Schedule Check Report

Plan Summary
TitleProject Implementation Schedule for Execute Stage
File nameC:\Users\rajka\OneDrive\Desktop\Project Implementation
Schedule for Execute Stage 4.plan
Plan finish date21/03/2023 15:00Tasks with no progress1148
Plan remaining duration1207In progress tasks0
Normal tasks759Completed tasks0
Summary tasks291Total tasks1148
Milestone tasks97Resource assignments0
Hammock tasks1Budget cost?0
Monitor tasks0Remaining cost?0
Calendars10Actual cost?0
Links1856Total cost?0
Resources5

Report Summary
Task viewAll tasks
Constraints0
Open-ended tasks (Does not include ignored links)4
Out of sequence updates ("broken logic")0
Lags longer than 0 units700
Negative lags ("leads")0
Positive lags on Finish-to-Start links509
Start-to-Finish links1
Lags between tasks with different calendars39
Links to / from summary tasks0
Duration uncertainty distribution shape 20
Total number of items found1253

Constraints
Schedule constraints have a significant effect on risk analysis results.
They should be used sparingly, and only when the constraint reflects
reality. Constraints to be particularly aware of are: � Must start on and
Must finish on � preceding delays will not delay the task, and preceding
time savings will not bring it earlier � Start on or after (SNET) and
Finish on or after (FNET) � preceding time savings will not bring the task
earlier Consider removing these constraints and replacing them with logic
(e.g. Finish-to-Start links) instead. Other types of constraints are less
significant because they do not influence the tasks' dates, only their
floats. For example, you can use a Finish on or before constraint to
indicate a desired completion date of a task � this will not force the
task to finish on that day, but the shortfall will be indicated in the
task's float.
None found.
Open-ended tasks (Does not include ignored links)
Options selected:Predecessors, Successors

For a schedule risk analysis to be meaningful, it is important that tasks'


dates are set by logic (e.g. Finish-to-Start links) rather than
constraints. This is so that the risk analysis will recognize the knock-on
effect of delays. An open-ended task is one that does not have at least
one predecessor and one successor � it indicates a possible lack of logic.
Consider closing open-ended tasks: � If a task has no predecessor, try to
find some other tasks which could potentially delay it. Leave it as
open-ended if it is the project start milestone. � If a task has no
successors, try to find some other tasks which it could potentially delay.
Leave it as open-ended if it is a project finish or reporting milestone.
Bookmark ID Description Type Remaining Duration Detail
KMS-1030Complete FEED ServicesFinish milestone0No predecessors
PR-BK-2140Preparation of Pre-cast Moulds for the Concrete
SleepersNormal32Finish has no successors
DE-SR-8560Issued for ConstructionNormal5Finish has no successors
KMS-3440Overall Project completion by CompanyFinish milestone0No
successors

Out of sequence updates ("broken logic")


The logic in a plan can be broken when tasks have started or finished
before their predecessors. It is recommended that any broken logic is
removed or corrected to ensure the project schedules as expected. For
example, if task A has a Finish-to-Start link to task B, but B has been
started (by giving it an Actual Start date), this is broken logic. It is
not clear whether B's remaining work should wait for task A to finish, or
start straight away. Consider fixing the broken logic by either removing
the link or removing the actual dates. Also consider using the retained
logic / progress override options on the Scheduling tab of the Plan |
Options dialog box.
None found.
Lags longer than 0 units
Option selected: Display lags greater then 0 Sub Unit

A lag is a gap in the logic between two tasks � a delay between the dates
of two tasks that are linked together. Lags cannot have risk or
uncertainty. In reality it is likely that the lag represents either work
or a delay, whose duration is uncertain. This is particularly significant
for long lags. Consider replacing the lag with a task, so that uncertainty
and risks can be assessed against it. Use the Convert Lags to Tasks tool
when a project contains a large number of long lags.
