity : 30 days

Term and Condition:


1 This price is exclude VAT 10%
2 Payment: follow remarks above
3 Acceptance: This quotation can be used as an official purchased order, if desired. Simply sign below to agree to all pricing,
terms and condition, and send completed form to fax: +62 31 9924654 or e-mail: marketing.seiso@yahoo.com

Acceptance of Quotation: Prepared by: Approved by:


Name:
Position: Ganes Putra A. A. Zainul Abidin
date: Cost Estimator Director

Das könnte Ihnen auch gefallen