Beruflich Dokumente
Kultur Dokumente
This report has been classified confidential in accordance with the provisions of the Local
Government Act 1993 (Act) as follows:
- Section 10A(2)(d) of the Act provides that Council can close a meeting to consider
commercial information of a confidential nature that would if disclosed prejudice the
commercial position of the person who supplied it.
- Section 10B(1)(a) and (b) of the Act provides that the discussion of the item in a
closed meeting must only:
(a) include as much of the discussion as is necessary to preserve the relevant
confidentiality, privilege or security; and
(b) occur if the Council is satisfied that discussion of the matter in an open meeting
would, on balance, be contrary to the public interest.
In respect to section 10D(2) of the Act, the grounds on which part of a meeting is to be
closed for the discussion of the particular item must be stated in the decision to close that
part of the meeting and must be recorded in the minutes of the meeting. Accordingly, an
appropriate resolution to proceed is required first.
MOTION TO PROCEED
The discussion of the confidential report take place in a closed session, with the press and
public excluded, for the following reasons:
A The matter relates to tenders for the Organics Processing Facility - Design and
Construction - Contract 2019/144T.
B It is contrary to the public interest to discuss tenders in an open meeting because the
information provided to Council by tenderers is provided on the basis that it will be
treated by Council as commercial-in-confidence. A practice of disclosing sensitive
commercial information to the public, including competitors, could result in the
withholding of such information by tenderers. This would lead to a reduction in the
supply of information relevant to Council's decision. A disclosure of confidential
information by Council could result in Council being the subject of litigation for breach
of confidence.
PURPOSE
To accept a tender for the design and construction of an Organics Processing Facility
(Facility) for combined Food Organics and Garden Organics (FOGO) at the Summerhill
Waste Management Centre (SWMC).
As the value of the contract exceeds $1 million, the Local Government (General)
Regulation 2005 (Regulation) and the Chief Executive Officer's delegation requires
Council's acceptance of the tender.
RECOMMENDATION
That Council:
1 Reject the lump sum tender prices submitted and endorse the engagement with
Barpa Pty Ltd through an Early Contractor Involvement (ECI) procurement model
based on a target budget of $20,365,222 (excl. GST) for the Organics Processing
Facility for Contract No. 2019/144T.
2 Award the contract based on delivery being comprised of two separable portions.
Council shall fund Separable Portion 1 (Design and Approvals). During Separable
Portion 1 City of Newcastle (CN) will seek third party funding. Commencement of
Separable Portion 2 (Construction) will be contingent on CN Officers reporting back
to Council regarding the success of this funding.
3 This confidential report relating to the matters specified in s10A(2)(d) of the Local
Government Act 1993 be treated as confidential and remain confidential until the
Chief Executive Officer determines otherwise.
KEY ISSUES
TENDER
4 The project is for the design and construction of the Facility at the SWMC.
CONTRACT TERM
5 The term of the contract for design and construction is 22 months, with a 12 month
defect liability period.
ADVERTISING OF TENDERS
TENDERS RECEIVED
EVALUATION PROCESS
9 The Tender Assessment Panel (Panel) consisted of four CN officers. The Project
Manager, Contracts Specialist, SWMC Business Development Manager, and SWMC
Site Operations Manager.
10 The inclusion of a weighting related to local content was not included as the tender
evaluation criteria were set and communicated to the market prior to CN’s adoption
of a new policy. It is not appropriate to change evaluation criteria for a tender at this
stage of the tender process.
RECOMMENDED TENDER
11 Following a thorough review of the four tenders submitted, the Panel recommends
that the tender is awarded to Barpa Pty Ltd. Barpa Pty Ltd have submitted a tender
that demonstrates a clear and thorough understanding of the project requirements.
12 The recommendation is to reject the lump sum tender price submitted and engage
with Barpa Pty Ltd through an ECI procurement model. The intent behind rejecting a
lump sum offer and entering into an ECI procurement model based on a target
budget, is that further development of the design will result in a higher value outcome
for CN in regards to the ongoing operational costs, and is likely to result in savings
from value engineering.
will continually seek grant funding opportunities at both Commonwealth and State
levels.
FINANCIAL IMPACT
16 The estimated total capital cost of this project including the proposed target budget
amount, allowances for project management, consultants and other associated
project costs excluded from the tendered scope, is $24,630,838 (excl. GST).
