Sie sind auf Seite 1von 10

ExamCost

http://www.examcost.com
ExamCost provides valid exam collection and save exam cost
Instant Download - Best Exam Practice Material - 100% Money Back Guarantee!
IT Certification Guaranteed, The Easy Way!

Exam : AACE-PSP

Title : Planning & Scheduling


Professional (PSP) Exam

Vendor : AACE International

Version : DEMO

1
Get Latest & Valid AACE-PSP Exam's Question and Answers from Examcost.com. 1
http://www.examcost.com/aace-psp-practice-exam.html
Instant Download - Best Exam Practice Material - 100% Money Back Guarantee!
IT Certification Guaranteed, The Easy Way!

NO.1 What method would be the best way to determine the most likely as-built critical path of a
project that is underway, and the schedule of which has been partially progressed?
A. Use the progressed portion of the critical path of the baseline schedule.
B. Use the forward-looking critical path of the most current updates.
C. Use the progressed portion of the critical path of all the updates previous to the current update.
D. Interview the project personnel for their perceptions and opinions because the schedule is usually
inadequate.
Answer: B

NO.2 For the late finish for Activity 11001, select the most appropriate response for transitioning
from the forward pass.

2
Get Latest & Valid AACE-PSP Exam's Question and Answers from Examcost.com. 2
http://www.examcost.com/aace-psp-practice-exam.html
Instant Download - Best Exam Practice Material - 100% Money Back Guarantee!
IT Certification Guaranteed, The Easy Way!

3
Get Latest & Valid AACE-PSP Exam's Question and Answers from Examcost.com. 3
http://www.examcost.com/aace-psp-practice-exam.html
Instant Download - Best Exam Practice Material - 100% Money Back Guarantee!
IT Certification Guaranteed, The Easy Way!

A. 02-19-04.
B. EF.11001.
C. EF.11001 + 1 day.
D. LS.11001 + 25 days.
Answer: A

NO.3 Identify the minimum project duration.

A. 21 months.
B. 16 months.
C. 19 months.
D. 20 months.
Answer: D

NO.4 At the end of month one, did the delay to the parking structure foundation delay the project?

4
Get Latest & Valid AACE-PSP Exam's Question and Answers from Examcost.com. 4
http://www.examcost.com/aace-psp-practice-exam.html
Instant Download - Best Exam Practice Material - 100% Money Back Guarantee!
IT Certification Guaranteed, The Easy Way!

A. Yes, by 14 calendar days.


B. Yes, by 4 calendar days.
C. NO.
D. Yes, by 9 calendar days.
Answer: B

NO.5 As a change to the network for the current update, activity 6002 is required to begin ten days
after the beginning of activity 6001. Which is the simplest logic organization?

5
Get Latest & Valid AACE-PSP Exam's Question and Answers from Examcost.com. 5
http://www.examcost.com/aace-psp-practice-exam.html
Instant Download - Best Exam Practice Material - 100% Money Back Guarantee!
IT Certification Guaranteed, The Easy Way!

6
Get Latest & Valid AACE-PSP Exam's Question and Answers from Examcost.com. 6
http://www.examcost.com/aace-psp-practice-exam.html
Instant Download - Best Exam Practice Material - 100% Money Back Guarantee!
IT Certification Guaranteed, The Easy Way!

A. A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be
dependent on activity 6002
B. A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag
C. A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to
activity 6002.
D. A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be
dependent on activity 6001
Answer: A

NO.6 Which is NOT an industry-recognized methodology for quantifying critical delay?


A. Time Impact.
B. Periodic Windows.
C. Collapsed As-Built.
D. Gantt Chart.
Answer: D

NO.7 What is the primary difference between the arrow diagramming method (ADM) and the
precedence diagramming method (PDM)?
A. ADM is manual CPM calculations, while PDM is computerized.
B. ADM is limited to finish-to-start logic relationships, while PDM is not.
C. ADM uses arrows, while PDM uses boxes.
D. PDM is a bar chart with network logic, while ADM is a pure logic network.
Answer: B

NO.8 Estimate to complete (ETC) is __________________.


A. The expected total cost of an activity, group of activities or the project
B. The costs actually incurred in accomplishing the work performed
C. The value of the completed work expressed in terms of the budget assigned to that work
D. The expected remaining cost needed to complete an activity, group of activities or the project
Answer: D

NO.9 Which activity is drawn in the incorrect position?

7
Get Latest & Valid AACE-PSP Exam's Question and Answers from Examcost.com. 7
http://www.examcost.com/aace-psp-practice-exam.html
Instant Download - Best Exam Practice Material - 100% Money Back Guarantee!
IT Certification Guaranteed, The Easy Way!

A. Activity E.
B. Activity
C. Activity G.
D. Activity
Answer: D

NO.10 What is the remaining work duration of Active D?

8
Get Latest & Valid AACE-PSP Exam's Question and Answers from Examcost.com. 8
http://www.examcost.com/aace-psp-practice-exam.html
Instant Download - Best Exam Practice Material - 100% Money Back Guarantee!
IT Certification Guaranteed, The Easy Way!

A. 11
B. 8.
C. 3.
D. 4.
Answer: D