Beruflich Dokumente
Kultur Dokumente
a) There are 2X100 M3 LDO tanks of 5 Meter height. The LDO tank-2 drain is
connected to HFO tank -2 drain (500 M3 - 8 Meter height) so that LDO can be
stored in HFO (Heavy Fuel Oil) tank-2 also. The maximum possible height of
storage is 4.7M as the overflow is tapped from that elevation.
The LDO from one tank may be transferred to the other tank by using LDO
unloading pump, to improve the level. The LDO tanks have electrical heaters
(4 Nos./Tank),to heat the LDO in case of requirement. These heaters have to
be manually switched “ON” from FOPH control panel and it will be switched
off at 25O C to 30OC automatically. The LDO tanks can also be kept in
parallel, in case of requirements, by opening the interconnection valves.
b) There are 3X100 M3 LDO screw pumps in FOPH (Fuel Oil Pump House). One
pump/Unit is required for start up and the third pump is common reserve for
both the Units. However, any pump to any Boiler is possible by opening the
pump discharge header appropriate interconnection valves.
c) 2X200% suction filters are provided at the LDO screw pump suction. One
filter has to be kept in closed condition, when the LDO screw pump/ pumps
are in service.
d) Each LDO pump supply oil to the Boiler, to cater the need of 2 start up
burners (2X3.25 = 6.50 T/Hr) located in combustor front/ rear wall. In case
of non requirement of LDO in Boiler, the LDO will go back to the tank,
through the LDO PCV. The LDO pump capacity is 150 LPM each and discharge
pressure is 28 ksc.
e) Service air at a pressure of about 7 KSc is tapped from Service air
compressor, is used for atomizing the LDO, for the proper combustion.
f) LPG is used for the ignition of LDO.
Page 1 of 21
g) The total oil required for the cold start is about 60KL.The dead stock of the 3
tanks (HFO +LDO) is about 135 KL for 1metre height. In case of HFO system
problem, prolonged operation with LDO has to be considered. Hence the LDO
minimum stock needed is about 235 KL before a Light up (100 KL for light up
till stabilization –provisional value).
h) Confirm that No LC is pending for starting of the LDO system for boiler light
up.
Note :
1. For all the pneumatic drive valves and dampers, the local instrument air valve
near the drive has to be kept open to facilitate the operation from DCS.
2. The Spiess Valves (6 Valves) view port cooling air valves has to be opened.
3. The Spiess Valves (7 Valves) sealing air valves has to be opened.
o
Pour Point, Max C 12 for Winter
4
21 for Summer
Page 2 of 21
2.0 System preparatory works @ LDO tank area:
2.3 Note that the Tank levels in Local indicator and inform to control room.
2.4 Check and confirm that the Fire fighting system is available in
FOPH area.
3.1 The following LDO system valves have to be kept in closed condition.
b) The individual Boiler main line isolation valve located before the PCV
3.2 The following LDO system valves have to be kept in opened condition.
Page 3 of 21
d) The PCV (from the Control room) full open.
j) The filter air vents valve has to be closed, once the free flow of oil
is observed.
a) Local latch has to be released for the pump to be started & the Reserve
pump.
c) Start the LDO screw pump from DCS with reserve pump selection.
d) Slowly adjust the LDO pressure by closing the LDO PCV bypass Valve
and adjusting the PCV.
Page 4 of 21
3.4 LDO to Boiler Front.:
a. Open the isolation valve before MTV valve in boiler front left corner.
b. Slowly Open the Boiler line valve located before the PCV inlet valve at
FOPH (Ref 3.1b), in co -ordination with the control room. Ensure that the
LDO header pressure is not dropping fast.
c. Adjust the LDO pressure at the Boiler front local (12 to 14 KSc) by using
LDO PCV from DCS.
d. Now the LDO is connected to Boiler front (Up to MTV) and also to the LDO
tank.
e. Put LDO PCV on auto mode at 12-14 ksc.
Page 5 of 21
5.0 Atomizing air system preparatory works:
b) The main isolation valve at 6.5 ML, Boiler left side has
to be opened.
d) The isolation valve before PCV inlet isolation valve has to be opened.
g) Open atomizing PCV and check for 7 ksc at outlet also in DCS.
a) Ensure 2/3 cylinders with sufficient gas are connected to the LPG bus.
b) LPG MTV Inlet and Outlet valves are open.
c) Adjust the LPG Pressure to 3- 4 KSc in inlet header.
