Beruflich Dokumente
Kultur Dokumente
Evaluation is the comparison of actual project impacts against the agreed strategic plans.
It looks at what you set out to do, at what you have accomplished, and how you
accomplished it. It can be formative (taking place during the life of a project or
organization, with the intention of improving the strategy or way of functioning of the
project or organization). It can also be summative (drawing learnings from a completed
project or an organization that is no longer functioning).
What monitoring and evaluation have in common is that they are geared towards learning
from what you are doing and how you are doing it, by focusing on:
• Efficiency
• Effectiveness
• Impact
Efficiency tells you that the input into the work is appropriate in terms of the output.
This could be input in terms of money, time, staff, equipment and so on. When you run a
project and are concerned about its replicability or about going to scale, then it is very
important to get the efficiency element right.
Impact tells you whether or not what you did made a difference to the problem situation
you were trying to address. In other words, was your strategy useful? Did ensuring that
teachers were better qualified improve the pass rate in the final year of school? Before
you decide to get bigger, or to replicate the project elsewhere, you need to be sure that what
you are doing makes sense in terms of the impact you want to achieve.
Plans are essential but they are not set in concrete (totally fixed). If they are not working,
or if the circumstances change, then plans need to change too. Monitoring and evaluation
are both tools which help a project or organization know when plans are not working, and
when circumstances have changed. They give management the information it needs to
make decisions about the project or organization, about changes that are necessary in
strategy or plans. Through this, the constants remain the pillars of the strategic
framework: the problem analysis, the vision, and the values of the project or organization.
Everything else is negotiable. Getting something wrong is not a crime but failing to learn
from past mistakes because you are not monitoring and evaluating, is. It is important to
recognize that monitoring and evaluation are not magic wands that can be waved to
make problems disappear, or to cure them, or to miraculously make changes without a lot
of hard work being put in by the project or organization. In themselves, they are not a
solution, but they are valuable tools. Monitoring and evaluation can:
Evaluation involves:
• Looking at what the project or organization intended to achieve – what difference
did it want to make? What impact did it want to make?
• Assessing its progress towards what it wanted to achieve, its impact targets.
• Looking at the strategy of the project or organization. Did it have a strategy? Was
it effective in following its strategy? Did the strategy work? If not, why not?
• Looking at how it worked. Was there an efficient use of resources? What were
the opportunity costs of the way it chose to work? How sustainable is the way in which
the project or organization works? What are the implications for the various
stakeholders in the way the organization works?
Sometimes people are more willing to speak to The team may not be specifically skilled or
insiders than to outsiders. trained in evaluation.
An internal evaluation will cost less than an It may cost less than an external evaluation; the
external evaluation. opportunity costs may be high.
External evaluation (done by a team or person with no vested interest in the project)
The evaluation is likely to be more objective Someone from outside the organization or
as the evaluators will have some distance from project may not understand the culture or even
the work. what the work is trying to achieve
Those directly involved may feel threatened by
The evaluators should have a range of outsiders and be less likely to talk openly and co-
evaluation skills and experience. operate in the process.
Sometimes people are more willing to speak External evaluation can be very costly.
to outsiders than to insiders.
• A commitment to deadlines.
• Objectivity, honesty and fairness.
• Logic and the ability to operate systematically.
• Ability to communicate verbally and in writing.
• A style and approach that fits with your organization.
• Negotiate a contract which makes provision for what will happen if output
expectations are not met.
• Ask for a work plan with outputs and timelines.
• Maintain contact – ask for interim reports as part of the contract
• Build in formal feedback times.
Do not expect any evaluator to be completely objective. S/he will have opinions and
ideas – you are not looking for someone who is a blank page! However, his/her
opinions must be clearly stated as such, and must not be disguised as “facts”. It is also
useful to have some idea of his/ her (or their) approach to evaluation.
DIFFERENT APPROACHES TO EVALUATION
Independent
Goal-free Assessing the full
determination of
range of project
needs and standards
effects, intended and What are all the
to judge project
unintended. outcomes? What
worth. Qualitative
value do they have?
and quantitative
techniques to uncover
any possible results.
Monitoring and evaluation should be part of your planning process. It is very difficult
to go back and set up monitoring and evaluation systems once things have begun to
happen. You need to begin gathering information about performance and in relation to
targets from the word go. The first information gathering should, in fact, take place
when you do your needs assessment (see the toolkit on overview of planning, the
section on doing the ground work). This will give you the information you need against
which to assess improvements over time. When you do your planning process, you
will set indicators (see Glossary of Terms). These indicators provide the framework
for your monitoring and evaluation system. They tell you what you want to know and
the kinds of information it will be useful to collect. In this section we look at:
There is not one set way of planning for monitoring and evaluation. The ideas
included in the toolkits on overview of planning, strategic planning and action
planning will help you to develop a useful framework for your monitoring and
evaluation system. If you are familiar with logical framework analysis and already use
it in your planning, this approach lends itself well to planning a monitoring and
evaluation system.
WHAT DO WE WANT TO KNOW?
What we want to know is linked to what we think is important. In development
work, what we think is important is linked to our values.
• Who is benefiting from what we do? How much are they benefiting?
• Are beneficiaries passive recipients or does the process enable them to have
some control over their lives?
• Are there lessons in what we are doing that have a broader impact than just
what is happening on our project?
• Can what we are doing be sustained in some way for the long-term, or will the
impact of our work cease when we leave?
• Are we getting optimum outputs for the least possible amount of inputs?
Both process and product should be part of your monitoring and evaluation system.
But how do we make process and product and values measurable? The answer lies in
the setting of indicators and this is dealt with in the sub-section that follows.
• Who?
• How many?
• How often?
• How much?
But you need to decide early on what your indicators are going to be so that you can
begin collecting the information immediately. You cannot use the number of television
aerials in a community as a sign of improved standard of living if you don’t know how
many there were at the beginning of the process. Some people argue that the problem
with measuring indicators is that other variables (or factors) may have impacted on
them as well. Community members may be participating more in meetings because a
number of new people with activist backgrounds have come to live in the area. Women
may have more time for development projects because the men of the village have
been attending a gender workshop and have made a decision to share the traditionally
female tasks. And so on. While this may be true, within a project it is possible to
identify other variables and take them into account. It is also important to note that,
if nothing is changing, if there is no improvement in the measurement of the key
indicators identified, then your strategy is not working and needs to be rethought.
DEVELOPING INDICATORS
Step 1: Identify the problem situation you are trying to address. The following
might be problems:
Step 2: Develop a vision for how you would like the problem areas to be/ look.
This will give you impact indicators.
What will tell you that the vision has been achieved? What signs will you see that you
can measure that will “prove” that the vision has been achieved? For example, if your
vision was that the people in your community would be healthy, then you can use
health indicators to measure how well you are doing. Has the infant mortality rate
gone down? Do fewer women die during child-birth? Has the HIV/AIDS infection
rate been reduced? If you can answer “yes” to these questions then progress is being
made.
Step 3: Develop a process vision for how you want things to be achieved. This will
give you process indicators.
If, for example, you want success to be achieved through community efforts and
participation, then your process vision might include things like community health
workers from the community trained and offering a competent service used by all;
community organizes clean-up events on a regular basis, and so on.
Here you can set indicators such as: planned workshops are run within the stated
timeframe, costs for workshops are kept to a maximum of US$ 2.50 per participant, no
more than 160 hours in total of staff time to be spent on organizing a conference; no
complaints about conference organization etc.
With this framework in place, you are in a position to monitor and evaluate
efficiency, effectiveness and impact.
DIFFERENT KINDS OF INFORMATION
(QUANTITATIVE AND QUALITATIVE)
Information used in monitoring and evaluation can be classified as:
• Quantitative
• Qualitative
Quantitative measurement tells you “how much or how many”. How many people
attended a workshop, how many people passed their final examinations, how much a
publication cost, how many people were infected with HIV, how far people have to
walk to get water or firewood, and so on. Quantitative measurement can be expressed
in absolute numbers (3 241 women in the sample are infected) or as a percentage
(50% of households in the area have television aerials). It can also be expressed as a
ratio (one doctor for every 30 000 people). One way or another, you get quantitative
(number) information by counting or measuring.
Qualitative measurement tells you how people feel about a situation or about how
things are done or how people behave. So, for example, although you might discover
that 50% of the teachers in a school are unhappy about the assessment criteria used,
this is still qualitative information, not quantitative information. You get qualitative
information by asking, observing, interpreting.
Some people find quantitative information comforting – it seems solid and reliable
and “objective”. They find qualitative information unconvincing and “subjective”. It is
a mistake to say that “quantitative information speaks for itself”. It requires just as
much interpretation in order to make it meaningful as does qualitative information. It
may be a “fact” that enrolment of girls at schools in some developing countries is
dropping – counting can tell us that, but it tells us nothing about why this drop is taking
place. In order to know that, you would need to go out and ask questions – to get
qualitative information. Choice of indicators is also subjective, whether you use
quantitative or qualitative methods to do the actual measuring. Researchers choose to
measure school enrolment figures for girls because they believe that this tells them
something about how women in a society are treated or viewed.
Usually you can use the reports, minutes, attendance registers, financial statements that
are part of your work anyway as a source of monitoring and evaluation information.
However, sometimes you need to use special tools that are simple but useful to add to
the basic information collected in the natural course of your work. Some of the more
common ones are:
• Case studies
• Recorded observation
• Diaries
It is a useful principle to look at every activity and say: What do we need to know
about this activity, both process (how it is being done) and product (what it is meant
to achieve), and what is the easiest way to find it out and record it as we go along?
CHAPTER-III
DESIGNING A MONITORING AND/OR EVALUATION PROCESS
As there are differences between the design of a monitoring system and that of an
evaluation process, we deal with them separately here.
• Purpose
• Key evaluation questions
• Methodology.
MONITORING
When you design a monitoring system, you are taking a formative view point and
establishing a system that will provide useful information on an ongoing basis so that
you can improve what you do and how you do it. On the next page, you will find a
suggested process for designing a monitoring system. For a case study of how an
organization went about designing a monitoring system, go to the section with examples,
and the example given of designing a monitoring system.