17 The project will be delivered over multiple financial years with works commencing in
2019/2020 and continuing in the 2020/2021 and 2021/2022. CN received $1.5 million
towards this project from the NSW Government’s ‘Waste less recycle more’ program
and it is intended that additional work is undertaken to source additional grant funding
during Phase 1 of the project.
18 This project will be funded from CN’s Works Program over a three year period with
total forecast expenditure budgeted as follows:
19 The project has an estimated life of approximately 25 years. During this time the
facility can divert approximately 168,000 tonnes of food organics (FO) that would
otherwise be landfilled at SWMC. It is estimated that CN will save $32.5 million
through avoided Section 88 waste levy payments from FO, over the 25 years.
20 The project also has the ability to process CN’s garden organics (GO) which are
currently transported to Bettergrow, located 173 km return trip from SWMC. This
contract expires in 2021 and costs approximately $1.3 million per annum.
21 In total it is anticipated that the facility will divert approximately 900,000 tonnes of
FOGO over its 25 year life, resulting in reduced levy liability and levy savings of
approximately $168.5 million over the life of the facility.
22 Key financial benefits / outcomes of the project are summarised in the table below.
Note that these elements are discussed in further detail in the Background section of
this report.
CITY OF NEWCASTLE
Confidential Report to Ordinary Council Meeting on 28 April 2020 Page 5
Cost to landfill Circa $210 per tonne The cost per tonne for the
excl. GST and project is cheaper than
margin. landfill.
Project life cycle cost $154 per tonne. Total unit cost of project is
cheaper than landfill.
Levy savings - Total $168.5M
Levy – Garden Organics $136M Already saved.
Levy – Food Organics $32.5M New savings.
Landfill airspace (FOGO)
420Kg/m3 1.4Mm3 Based on 880K total FOGO
630Kg/m3 2.1Mm3. over life of project.
Capital deferred Cell 9 is 2.9Mm3
420Kg/m3 $12M Capex based on Cell 9 flat
630Kg/m3 $18M capex per cubic metre.
23 The project will generate revenue from the sale of compost estimated at between $7
million to $18 million over the life of the project with significant upside potential.
24 The budget has an allowance for price escalation such as changes in labour costs or
FOREX rates. The approach to develop the design with the contractor not only allows
the project to investigate and seek cost saving opportunities but to also ‘design out’
solutions that are susceptible to fluctuations in the foreign exchange rate. Where
CITY OF NEWCASTLE
Confidential Report to Ordinary Council Meeting on 28 April 2020 Page 6
25 The COVID-19 pandemic may have some impact on the project. The construction
industry has adapted like many other industries with the use of communication
technology and remote working capabilities. It is expected that the design and
approvals phase of the project can be completed successfully without the ability to
hold person to person meetings and limited site visits. Engineering firms are equipped
to work remotely and have been undertaking work from distance for several years.
26 The social distancing measures currently in place would not prevent the construction
works commencing. Procedures and methods for construction have been
implemented across the industry to ensure social distancing can be maintained.
These measures may include larger site amenities, smaller worker crews, increased
hand washing facilities and clear protocols if a worker tests positive for the COVID-
19 virus. As the project is not multi-storey, it is possible to provide worker access to
the site in conformance with the social distancing rules without restricting productivity.
27 By awarding a contract with two sperate separable portions (ie. the contract is in two
stages), CN retains the ability not to proceed with the construction works should the
risk of impact from COVID-19 be assessed as too high.
IMPLICATIONS
POLICY IMPLICATIONS
28 This project aligns with the following Newcastle 2030 Community Strategic Plan
(CSP) direction:
2.1.1 Improve waste minimisation and recycling practices in homes, work places,
development sites and public spaces.
30 The project is a key component of CN’s Draft Waste Strategy, currently under
development.
Environmental, social or
Project benefit/outcome
economic element
Diversion from landfill. 880,000 tonnes total organic material processed
(including 168,000 additional FO tonnes).
Reduced greenhouse gas Over 900,000 CO2 eq – 242,000 cars for one
emissions. year*.
Soil, water and fertilizer Improved soil productivity, useable product,
benefits. increased water retention, reduced inorganic
fertilizer.
Energy Potential renewable energy source.
Employment Construction plus five local jobs.
Community expectation One in ten unprompted indicated they expect
organics similar to Lake Macquarie City Council.
98% believe increased diversion is important.
