The worksheet "Basic principles" contains all the relevant information and
details for the other table worksheets.
All the cells highlighted in blue and yellow from the worksheet ”Basic
principles" are connected and will alter the information from all the other
table worksheets.
If you must add columns with numbers due to other components requested
- that are not taken into consideration in this model - make sure that the
data included in these cells will be included in the forms from uncoloured
cells containing data
145
Basic principles for cost calculation
ONLY the cells highlighted in yellow can
be modified by the tenderer
Unit prices
Currency RON
146
Consumables
Electricity
number of
Consumers consumption Operating period Total consumption Specific cost in kWh
units
kW h/year kWh/year RON/kWh
Horizontal conveyor belt with bunker 0.00 0.53
Tilted conveyor belt for supply of the
sorting cabin 0.00 0.53
Horizontal conveyor belt for the sorting
cabin 0.00 0.53
Horizontal conveyor belt for supply of
the baling machine 0.00 0.53
Sorting cabin with ventilation system 1 0.00 0.53
Magnetic separator 1 0.00 0.53
Total electricity
Fuel
number of
Consumers consumption Operating period Total consumption Specific cost in kWh
units
l h/year l/year RON/l
Front loader 2,50 mc 1 0.00 6.00
Front loader 1,10 mc 1 0.00 6.00
Hooklift 1 0.00 6.00
Others 0.00 6.00
Total fuel consumed
Fuel Costs
147
Total costs per year
RON/year
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Annual costs
RON
0.00
0.00
Annual costs
RON
0.00
0.00
147
Staff
148
Operating costs for Sorting station Entry to Sorting Station 6,000 t/a
149
Operating costs of the Sorting Station SS Entrance 6,000 t/a
Monitoring
150
150