CONSTRUCTION PHASE
Duration 170 days
Start 2/19/18 8:00 AM
Finish 9/15/18 5:00 PM
Site Works
Duration 6 days
Start 2/19/18 8:00 AM
Finish 2/24/18 5:00 PM
Sub-Structure
Duration 14 days
Start 2/26/18 8:00 AM
Finish 3/13/18 5:00 PM
Obtain Building Permit
Duration 11 days
Start 2/5/18 8:00 AM
Finish 2/16/18 5:00 PM
Excavation
Duration 4 days
Start 2/21/18 8:00 AM
Finish 2/24/18 5:00 PM
Foundation
Duration 6 days
Start 2/26/18 8:00 AM
Finish 3/3/18 5:00 PM
Ground Floor
Duration 20 days
Start 3/14/18 8:00 AM
Finish 4/13/18 5:00 PM
Tie Beam
Duration 6 days
Start 2/26/18 8:00 AM
Finish 3/3/18 5:00 PM
Elevator Pit
Duration 3 days
Start 3/1/18 8:00 AM
Finish 3/3/18 5:00 PM
Superstructure
Duration 103 days
Start 3/14/18 8:00 AM
Finish 7/21/18 5:00 PM
Install Electrical Underground Rough-In and Installation Ins... Quality and Safety Inspection
Duration 3 days Duration 1 day Duration 1 day
Start 3/8/18 8:00 AM Start 3/12/18 8:00 AM Start 3/13/18 8:00 AM
Finish 3/10/18 5:00 PM Finish 3/12/18 5:00 PM Finish 3/13/18 5:00 PM
Column Slab
Duration 6 days Duration 7.375 days
Start 3/14/18 8:00 AM Start 3/21/18 8:00 AM
Finish 3/20/18 5:00 PM Finish 3/31/18 11:00 AM
CHB Wall
Duration 4 days
Start 4/10/18 8:00 AM
Finish 4/13/18 5:00 PM
Column
Duration 5 days
Start 4/10/18 8:00 AM
Finish 4/14/18 5:00 PM
Slab
Duration 9 days
Start 4/16/18 8:00 AM
Finish 4/25/18 5:00 PM
ACCU and Exhaust for Groun... Fire Protection Pipes for Grou...
Duration 8 days Duration 6 days
Start 4/26/18 8:00 AM Start 5/7/18 8:00 AM
Finish 5/5/18 5:00 PM Finish 5/12/18 5:00 PM
Beam
Duration 8 days
Start 4/26/18 8:00 AM
Finish 5/5/18 5:00 PM
Third Floor
Duration 30 days
Start 5/7/18 8:00 AM
Finish 6/9/18 5:00 PM
Quality and Safety Inspection
Duration 1 day
Start 5/12/18 8:00 AM
Finish 5/12/18 5:00 PM
CHB Wall
Duration 5 days
Start 5/7/18 8:00 AM
Finish 5/11/18 5:00 PM
Column Slab
Duration 6 days Duration 9 days
Start 5/7/18 8:00 AM Start 5/14/18 8:00 AM
Finish 5/12/18 5:00 PM Finish 5/23/18 5:00 PM
Install Pl
Duration
Start
Finish
Electrical
Duration
Start
Finish
ACCU &
Duration
Start
Finish
Beam
Install Plumbing Pipe Fittings
Duration 3 days
Start 5/24/18 8:00 AM
Finish 5/26/18 5:00 PM
ACCU & Exhaust for Second ... Fire Protection Pipes for Seco...
Duration 9 days Duration 6 days
Start 5/24/18 8:00 AM Start 6/4/18 8:00 AM
Finish 6/2/18 5:00 PM Finish 6/9/18 5:00 PM
Beam Staircase
Fourth Floor
Duration 27 days
Start 5/30/18 8:00 AM
Finish 6/30/18 5:00 PM
Quality and Safety Inspection
Duration 1 day
Start 6/2/18 8:00 AM
Finish 6/2/18 5:00 PM
CHB Wall
Duration 3 days
Start 5/30/18 8:00 AM
Finish 6/1/18 5:00 PM
Column Slab
Duration 4 days Duration 8 days
Start 5/30/18 8:00 AM Start 6/4/18 8:00 AM
Finish 6/2/18 5:00 PM Finish 6/13/18 5:00 PM
Beam Staircase
Duration 5 days Duration
Start 6/14/18 8:00 AM Start
Fire Protection Pipes for Thir...