* compared to landfill with no gas collection
ENVIRONMENTAL IMPLICATIONS
ECOLOGICAL SUSTAINABILITY
IMPLEMENTATION
34 The Facility will require five full-time staff to manage ongoing operations.
Appointment of these roles will be required in the fourth quarter of financial year
2020/2021. At start up the financial analysis requires four operations staff (one per
5,000 tonnes of input material) and a Facility Manager to ensure, among other things,
quality control and assurance. This is discussed in the section relating to operational
expenditure.
CONSULTATION/COMMUNICATION
CITY OF NEWCASTLE
Confidential Report to Ordinary Council Meeting on 28 April 2020 Page 8
35 Included with the design and construct scope is the management of all approvals
required to construct the Facility. This will involve an Environmental Impact
Statement, Development Application and an Environmental Protection Licence
variation.
BACKGROUND
Organics diversion
38 SWMC was originally conceived as a ‘waste precinct’ and in recent years, significant
work has been completed on the concept of a bio-hub.
i) Financial:
a) marginal cost to community, or nil additional cost where multiple revenue
streams,
b) reduction in landfill consumption – allows for commercial revenue, and
c) lower levy liability.
ii) Environmental:
a) reduced greenhouse gas emissions,
b) potential renewable energy source,
c) increased diversion of waste from landfill,
d) organic products displacing inorganic fertilizers, and
e) soil quality, water retention and soil productivity improvements.
iv) customer:
a) higher level of service, and
CITY OF NEWCASTLE
Confidential Report to Ordinary Council Meeting on 28 April 2020 Page 9
Project history
40 In the 2018/2019 Our Budget CN identified its intention to construct a Facility for
combined FOGO at SWMC. The Facility would accept source-separated organic
wastes currently disposed in both red and green bins and process the waste to
produce compost material that meets the requirements of AS4454-2012 as well as
relevant NSW EPA regulations.
42 Compliance and generation of a product which meets the standard ensures the
product generated is fit for sale.
43 The Organics Facility project objectives were to deliver the following benefits
i) Economic: to minimise waste management costs to CN and ensure adherence
to waste diversion targets established by the NSW Government Waste
Avoidance and Resource Recovery Strategy 2014-2021 (WARR Strategy);
ii) Security of Service: to provide an effective and ongoing resource recovery and
disposal service;
v) Social: to provide a best value solution for CN while meeting the community’s
existing and future needs and expectation for waste management, having
regard to transport and other community impacts; and
44 CN originally made application to the New South Wales EPA for a grant to construct
an organics processing facility and in December 2014 received a $1.8 million grant
(50% of an estimated $3.6 million project spend).
46 A value for money assessment was completed which concluded at +$10 million the
project remained viable.
48 In April 2017, CN indicated its intent to continue with the project. The EPA however
rejected the extension of the project and in September 2017 the original grant was
formally terminated.
50 A design and construct tender went to market in May 2019 with tenders closing in
July 2019. Evaluation was completed over a four month period with a presentation to
Councillors held in December 2019 and a second presentation in April 2020 to
identify further components of the contract and identified risks.
51 The calling of tenders was in accordance with the requirements of Section 55 of the
Act. The process followed was in accordance with Part 7 of the Regulation. Council
is required to accept tenders in accordance with clause 178 of the Regulation (see
Options).
52 Since this time additional work on risk and sensitivity modelling of financial outcomes
has been completed.
53 Most recent tenders received represent a significant increase over the $13 million
capital estimate resulting from the previous tender process in 2014. There are several
reasons for this increase in capital cost, including:
ii) the original estimate was based on an open windrow maturation composting
process,
CITY OF NEWCASTLE
Confidential Report to Ordinary Council Meeting on 28 April 2020 Page 11
iii) since this time, it has become apparent that unless the entire facility is fully
enclosed it is unlikely to receive the appropriate approvals due to concerns
regarding the likely impact of odour from the project on nearby residents,
iv) during the tender evaluation process referee checks of reference operations
indicated a fundamental constraint and failure of existing projects related to
odour controls and under sizing the facilities – several facilities reported
requiring significant upgrades shortly after opening due to inadequate design,
v) learnings from the recent Lake Macquarie City Council project, indicated that
an unenclosed facility resulted in significant odour complaints and that the
facility was undersized,
vi) the most recent capital estimate is market tested based on contemporary
technology and approvals requirements, with only the recommended tenderer
complying with what are the contemporary requirements for the project
(capacity, residence time and being fully enclosed).