7.1 The following BP-1 TRIP CONDITIONS should not exist (Observe in
DCS):
a) Boiler Emergency Trip from OWS or CD or UCP
b) ID-Fan 1&2 Speed < 150 rpm
c) Both ID Fan Off
d) MS Pressure before Stop Valve > 20 Ksc and Boiler Stop Valve Not Open
Page 6 of 21
e) Turbine Trip & (HP BP 1&2) < Min (Position < 2 %) & MS Pressure before HP
BP > 40 Ksc & Combustion Lower temperature > 450 oC with a delay of 4
seconds.
f) Inlet Convective Pass pressure > 30 mbar
g) Compensated drum level < – 225mm Or Deaerator Level < 800 mm
h) Compensated Drum Level > +250 mm
i) MS temperature at SH outlet > 560 oC
j) HRH temperature at RH outlet > 560 oC
k) Instrument Air Pressure < 4.5 Ksc
l) Both DMCW BPs Off (5 sec delay)
m) Combustor temperature Lower > 950 oC
n) Combustor temperature Middle > 950 oC
o) Cyclone 1 Outlet temperature > 950 oC
p) Cyclone 2 Outlet temperature > 950 oC
7.2 The following NO MFT CONDITIONS should exist
(Observe in DCS):
Page 7 of 21
o) Any LDO Burner Selection & LDO pressure OK
(Or) Any HFO Burner Selection & HFO pressure OK & HFO temp OK
p) No Flame Failure Trip
q) No loss of Fuel Trip
r) Any ID Fan in Service
s) Boiler Protection –I Not Acted
A.Permissives:
1. Purging Completed
2. No MFT.
3. LDO Manual Feed valve Open.
4. LDO selected.
Page 8 of 21
5. LDO Pressure OK (12 KSc)
6. Atomizing Air Pressure OK. ( 5 KSc)
7. Keep the SUB air flow around 10 to 12 T/Hr.
B Start up Sequence
a. BP-1 Acted
b. Combustion air flow is less than minimum. (<2.7 Kg/sec)(9.7 T/hr)
c. PA Air Flow < 15 Kg/sec (54 Tons/Hr)
d. NO MFT CONDITION acted.
e. SUB Emergency Push Button Pressed (OWS Or UCP)
f. No. of failed ignitions > 4.
g. LDO manual valve not opened
h. LDO ATM. Trip valve not opened.
i. Scavenging valve not closed.
D. MTV CLOSE:
a. LDO pressure low.
b. LDO pressure high.
c. Any LDO deselected.
d. ∆P low.
Page 9 of 21
NOTE:
a. While cutting in the Burner, a person shall be available in Local with walkie
talkie for monitoring the sequence and safety purpose.
b. During the cold start of Boiler, the initial LDO oil pressure in DCS shall be about
3 to 4ksc so that the LDO flow will be about 1.0 T/Hr. The LDO PCV opening will
be about 30% for this pressure.
c. In case of oil leak in Burner, Control room has to be informed to stop the
burner immediately. Also the Hand operated Valve (HOV) in the Burner station
shall be closed.
d. In case of oil leak observed between LDO MTV and the Burner HOV,
immediately inform control room to close the MTV and to stop the LDO
pressurizing pump.
e. After the Burner is cut in, check the smoke at chimney for proper combustion
indication (i.e. No black colour in the smoke). In case of black colour, adjust the
air flow / atomizing air Pressure.
f. After the Burner is cut in Check for LDO oil Pressure and Atomizing air pressure
at Burner station and inform the Control room for comparison and healthiness of
Burner. When the Burner pressure is more (nearer to the pump pressure)
means the Oil gun is choked. The same has to be cleaned.
g. After the Burner is cut in, the suction filter ∆p and LDO tank level has to be
closely monitored on hourly basis, to avoid pump Trip on suction Pressure Very
Low.
h. During oil firing, frequent local checks have to be carried out in burner area to
watch out for any oil leak /fire and earlier detection.
i. If burner ∆p (Atomizing air pressure – LDO oil pressure) is not in auto, adjust
the ∆p to be about 0.5 to 1.0 KSc, for better combustion.
j. If the Burner flame is not established within 30 minutes after the purge
completion or after 4 unsuccessful attempts, re purging has to be carried out.
k. The rate of rise of combustor middle temperature (reference temperature)
permissible is 50-70°c for smooth heating up of the refractory. The firing has to
be adjusted to match the above rate. The oil flow details are furnished below.
Page 10 of 21
II. LDO OIL FLOW VS PRESSURE DETAILS (APPROX) :
No flow pressure
Pressure flow
ksc *
t/hr ksc * t/hr
1. Inform the UCR/Shift in charge before stopping the burner and obtain the
concurrence.
2. Before cutting out the SUB, please ensure that the Lignite Flow Low
annunciation vanishes which ensure stability of Boiler firing. (About 37 T /Hr )
3. Initiate stop command from DCS and ensure the following sequence.
a. BTV Close.
b. Atomizing Valve remains Open
Page 11 of 21
c. Scavenging Valve Open & Pilot ON – 60 Seconds.
d. Scavenging Valve Close.
e. Atomizing Valve Close.