From TaskTo Task
Bookmark ID Description Type Bookmark ID Description Type
Link
CN-PF-1240Loadout & Transportation of the Pipeline Materials for
ZW-100 to WSPNormalCN-PL-3610Laying of pipelineNormalSS[16]
DE-3P-9020Receive Approval on the SoW for the
SurveysNormalDE-3P-9030Receive Offers /Complete Evaluation and
Finalise the VendorNormalFF[4]
DE-3P-9040Award Sub-contractNormalDE-PL-4060Prepare & Issue for
ReviewNormalFS[14]
DE-3P-9040Award Sub-contractNormalCN-PL-3000Mobilization of Team /
Application & Receipt of Security Passes, Preparation of
ProceduresNormalFS[127]
KMS-3180HAZOP WorkshopFinish milestoneDE-3P-1170SIL Study &
Verification WorkshopNormalFS[5]
KMS-3180HAZOP WorkshopFinish milestoneDE-PR-2390Incorporate Comments
& Issue for ApprovalNormalFS[11]
KMS-3180HAZOP WorkshopFinish milestoneDE-PR-2400Incorporate Comments
& Issue for ApprovalNormalFS[11]
KMS-3180HAZOP WorkshopFinish milestoneDE-PR-2460Incorporate Comments
& Issue for ApprovalNormalFS[11]
KMS-3180HAZOP WorkshopFinish milestoneDE-PI-3600Incorporate Comments
& Issue for ApprovalNormalFS[5]
KMS-3180HAZOP WorkshopFinish milestoneDE-PR-2420Incorporate Comments
& Issue for ApprovalNormalFS[11]
KMS-3180HAZOP WorkshopFinish milestoneDE-PR-2450Incorporate Comments
& Issue for ApprovalNormalFS[11]
KMS-3180HAZOP WorkshopFinish milestoneDE-PR-2520Incorporate Comments
& Issue for ApprovalNormalFS[11]
KMS-3150Initial Hydraulics, Process Simulation runs CompletedFinish
milestoneDE-PR-2030Prepare & Issue for ReviewNormalFF[11]
KMS-3200Constructability / SIMOPS Workshop CompletedFinish
milestoneMS-1250Participate in PHSER-III WorkshopFinish
milestoneFS[5]
KMS-321090% Model Review ConductedFinish milestoneMS-1310Completion
of Major EngineeringFinish milestoneFS[18]
KMS-321090% Model Review ConductedFinish milestoneKMS-3010Completion
of Major EngineeringFinish milestoneFS[18]
KMS-319060% Model Review ConductedFinish milestoneMS-1310Completion
of Major EngineeringFinish milestoneFS[42]
KMS-319060% Model Review ConductedFinish milestoneKMS-3010Completion
of Major EngineeringFinish milestoneFS[42]
KMS-317030% Model Review ConductedFinish milestoneDE-3P-1110Value
Engineering WorkshopNormalFS[5]
KMS-3040ESD Valve DeliveredFinish milestoneCN-TS-2510Piping
Modification Works, Valve/Equipment InstallationNormalFF[12]
KMS-3040ESD Valve DeliveredFinish milestoneCN-TS-2010Jack-up Barge
Set-up, Operation isolation, spading, depressurization
etc.NormalFS[1]
KMS-3000KOM CompletedFinish milestoneMS-1070Conduct Lessons Learnt
WorkshopFinish milestoneFS[5]
CN-PL-3880ZW-100 Set-up Laybarge, Install Risers, spools & riser
fenderNormalCN-PL-3400As-Built SurveyNormalFF[1]
CN-TS-2550Commence Offshore Top-side modification WorksStart
milestoneCN-TS-2490Jack-up Barge Mobilization Set-up, Operation
isolation, spading, depressurization etc.NormalFS[1]
CN-TS-2510Piping Modification Works, Valve/Equipment
InstallationNormalCN-TS-2520Electrical and instrumentation
worksNormalFF[12]
CN-TS-2500Module Installation, Deck Extension/Structural
Modification WorksNormalCN-TS-2510Piping Modification Works,
Valve/Equipment InstallationNormalSS[20]
CN-TS-2370Piping Modification Works, Valve/Equipment