For a case study of how an organization went about designing a monitoring system,
go to examples.
Step 1: At a workshop with appropriate staff and/or volunteers, and run by you
or a consultant:Introduce the concepts of efficiency, effectiveness and
impact.
• Explain that a monitoring system needs to cover all three.
• Generate a list of indicators for each of the three aspects.
• Clarify what variables need to be linked. So, for example, do you
want to be able to link the age of a teacher with his/her qualifications in order to answer
the question: Are older teachers more or less likely to have higher qualifications?
• Clarify what information the project or organization is already
collecting.
Step 2: Turn the input from the workshop into a brief for the questions your
monitoring system must be able to answer. Depending on how complex
your requirements are, and what your capacity is, you may decide to go
for a computerized data base or a manual one. If you want to be able to
link many variables across many cases (e.g. participants, schools, parent
involvement, resources, urban/rural etc), you may need to go the computer
route. If you have a few variables, you can probably do it manually. The
important thing is to begin by knowing what variables you are interested
in and to keep data on these variables. Linking and analysis can take place
later.
From the workshop you will know what you want to monitor. You will
have the indicators of efficiency, effectiveness and impact that have
been prioritized. You will then choose the variables that will help you
answer the questions you think are important.
So, for example, you might have an indicator of impact which is that
“safer sex options are chosen” as an indicator that “young people are
now making informed and mature lifestyle choices”. The variables that
might affect the indicator include:
• Age
• Gender
• Religion
• Urban/rural
• Economic category
• Family environment
• Length of exposure to your project’s initiative
Step 3: Decide how you will collect the information you need (see collecting
information) and where it will be kept (on computer, in manual files).
Step 4: Decide how often you will analyze the information – this means
putting it together and trying to answer the questions you think are
important.
EVALUATION
Designing an evaluation process means being able to develop Terms of Reference for
such a process (if you are the project or organization) or being able to draw up a
sensible proposal to meet the needs of the project or organization (if you are a
consultant).
The main sections in Terms of Reference for an evaluation process usually include:
• Key evaluation questions: What the central questions are that the
evaluation must address.
• Specific objectives: What specific areas, internal and/or external, you want
the evaluation to address. So, for example, you might want the evaluation to include a
review of finances, or to include certain specific program sites.
• Methodology: here you might give broad parameters of the kind of approach
you favor in evaluation (see the section on more about monitoring and evaluation).
You might also suggest the kinds of techniques you would like the evaluation team to
use.
Purpose
The purpose of an evaluation is the reason why you are doing it. It goes beyond what you
want to know to why you want to know it. It is usually a sentence or, at most, a
paragraph. It has two parts:
The key evaluation questions are the central questions you want the evaluation process
to answer. They are not simple questions. You can seldom answer “yes” or “no”
them. A useful evaluation question is:
• Thought provoking
• Challenges assumptions.
• Focuses inquiry and reflection.
• Raises many additional questions.
Some examples of key evaluation questions related to a project purpose:
The purpose of the evaluation is to assess how efficient the project is in delivering
benefits to the identified community in order to inform Board decisions about continuity
and replicability.
• Do the inputs (in money and time) justify the outputs and, if so/if not, on what
basis is this claim justified?
• What would improve the efficiency, effectiveness and impact of the current
project?
• What are the lessons that can be learned from this project in terms of
replicability?
Note that none of these questions deals with a specific element or area of the internal or
external functioning of the project or organization. Most would require the evaluation
team to deal with a range of project or organizational elements in order to answer them.
• What are the most effective ways in which a project of this kind can
address the problem identified?
• To what extent does the internal functioning and structure of the organization
impact positively on the program work?
• What learning from this project would have applicability across the full
development spectrum?
Clearly, there could be many, many examples. Our experience has shown us that,
when an evaluation process is designed with such questions in mind, it produces far
more interesting insights than simply impact are we having?
Methodology of Evaluation
“Methodology” as opposed to “methods” deals more with the kind of approach you
use in your evaluation process. (See also more about monitoring and evaluation earlier
in the toolkit). You could, for example, commission or do an evaluation process that
looked almost entirely at written sources, primary or secondary: reports, data sheets,
minutes and so on. Or you could ask for an evaluation process that involved getting
input from all the key stakeholder groups. Most terms of reference will ask for some
combination of these but they may also specify how they want the evaluation team to
get input from stakeholder groups for example:
• Through a survey;
Here too one would expect to find some indication of reporting formats: Will all
reporting be written? Will the team report to management, or to all staff, or to staff
and Board and beneficiaries? Will there be interim reports or only a final report? What
sort of evidence does the organization or project require to back up evaluator opinions?
Who will be involved in analysis?
The methodology section of Terms of Reference should provide a broad framework for
how the project or organization wants the work of the evaluation done.
CHAPTER-IV
COLLECTING INFORMATION
(This is also dealt with in the toolkit on action planning, in the section on monitoring,
collecting information as you go along.)
By damage control we mean what you need to do if you failed to get baseline
information when you started out.
Ideally, if you have done your planning well and collected information about the
situation at the beginning of your intervention, you will have baseline data.
Baseline data is the information you have about the situation before you do anything.
It is the information on which your problem analysis is based. It is very difficult to
measure the impact of your initiative if you do not know what the situation was when
you began it. (See also the toolkit on overview of planning, the section on doing the
ground work.) You need baseline data that is relevant to the indicators you have
decided will help you measure the impact of your work.
• If you are working with individuals, then you need “intake” information –
documented information about their situation at the time you began working with
them. For example, you might want to know, in addition to age, gender, name and so
on, current income, employment status, current levels of education, amount of money
spent on leisure activities, amount of time spent on leisure activities, ambitions and so
on, for each individual participant. Again, you will probably get the information from
a combination of interviewing and filling in of basic questionnaires, and you should
focus on the indicators which you think are important.
It is very difficult to go back and get this kind of baseline information after you have
begun work and the situation has changed. But what if you didn’t collect this
information at the beginning of the process? There are ways of doing damage
control. You can get anecdotal information (see Glossary of Terms) from those who
were involved at the beginning and you can ask participants if they remember what
the situation was when the project began. You may not even have decided what your
important indicators are when you began your work. You will have to work it out
“backwards”, and then try to get information about the situation related to those
indicators when you started out. You can speak to people, look at records and other
written sources such as minutes, reports and so on. One useful way of making
meaningful comparisons where you do not have baseline information is through
using control groups. Control groups are groups of people, businesses, families or
whatever unit you are focusing on, that has not had input from your project or
organization but are, in most other ways, very similar to those you are working with.
For example: You have been working with groups of school children around the
country in order to build their self-esteem and knowledge as a way of combating the
spread of HIV/AIDS and preventing teenage pregnancies. After a few years, you want
to measure what impact you have had on these children. You are going to run a series
of focus groups (see methods) with the children at the schools where you have
worked. But you did not do any baseline study with them. How will you know
what difference you have made?
You could set up a control groups at schools in the same areas, with the same kinds of
profiles, where you have not worked. By asking both the children at those schools you
have worked at, and the children at the schools where you have not worked, the same
sorts of questions about self-esteem, sexual behavior and so on, you should be able to
tell whether or not your work has made any difference. When you set up control
groups, you should try to ensure that:
• The profiles of the control groups are very similar to those of the groups you
have worked with. For example, it might be schools that serve the same economic
group, in the same geographical area, with the same gender ratio, age groups, ethnic
or racial mix.
• There are no other very clear variables that could affect the findings or
comparisons. For example, if another project, doing similar work, has been involved
with the school, this school would not be a good place to establish a control group. You
want a situation as close to what the situation was,with the beneficiaries of your
project when you started out.
METHODS
In this section we are going to give you a “shopping list” of the different kinds of
methods that can be used to collect information for monitoring and evaluation
purposes. You need to select methods that suit your purposes and your resources. Do
not plan to do a comprehensive survey of 100 000 households if you have two weeks
and very little money! Use sampling in this case.
Sampling is another important concept when using various tools for a monitoring or
evaluation process. Sampling is not really a tool in itself, but used with other tools it
is very useful. Sampling answers the question: Who do we survey, interview, include
in a focus group etc? It is a way of narrowing down the number of possible
respondents to make it manageable and affordable. Sometimes it is necessary to be
comprehensive. This means getting to every possible household, or school or teacher
or clinic etc. In an evaluation, you might well use all the information collected in
every case during the monitoring process in an overall analysis. Usually, however,
unless numbers are very small, for in-depth exploration you will use a sample.
Sampling techniques include:
• Random sampling (In theory random sampling means doing the sampling on a
sort of lottery basis where, for example all the names go into a container, are
tumbled around and then the required number are drawn out. This sort of
random sampling is very difficult to use in the kind of work we are talking
about. For practical purposes you are more likely to, for example, select every
seventh household or every third person on the list. The idea is that there is no
bias in the selection.)
• Stratified sampling (e.g. every seventh household in the upper income bracket,
every third household in the lower income bracket)
• Cluster sampling (e.g. only those people who have been on the project for at
least two years).
It is also usually best to use triangulation (See Glossary of Terms). This is a fancy
word that means that one set of data or information is confirmed by another. You
usually look for confirmation from a number of sources saying the same thing.
Tool Description Usefulness Disadvantages
Interviews
These can be Can be used with almost
structured, anyone who has some
semi-structured or involvement with the
unstructured. project. Requires some skill in
the interviewer.
They involve asking
specific questions Can be done in person or
aimed at getting on the telephone or even
information that will by e-mail.
enable indicators to
be measured.
Questions can be Very flexible
open-ended or
closed (yes/no
answers).
Can be a source of
qualitative and
quantitative
information.
Needs a skilled
As these key informants
interviewer with a
These are interviews often have little to do good
that with the project or
understanding of the
Key informant are carried out with organization, they can be topic. Be careful not
Interviews specialists in a topic quite objective and offer to
or useful insights. They can
turn something into
someone who may provide something of the an
be able to shed a “big picture” where
absolute truth (cannot
particular light on people more involved
be challenged)
the process. may focus
because it has been
at the micro (small)
said by a key
level.
informant.
With people who do
not read and write,
someone has to go
through the
questionnaire with
them which means no
time is saved and the
numbers one can
reach are limited.