Duration 6 days
6/25/18 8:00 AM
6/30/18 5:00 PM
Staircase
Duration 3 days
6/20/18 8:00 AM
Roof Deck
Duration 28 days
Start 6/20/18 8:00 AM
Finish 7/21/18 5:00 PM
Quality and Safety Inspection
Duration 1 day
Start 6/23/18 8:00 AM
Finish 6/23/18 5:00 PM
CHB Wall
Duration
Start
Finish
Column
Duration
Start
Finish
6/20/18 8:00 AM
6/22/18 5:00 PM
CHB Wall
Duration 3 days
6/20/18 8:00 AM
6/22/18 5:00 PM
Column Slab
Duration 4 days Duration 9 days
6/20/18 8:00 AM Start 6/25/18 8:00 AM
6/23/18 5:00 PM Finish 7/4/18 5:00 PM
Waterproofing
Duration 3 days
Start 7/5/18 8:00 AM
Finish 7/7/18 5:00 PM
ACCU & Exhaust for Fourth ... Fire Protection Pipe for Fouth...
Duration 8 days Duration 4 days
Start 7/5/18 8:00 AM Start 7/14/18 8:00 AM
Finish 7/13/18 5:00 PM Finish 7/18/18 5:00 PM
Internal Construction & Finis...
Duration 41 days
Start 7/23/18 8:00 AM
Finish 9/8/18 5:00 PM
Painting
Quality and Safety Inspection
Duration 1 day
Start 7/21/18 8:00 AM
Finish 7/21/18 5:00 PM
Windows
Duration 5 days
Start 8/27/18 8:00 AM
Finish 9/1/18 5:00 PM
Ceiling
Duration 17 days
Start 8/13/18 8:00 AM
Finish 9/1/18 5:00 PM
Beam CHB Wall
Duration 5 days Duration 3 days
Start 7/5/18 8:00 AM Start 7/11/18 8:00 AM
Finish 7/10/18 5:00 PM Finish 7/13/18 5:00 PM
Roof
Duration 3 days
Start 7/11/18 8:00 AM
Finish 7/13/18 5:00 PM
Aluminum Handrails
Duration 6 days
Start 9/3/18 8:00 AM
Finish 9/8/18 5:00 PM
Plumbing
Duration 23 days
Start 8/20/18 8:00 AM
Finish 9/15/18 5:00 PM
Electrical
Duration 12 days
Start 9/3/18 8:00 AM
Finish 9/15/18 5:00 PM
Mechanical
Duration 17 days
Start 8/28/18 8:00 AM
Finish 9/15/18 5:00 PM
Fire Protection
Duration 1 day
Start 7/24/18 8:00 AM
Finish 7/24/18 5:00 PM
Miscellaneous Landscape
Duration 10 days Duration 10 days
Start 8/20/18 8:00 AM Start 8/20/18 8:00 AM
Finish 8/31/18 5:00 PM Finish 8/31/18 5:00 PM
Install Elevator Shaft & Mach... Testing and Commissioning
Duration 16 days Duration 1 day
Start 8/28/18 8:00 AM Start 9/15/18 8:00 AM
Finish 9/14/18 5:00 PM Finish 9/15/18 5:00 PM
Install Plumbing fixtures Testing and Co
Duration 22 days Duration 1 d
Start 8/20/18 8:00 AM Start 9/15/18 8:
Finish 9/14/18 5:00 PM Finish 9/15/18 5:
Signage
Duration 4 days
Start 8/28/18 8:00 AM
Finish 8/31/18 5:00 PM
CLOSE-OUT PHASE
Duration 12 days
Start 9/17/18 8:00 AM
Finish 9/29/18 5:00 PM
Close-out Documents
Duration 11 days
Start 9/18/18 8:00 AM
Finish 9/29/18 5:00 PM
Final Clean-up and Occupancy
Duration 6 days
Start 9/24/18 8:00 AM
Finish 9/29/18 5:00 PM