Sie sind auf Seite 1von 63

4-STOREY COMMERCIAL B... PRE-CONSTRUCTION PHA... Receive Notice to Proceed and...

Design and Planning


Duration 210 days Duration 29 days Duration 0 days Duration 18 days
Start 1/15/18 8:00 AM Start 1/15/18 8:00 AM Start 1/15/18 8:00 AM Start 1/15/18 8:00 AM
Finish 9/29/18 5:00 PM Finish 2/16/18 5:00 PM Finish 1/15/18 8:00 AM Finish 2/3/18 5:00 PM

CONSTRUCTION PHASE
Duration 170 days
Start 2/19/18 8:00 AM
Finish 9/15/18 5:00 PM

Site Works
Duration 6 days
Start 2/19/18 8:00 AM
Finish 2/24/18 5:00 PM

Sub-Structure
Duration 14 days
Start 2/26/18 8:00 AM
Finish 3/13/18 5:00 PM
Obtain Building Permit
Duration 11 days
Start 2/5/18 8:00 AM
Finish 2/16/18 5:00 PM

Procurement and Sample App...


Duration 11 days
Start 2/5/18 8:00 AM
Finish 2/16/18 5:00 PM

Submit Bond and Insurances


Duration 2 days
Start 2/5/18 8:00 AM
Finish 2/6/18 5:00 PM

Site Grading and Layout Temporary Facilities and Util...


Duration 2 days Duration 4 days
Start 2/19/18 8:00 AM Start 2/21/18 8:00 AM
Finish 2/20/18 5:00 PM Finish 2/24/18 5:00 PM

Excavation
Duration 4 days
Start 2/21/18 8:00 AM
Finish 2/24/18 5:00 PM

Foundation
Duration 6 days
Start 2/26/18 8:00 AM
Finish 3/3/18 5:00 PM
Ground Floor
Duration 20 days
Start 3/14/18 8:00 AM
Finish 4/13/18 5:00 PM
Tie Beam
Duration 6 days
Start 2/26/18 8:00 AM
Finish 3/3/18 5:00 PM

Elevator Pit
Duration 3 days
Start 3/1/18 8:00 AM
Finish 3/3/18 5:00 PM

Superstructure
Duration 103 days
Start 3/14/18 8:00 AM
Finish 7/21/18 5:00 PM

Rough-In floor Utilities (inclu...


Duration 3 days
Start 3/26/18 8:00 AM
Finish 3/28/18 5:00 PM
MEP Rough-In Install Plumbing Underground
Duration 3 days Duration 3 days
Start 3/5/18 8:00 AM Start 3/8/18 8:00 AM
Finish 3/7/18 5:00 PM Finish 3/10/18 5:00 PM

Install Electrical Underground Rough-In and Installation Ins... Quality and Safety Inspection
Duration 3 days Duration 1 day Duration 1 day
Start 3/8/18 8:00 AM Start 3/12/18 8:00 AM Start 3/13/18 8:00 AM
Finish 3/10/18 5:00 PM Finish 3/12/18 5:00 PM Finish 3/13/18 5:00 PM

Column Slab
Duration 6 days Duration 7.375 days
Start 3/14/18 8:00 AM Start 3/21/18 8:00 AM
Finish 3/20/18 5:00 PM Finish 3/31/18 11:00 AM

Install Plumbing Pipe Fittings


Duration 3 days
Start 4/2/18 8:00 AM
Finish 4/4/18 5:00 PM

Electrical Wire Pulling & Acc...


Duration 3 days
Start 4/2/18 8:00 AM
Finish 4/4/18 5:00 PM

Elevator Shaft Wall & Accesory Beam Staircase


Duration 4 days Duration 6 days Duration 3 days
Start 3/14/18 8:00 AM Start 4/2/18 8:00 AM Start 4/10/18 8:00 AM
Second Floor
Duration 28 days
Start 4/10/18 8:00 AM
Finish 5/12/18 5:00 PM
Quality and Safety Inspection
Duration 1 day
Start 3/14/18 8:00 AM
Finish 3/14/18 5:00 PM

Rough-In floor Utilities (inclu...