This tool can save lots of
With questionnaires,
time if it is
These are written it is not possible to
self-completing, enabling
questions that are explore what people
you to get to many
used to get written are saying any
people. Done in this way
Questionnaires responses which, further.
it gives people a feeling
when analysed, will
of anonymity and theyQuestionnaires are
enable indicators to
may say things theyalso over-used and
be measured.
would not say to anpeople get tired of
interviewer. completing them.
Questionnaires must
be piloted to ensure
that questions can be
understood and cannot
be misunderstood. If
the questionnaire is
complex and will need
computerised analysis,
you need expert help
in
Tool Description Usefulness Disadvantages
It is quite difficult to
do random sampling
for focus groups and
this means findings
may not be
generalized.
In a focus group, a Sometimes people
group of about six to influence one another
12 people are either to say
interviewed together something or to keep
by a skilledThis can be a useful quiet about something.
interviewer/ way of getting opinions If possible, focus
Focus Group facilitator with afrom quite a large groups interviews
carefully structuredsample of people. should be recorded
interview schedule. and then transcribed.
Questions are Difficult to facilitate –
usually focused requires a very
around a specific experienced
topic or issue. facilitator. May
require breaking into
small groups followed
by plenary sessions
when everyone comes
together again.
This involves a
Community meetings are
gathering of a fairly
useful for getting a broad
large group of
response from many
beneficiaries to
Community people on specific issues.
whom questions,
meetings It is also a way of
problems, situations
involving beneficiariesRelies on field
are put for input to
directly in an evaluationworkers being
help in measuring
process, giving them adisciplined and
indicators.
sense of ownership of theinsightful.
process. They are useful
to have at critical points
in community projects.
Visual/audio
stimuli These include Very useful to use You have to have
pictures, movies, together with other tools, appropriate stimuli
tapes, stories, role particularly with people and the facilitator
plays, who cannot read or needs to be skilled in
photographs, used write. using such stimuli.
to illustrate
problems or issues
or past events or
even future events.
This involves
getting participants Can be very useful,
Self-drawings
to draw pictures, particularly with younger
usually of how children.
they feel or think
about something. Can be difficult to
explain and
interpret.
INTERVIEWING SKILLS
Some do’s and don’ts for interviewing:
• DO test the interview schedule beforehand for clarity, and to make sure questions
cannot be misunderstood.
• DO state clearly what the purpose of the interview is.
• DO assure the interviewee that what is said will be treated in confidence.
• DO ask if the interviewee minds if you take notes or tape record the interview.
• DO record the exact words of the interviewee as far as possible.
• DO keep talking as you write.
• DO keep the interview to the point.
• DO cover the full schedule of questions.
• DO watch for answers that are vague and probe for more information.
• DO be flexible and note down everything interesting that is said, even if it isn’t
on the schedule.
• DON’T offend the interviewee in any way.
• DON’T say things that are judgmental.
• DON’T interrupt in mid-sentence.
• DON’T put words into the interviewee’s mouth.
• DON’T show what you are thinking through changed tone of voice.
CHAPTER-V
ANALYSING INFORMATION
Whether you are looking at monitoring or evaluation, at some point you are going to
find yourself with a large amount of information and you will have to decide how to
make sense of it or to analyze it. If you are using an external evaluation team, it will be
up to this team to do the analysis, but, sometimes in evaluation, and certainly in
monitoring, you, the organization or project, have to do the analysis.
Monitoring and evaluation have little value if the organisation or project does not act
on the information that comes out of the analysis of data collected. Once you have the
findings, conclusions and recommendations from your monitoring and evaluation
process, you need to:
REPORTING
Whether you are monitoring or evaluating, at some point, or points, there will be a
reporting process. This reporting process follows the stage of analysing information.
You will report to different stakeholders in different ways, sometimes in written form,
sometimes verbally and, increasingly, making use of tools such as PowerPoint
presentations, slides and videos.
Below is a table, suggesting different reporting mechanisms that might be
appropriate for different stakeholders and at different times in project cycles. For
writing tips, go to the toolkit on effective writing for organizations.
SECTION 4:
RECOMMENDATIONS: This would give specific ideas for a way
forward in terms of addressing weaknesses and
building on strengths.
LEARNING
Learning is, or should be, the main reason why a project or organization monitors its
work or does an evaluation. By learning what works and what does not, what you are
doing right and what you are doing wrong, you, as project or organization
management, are empowered to act in an informed and constructive way. This is part of
a cycle of action reflection. (See the diagram in the section on why do monitoring and
evaluation?)
The purpose of learning is to make changes where necessary, and to identify and
build on strengths where they exist. Learning also helps you to understand, to make
conscious, assumptions you have. So, for example, perhaps you assumed that
children at more affluent schools would have benefited less from your intervention
than those from less affluent schools. Your monitoring data might show you that this
assumption was wrong. Once you realize this, you will probably view your
interactions with these schools differently.
EFFECTIVE DECISION-MAKING
As project or organization management, you need the conclusions and
recommendations that come out of monitoring and evaluation to help you make
decisions about your work and the way you do it. The success of the process is
dependent on the ability of those with management responsibilities to make decisions
and take action. The steps involved in the whole process are:
• Plan properly – know what you are trying to achieve and how you intend to
achieve it
• Implement
• Monitor and evaluate.
• Analyze the information you get from monitoring and evaluation and work out
what it is telling you.
• Look at the potential consequences to your plans of what you have learned from
the analysis of your monitoring and evaluation data.
• Draw up a list of options for action.
• Get consensus on what you should do and a mandate to take action.
• Share adjustments and plans with the rest of the organization and, if necessary,
your donors and beneficiaries.
• Implement.
• Monitor and evaluate.
Not everyone will be pleased about any changes in plans you decide need to be made.
People often resist change. Some of the reasons for this include:
• People are comfortable with things the way they are – they don’t want to be
pushed out of their comfort zones.
• People worry that any changes will lessen their levels of productivity – they
feel judged by what they do and how much they do, and don’t want to take the time
out necessary to change plans or ways of doing things.
• People don’t like to rush into change – how do we know that something
different will be better? They spend so long thinking about it that it is too late for
useful changes to be made.
• People don’t have a “big picture”. They know what they are doing and they
can see it is working, so they can’t see any reason to change anything at all.
• People don’t have a long term commitment to the project or the organization –
they see it as a stepping stone on their career path. They don’t want change
because it will delay the items they want to be able to tick off on their CV.
• People feel they can’t cope – they have to keep doing what they are doing but
also
• Work at bringing about change. It’s all too much.
• Make the reasons why change is needed very clear – take people through the
findings and conclusions of the monitoring and evaluation processes, involve them in
decision-making.
• Help people see the whole picture – beyond their little bit to the overall impact
on the problem analyzed.
• Focus on the key issues – we have to do something about this!
• Recognize anger, fear, and resistance. Listen to people; give them the
opportunity to express frustration and other emotions.
• Find common ground – things that they also want to see changed.
• Encourage a feeling that change is exciting, that it frees people from doing
things that are not working so they can try new things that are likely to work, that it
releases productive energy.
• Emphasize the importance of everyone being committed to making it work.
• Create conditions for regular interaction – anything from a seminar to graffiti
on a notice board - to discuss what is happening and how it is going.
• Pace change so that people can deal with it.
CHAPTER-VI
BEST PRACTICE
EXAMPLES OF INDICATORS
Please note that these are just examples – they may or may not suit your needs but
they should give you some idea of the kind of indicators you can use, especially for
measuring impact.
• Death rate
• Life expectancy at birth
• Infant mortality rates
• Causes of death
• Number of doctors per capita
• Number of hospital beds per capita
• Number of nurses per capita
• Literacy rates, by age and gender
• Student: teacher ratios
• Retention rate by school level
• School completion rates by exit points
• Public spending per student
• Number of suicides
• Causes of accidents
• Dwellings with running water
• Dwellings with electricity
• Number of homeless
• Number of violent crimes
• Birth rate
• Fertility rate
• Gini distribution of income (see Glossary of Terms)
• Infant mortality rate
• Rates of hospitalization
• Rates of HIV infection
• Rates of AIDS deaths
• Number of movie theatres/swimming pools per 1000 residents
• Number of radios/televisions per capita
• Availability of books in traditional languages
• Traditional languages taught in schools
• Time spent on listening to radio/watching television by gender
• Number of programs on television and radio in traditional languages and/or
dealing with traditional customs
• Church participation, by age and gender
The main work of the organization is presenting workshopped plays and/or puppet
shows related to lifeskill issues, especially those lifeskills to do with sexuality, at
schools, across the country. The organization works with a range of age groups, with
different “products” (scripts) being appropriate at different levels.
Puppets against AIDS wanted to develop a monitoring and evaluation system that
provided useful information on the efficiency, effectiveness and impact of its
operations. To this end, it wanted to develop a data base that:
• Provided all the basic information the organization needed about clients and
services given.
• Produced reports that enabled the organization to inform itself and other
stakeholders, including donors, partners and even schools, about the impact of the
work, and what affected the impact of the work.
At an initial workshop with staff, facilitated by consultants, the staff generated a list
of indicators for efficiency, effectiveness and impact, in relation to their work. These
were the things staff wanted to know from the system about what they did, how they
did it, and what difference it made. The terms were defined as follows:
Efficiency Here what needed to be assessed was how quickly, how correctly, how
cost effectively and with what use of resources the services of the
organization were offered. Much of this information was already
collected and was contained in reports which reflected planning
against achievement. It needed to be made “computer friendly”.
Effectiveness Here what needed to be assessed was getting results in terms of the
strategy and shorter-term impact. For example, were the puppet
shows an effective means of communicating messages about
sexuality? Again, this information was already being collected
and just needed to be adapted to fit the computerized system.
Impact Here what needed to be assessed was whether the strategy worked in that it
had an impact on changing behavior in individuals (in this case the
students) and that that change in behavior impacted positively on
the society of which the individuals are a part. The organization
had a strong intuitive feeling that it was working, but wanted to
be able to measure this more scientifically and to be able to look
at what variables made impact more or less likely, or affected the
degree of impact.