4. Keep SUB air flow in line with MCR load, based on revised SUB secondary air flow
curve.
Page 12 of 21
4 Pilot flame - a) Flame scanner not
established but picking up pilot re-sight
scanner not sensing scanner.
flame. b) Flame relay wiring not
proper-check and rewire.
c) Excessive combustion
air through register is
causing the pilot to burn
in the hood. Reduce air
flow.
d) Faulty flame scanner
lens. Remove and wash
with soap & water and
remove any foreign
material in the sight tube.
5 Main flame not - a) Check condition of
established atomizing /main fuel train
valves, manual cocks etc.
Page 13 of 21
Oil-Water
FOPH LAYOUT
Separator Pumps
HFO / LDO
Decanting Point
LDO LDO
1 2
HFO
2
HFO Tanks
HFO
1
Unit-2
F
HFO Filters
W S W S W S
Heater-2
Heater-3
Heater-1
Unloading Unloading
For Lime Unit-1
Pumps Pumps
Plant
F F
To Sump Pump
C B A C B A
Staircase
Entrance To FOPH
Page 14 of 21
LDO TANKS AND CONNECTIONS
Hi_LS 0 Hi_LS 0
1 1
LDO LDO
Tank-I 2 Tank-II 2
Manhole Manhole
100 m3 100 m3 3
3
Elect. Heaters
4 LT 4 Nos Each 4
Lo_LS Lo_LS LT
VLo_LS 5 VLo_LS 5
LDO To DOT
Tanks Interconnection
NOTE:
1. LDO Tank -2 ( Lignite Handling System Side)
2. LDO Tank -2 Drain is connected to HFO Tank -2 for more LDO storage purpose
LDO Suction
LDO to Lime Handling Sys
LDO to DOT
W S ∆P Filter ∆P
LDO To P/H Unit
PS PS
PS PS PS
TE TE PT PT
TE
PG PG PG PG
LDO To Unit #1
PG PG
LDO Pump-C
LDO To Unit #2
PG
PG LDO Pump-B
Page 16 of 21
LDO Pump-A
HFO SUB-2 Station (10.5 ML)
From Z Bed Lance Station (6.5 ML)
PG PG
Scavenging
valve
FM SUB-2 BTV BTV
From PT PG Impulse Lines
HFO Long
Return BTV BTV
Y Return from
(Steam) SUB-2 T
FCV
PCV
PG Impulse Lines PT X
HFO
LDO
To SUB-1
X
Impulse Lines PG
LDO
To SUB-2
To SUB-1
LDO From PG PT PG
MTV
LDO Station (10.5 ML)
FOPH FM
FM
To DOT FCV PCV
TE PG PS PT TG PG PG PG
TE TG
MTV PT
Vent
FM
FM HFO From
Atomizing
Air
Y
Atomizing
Steam
Atm.
Drain
From DOT
FM HFO Return Line (10.5 ML)
Return
HFO Return Atomizing Steam & Air Station (10.5 ML)
Valve From X Page 17 of 21
From A (Long Return) From Unit-1
From SUB 1&2 To FO Tank at FOPH
NLC - BTPP -2 X125 MW - UNIT START UP SEQUENCE - BRIEF WRITE UP
No Activity /operation
1 The following equipments /systems are in service.(Prior to Boiler Light up)
(Note: As the unit is under shut down, the power supply is from grid.)
DMCW pump
Turbine on barring gear.( Main oil pump and Lifting oil pump are in service )
2 LDO in circulation.
4 Water side drains in closed condition after filling up to normal working level in Drum.
Page 18 of 21
No Activity /operation
8 Both Super heater Start up vents in open condition
12 The drain before Boiler stop valve in open condition to IBD tank.
15 Ensure power supply for all fans, blowers and local checking for start up.
ID fan ( Preferably both ID fans )- Ensure air conditioning in ESP Control Room
Boiler light up with Startup burner-2(SUB-2) . SUB-1 as per requirement. The firing
18 rate shall be about 60 -80 deg C /hour to rise in middle bed temperature.
Page 19 of 21
No Activity /operation
HT AST header.
LT AST header.
Atomizing steam.
Fuel oil heating steam line to FOPH .(secondary heater included )-Only if HFO is to be
taken
22 Boiler Feed pump start with Ammonia and Hydrazine dosing system inclusion..
Heavy Fuel oil tank heating.HFO pump start with short circulation when tank
temperature is about 50 deg C.
Page 20 of 21
No Activity /operation
28 Gland steam charging.
29 Vacuum pulling.
34 Switch over one LDO SUB to HFO.( If necessary both SUB on HFO )
40 Rolling.
41 Synchronizing.
Page 21 of 21