4 Shuttering
4a Footing and Column, Plinth, Lintel 833.93
1533.93 33.00 sft 50619.69
4b Roof Beam and Slab 700.00
5 Reinforcement Steel
5a Footing Mat 0.25
5b Columns 0.70
1.99 57000.00 MT 113430.00
5c Plinth Beam 0.31
5d Roof Beam and Slab 0.69
6 R.C.C 1:1.5:3
6a Footing,Plinth,Columns 481.83
721.89 182.00 cft 131383.62
6b Roof Beam,Slab 240.06
9 Tile Work
9a Virtified tile Flooring 730
9b Toilet and Kitchen wall tiles upto 7' ht 178.5 908.50 104.74 sq.ft 95160.09
. . .
10 Granite for Steps and Counter Tops 57.88 57.88 208.00 sq.ft 12039.04
11 Supply and Fixing Joineries Necessary fittings etc
11a Main door( Teak wood ) 1.00 30000.00 L.S 30000.00
11b Internal doors 1.00 10000.00 L.S 10000.00
11c Toilet doors(PVC doors) 1.00 3000.00 L.S 3000.00
11d Windows(w4) 1.00 10000.00 L.S 10000.00
11e Windows(Kw) 2.00 8000.00 L.S 16000.00
11f French Windows (Fw) 2.00 10000.00 L.S 20000
11g Ventilator 2.00 3000.00 L.S 6000.00
12 Painting Work
12a Exterior Paint- Emulsion 2710.00
4803.00 24.00 sq.ft 115272.00
12b Interior Paint- Emulsion 2093.00
TOTAL 1364518.91
CERTIFICATE
Certified that the cost required forthe above mentioned building work is Rs.13,64,518.91/-
(Rupees Thirteen Lakhs Sixty Four Thousand Five Hundred and Eighteen Rupees Only)