Staff generated a list of the different variables that they thought might be important in
assessing and accounting for differences of impact. The monitoring system would
need to link information on impact to these variables. The intention was to provide
both qualitative and quantitative information.
The consultants and a senior staff member then developed measurable indicators of
impact and a tabulation of important variables which included:
The organization indicated that it wanted the system to generate reports that would
enable it to know:
• What difference is there between the indicator ratings on the impact objective
at the beginning and end of the process?
• What difference is there between teacher attitudes at the beginning and end of
the process?
• What variables to do with the school and school environment impact on the
degree of difference between indicators at the beginning and end of the process?
• What variables to do with the way in which the shows are presented impact on
the degree of difference at the beginning and end of the process?
All this was written up as a brief which was given to software experts who then came
up with a system that would meet the necessary requirements. The process was slow
and demanding but eventually the system was in place and it is currently being tested.
FIELDWORKER REPORTING FORMAT
This format was used by an early childhood development learning centre to measure
the following indicators in the informal schools with which it worked:
FIE
LD VISIT REPORT
Date:
Name of school:
--------------------------------------------------------------------------------
-------------
1. List the skills used by the teachers in the time period of your visit to the school:
4. Record-keeping assessment:
Up-to-date
Kind of Up-to-date but not Not up -to- Not attempted
Record and accurate very date
accurate
Bookkeeping
Petty cash
Filing
Correspondence
Stock control
Registers
Many investment projects are addition to existing facilities/ activities and thus
benefits and costs relevant to the new project are those that are incremental to what would
have occurred if the new project had not been added. During the operating life of a project,
it is very important to measure all costs and benefits as the difference between what these
variables would be if no project (without project) were undertaken and what they will be
should the project be implemented (with project). It is very common error to assume that all
costs and benefits are incremental to the new project when, in fact, they are not. Hence,
considerable care must be taken in defining a “base case” which realistically sets out the
profile of costs and benefits expected if no additional investment is undertaken.
• Practical Examples
• Undiscounted Measures
o Profit & Loss Account
o Break-even analysis
o Pay back period
--------------------------------------------------------------------------------------------
*Sensitivity analysis is undertaken under both financial and economic analyses.
Appendix-II
The Project: The objective of the project is to establish of a Soda Ash plant to meet
the domestic demand of the country. The salient features of the project are as under:
• Capital Cost: Million Rs.
o Local Cost 517.12
o F.E.C 198.88
Total: 716.00
• Break down of capital cost
Serial Items Cost
( Rs in million)
1 Land 25.00
2 Civil Works 43.60
3 Machinery (L) 173.61
4 Machinery (F) 163.10
5 Transport 9.00
6 Duty & Taxes 52.20
7 Insurance & Frreight. 12.80
8 Procurement 13.85
9 Transfer of technology 35.78
10 Erection Exp. 33.40
11 Training 2.00
12 Ph.contingencies 28.22
13 Price contingencies 46.15
14 PMU 10.00
15 IDC 67.28
Total: 716.00
• Sources of financing
o Equity Rs. 242 Million 34 %
o Loan Rs.474 Million 76 %
• Terms & conditions of the loan
oInterest rate 11% per annum
oRepayment period 10 years.
oTen annual equal installments with no grace period.
oInterest during construction to be paid
• O & M Cost
Cost (Rs in Million)
Serial Items / Year
Year 1 Year 2 Year 3 Year4-10
VARIABLE COST
1 Sea Salt 7.93 9.25 10.02 11.70
2 Lime Stone 2.25 2.62 3.28 3.47
3 Ammonia 0.9 2.50 3.13 3.31
4 Caustic 2.24 4.12 6.50 6.89
5 Hydrochloric Acid 0.31 0.36 0.45 0.48
6 Gas 0.79 0.92 1.15 1.22
7 Coke 24 27.86 34.83 35.50
8 Electricity 0.5 1.50 2.75 4.50
9 Water 2.8 3.26 4.08 4.32
10 Sales Tax 2.5 3.50 5.91 5.50
11 Packing material 4.92 5.73 6.50 6.19
12 Freight 3.75 4.37 5.46 5.79
13 Marketing expenses 3.50 4.00 4.50 5.00
14 Wages 2.50 3.00 3.50 4.00
FIXED COST
1 Wages 7.5 7.5 7.5 7.5
2 Insurance 2.3 3.5 4.95 5.63
Total: 68.69 84.00 104.50 111.00
Interest rate
Rs in Million % Share Weightage
(%)
Equity 242 34% 8.22 2.78%
Loan 474 66% 11.00 7.28%
Total 716 100 - 10.06%
Results are obtained by using Microsoft Excel i.e. by using the icon ‘fx” on
computer Toolbar.
• Financial Analysis: The following analyses have been undertaken in the financial
analysis.
o Project Financing Annex- A
• Economic Analysis:
o Economic Prices of the output is taken as Rs.35000 per tons.
o The financial capital cost and O&M cost of traded items has been
converted into economic cost by deducting taxes and duties.
o The non – traded costs have been converted into economic cost by
using standard conversion factor of 0.909.
In Economic Analysis, the following analyses have been undertaken:-
Conversion of capital cost into economic cost Annex-O & P
• Loan amount
o Year 0 0
o Year 1 124.00
o Year 2 350.00
Total 474.00
O & M COST
Annex- E
To Appendix-II
Depreciation Schedule
Salvage Value
Amount
Items Cost Rate (Rs in Million)
0.00
1. Land 25.00 100% 25.00
2. Civil works 43.60 75% 32.70
3. Machinery 486.75 15% 73.01
4. Transport 9.00 25% 2.25
5. Training 2.00 0% 0.00
6. Ph.Contingencies 28.22 10% 2.82
Total 626.65 135.78
Annex- G
To Appendix-II
FINANCIAL ANALYSIS OF AN INDUSTRIAL PROJECT
(PROFIT AND LOSS ACCOUNT)
1008.4
• Present Value of Cost (PVC) : 4 (Rs in Million)
1274.9
• Present Value of Benefits (PVB) : 3 (Rs in Million).
• Net Present Value (NPV) : 266.50 (Rs in Million)
• Benefit Cost Ratio (BCR) : 1.26 : 1
• Financial Internal Rate of Return (FIRR) : 17.76%
* Replacement cost of vehicle
Annex- J
To Appendix-II
Year
COST OVER-RUN BY 10% (Rs in Million)
Capital Cost O&M Cost Total Cost Benefit Net Benefits
0 118.78 0.00 118.78 0.00 -118.78
1 253.66 0.00 253.66 0.00 -253.66
2 290.39 0.00 290.39 0.00 -290.39
3 0.00 68.69 68.69 166.25 97.56
4 0.00 84.00 84.00 213.75 129.75
5 0.00 104.50 104.50 237.50 133.00
6 0.00 111.00 111.00 285.00 174.00
7* 9.90 111.00 120.90 285.00 164.10
8 0.00 111.00 111.00 285.00 174.00
9 0.00 111.00 111.00 285.00 174.00
10 0.00 111.00 111.00 285.00 174.00
11 0.00 111.00 111.00 285.00 174.00
12 0.00 111.00 111.00 285.00 174.00
13 -135.78 0.00 -135.78 0.00 135.78
Total 536.94 1034.20 1571.14 2612.50 1041.36
Year
(Rs in Million)
Capital Cost O&M Cost Total Cost Benefit Net Benefits
0 107.98 0.00 107.98 0.00 -107.98
1 230.60 0.00 230.60 0.00 -230.60
2 263.99 0.00 263.99 0.00 -263.99
3 0.00 0.00 0.00 0.00 0.00
4 0.00 68.69 68.69 166.25 97.56
5 0.00 84.00 84.00 213.75 129.75
6 0.00 104.50 104.50 237.50 133.00
7 0.00 111.00 111.00 285.00 174.00
8 * 9.00 111.00 120.00 285.00 165.00
9 0.00 111.00 111.00 285.00 174.00
10 0.00 111.00 111.00 285.00 174.00
11 0.00 111.00 111.00 285.00 174.00
12 0.00 111.00 111.00 285.00 174.00
13 0.00 111.00 111.00 285.00 174.00
14 -135.78 0.00 -135.78 0.00 135.78
Total 475.78 1034.20 1509.98 2612.50 1102.52
(Rs in Million)
Year
Equity Profit after Taxes Depreciation Net Flow
0 112.00 0.00 0.00 -112.00
1 130.00 0.00 0.00 -130.00
2 0.00 0.00 0.00 0.00
3 0.00 -33.27 53.84 20.57
4 0.00 79.91 53.84 133.75
5 0.00 50.19 53.84 104.03
6 0.00 75.09 53.84 128.94
7 0.00 75.09 53.84 128.94
8 0.00 75.09 53.84 128.94
9 0.00 75.09 53.84 128.94
10 0.00 75.09 53.84 128.94
11 0.00 75.09 53.84 128.94
12 0.00 75.09 53.84 128.94
13 -135.78 0.00 0.00 135.78
Total 242.00 622.49 538.43 918.92
( Rs in Million)
Cumulativ
Year O &M Cumulative
Capital Cost Total Cost e Benefits
cost Benefits
Costs
0 107.98 0.00 107.98 107.98 0.00 0.00
1 230.60 0.00 230.60 338.58 0.00 0.00
2 263.99 0.00 263.99 602.57 0.00 0.00
3 0.00 68.69 68.69 671.26 166.25 166.25
4 0.00 84.00 84.00 755.26 213.75 380.00
5 0.00 104.50 104.50 859.76 237.50 617.50
6 0.00 111.00 111.00 970.76 285.00 902.50
7 9.00 111.00 120.00 1090.76 285.00 1187.50
8 0.00 111.00 111.00 1201.76 285.00 1472.50
To Appendix-II
1 2 3 4 5 6 7 8 9 10
1.Land 25.00 0% 0.00 0.00 25.00 1 25.00 25.00
2. Civil Works 6.54 30% 1.96 20% 1.57 4.58 0.909 4.16 5.73
3 Machinery (L) 26.09 100% 26.09 30% 18.26 0.00 0.00 18.26
4. Machinery (F) 24.47 100% 24.47 30% 17.13 0.00 0.00 17.13
5. Transport 1.35 100% 1.35 25% 1.01 0.00 0.00 1.01
6. Duty & Taxes 7.83 0 0.00 0 0.00 7.83 0.00 0.00 0.00
7. Insurance & Fr. 1.92 100% 1.92 10% 1.73 0.00 0.909 0.00 1.73
8. Procurement 2.12 50% 1.06 20% 0.85 1.06 0.00 0.85
9. Technology transfer 5.79 100% 5.79 10% 5.21 0.00 0.00 5.21
10. Erection Exp. 0.00 50% 0.00 15% 0.00 0.00 0.00 0.00
11.Training 0.30 100% 0.30 0% 0.30 0.00 0.00 0.30
12. Ph. Contingencies 5% 5.07 30% 1.52 0% 1.52 3.55 0.00 1.52
13 Price contingencies 6.5% 0.00 0% 0.00 0% 0.00 0.00 0.00 0.00
14 PMU 1.50 0% 0.00 0% 0.00 1.50 0.909 1.36 1.36
15. IDC * 0 0% 0.00 0% 0.00 0.00 0.00 0.00
Total 107.98 7.60 64.46 1.60 47.58 43.52 3.73 30.52 78.11
* IDC & Price contingencies are not treated as a cost in discounted analysis.