Duration 3 days
Start 4/19/18 8:00 AM
Finish 4/21/18 5:00 PM
Start 3/14/18 8:00 AM Start 4/2/18 8:00 AM Start 4/10/18 8:00 AM
Finish 3/17/18 5:00 PM Finish 4/7/18 5:00 PM Finish 4/12/18 5:00 PM

CHB Wall
Duration 4 days
Start 4/10/18 8:00 AM
Finish 4/13/18 5:00 PM

Column
Duration 5 days
Start 4/10/18 8:00 AM
Finish 4/14/18 5:00 PM
Slab
Duration 9 days
Start 4/16/18 8:00 AM
Finish 4/25/18 5:00 PM

Install Plumbing Pipe Fittings


Duration 3 days
Start 4/26/18 8:00 AM
Finish 4/28/18 5:00 PM

Electrical Wire Pulling & Acc...


Duration 3 days
Start 4/26/18 8:00 AM
Finish 4/28/18 5:00 PM

ACCU and Exhaust for Groun... Fire Protection Pipes for Grou...
Duration 8 days Duration 6 days
Start 4/26/18 8:00 AM Start 5/7/18 8:00 AM
Finish 5/5/18 5:00 PM Finish 5/12/18 5:00 PM

Beam
Duration 8 days
Start 4/26/18 8:00 AM
Finish 5/5/18 5:00 PM
Third Floor
Duration 30 days
Start 5/7/18 8:00 AM
Finish 6/9/18 5:00 PM
Quality and Safety Inspection
Duration 1 day
Start 5/12/18 8:00 AM
Finish 5/12/18 5:00 PM

Rough-In floor Utilities (inclu...


Duration 3 days
Start 5/17/18 8:00 AM
Finish 5/19/18 5:00 PM
Elevator Shaft & Accessory
Duration 5 days
Start 4/10/18 8:00 AM
Finish 4/14/18 5:00 PM

Elevator Shaft & Accessory


Duration 6 days
Start 5/7/18 8:00 AM
Finish 5/12/18 5:00 PM
Staircase
Duration 3 days
Start 5/7/18 8:00 AM
Finish 5/9/18 5:00 PM

CHB Wall
Duration 5 days
Start 5/7/18 8:00 AM
Finish 5/11/18 5:00 PM

Column Slab
Duration 6 days Duration 9 days
Start 5/7/18 8:00 AM Start 5/14/18 8:00 AM
Finish 5/12/18 5:00 PM Finish 5/23/18 5:00 PM

Install Pl
Duration
Start
Finish

Electrical
Duration
Start
Finish

ACCU &
Duration
Start
Finish

Beam
Install Plumbing Pipe Fittings
Duration 3 days
Start 5/24/18 8:00 AM
Finish 5/26/18 5:00 PM

Electrical Wire Pulling & Acc...


Duration 3 days
Start 5/24/18 8:00 AM
Finish 5/26/18 5:00 PM

ACCU & Exhaust for Second ... Fire Protection Pipes for Seco...
Duration 9 days Duration 6 days
Start 5/24/18 8:00 AM Start 6/4/18 8:00 AM
Finish 6/2/18 5:00 PM Finish 6/9/18 5:00 PM

Beam Staircase
Fourth Floor
Duration 27 days
Start 5/30/18 8:00 AM
Finish 6/30/18 5:00 PM
Quality and Safety Inspection
Duration 1 day
Start 6/2/18 8:00 AM
Finish 6/2/18 5:00 PM

Rough-In floor Utilities (inclu...