InstallationNormalCN-TS-2380Electrical and instrumentation
worksNormalFF[7]
CN-TS-2360Module Installation, Deck Extension/Structural
Modification WorksNormalCN-TS-2370Piping Modification Works,
Valve/Equipment InstallationNormalFF[7]
CN-PL-3610Laying of pipelineNormalCN-PL-3490As-Laid
SurveyNormalFF[7]
CN-PL-3560Installation of Concrete Sleepers and pre-installation
freespan correctionNormalCN-PL-3600Anchor Set-upNormalSS[7]
PR-MM-1890Vendor Data
ReviewNormalPR-MM-1880ManufacturingNormalFF[21]
PR-MM-1870PO AcceptanceFinish milestonePR-MM-1890Vendor Data
ReviewNormalFS[9]
DE-PL-5090Prepare & Issue for ReviewNormalDE-PL-5100Issued for
PurchaseNormalFS[4]
DE-PL-5070Incorporate Comments & Issue for
ApprovalNormalDE-PL-5080Issued for PurchaseNormalFS[9]
DE-PL-5060Prepare & Issue for ReviewNormalDE-PL-5070Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-5060Prepare & Issue for ReviewNormalDE-PL-5110RFQ / Receive
Bids from VendorNormalFS[9]
DE-PL-5040Incorporate Comments & Issue for
ApprovalNormalDE-PL-5050Issued for PurchaseNormalFS[9]
DE-PL-5030Prepare & Issue for ReviewNormalDE-PL-5040Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-5010Incorporate Comments & Issue for
ApprovalNormalDE-PL-5020Issued for PurchaseNormalFS[9]
DE-PL-5000Prepare & Issue for ReviewNormalDE-PL-5010Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4970Issued for PurchaseNormalPR-MM-1000PO AcceptanceFinish
milestoneFS[2]
DE-PL-4960Prepare & Issue for ReviewNormalDE-PL-4970Issued for
PurchaseNormalFS[4]
DE-PL-4940Incorporate Comments & Issue for
ApprovalNormalDE-PL-4950Issued for PurchaseNormalFS[9]
DE-PL-4930Prepare & Issue for ReviewNormalDE-PL-4940Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4930Prepare & Issue for ReviewNormalDE-PL-4980RFQ / Receive
Bids from VendorNormalFS[5]
DE-PL-4910Incorporate Comments & Issue for
ApprovalNormalDE-PL-4920Issued for PurchaseNormalFS[9]
DE-PL-4900Prepare & Issue for ReviewNormalDE-PL-4930Prepare & Issue
for ReviewNormalSS[2]
DE-PL-4900Prepare & Issue for ReviewNormalDE-PL-4910Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4880Incorporate Comments & Issue for
ApprovalNormalDE-PL-4890Issued for PurchaseNormalFS[9]
DE-PL-4870Prepare & Issue for ReviewNormalDE-PL-4880Incorporate
Comments & Issue for ApprovalNormalFS[9]
GN-1280-A10Management ApprovalNormalGN-1280-10EPC ITT to Award Of
EPC ContractNormalFS[3]
KMS-1030Complete FEED ServicesFinish milestoneGN-1280-A10Management
ApprovalNormalFS[1]
KMS-3130Overall EPC completionFinish milestoneKMS-3440Overall
Project completion by CompanyFinish milestoneFS[13]
CN-PL-3130Submission of Final ReportNormalCN-PL-3110Mobilization of
DP-2 Vessel for Sleeper InstallationNormalFS[67]
CN-PL-3090Processing and Submission of Report for
ReviewNormalKMS-3220Commencement of Pipeline Sleeper
InstallationStart milestoneFS[7]
CN-PL-3090Processing and Submission of Report for
ReviewNormalCN-PL-3110Mobilization of DP-2 Vessel for Sleeper
InstallationNormalFS[7]
CN-TS-2090Piping Modification Works, Valve/Equipment
InstallationNormalCN-TS-2600Touch painting /Removal of
ScafoldingNormalFS[1]
CN-TS-2090Piping Modification Works, Valve/Equipment
InstallationNormalCN-TS-2100Electrical and instrumentation