Annex- P
To Appendix-II
CONVERSION OF FINANCIAL COST INTO ECONOMIC COST
CAPITAL COST-Y 2 (Rs in Million)
Economic Economic Total
Traded Cost Non- Standard
Item Financial Taxes cost cost (non- Economic
Traded Conversion
Cost % (traded traded Cost
Cost Factor
% Actual items) items) (Col. 6+9)
1 2 3 4 5 6 7 8 9 10
1.Land 0 0% 0.00 0.00 0.00 1 0.00 0.00
2. Civil Works 19.62 30% 5.89 20% 4.71 13.73 0.909 12.48 17.19
3 Machinery (L) 78.26 100% 78.26 30% 54.78 0.00 0.00 54.78
4. Machinery (F) 73.4 100% 73.40 30% 51.38 0.00 0.00 51.38
5. Transport 0 100% 0.00 25% 0.00 0.00 0.00 0.00
6. Duty & Taxes 23.49 0 0.00 0 0.00 23.49 0.00 0.00 0.00
7. Insurance & Fr. 5.76 100% 5.76 10% 5.18 0.00 0.909 0.00 5.18
8. Procurement 6.21 50% 3.11 20% 2.48 3.11 0.00 2.48
9. Technology transfer 17.29 100% 17.29 10% 15.56 0.00 0.00 15.56
10. Erection Exp. 22.2 50% 11.10 15% 9.44 11.10 0.00 9.44
11.Training 0.9 100% 0.90 0% 0.90 0.00 0.00 0.90
12. Ph. Contingencies
5% 12.36 30% 3.71 0% 3.71 8.65 0.00 3.71
13 Price contingencies
6.5% 32.13 0% 0.00 0% 0.00 32.13 0.00 0.00
14 PMU 4.50 0% 0.00 0% 0.00 4.50 0.909 4.09 4.09
15. IDC * 53.64 0% 0.00 0% 0.00 53.64 0.00 0.00
Total 349.75 7.60 199.41 1.60 148.14 150.35 3.73 16.57 164.72
* IDC & Price contingencies are not treated as a cost in discounted analysis.
Annex- Q
To Appendix-II
CONVERSION OF FINANCIAL O&M COST INTO ECONOMIC COST
O & M COST- Year1 (Rs in Million)
Economic
Traded Cost Economic Non- Total
Financial Taxes Standard cost (non-
Item cost Traded Economic
Cost % Conversion traded
(traded Cost Cost
Factor items)
items) (Col 6+9)
% Actual
1 2 3 4 5 6 7 8 9 10
VARIABLE COST
1. Sea Salt 7.93 0 0.00 0 0.00 7.93 0.909 7.21 7.21
2. Lime Stone 2.25 0 0.00 0 0.00 2.25 0.909 2.05 2.05
3. Ammonia 0.9 100% 0.90 30% 0.63 0.00 0.00 0.63
4. Caustic 2.24 100% 2.24 25% 1.68 0.00 0.00 1.68
5. Hydrochloric Acid 0.31 100% 0.31 20% 0.25 0.00 0.00 0.25
6. Gas 0.79 0 0.00 0 0.00 0.79 2 1.58 1.58
7. Coke 24 100% 24.00 32.5% 16.20 0.00 0.00 16.20
8. Electricity 0.5 0 0.00 0 0.00 0.50 1 0.50 0.50
9. Water 2.8 0 0.00 0 0.00 2.80 2 5.60 5.60
10. Sales Tax 2.5 0 0.00 0 0.00 2.50 0 0.00 0.00
11. Packing material 4.92 50% 2.46 40% 1.48 2.46 0.909 2.24 3.71
12. Freight 3.75 50% 1.88 0 1.88 1.88 0.909 1.70 3.58
13 Marketing expenses 3.5 50% 1.75 32% 1.19 1.75 0.909 1.59 2.78
14 Wages 2.5 0% 0.00 0 0.00 2.50 1 2.50 2.50
FIXED COST
1.Management 7.5 0% 0.00 0 0.00 7.50 1 7.50 7.50
2. Insurance 2.3 0 0.00 0 0.00 2.30 1 2.30 2.30
Total 68.69 - 33.54 1.80 23.30 35.16 12.55 34.76 58.06
Annex- R
To Appendix-II
CONVERSION OF FINANCIAL O&M COST INTO ECONOMIC COST
O & M COST- Year 2 (Rs in Million)
Economic
Traded Cost Economic Non- Total
Financial Taxes Standard cost (non-
Item cost Traded Economic
Cost % Conversion traded
(traded Cost Cost
Factor items)
items) (Col 6+9)
% Actual
1 2 3 4 5 6 7 8 9 10
VARIABLE COST
1. Sea Salt 9.25 0 0.00 0 0.00 9.25 0.909 8.41 8.41
2. Lime Stone 2.62 0 0.00 0 0.00 2.62 0.909 2.38 2.38
3. Ammonia 2.50 100% 2.50 30% 1.75 0.00 0.00 1.75
4. Caustic 4.12 100% 4.12 25% 3.09 0.00 0.00 3.09
5. Hydrochloric Acid 0.36 100% 0.36 20% 0.29 0.00 0.00 0.29
6. Gas 0.92 0 0.00 0 0.00 0.92 2 1.84 1.84
7. Coke 27.86 100% 27.86 32.5% 18.81 0.00 0.00 18.81
8. Electricity 1.50 0 0.00 0 0.00 1.50 1 1.50 1.50
9. Water 3.26 0 0.00 0 0.00 3.26 2 6.52 6.52
10. Sales Tax 3.50 0 0.00 0 0.00 3.50 0 0.00 0.00
11. Packing material 5.73 50% 2.87 40% 1.72 2.87 0.909 2.61 4.32
12. Freight 4.37 50% 2.18 25% 1.64 2.18 0.909 1.99 3.62
13 Marketing expenses 4.00 50% 2.00 32% 1.36 2.00 0.909 1.82 3.18
14 Wages 3.00 0% 0.00 0 0.00 3.00 1 3.00 3.00
FIXED COST
1.Management 7.50 0% 0.00 0 0.00 7.50 1 7.50 7.50
2. Insurance 3.50 0 0.00 0 0.00 3.50 1 3.50 3.50
Total 84.00 - 41.89 2.05 28.65 42.11 12.55 41.07 69.72
Annex- S
To Appendix-II
CONVERSION OF FINANCIAL O&M COST INTO ECONOMIC COST
O & M COST- Year 4 (Rs in Million)
Economic
Traded Cost Economic Non- Total
Financial Taxes Standard cost (non-
Item cost Traded Economic
Cost % Conversion traded
(traded Cost Cost
Factor items)
items) (Col 6+9)
% Actual
1 2 3 4 5 6 7 8 9 10
VARIABLE COST
1. Sea Salt 11.70 0 0.00 0 0.00 11.70 0.909 10.63 10.63
2. Lime Stone 3.47 0 0.00 0 0.00 3.47 0.909 3.16 3.16
3. Ammonia 3.31 100% 3.31 30% 2.32 0.00 0.00 2.32
4. Caustic 6.89 100% 6.89 25% 5.17 0.00 0.00 5.17
5. Hydrochloric Acid 0.48 100% 0.48 20% 0.38 0.00 0.00 0.38
6. Gas 1.22 0 0.00 0 0.00 1.22 2 2.44 2.44
7. Coke 35.50 100% 35.50 32.5% 23.96 0.00 0.00 23.96
8. Electricity 4.50 0 0.00 0 0.00 4.50 1 4.50 4.50
9. Water 4.32 0 0.00 0 0.00 4.32 2 8.64 8.64
10. Sales Tax 5.50 0 0.00 0 0.00 5.50 0 0.00 0.00
11. Packing material 6.19 50% 3.10 40% 1.86 3.10 0.909 2.81 4.67
12. Freight 5.79 50% 2.89 0 2.89 2.89 0.909 2.63 5.53
13 Marketing expenses 5.00 50% 2.50 32% 1.70 2.50 0.909 2.27 3.97
14 Wages 4.00 0% 0.00 0 0.00 4.00 1 4.00 4.00
FIXED COST
1.Management 7.50 0% 0.00 0 0.00 7.50 1 7.50 7.50
2. Insurance 5.63 0 0.00 0 0.00 5.63 1 5.63 5.63
Total 111.00 - 54.67 1.80 38.28 56.33 12.55 54.22 92.50
Appendix-III
ADT
Serial Mode of Transport
(Base Year)
1 Motor Cycle 100
2 Car/ Jeep 3950
3 Mini Bus/ Pickup 1525
4 Bus 403
5 Tractor Trolleys 500
6 Trucks 187
• Traffic Growth: Traffic growth rate per annum of 2 % during construction period and
5%, 4%, 3% and 2% for the first, 2nd, 3rd and 4th five years respectively over the life of the
project has been assumed. Based on the above growth rates, the traffic projections are
given at Annex-A.