Duration 3 days
Start 6/7/18 8:00 AM
Finish 6/9/18 5:00 PM
Elevator Shaft & Accessory
Duration 4 days
Start 5/30/18 8:00 AM
Finish 6/2/18 5:00 PM
Beam
Duration
Start
Finish
Beam Staircase
Duration 5 days Duration 3 days
Start 5/24/18 8:00 AM Start 5/30/18 8:00 AM
Finish 5/29/18 5:00 PM Finish 6/1/18 5:00 PM

CHB Wall
Duration 3 days
Start 5/30/18 8:00 AM
Finish 6/1/18 5:00 PM

Column Slab
Duration 4 days Duration 8 days
Start 5/30/18 8:00 AM Start 6/4/18 8:00 AM
Finish 6/2/18 5:00 PM Finish 6/13/18 5:00 PM

Install Plumbing Pipe Fittings


Duration 3 days
Start 6/14/18 8:00 AM
Finish 6/16/18 5:00 PM

Electrical Wire Pulling & Acc...


Duration 3 days
Start 6/14/18 8:00 AM
Finish 6/16/18 5:00 PM

ACCU & Exhaust for Third Flr Fire Protecti


Duration 9 days Duration
Start 6/14/18 8:00 AM Start
Finish 6/23/18 5:00 PM Finish

Beam Staircase
Duration 5 days Duration
Start 6/14/18 8:00 AM Start
Fire Protection Pipes for Thir...
Duration 6 days
6/25/18 8:00 AM
6/30/18 5:00 PM

Staircase
Duration 3 days
6/20/18 8:00 AM
Roof Deck
Duration 28 days
Start 6/20/18 8:00 AM
Finish 7/21/18 5:00 PM
Quality and Safety Inspection
Duration 1 day
Start 6/23/18 8:00 AM
Finish 6/23/18 5:00 PM

Rough-In floor Utilities (inclu...


Duration 3 days
Start 6/28/18 8:00 AM
Finish 6/30/18 5:00 PM
Elevator Shaft & Accessory
Duration 10 days
Start 6/20/18 8:00 AM
Finish 6/30/18 5:00 PM
Start 6/14/18 8:00 AM Start
Finish 6/19/18 5:00 PM Finish

CHB Wall
Duration
Start
Finish

Column
Duration
Start
Finish
6/20/18 8:00 AM
6/22/18 5:00 PM

CHB Wall
Duration 3 days
6/20/18 8:00 AM
6/22/18 5:00 PM

Column Slab
Duration 4 days Duration 9 days
6/20/18 8:00 AM Start 6/25/18 8:00 AM
6/23/18 5:00 PM Finish 7/4/18 5:00 PM

Waterproofing
Duration 3 days
Start 7/5/18 8:00 AM
Finish 7/7/18 5:00 PM

Install Plumbing Pipe Fittings


Duration 3 days
Start 7/5/18 8:00 AM
Finish 7/7/18 5:00 PM

Electrical Wire Pulling & Acc...


Duration 3 days
Start 7/5/18 8:00 AM
Finish 7/7/18 5:00 PM

ACCU & Exhaust for Fourth ... Fire Protection Pipe for Fouth...
Duration 8 days Duration 4 days
Start 7/5/18 8:00 AM Start 7/14/18 8:00 AM
Finish 7/13/18 5:00 PM Finish 7/18/18 5:00 PM
Internal Construction & Finis...
Duration 41 days
Start 7/23/18 8:00 AM
Finish 9/8/18 5:00 PM

Painting
Quality and Safety Inspection
Duration 1 day
Start 7/21/18 8:00 AM
Finish 7/21/18 5:00 PM

Dry Wall Tiling Doors


Duration 12 days Duration 18 days Duration 5 days
Start 7/23/18 8:00 AM Start 8/6/18 8:00 AM Start 8/27/18 8:00 AM
Finish 8/4/18 5:00 PM Finish 8/25/18 5:00 PM Finish 9/1/18 5:00 PM