54 A design and construct tender model typically incentivises a lower capital cost. During
tender evaluation and analysis of the project, it has become apparent that operating
costs represent the largest cost driver of the project. As a result, a design and
construct tender model does not necessarily result in the best outcome for CN.
56 By opting not to proceed with a lump sum contract award, there is a risk of financial
over runs that require targeted management and mitigation. This financial risk can be
managed by the following:
i) validation of the budget through market tender - not just preliminary feasibility
budgets,
iv) utilising independent cost checks by a third party construction cost consultant
to validate the costs,
vi) utilising independent technical reviews by a third party peer review consultant
to validate the design,
vii) locking in preliminary/staff rates and profit margin before awarding the contract,
CITY OF NEWCASTLE
Confidential Report to Ordinary Council Meeting on 28 April 2020 Page 12
ix) letting sub-contract trade packages as fixed price lump sum awards.
57 A review of the feasibility of the project has been completed since the provision of
higher capital costs from the market. Some of the major benefits and outcomes of
this assessment as summarised below under the key headings of:
i) financial,
ii) environmental,
Financial
58 The current cost to landfill exceeds approximately $210 per tonne, excluding GST
and margin. The cost of processing organic material under the revised business
model is approximately $154 per tonne. Approximately 74% of this cost is
operational.
59 Various sensitivity analysis were conducted over the base case as summarised in
the following table:
i) avoidance of levy,
iii) avoidance of out of LGA travel costs if an alternative organics facility is utilised.
63 If the organic material is not diverted from landfill, the additional tonnes to landfill will
use up airspace in Cell 9. Using the per cubic metre capital cost of Cell 9, and
considering the amount of space the organic waste would take in the landfill, a high
level estimate of the potential deferred capital costs are shown in Figure 2.
$50,000,000
$40,000,000
$30,000,000
$20,000,000
$10,000,000
$-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Figure 3 – Increased potential transport costs (80+ km one way excluding loading capital and operating
requirements).
66 Financially it can be shown that even with an increased capital cost of over $24 million
(total current capital requirement including $20 million construction), the project:
ii) has the potential to result in a reduction in levy liability when compared to landfill
of over $168.5 million – with new savings of at least $32.5 million,
iii) would otherwise use up at least $12 million in landfill capital requirements, and
iv) locating the facility close to CN results in bulk transport savings which exceed
$20 million (excluding loading capital and operating expenses) over the life of
the project.
67 When previous tenders were not accepted (2017) CN entered into a short-term
contract with a firm to process GO at Ravensworth. The initial term of this contract
expired in January 2020. A 12 month extension at CN’s discretion has been executed
which takes this contract through to January 2021. Only one further extension option
remains, meaning this contract will expire in January 2022.
68 It is not possible to directly compare, nor is it feasible to continually extend the current
option with the organics project for the following key reasons:
CITY OF NEWCASTLE
Confidential Report to Ordinary Council Meeting on 28 April 2020 Page 15
i) the current operator leases land and there may be limitations to the long term
ability to utilise the site,
iii) the current operator has sought to increase capacity, however the NSW EPA
has advised any new facility must be fully enclosed (similar to what has now
been proposed for CN), at much greater cost than originally factored – as a
result the feasibility of this upgrade is being reviewed, and
iv) CN’s recent experience with the EPA related to its temporary bulk up facility for
recyclables, indicates that any long term transfer arrangement is likely to require
a dedicated fully covered and enclosed shed – this will add additional capital to
meet this requirement.
69 There is also a significant risk in the future that organics may be banned from landfill.
This has occurred in many European countries including the UK, and is currently
being debated in some Australian States.
70 A key reason to consider the potential for working with other partners (such as Hunter
Water) includes the potential to unlock anaerobic digestion options. This can result
in an additional revenue stream from options such as renewable gas, power
generation, or displacing the use of diesel.
FFF
Environmental
CITY OF NEWCASTLE
Confidential Report to Ordinary Council Meeting on 28 April 2020 Page 16
72 There are significant environmental benefits from the diversion and processing of
organics from landfill. These include lower emissions, the ability to displace fossil fuel
(where a gas is generated), the ability to displace inorganic fertilisers, much improved
soil characteristics and productivity.
73 Whilst starting at around 20,000 tonnes per annum of garden organics diverted from
landfill, this facility is expected to grow in capacity (under current scenarios) to around
50,000 tonnes per annum. FO is currently planned to be introduced in around year
4, to allow for collection configuration planning and community education. There is
the potential to divert more material if CN is able to partner with other sources of
organic feedstock such as neighbouring councils, commercial sources or Hunter
Water, for example.