• Proposed Toll Tax
Proposed
Serial Mode of Transport
Toll Tax (Rs)
1 Car/Jeep 20.00
2 Mini Bus/Pickup 30.00
3 Bus 80.00
4 Trucks 100.00
Based on the above toll, the revenues are also given at Annex-A
• Economic cost: The financial cost has been converted into economic cost by deducting
taxes and duties from the traded cost and the non-traded cost has been multiplied by the
• Economic Benefits: Per vehicle economic benefits have been worked out and given at
Annex-G. The value of savings in travel time, VOC and reduction in distance have
been assumed as under:
o Savings in Travel Time:
Value of T. Time
Serial Mode of Transport
Rupees/ Hour
1 Car 150
2 Pickup/ wagon 120
3 Bus 350
4 Truck (Light) 120
5 Truck (Medium) 150
6 Truck (Heavy) 175
The details of the benefits on account of savings in Travel Time are given at
Annex-H.
o Savings in Vehicles Operating Cost (VOC):
Without Project With Project
Savings
Vehicle Speed VOC Speed VOC
(Rs/
Type (km/hr (Rs/ (km/hr (Rs/
km)
) km) ) km)
Car 50 11.50 70 10.50 1.00
Wagon 40 9.68 60 8.40 1.28
Bus 35 19.79 55 17.76 2.03
Truck 30 20.81 50 18.71 2.10
(All
Types)
The details of savings in VOC for are given at Annex- J. (The benefits on
account of Motor Cycle and Tractor Trolleys have not been taken into account
being a traffic hazard)
o Benefits on account of 5 kms reduction in distance: (Annex-K)
• Result of Economic Analysis: The economic analysis of the project has been carried out
and are given in the following annexes:-
o Economic Analysis(EIRR,NPV & BCR) Annex-L
Annex- B
To Appendix – III
FINANCIAL ANALYSIS
CONSTRUCTION OF 20 KM ROAD
(Rs in Million)
YEAR CAPITAL O & M TOTAL BENEFITS NET
COST COST COST (Toll Revenue) BENEFITS
0 603.50 0.00 603.50 0.00 -603.50
1 691.50 0.00 691.50 0.00 -691.50
2 0.00 12.95 12.95 70.05 57.10
3 0.00 12.95 12.95 73.56 60.61
4 0.00 12.95 12.95 77.23 64.28
5 0.00 12.95 12.95 81.10 68.15
6 0.00 64.75 64.75 85.15 20.40
7 0.00 12.95 12.95 88.56 75.61
8 0.00 12.95 12.95 92.10 79.15
9 0.00 12.95 12.95 95.78 82.83
10 0.00 12.95 12.95 99.61 86.66
11 0.00 64.75 64.75 103.60 38.85
12 0.00 12.95 12.95 106.71 93.76
13 0.00 12.95 12.95 109.91 96.96
14 0.00 12.95 12.95 113.20 100.25
15 0.00 12.95 12.95 116.60 103.65
16 0.00 64.75 64.75 120.10 55.35
17 0.00 12.95 12.95 122.50 109.55
18 0.00 12.95 12.95 124.95 112.00
19 0.00 12.95 12.95 127.45 114.50
20 0.00 12.95 12.95 130.00 117.05
21 0.00 12.95 12.95 132.60 119.65
TOTAL: 1295.00 414.40 1709.40 2070.76 361.36
Annex- D
To Appendix – III
FINANCIAL ANALYSIS
CONSTRUCTION OF 20 KM ROAD
SENSITIVITY ANALYSIS - Benefits delayed by one year (Rs in Million)
YEAR CAPITAL O&M TOTAL BENEFITS NET
COST COST COST BENEFITS
0 603.50 0.00 603.50 0.00 -603.50
1 691.50 0.00 691.50 0.00 -691.50
2 0.00 0.00 0.00 0.00 0.00
3 0.00 12.95 12.95 70.05 57.10
4 0.00 12.95 12.95 73.56 60.61
5 0.00 12.95 12.95 77.23 64.28
6 0.00 12.95 64.75 81.10 16.35
7 0.00 64.75 12.95 85.15 72.20
8 0.00 12.95 12.95 88.56 75.61
9 0.00 12.95 12.95 92.10 79.15
10 0.00 12.95 12.95 95.78 82.83
11 0.00 12.95 64.75 99.61 34.86
12 0.00 64.75 12.95 103.60 90.65
13 0.00 12.95 12.95 106.71 93.76
14 0.00 12.95 12.95 109.91 96.96
15 0.00 12.95 12.95 113.20 100.25
16 0.00 12.95 64.75 116.60 51.85
17 0.00 64.75 12.95 120.10 107.15
18 0.00 12.95 12.95 122.50 109.55
19 0.00 12.95 12.95 124.95 112.00
20 0.00 12.95 12.95 127.45 114.50
21 0.00 12.95 12.95 130.00 117.05
22 0.00 12.95 0.00 132.60 132.60
TOTAL: 1295.00 401.45 1683.50 1808.16 124.66
Annex- E
To Appendix – III
FINANCIAL ANALYSIS
(BREAK-EVEN TOLL TAX)
CONSTRUCTION OF 20 KM ROAD
(Rs in Million)
Traffic Cars
YEAR CAPITAL O & M TOTAL Equivalent
COST COST COST
1 603.50 0.00 603.50 0.00
2 691.50 0.00 691.50 0.00
3 0.00 12.95 12.95 3267420
4 0.00 12.95 12.95 3430791
5 0.00 12.95 12.95 3602331
6 0.00 12.95 12.95 3782447
7 0.00 64.75 64.75 3971569
8 0.00 12.95 12.95 4130432
9 0.00 12.95 12.95 4295650
10 0.00 12.95 12.95 4467476
11 0.00 12.95 12.95 4646175
12 0.00 64.75 64.75 4832022
13 0.00 12.95 12.95 4976982
14 0.00 12.95 12.95 5126292
15 0.00 12.95 12.95 5280080
16 0.00 12.95 12.95 5438483
17 0.00 64.75 64.75 5601637
18 0.00 12.95 12.95 5713670
19 0.00 12.95 12.95 5827943
20 0.00 12.95 12.95 5944502
21 0.00 12.95 12.95 6063392
22 0.00 12.95 12.95 6184660
TOTAL: 1295.00 414.40 1709.40 96583954
Cont-
Annex- E
To Appendix – III
FINANCIAL ANALYSIS
(BREAK-EVEN TOLL TAX)
CONSTRUCTION OF 20 KM ROAD
(Rs in Million)
YEAR Cars Pickup/ Buses Total
Trucks
Wagons
Time Value Rs. 150/ hr Rs. 120/ hr Rs.350 /hr Rs.175/ hr
1 50.62 21.28 19.72 5.65 97.28
2 53.16 22.35 20.71 5.94 102.15
3 55.81 23.46 21.74 6.23 107.25
4 58.60 24.64 22.83 6.55 112.62
5 61.53 25.87 23.97 6.87 118.25
6 64.00 26.90 24.93 7.15 122.98
7 66.56 27.98 25.93 7.43 127.90
8 69.22 29.10 26.96 7.73 133.01
9 71.99 30.26 28.04 8.04 138.33
10 74.87 31.47 29.16 8.36 143.87
11 77.11 32.42 30.04 8.61 148.18
12 79.43 33.39 30.94 8.87 152.63
13 81.81 34.39 31.87 9.14 157.21
14 84.26 35.42 32.82 9.41 161.92
15 86.79 36.49 33.81 9.69 166.78
16 88.53 37.22 34.49 9.89 170.12
17 90.30 37.96 35.18 10.09 173.52
18 92.10 38.72 35.88 10.29 176.99
19 93.95 39.49 36.60 10.49 180.53
20 95.82 40.28 37.33 10.70 184.14
Annex- J
To Appendix – III
BENEFITS ON ACCOUNT OF SAVING IN VOC
CONSTRUCTION OF 20 KM ROAD
(Rs in Million)
YEAR
Pickup/ Total
Cars Buses Trucks
Wagons Benefits
Savings/ Km Rs. 1.00 Rs.1.00 Rs. 2.03 Rs. 2.10
1 39.37 19.46 8.15 3.91 70.90
2 41.34 20.43 8.56 4.11 74.45
3 43.41 21.45 8.99 4.32 78.17
4 45.58 22.53 9.44 4.53 82.08
5 47.86 23.65 9.91 4.76 86.18
6 49.77 24.60 10.31 4.95 89.63
7 51.77 25.58 10.72 5.15 93.22
8 53.84 26.60 11.15 5.35 96.94
9 55.99 27.67 11.60 5.57 100.82
10 58.23 28.78 12.06 5.79 104.85
11 59.98 29.64 12.42 5.96 108.00
12 61.78 30.53 12.79 6.14 111.24
13 63.63 31.44 13.18 6.33 114.58
14 65.54 32.39 13.57 6.52 118.01
15 67.50 33.36 13.98 6.71 121.55
16 68.85 34.03 14.26 6.85 123.99
17 70.23 34.71 14.55 6.98 126.47
18 71.64 35.40 14.84 7.12 129.00
19 73.07 36.11 15.13 7.26 131.57
20 74.53 36.83 15.44 7.41 134.21
Annex- K
To Appendix – III
Pickup/ Total
YEAR Cars Buses Trucks
Wagons Benefits
(Rs in Mn) (Rs in Mn) (Rs in Mn)
(Rs in Mn) (Rs in Mn)
Savings/ Km(Rs.) 11.50 9.68 19.79 20.81
1 90.56 29.43 15.90 7.76 143.65
2 95.09 30.90 16.70 8.15 150.83
3 99.84 32.45 17.53 8.55 158.38
4 104.84 34.07 18.41 8.98 166.29
5 110.08 35.77 19.33 9.43 174.61
6 114.48 37.20 20.10 9.81 181.59
7 119.06 38.69 20.90 10.20 188.86
8 123.82 40.24 21.74 10.61 196.41
9 128.78 41.85 22.61 11.03 204.27
10 133.93 43.52 23.51 11.47 212.44
11 137.95 44.83 24.22 11.82 218.81
12 142.08 46.17 24.95 12.17 225.38
13 146.35 47.56 25.69 12.54 232.14
14 150.74 48.99 26.47 12.91 239.10
15 155.26 50.46 27.26 13.30 246.27
16 158.36 51.46 27.80 13.57 251.20
17 161.53 52.49 28.36 13.84 256.22
18 164.76 53.54 28.93 14.11 261.35
19 168.06 54.61 29.51 14.40 266.58
20 171.42 55.71 30.10 14.69 271.91
Annex- L
To Appendix – III
ECONOMIC ANALYSIS
CONSTRUCTION OF 20 KM ROAD
BENEFITS
CAPITAL O&M TOTAL Reduction Net
YEAR Time
COST COST COST VOC of Total Benefits
Savings
Distance
0 572.95 0.00 572.95 0 0 0 0 -572.95
1 592.45 0.00 592.45 0 0 0 0 -592.45
2 0.00 11.65 11.65 97.28 70.90 143.65 311.84 300.18
3 0.00 11.65 11.65 102.15 74.45 150.83 327.43 315.77
4 0.00 11.65 11.65 107.25 78.17 158.38 343.80 332.15
5 0.00 11.65 11.65 112.62 82.08 166.29 360.99 349.34
6 0.00 58.27 58.27 118.25 86.18 174.61 379.04 320.77
7 0.00 11.65 11.65 122.98 89.63 181.59 394.20 382.55
8 0.00 11.65 11.65 127.90 93.22 188.86 409.97 398.31
9 0.00 11.65 11.65 133.01 96.94 196.41 426.37 414.71
10 0.00 11.65 11.65 138.33 100.82 204.27 443.42 431.77
11 0.00 58.27 58.27 143.87 104.85 212.44 461.16 402.89
12 0.00 11.65 11.65 148.18 108.00 218.81 474.99 463.34
13 0.00 11.65 11.65 152.63 111.24 225.38 489.24 477.59
14 0.00 11.65 11.65 157.21 114.58 232.14 503.92 492.27
15 0.00 11.65 11.65 161.92 118.01 239.10 519.04 507.38
16 0.00 58.27 58.27 166.78 121.55 246.27 534.61 476.34
17 0.00 11.65 11.65 170.12 123.99 251.20 545.30 533.65
18 0.00 11.65 11.65 173.52 126.47 256.22 556.21 544.55
19 0.00 11.65 11.65 176.99 129.00 261.35 567.33 555.68
20 0.00 11.65 11.65 180.53 131.57 266.58 578.68 567.03
21 0.00 11.65 11.65 184.14 134.21 271.91 590.25 578.60
TOTAL: 1165.40 361.27 1526.67 2691.51 1961.65 3974.38 8627.54 7100.87
Cont-
Annex- L
To Appendix – III
ECONOMIC ANALYSIS
CONSTRUCTION OF 20 KM ROAD
Annex- M
To Appendix – III
ECONOMIC ANALYSIS
CONSTRUCTION OF 20 KM ROAD
93
Appendix-IV
Example – Social Sector Project
Establishment of a Computer Institute: M/S ABC has planned to establish a
Computer Institute. The project is designed to impart I.T education to the students. The statistical
data provided by the sponsors and used in undertaking the Unit Cost analysis is as follows:
• Capital Cost
Capital Cost
Years
(Rs in Million)
1 40.250
2 75.170
3 45.330
4 38.923
Total 199.673
Annual Revenue
Details / Year st
1 Year 2 Year 3rd Year 4th Year
nd
95
PART-III
CHAPTER-VIII
MONITERING & EVALUATION PROFORMAS
96
Revised 2005
PC-1 FORM
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
(INFRASTRUCTURE SECTORS)
• Telecommunication
• Information Technology
97
Revised 2005
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
PC-1 FORM
(INFRASTRUCTURE SECTORS)
1. Name of the project
2. Location
4. Plan provision
98
13. Management structure and manpower requirements including specialized skills
during construction and operational phases
15. Certified that the project proposal has been prepared on the basis of instructions
provided by the Planning Commission for the preparation of PC-I for
Infrastructure sector projects.
Prepared by _______________________
Name, Designation & Phone #
Checked by _______________________
Name, Designation & Phone #
Approved by _______________________
Name, Designation & Phone #
99
Revised 2005
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
Instructions to Fill-in PC-I Proforma(Infrastructure Sectors)
2. Location
• Provide name of the district/province.
• Attach a map of the area, clearly indicating the project location.
5. Project Objectives
• The objectives of the sector/sub sector as indicated in the medium term/five year
plan be reproduced. Indicate objectives of the project and develop a linkage
between the proposed project and sectoral objectives.
• In case of revised Projects, indicate objectives of the project if different from
original PC-I.
6. Description and Justification of Project (enclose feasibility study for projects costing
Rs.300 million & above.)
Describe the project and indicate existing facilities in the area and justify
the establishment of the Project.
Provide technical parameters i.e. input and output of the project. `Also
discuss technological aspect of the project.
Provide details of civil works, equipment, machinery and other physical
facilities required for the project.
100
Indicate governance issues of the sector relevant to the project and
strategy to resolve them.
• Provide technical parameters i.e. selected design features and capacity of the
proposed facilities alongwith alternates available.
• For roads, provide information regarding land width, geometric and pavement
design including formation width, pavement width.
• Design speed, traffic capacity of road in terms of passenger car units per day.
• Saving in distance for diverted traffic. Average daily traffic of motor vehicles
by category as well as the car units be provided.
• In case of improvement within the urban areas, separate traffic counts within
that area should be given. Brief information regarding traffic and pavement
width etc. in adjoining sections should also be given.
•For bridges provide location, total length of bridge, number of spans with
length of each span, width roadway and footpath, type of sub and
superstructure and load classification.
Telecommunication
• Mention alternate means of providing the same facilities (for example microwaves
verses optic fiber cable, underground cable versus overhead cable etc.) and the cost
of each of the alternatives means.
Information Technology
Fuel
• Detailed description of major equipments, items and structure.
• Provide basis of design of the project.
• Indicate alternate technology alongwith the selected one with justification.
• For exploration projects give details of previously work undertaken.
101
Power
• Give detailed description of major equipment and structure.
• For Hydroelectric projects: Give information regarding geological investigations,
flow duration curve, water storage, estimated monthly kilowatt hours generation
under minimum and average flow conditions and the flow conditions assumed in
the project and operational regime i.e. base load or peak load plant. Rainfall
record, stream flow calculation, hydrograph and other available water data
alongwith siltation problems be provided.
• For thermal projects: Give information on sources and availability of cooling
water and fuel, calorific value, heat rate price (with custom duties and taxes shown
separately) and disposal of ash and effluents.
• Give a comprehensive, comparison of available technology and rationale/criteria
for selection of specified technology.
• Provide analysis of adopted technology with respect to existing system.
• Indicate whether maintenance facilities are available. If not, provide details/plans
for maintenance facilities.
• For transmission and distribution system: Basis of design voltage drop allowance
system stability, reliability, operating voltage, policy regarding reserves, design and
material to be used for supporting structure, average span length and conductor
size, type of spacing.
• Load flow studies for the year in which plant is proposed to be commissioned and
five years thereafter.
• For sub-stations and switching stations: Give location and purpose of each station
KVA voltage, type and structure, number of circuits, type of transformers and
major circuit breakers.
• Load conditions of the existing facilities, in case of extention facilities.
• In case of new projects, loading conditions of sub stations be provided.
• Provide alternate designs and proposed design features of the project, keeping in view
the income levels, family size of the population to be served alongwith weather
conditions etc.
• Mention the nature and size of land available and indicate whether the design ensures
the most economical use of space.
• Indicate whether the project is in consonance with the master plan of the city.
• Town Planning and covered area parameters/space standards applied in determining
land and flood area requirements.
• Specifications of the civil works.
102
7. Capital cost estimates
• Phasing of capital cost be worked out on the basis of each item of work as stated
above and provide as per following:
Sources of financing
103
(a) Equity:
b) Debt
Indicate the local & foreign debt, interest rate, grace period and repayment
period for each loan separately. The loan repayment schedule be also annexed.
• Financial analysis
104
• Economic analysis
• Provide taxes & duties separately in the capital and operating cost
• Net present value (NPV) and benefit cost ratio (BCR)
• Internal economic rate of Return (IERR)
• Employment analysis
• Sensitivity analysis
105
14. Additional projects/decisions required
15. Certificate
• The name, designation and Phone # of the officer responsible for preparing
and checking be provided. It may also be confirmed that PC-I has been
prepared as per guidelines issued by the Planning Commission for the
preparation of PC-I for Infrastructure Sector projects.
106
Revised 2005
PC-1 FORM
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
(SOCIAL SECTORS)
• Mass Media
• Governance
• Research
107
Revised 2005
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
PC-1 FORM
(SOCIAL SECTORS)
2. Location
v. Sponsoring
vi. Execution
vii. Operation and maintenance
viii. Concerned federal ministry
4. Plan Provision
i. Financial
ii. Social benefits with indicators
iii. Employment generation (direct and indirect)
iv. Environmental impact
v. Impact of delays on project cost and viability
108
14. Additional projects/decisions required to maximize socio-economic
benefits from the proposed project
15. Certified that the project proposal has been prepared on the basis of
instructions provided by the Planning Commission for the preparation of
PC-I for Social Sector projects.
Prepared by _________________________
Name, Designation & Phone#
Checked by _________________________
Name, Designation & Phone#
Approved by _________________________
Name, Designation & Phone#
109
Revised 2005
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
Instructions to Fill-in PC-I Proforma(Social Sectors)
1. Name of the Project
Indicate name of the project.
2. Location
• Provide name of District/Province.
• Attach a map of the area, clearly indicating the project location.
3. Authorities responsible for
Indicate name of the agency responsible for sponsoring, execution, operation and
maintenance. For provincial projects, name of the concerned federal ministry be
provided.
4. (a) Plan provision
Describe the project and indicate existing facilities in the area and justify
the establishment of the Project.
Provide technical parameters and discuss technology aspect of the
Project.
Provide details of civil works, equipment, machinery and other physical
facilities required for the project.
