FACULTY OF CIVIL ENGINEERING AND BUILT ENVIRONMENT (FKAAB)

UNIVERSITI TUN HUSSEIN ONN MALAYSIA

BFC 43201 - Civil Engineering Software (Microsoft Project)


SEM II, 2019/2020

INDIVIDUAL ASSIGNMENT (10% marks)

NAME :
SECTION :
LECTURER :

Instruction

Please answer and submit your individual assignment at the end of the class (week 2)
through Edmodo.

Q1 Activities involved in the design stage of construction is shown in Table Q1. From
the table;

(a) Establish an Arrow Diagram Network for this project.

(2 marks)

(b) Define the values of Early Start (ES), Early Finish (EF), Late Start (LS) and
Late Finish (LF) of each activity.

(3 marks)

(c) Calculate the total float of each activity.

(2 marks)

(d) How many days to complete the project.

(1 marks)

(e) List out the critical activity and show the critical path in your diagram.
(2 marks)

Table Q1

Activity Activity Duration Predecessor(s)


ID (weeks)
01 Site survey 6 -
02 Develop an initial 8 -
proposal
03 Obtain approval by a 12 01, 02
government agency
04 Choose architects 4 03
05 Work out budget 6 03
06 Finalise design 15 04,05
07 Agree on cost and 12 05
design
08 Hire contractor 8 06,07