worksNormalSS[4]
CN-TS-2090Piping Modification Works, Valve/Equipment
InstallationNormalCN-TS-2100Electrical and instrumentation
worksNormalFF[11]
CN-TS-2030Module Installation, Deck Extension/Structural
Modification WorksNormalCN-TS-2090Piping Modification Works,
Valve/Equipment InstallationNormalFF[12]
CN-PF-1060Loadout & Transport Riser with Spools for WSP,PW-32,
ZW-100NormalCN-PL-3800WSP Set up the Laybarge, Install Risers,
spools & riser fenderNormalSS[8]
CN-PF-1140Valve and Equipment Installation before
LoadoutNormalCN-TS-2550Commence Offshore Top-side modification
WorksStart milestoneSS[25]
CN-PF-1010Pre-Fabrication of Riser with SpoolsNormalPR-MM-14603LPP
and Concrete Coating of Line Pipe and Induction BendsNormalFF[11]
CN-PF-1000Pre-Fabrication of Structural Steel Works, Piping Spools
for Offshore HookupNormalCN-PF-1010Pre-Fabrication of Riser with
SpoolsNormalSS[16]
CN-PF-1000Pre-Fabrication of Structural Steel Works, Piping Spools
for Offshore HookupNormalCN-PF-1140Valve and Equipment Installation
before LoadoutNormalSS[13]
CN-PF-1000Pre-Fabrication of Structural Steel Works, Piping Spools
for Offshore HookupNormalCN-PF-1140Valve and Equipment Installation
before LoadoutNormalFF[6]
CN-PF-1000Pre-Fabrication of Structural Steel Works, Piping Spools
for Offshore HookupNormalCN-PF-1220Loadout & Transport
pre-fabricated modules and structures ZW-100NormalSS[51]
PR-BK-2000PO AcceptanceFinish milestonePR-BK-2020PO AcceptanceFinish
milestoneFS[2]
PR-BK-2120Vendor Data
ReviewNormalPR-BK-2100ManufacturingNormalFF[21]
PR-BK-2080PO AcceptanceFinish milestonePR-BK-2120Vendor Data
ReviewNormalFS[9]
PR-BK-2090Vendor Data
ReviewNormalPR-BK-2070ManufacturingNormalFF[21]
PR-BK-2050PO AcceptanceFinish milestonePR-BK-2090Vendor Data
ReviewNormalFS[9]
PR-BK-2150Pre-casting of Sleepers, Curing and Protective Coating for
the Concrete SleepersNormalPR-BK-2170Concrete Sleepers ready for
Installation ZW-100 to WSPNormalSS[21]
PR-BK-2150Pre-casting of Sleepers, Curing and Protective Coating for
the Concrete SleepersNormalPR-BK-2190Concrete Sleepers ready for
Installation PW-32 to WSPNormalFF[21]
PR-BK-2140Preparation of Pre-cast Moulds for the Concrete
SleepersNormalPR-BK-2150Pre-casting of Sleepers, Curing and
Protective Coating for the Concrete SleepersNormalSS[13]
PR-BK-2130Material Submittal / Fabrication Drawing Approvals for the
Concrete SleepersNormalPR-BK-2140Preparation of Pre-cast Moulds for
the Concrete SleepersNormalFF[11]
PR-MM-1800Delivery & ClearanceNormalCN-TS-2010Jack-up Barge Set-up,
Operation isolation, spading, depressurization etc.NormalFS[1]
PR-MM-1610Vendor Data
ReviewNormalPR-MM-1590ManufacturingNormalFF[21]
PR-MM-1570PO AcceptanceFinish milestonePR-MM-1610Vendor Data
ReviewNormalFS[9]
PR-MM-1250Vendor Data
ReviewNormalPR-MM-1210ManufacturingNormalFF[32]
PR-MM-1170PO AcceptanceFinish milestonePR-MM-1250Vendor Data
ReviewNormalFS[9]
PR-MM-1260Vendor Data
ReviewNormalPR-MM-1220ManufacturingNormalFF[21]
PR-MM-1200PO AcceptanceFinish milestonePR-MM-1260Vendor Data
ReviewNormalFS[9]
PR-MM-1770Delivery & ClearanceNormalCN-PF-1140Valve and Equipment
Installation before LoadoutNormalFF[5]
PR-MM-1150PO AcceptanceFinish milestonePR-MM-1230Vendor Data
