PEB 702 Engineering & Society

Tutorial Exercises: CPM (7 MARKS)

Date: 23 /4/2019

Problem A.

1. Construct an activity arrow network based on the activity descriptions. Show all your work.
Label activities by their activity letters.
2. Construct a precedence network diagram based on the activity descriptions using your key
box.
3. DETERMINE THE ES, EF, LS, LF AND FLOAT/SLACK
4. SUMMARIZE ALL RESULTS IN MATRIX FORMAT
a. ES
b. EF
c. LS
d. LF
e. SLACK
f. IDENTIFY THE CRITICAL PATH AND UNCRITICAL PATHS

Activity IMMEDIATE PREDECESSOR DURATION


A - 6
B A 6
C A 3
D C 10
E B 6
F C 4
G D,E 3
H B 8
I H 4
J G, I 4

Problem B.

1. Construct an activity arrow network based on the activity descriptions. Show all your work.
Label activities by their activity letters.
2. Construct a precedence network diagram based on the activity descriptions using your key
box.
3. DETERMINE THE ES, EF, LS, LF AND FLOAT/SLACK
4. SUMMARIZE ALL RESULTS IN MATRIX FORMAT
a. ES
b. EF
c. LS
d. LF
e. SLACK
f. Identify the critical path and uncritical paths

Tutorial exercise CPM Page 1 of 2


Activity IMMEDIATE PREDECESSOR DURATION
A - 6
B - 4
C A 3
D A 5
E A 1
F B,C 4
G B,C 2
H E,F 6
I E,F 5
J D, H 3
K G,I 5

Tutorial exercise CPM Page 2 of 2