Windows
Duration 5 days
Start 8/27/18 8:00 AM
Finish 9/1/18 5:00 PM

Ceiling
Duration 17 days
Start 8/13/18 8:00 AM
Finish 9/1/18 5:00 PM
Beam CHB Wall
Duration 5 days Duration 3 days
Start 7/5/18 8:00 AM Start 7/11/18 8:00 AM
Finish 7/10/18 5:00 PM Finish 7/13/18 5:00 PM

Roof
Duration 3 days
Start 7/11/18 8:00 AM
Finish 7/13/18 5:00 PM

ACCU & Exhaust for Roof Deck Fire Protection P


Duration 3 days Duration 2 d
Start 7/14/18 8:00 AM Start 7/19/18 8:
Finish 7/17/18 5:00 PM Finish 7/20/18 5:
Protection Pipe for Roof ...
days
7/19/18 8:00 AM
7/20/18 5:00 PM
Painting
Duration 35 days
Start 7/30/18 8:00 AM
Finish 9/8/18 5:00 PM

Aluminum Handrails
Duration 6 days
Start 9/3/18 8:00 AM
Finish 9/8/18 5:00 PM

Steel Fence @ Roofdeck


Duration 6 days
Start 9/3/18 8:00 AM
Finish 9/8/18 5:00 PM

Plumbing
Duration 23 days
Start 8/20/18 8:00 AM
Finish 9/15/18 5:00 PM

Electrical
Duration 12 days
Start 9/3/18 8:00 AM
Finish 9/15/18 5:00 PM

Mechanical
Duration 17 days
Start 8/28/18 8:00 AM
Finish 9/15/18 5:00 PM

Fire Protection
Duration 1 day
Start 7/24/18 8:00 AM
Finish 7/24/18 5:00 PM

Miscellaneous Landscape
Duration 10 days Duration 10 days
Start 8/20/18 8:00 AM Start 8/20/18 8:00 AM
Finish 8/31/18 5:00 PM Finish 8/31/18 5:00 PM
Install Elevator Shaft & Mach... Testing and Commissioning
Duration 16 days Duration 1 day
Start 8/28/18 8:00 AM Start 9/15/18 8:00 AM
Finish 9/14/18 5:00 PM Finish 9/15/18 5:00 PM
Install Plumbing fixtures Testing and Co
Duration 22 days Duration 1 d
Start 8/20/18 8:00 AM Start 9/15/18 8:
Finish 9/14/18 5:00 PM Finish 9/15/18 5:

Install Lighting Fixtures Testing and Co


Duration 11 days Duration 1 d
Start 9/3/18 8:00 AM Start 9/15/18 8:
Finish 9/14/18 5:00 PM Finish 9/15/18 5:
ting and Commissioning
day
9/15/18 8:00 AM
9/15/18 5:00 PM

ting and Commissioning


day
9/15/18 8:00 AM
9/15/18 5:00 PM

Testing and Commissioning


Duration 1 day
Start 7/24/18 8:00 AM
Finish 7/24/18 5:00 PM
Finish 8/31/18 5:00 PM Finish 8/31/18 5:00 PM

Signage
Duration 4 days
Start 8/28/18 8:00 AM
Finish 8/31/18 5:00 PM

CLOSE-OUT PHASE
Duration 12 days
Start 9/17/18 8:00 AM
Finish 9/29/18 5:00 PM

Final Inspection Punchlists Repair


Duration 1 day Duration 5 days
Start 9/17/18 8:00 AM Start 9/18/18 8:00 AM
Finish 9/17/18 5:00 PM Finish 9/22/18 5:00 PM

Close-out Documents
Duration 11 days
Start 9/18/18 8:00 AM
Finish 9/29/18 5:00 PM
Final Clean-up and Occupancy
Duration 6 days
Start 9/24/18 8:00 AM
Finish 9/29/18 5:00 PM

Das könnte Ihnen auch gefallen