ReviewNormalFS[9]
PR-MM-1580Vendor Data
ReviewNormalPR-MM-1540ManufacturingNormalFF[32]
PR-MM-1470PO AcceptanceFinish milestonePR-MM-1580Vendor Data
ReviewNormalFS[9]
PR-MM-1470PO AcceptanceFinish milestonePR-MM-1390PO AcceptanceFinish
milestoneFS[2]
PR-MM-1810Delivery & ClearanceNormalCN-TS-2010Jack-up Barge Set-up,
Operation isolation, spading, depressurization etc.NormalFS[1]
PR-MM-1550Vendor Data
ReviewNormalPR-MM-1510ManufacturingNormalFF[32]
PR-MM-1390PO AcceptanceFinish milestonePR-MM-1550Vendor Data
ReviewNormalFS[9]
PR-MM-1860Delivery & ClearanceNormalCN-TS-2520Electrical and
instrumentation worksNormalFS[13]
PR-MM-1860Delivery & ClearanceNormalCN-TS-2010Jack-up Barge Set-up,
Operation isolation, spading, depressurization etc.NormalFS[1]
PR-MM-1660OEM Activities / Preparation of
DocumentsNormalDE-IC-7780Prepare & Issue for ReviewNormalSS[30]
PR-MM-1660OEM Activities / Preparation of
DocumentsNormalDE-GN-1260Prepare & Issue for ReviewNormalSS[21]
PR-MM-1760Delivery & ClearanceNormalCN-TS-2010Jack-up Barge Set-up,
Operation isolation, spading, depressurization etc.NormalFS[1]
PR-MM-1560Vendor Data
ReviewNormalPR-MM-1500ManufacturingNormalFF[21]
PR-MM-1440PO AcceptanceFinish milestonePR-MM-1560Vendor Data
ReviewNormalFS[9]
PR-MM-1400Vendor Data
ReviewNormalPR-MM-1300ManufacturingNormalFF[53]
PR-MM-1270PO AcceptanceFinish milestonePR-MM-1400Vendor Data
ReviewNormalFS[9]
PR-MM-1270PO AcceptanceFinish milestonePR-MM-1870PO AcceptanceFinish
milestoneFS[2]
PR-MM-1130Vendor Data
ReviewNormalPR-MM-1090ManufacturingNormalFF[32]
PR-MM-1130Vendor Data ReviewNormalDE-ST-9380Issued for
ConstructionNormalSS[11]
PR-MM-1080PO AcceptanceFinish milestonePR-MM-1130Vendor Data
ReviewNormalFS[9]
PR-MM-1830Delivery & ClearanceNormalCN-PF-1010Pre-Fabrication of
Riser with SpoolsNormalFF[40]
PR-MM-1710Vendor Data
ReviewNormalPR-MM-1670ManufacturingNormalFF[21]
PR-MM-1650PO AcceptanceFinish milestonePR-MM-1710Vendor Data
ReviewNormalFS[9]
PR-MM-14603LPP and Concrete Coating of Line Pipe and Induction
BendsNormalCN-PF-1240Loadout & Transportation of the Pipeline
Materials for ZW-100 to WSPNormalSS[69]
PR-MM-14603LPP and Concrete Coating of Line Pipe and Induction
BendsNormalCN-PL-3170Mobilization of LaybargeNormalFS[1]
PR-MM-14603LPP and Concrete Coating of Line Pipe and Induction
BendsNormalCN-PL-3170Mobilization of LaybargeNormalSS[51]
PR-MM-1010PO AcceptanceFinish
milestonePR-MM-1030ManufacturingNormalFF[41]
PR-MM-1020ManufacturingNormalPR-MM-1030ManufacturingNormalSS[333]
PR-MM-1040Vendor Data
ReviewNormalPR-MM-1020ManufacturingNormalFF[32]
PR-MM-1000PO AcceptanceFinish milestonePR-MM-1040Vendor Data
ReviewNormalFS[9]
MS-1380RFSU for All Facilities CompleteFinish
milestoneAS-GN-1300As-bulit PackageNormalFS[1]
MS-1380RFSU for All Facilities CompleteFinish milestoneMS-2580Issue
PACFinish milestoneFS[1]
MS-1360ESD Valve DeliveredFinish milestoneCN-TS-2510Piping
Modification Works, Valve/Equipment InstallationNormalFF[12]
MS-1360ESD Valve DeliveredFinish milestoneCN-TS-2010Jack-up Barge
Set-up, Operation isolation, spading, depressurization
etc.NormalFS[1]
MS-1070Conduct Lessons Learnt WorkshopFinish milestoneMS-1130Plot