74 Over the life of the facility under current scenarios, the facility will divert over 880,000
tonnes of organic material from landfill, to be turned into useable compost and other
products as shown in Figure 5.
2045
2046
75 When compared to landfill, the project has a significant reduction in greenhouse gas
emissions.
76 The project will produce a useable product from otherwise discarded materials.
Customer expectations
OPTIONS
Option 1
Option 2
79 Council defers a decision at this time to allow further consideration of the tenders
received. This is not the recommended option.
Option 3
80 Council resolves not to accept any tender and invite fresh tenders. This is not the
recommended option.
Option 4
81 Council resolves not to accept any tender and enter into negotiations with any party
with a view to entering into a contract. Council must state a reason for this in its
resolution. This is not the recommended option.
Option 5
82 Council resolves not to accept any tender and not proceed with the contract. Council
must state a reason for this in its resolution. This is not the recommended option.
ATTACHMENTS
Construction
Bettergrow
Percentage
(Australia)
Weightings
& Building
Barpa Pty
Kingston
Pty Ltd**
Building
Pty Ltd
Pty Ltd
North
Ltd
ASSESSMENT CRITERIA
RANKING 2 3 1 Non-conforming
Tender Price*
$14,073,180.78 $17,978,226.87 $20,910,676.55 Not submitted
(GST exclusive)
*Estimates for items that will be required that were excluded from the tender prices have been added to ensure a “like for like”
comparison for the evaluation process.
** Bettergrow Pty Ltd did not submit a tender for a FOGO facility. Relevant schedules (including pricing) and other documentation were
not provided.
CITY OF NEWCASTLE
Confidential Report to Ordinary Council Meeting on 28 April 2020 Page 19
NOTES:
1 The two key considerations that were identified throughout the assessment were odour risk and quality of compost produced. The
potential damage caused by odour issues extend to: continual community complaints, WHS issues for CN staff, breaches of EPA
licensing conditions, limitations imposed on existing SWMC operations, devaluation of the value of the SWMC site and potential
negative impacts on the surrounding residential market value. A poor quality of AS4454 compliant compost product could result in
the stockpiling of product, with limited demand creating a logistical challenge and an ongoing waste levy liability.
2 Barpa Pty Ltd have proposed to partner with Waste Treatment Technologies (WTT) as their ‘waste technology providers’. WTT
have an extensive list of references for design and construction of anaerobic digestion, waste to energy, mechanical treatment,
mechanical biological treatment and composting. WTT have designed approximately 120 composting facilities world-wide over a
period of approx. 30 years. WTT have two Australian based reference projects with a list of 27 other comparative projects in Europe.
3 Barpa Pty Ltd’s proposed design and methodology is superior and more robust than the offers from Kingston and North. The risk
of odour issues to the surrounding residential areas are substantially better addressed with the Barpa Pty Ltd solution due to
examples such as: increased allowance in scale for a longer composting process time (72 days), more air changes per hour
throughout the building (2-4 per hour), larger bio filters to manage odour, increased segregation of areas within the building, 100%
fully enclosed operation, incorporation of an ‘air scrubber’ and more advanced control systems. An increased processing time
provides more certainty of producing an AS4454 compliant product that is of high quality and in high demand.
4 All of the items noted above provide greater flexibility in regard to responding to equipment failures or changing external variables
such as environmental/weather conditions and organic feedstock. Barpa Pty Ltd have allowed for a more advanced design for not
only fire detection but also suppression systems within the facility which provide a higher degree of life safety and overall protection
of the asset.
5 A thorough review of the Kingston proposal has identified that the tendered solution has technical shortcomings and would produce
a compost product that would be AS4454 compliant but of lower grade and more difficult to sell. This is supported by the fact that
the design is based on a total composting process time that is 40% shorter than not only the other two tenders submitted but also
shorter than the processing times of four reference facilities contacted throughout the evaluation. Furthermore, the shortcomings
identified would increase the risk of odour issues due to an inadequately sized mechanical ventilation system. Reference checks on
two similar facilities involving the waste technology partner of Kingston Building have required upgrades in the order of $2.5-5M in
the years following to address the issues identified in the evaluation.
CITY OF NEWCASTLE
Confidential Report to Ordinary Council Meeting on 28 April 2020 Page 20
** CONFIDENTIAL **