Sie sind auf Seite 1von 10

ENGR. MA. KATHLEEN L.

DURAN, CIE, AAE, CLSSGB September 30, 2019

Colegio de San Juan de Letran Calamba


City of Calamba, Laguna, Philippines 4027 www.letran-calamba.edu.ph +63(049) 545-5453loc2030

School of Engineering and Architecture

Production Systems
Project Management

What is a project?
– Any unique endeavour with specific objectives

– With multiple activities

– With defined precedent relationships

– With a specific time period for completion

• Example

– Major event like a wedding, concert etc.

– Any construction project

– Designing a political campaign

IE Department © 2019 Letran – Calamba 2

1
ENGR. MA. KATHLEEN L. DURAN, CIE, AAE, CLSSGB September 30, 2019

Project Life Cycle


• Conception: identify the need

• Feasibility analysis or study: costs benefits, and risks

• Planning: who, how long, what to do?

• Execution: doing the project

• Termination: ending the project

IE Department © 2019 Letran – Calamba 3

Network Planning Techniques


• Network representation is useful for project analysis.

• Networks show how project activities are organized and are used
to determine time duration of projects.

• Network techniques used are:


– CPM (Critical Path Method)

– PERT (Project Evaluation and Review Technique)

• Developed independently during late 1950’s.

IE Department © 2019 Letran – Calamba 4

2
ENGR. MA. KATHLEEN L. DURAN, CIE, AAE, CLSSGB September 30, 2019

Project Planning
• All activities (steps) of the project should be identified.

• The sequential relationships of the activities (which activity


comes first, which follows, etc.) is identified by precedence
relationships.

• Steps of project planning:


– Make time estimates for activities, determine project completion time.

– Compare project schedule objectives, determine resource requirements.

IE Department © 2019 Letran – Calamba 5

Elements of Project Management Project Scheduling

■ Project Schedule : Timely completion of project.

■ Schedule development steps:


1. Define activities,

2. Sequence activities,

3. Estimate activity times,

4. Construct schedule.

■ Gantt chart and CPM/PERT techniques can be useful.

■ Computer software packages available, e.g. Microsoft Project.

IE Department © 2019 Letran – Calamba 6

3
ENGR. MA. KATHLEEN L. DURAN, CIE, AAE, CLSSGB September 30, 2019

Elements of Project Management Gantt Chart (1 of 2)

■ Popular, traditional technique, also known as a bar chart -


developed by Henry Gantt (1914).

■ Used in CPM/PERT for monitoring work progress.

■ A visual display of project schedule showing activity start and


finish times and where extra time is available.

■ Gantt Chart is suitable for projects with few activities and


precedence relationships.

IE Department © 2019 Letran – Calamba 7

Elements of Project Management Gantt Chart (2 of 2)

Figure 8.4 A Gantt chart

IE Department © 2019 Letran – Calamba 8

4
ENGR. MA. KATHLEEN L. DURAN, CIE, AAE, CLSSGB September 30, 2019

The Project Network: CPM/PERT


• Activity-on-Arc (AOA) Network
– A branch reflects an activity of a project.

– A node represents the beginning and end of activities, referred to as events.

– Branches in the network indicate precedence relationships.

– When an activity is completed at a node, it has been realized.

IE Department © 2019 Letran – Calamba 9

The Project Network: Concurrent Activities

■ Time duration of activities shown on branches.

■ Activities can occur at the same time (concurrently).

■ A dummy activity shows a precedence relationship but reflects no


passage of time.

■ Two or more activities cannot share the same start and end
nodes.

Figure 8. 7 A Dummy Activity


IE Department © 2019 Letran – Calamba 10

5
ENGR. MA. KATHLEEN L. DURAN, CIE, AAE, CLSSGB September 30, 2019

The Project Network:


AOA Network for House Building Project

Figure 8.6
Expanded Network for Building a House
Showing Concurrent Activities

IE Department © 2019 Letran – Calamba 11

The Project Network:


AON Network for House Building Project
• Activity-on-Node (AON) Network
– A node represents an activity, with its label and time shown on the node

– The branches show the precedence relationships

– Convention used in Microsoft Project software

Label

Duration
Figure 8.8

IE Department © 2019 Letran – Calamba 12

6
ENGR. MA. KATHLEEN L. DURAN, CIE, AAE, CLSSGB September 30, 2019

The Project Network: Paths Through a Network

Path Events
A 1247
B 12567
C 1347
D 13567

Table 8.1
Paths Through the House-Building Network

IE Department © 2019 Letran – Calamba 13

The Project Network: The Critical Path


The critical path is the longest path through the network; the minimum
time the network can be completed. From Figure 8.8:

Path A: 1  2  4  7 3 + 2 + 3 + 1 = 9 months

Path B: 1  2  5  6  7 3 + 2 + 1 + 1 + 1= 8 months

Path C: 1  3  4  7 3 + 1 + 3 + 1 = 8 months

Path D: 1  3  5  6  7 3 + 1 + 1 + 1 + 1 = 7 months

IE Department © 2019 Letran – Calamba 14

7
ENGR. MA. KATHLEEN L. DURAN, CIE, AAE, CLSSGB September 30, 2019

The Project Network


Detailed Analysis of Critical Path (1  2  4  7)

Figure 8.9 Activity start time

IE Department © 2019 Letran – Calamba 15

The Project Network: Activity-on-Node Configuration

Figure 8.10 Activity-on-Node Configuration


IE Department © 2019 Letran – Calamba 16

8
ENGR. MA. KATHLEEN L. DURAN, CIE, AAE, CLSSGB September 30, 2019

The Project Network


Activity Scheduling : Earliest Times

■ ES is the earliest time an activity can start: ES = Maximum (EF)


■ EF is the earliest start time plus the activity time: EF = ES + t

Figure 8.11 Earliest activity start and finish times


IE Department © 2019 Letran – Calamba 17

The Project Network


Activity Scheduling : Latest Times

■ LS is the latest time an activity can start without delaying critical path time:
LS = LF - t
■ LF is the latest finish time. LF = Minimum (LS)

Figure 8.12 Latest activity start and finish times


IE Department © 2019 Letran – Calamba 18

9
ENGR. MA. KATHLEEN L. DURAN, CIE, AAE, CLSSGB September 30, 2019

The Project Network: Activity Slack Time (1 of 2)

 Slack is the amount of time an activity can be delayed without


delaying the project: S = LS – ES = LF - EF
 Slack Time exists for those activities not on the critical path
for which the earliest and latest start times are not equal.

Activity LS ES LF EF Slack, S
*1 0 0 3 3 0* Table 8.2
*2 3 3 5 5 0*
3 4 3 5 4 1
*4 5 5 8 8 0*
5 6 5 7 6 1
6 7 6 8 7 1
*7 8 8 9 9 0* *Critical path

IE Department © 2019 Letran – Calamba 19

The Project Network: Activity Slack Time (2 of 2)

Figure 8.13 Activity slack


IE Department © 2019 Letran – Calamba 20

10

Das könnte Ihnen auch gefallen