Indicate governance issues of the sector relevant to the project and
strategy to resolve them.
110
In addition to above, the following sector specific information be provided
• Give student-teacher ratio for the project and the national average for the proposed
level of education.
• Year-wise proposed enrolment of the institution for 5 years.
• For scholarship projects, indicate number of scholarships to be awarded each year
alongwith selection criteria .
• Provide faculty strength in relevant discipline, in case of expansion of facilities.
• Indicate the extent of library and laboratory facilities available in case of secondary,
college and university education.
• Provide details of technical staff required for operation & maintenance of laboratories.
a) Health projects
b) Nutrition
c) Family planning
111
• Capacity of existing departments to maintain archaeological sites/museums.
• Relationship of archaeological projects with internal and foreign tourism.
Mass media
• Indicate area and population to be covered with proposed project.
Research
• Indicate benefits of the research to the economy.
• Mention number of studies/papers to be produced.
• Indicate whether these studies would result in commercial application of the process
developed (if applicable).
7. Capital cost estimates
Indicate date of estimation of Project cost.
Basis of determining the capital cost be provided. It includes market survey,
schedule rates, estimation on the basis of previous work done etc.
Provide year-wise estimates of Physical activities by main components
as per following:
Component-wise, year-wise physical activities
112
governance & culture, sports & tourism sectors
• Existing capacity of services and its supply
• Projected demand for ten years
• Capacity of projects being implemented both in the public & private sector
• Supply – demand gap
• Designed capacity & output of the proposed project
10. Financial plan
Sources of financing
(a) Equity:
Indicate the amount of equity to be financed from each source
Sponsors own resources
Federal government
Provincial government
DFI's/banks
General public
Foreign equity (indicate partner agency)
NGO’s/beneficiaries
Others
b) Debt
Indicate the local & foreign debt, interest rate, grace period and repayment
period for each loan separately. The loan repayment schedule be also annexed.
15. Certificate
• The name, designation and phone # of the officer responsible for , preparing
and checking be provided. It may also be confirmed that PC-I has been
prepared as per instructions for the preparation of PC-I for social sector
projects.
• The PC-I alongwith certificate must be signed by the Principal Accounting
Officer to ensure its ownership.
114
Revised 2005
PC-1 FORM
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
(PRODUCTION SECTORS)
• Agriculture Production
• Agriculture Extension
• Industries, Commerce
And Minerals
115
Revised 2005
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
PC-1 FORM
(PRODUCTION SECTORS)
1. Name of the project
2. Location
3. Authorities responsible for:
ix. Sponsoring
x. Execution
xi. Operation and maintenance
xii. Concerned federal ministry
4. Plan provision
5. Project objectives and its relationship with sector objectives
6. Description, justification, technical parameters and technology transfer aspects
(enclose feasibility study for projects costing Rs 300 million and above)
Prepared by ______________________
Name, Designation & Phone #
Checked by _______________________
Name, Designation & Phone #
116
Approved by _______________________
Name, Designation & Phone #
117
Revised 2005
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
Instructions to Fill-in PC-I Proforma (Production Sector)
1. Name of the Project
Indicate name of the project.
2. Location
• Provide name of district and province.
• Attach a map of the area, clearly indicating the projects location.
4. Authorities responsible for
• Indicate name of the agency responsible for sponsoring, execution, operation
and maintenance
• In case of more than one agency, give their component-wise responsibility.
For provincial projects, name of the concerned federal ministry be provided.
Agriculture extension
Provide history of extension work in and around project area and justify the
extension work.
Provide transport, equipment and field machinery etc available with the
department.
119
Total
120
• Social: Benefits with indicators
• The name, designation and phone # of the officer responsible for preparing
and checking be provided. It may also be confirmed that PC-I has been
prepared as per instructions issued by the Planning Commission for the
preparation of PC-I for Production Sector projects.
• The PC-I alongwith certificate must be signed by the Principal Accounting
Officer to ensure its ownership.
122
Revised 2005
PC-II FORM
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
123
Revised 2005
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
PC-1I FORM
PROFORMA FOR DEVELOPMENT PROJECTS
(SURVEY AND FEASIBILITY STUDIES)
.
i) Sponsoring
ii) Execution
3) Details of survey/feasibility study
Prepared by _______________________
Name, Designation & Phone #
Checked by _______________________
Name, Designation & Phone #
Approved by _______________________
Name, Designation & Phone #
124
Revised 2005
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
Instructions to fill in PC-II Proforma
2. Administrative authority
Indicate name of the agency responsible for sponsoring and execution of the
project.
4. Expected outcome
125
PC-III (a) Form
(Revised – 2005)
Government of Pakistan
Planning Commission
Implementation of Development Projects
(Physical Targets based on PSDP allocation)
To be furnished by 1st July of each year
1. Name of the Project:
(Million Rs)
2. Approved Capital Cost:
(Million Rs)
3. Expenditure up to the end of Actual Accrued Total
last Financial Year:
(Million Rs)
4. PSDP allocations for the Total Local FEC
Current year:
5. Annual Work Plan:
As per PC-IAchievements Target for
Item Unit Quantities upto the end current year
of last year
7. Cash Plan:
(Rs
Millions)
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
8. Output indicators:
(Revised 2005)
126
Government of Pakistan
Planning Commission
Instructions to fill-in PC-III (a) Proforma
1. Name of the Project:
Indicate name of the project.
2. Approved capital cost:
Provide approved capital cost by the competent forum.
3. Expenditure upto the end of last financial year:
Provide the actual and accrued expenditure upto end of last
financial year.
4. PSDP allocations for the current year:
Provide allocations for the project as shown in the
PSDP/ADP.
5. Annual Work Plan:
8. Output indicators:
A number of projects start yielding results during its
implementation. In such projects the recurring cost is
capitalized and the project start yielding results during its
implementation. Indicate quantifiable outcome of the
projects for the current year.
1. Name of project:
(Million Rs.)
2. Financial Status
((Million Rs)
• PSDP allocations for the
Current year
(Million Rs)
• Current quarter
requirements as per cash
plan
(Million Rs)
• Releases during the
month
(Million Rs)
• Expenditure during the month
3. Physical Status
Physical achievements during the month under report
4. Output Indicators
(Revised 2005)
Government of Pakistan
128
Planning Commission
Instructions to fill-in PC-III(B) Proforma
3. Physical status:
4. Output indicators:
5. Issues/Bottlenecks:
Revised 2005
PC-IV FORM
129
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
From PC-IV
Revised 2005
Government of Pakistan
Planning Commission
To be furnished immediately after completion of Project regardless of
whether or not the accounts of the Project have been closed.
2. Implementation period:
130
Commencement Completion
a) As per PC-I:
131
b) As per actual:
3. Capital cost:
Planned Actual
Rs in Million
a) Financial
b) Economic
c) Social
d) Employment generated
8. Financial/Economic results based on actual cost:
a) Financial
b) Economic
a) Project identification
b) Project preparation
c) Project approval
d) Project financing
e) Project implementation
12. Suggestions for planning & implementation of similar projects:
(Revised 2005)
Government of Pakistan
Planning Commission
Instructions to fill in PC-IV Proforma
1. Name of the project: Indicate name of the project.
PC-V FORM
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
Anecdotal information: Anecdotal information is information that comes in the form of stories
people remember that are relevant to the indicators you are interested in. They do not have scientific
validity, but they can provide useful qualitative information.
Baseline data: Baseline information comes from a study done before an intervention. It provides
you with data (information) about the situation before an intervention. This information is very
important when you get to monitoring and evaluation as it enables you to assess what difference the
intervention has made.
Bottom line: In business, bottom line refers to the bottom line of your profit and loss report – it
tells you whether or not you are making a profit. This is how business assesses success. In
development work, the “bottom line” is -Are we making a difference to the problem or not?
Efficiency, effectiveness, impact: Efficiency tells you that the input into the work is
appropriate in terms of the output. This could be input in terms of money, time, staff, equipment
and so on. Effectiveness is a measure of the extent to which a development program or project
achieves the specific objectives it set. Impact tells you whether or not what you did made a difference
to the problem situation you were trying to address. In other words, was your strategy useful?
Gini distribution of income: The difference between the top end and bottom end of the
economic scale in a society.
Go to scale: Take a project from dealing with small numbers of beneficiaries to dealing with
large numbers of beneficiaries.
Indicators: Indicators are a measurable or tangible sign that something has been done. So, for
example, an increase in the number of students passing is an indicator of an improved culture of
learning and teaching. The means of verification (proof) is the officially published list of passes.
Opportunity costs: Opportunity costs are the opportunities you give up when you decide to do
one thing rather than another. For example, If you spend your money upgrading teachers, you give
up the opportunity of using the money to buy more text books. You have to decide which one is the
better use of the money.
Outputs: Outputs here usually include a draft written report, a verbal presentation, a final written
report in hard copy and electronic form (specifying program compatibility). They can also include
interim reports, interview schedules that must be signed off by the client and so on.
Progress data: This is data (information) that you get during the monitoring of the progress of the
project.
Qualitative: Qualitative data or information deals with how people feel about something,
opinions, experiences, rather than with numbers (quantitative data).
Rigorous: Disciplined, thorough and done with honesty and integrity.
Sampling: Sampling is a way of selecting who to speak to, who to interview, who to survey when
you are doing an evaluation, and cannot cover all the cases that exist.
Secondary data: Secondary data is information that already exists, collected by other people,
organizations. If it comes from your own organization it is primary data. Primary data is
information collected by you – from other project stakeholders, the general population, your own
observation and so on.
Terms of Reference: Terms of Reference form the basis on which you ask for proposals and
against which you assess what you are getting. They should include: some background to the project
and/or organization, what the purpose of the evaluation is (why you want it done), the key evaluation
questions you want answered, the specific aspects you want included (although this should be open to
negotiation), the kinds of methodologies you have in mind (again, open to negotiation), the outputs
you expect, the time frame for both submission of proposals and for doing the evaluation.
Variable: A variable is a changing element of the situation which may or may not affect
efficiency, effectiveness and/or impact, and which you want to be able to link to other variables in
your indicators. Income level of parents in a school is a variable, so is location in terms of rural or
urban areas.