Plans Issued for ReviewFinish milestoneFS[5]
MS-1070Conduct Lessons Learnt WorkshopFinish milestoneMS-1080Conduct
Risk Assessment WorkshopFinish milestoneFS[5]
MS-1130Plot Plans Issued for ReviewFinish milestoneDE-PI-3140Plot
Plan ReviewNormalFS[11]
MS-1120PFD, HMB Issued for ReviewFinish milestoneDE-PR-2180Prepare &
Issue for ReviewNormalFF[5]
MS-1120PFD, HMB Issued for ReviewFinish milestoneDE-PR-2290Issue for
HAZOPNormalFS[11]
MS-1210HAZOP WorkshopFinish milestoneDE-3P-1170SIL Study &
Verification WorkshopNormalFS[5]
MS-1210HAZOP WorkshopFinish milestoneDE-PR-2390Incorporate Comments
& Issue for ApprovalNormalFS[11]
MS-1210HAZOP WorkshopFinish milestoneDE-PR-2400Incorporate Comments
& Issue for ApprovalNormalFS[11]
MS-1210HAZOP WorkshopFinish milestoneDE-PR-2460Incorporate Comments
& Issue for ApprovalNormalFS[11]
MS-1210HAZOP WorkshopFinish milestoneDE-PI-3600Incorporate Comments
& Issue for ApprovalNormalFS[5]
MS-1210HAZOP WorkshopFinish milestoneDE-PR-2420Incorporate Comments
& Issue for ApprovalNormalFS[11]
MS-1210HAZOP WorkshopFinish milestoneDE-PR-2450Incorporate Comments
& Issue for ApprovalNormalFS[11]
MS-1210HAZOP WorkshopFinish milestoneDE-PR-2520Incorporate Comments
& Issue for ApprovalNormalFS[11]
MS-1250Participate in PHSER-III WorkshopFinish
milestoneDE-SR-8650Prepare & Issue for ReviewNormalFS[16]
MS-1200Value Engineering Workshop ConductedFinish
milestoneDE-PI-366090% Modeling WorksNormalFF[5]
MS-1090Process BOD Issued for reviewFinish
milestoneDE-PR-2080Incorporate Comments & Issue for
ApprovalNormalFS[11]
MS-1090Process BOD Issued for reviewFinish
milestoneDE-PR-2030Prepare & Issue for ReviewNormalFF[11]
MS-1110Planning Package Issued for ReviewFinish
milestoneDE-GN-1170Incorporate Comments & Issue for
ApprovalNormalFS[11]
MS-1060KOM CompletedFinish milestoneMS-1070Conduct Lessons Learnt
WorkshopFinish milestoneFS[5]
MS-1100Initial Hydraulics, Process Simulation runs CompletedFinish
milestoneDE-PR-2030Prepare & Issue for ReviewNormalFF[11]
MS-1240Constructability / SIMOPS Workshop CompletedFinish
milestoneMS-1250Participate in PHSER-III WorkshopFinish
milestoneFS[5]
MS-1050Mobilization and Allocation of Key Resources CompletedFinish
milestoneDE-PR-2270P&ID Design ReviewNormalFS[18]
MS-1050Mobilization and Allocation of Key Resources CompletedFinish
milestoneDE-PL-4220Issued for ConstructionNormalFS[18]
MS-1050Mobilization and Allocation of Key Resources CompletedFinish
milestoneDE-PL-4350Issued for ConstructionNormalFS[18]
MS-1050Mobilization and Allocation of Key Resources CompletedFinish
milestoneDE-PL-4280Issued for ConstructionNormalFF[18]
MS-127090% Model Review ConductedFinish milestoneMS-1310Completion
of Major EngineeringFinish milestoneFS[18]
MS-127090% Model Review ConductedFinish milestoneKMS-3010Completion
of Major EngineeringFinish milestoneFS[18]
MS-123060% Model Review ConductedFinish milestoneMS-1310Completion
of Major EngineeringFinish milestoneFS[42]
MS-123060% Model Review ConductedFinish milestoneKMS-3010Completion
of Major EngineeringFinish milestoneFS[42]
MS-118030% Model Review ConductedFinish milestoneDE-3P-1110Value
Engineering WorkshopNormalFS[5]
MS-1150P&ID Issued for ReviewFinish milestoneDE-PR-2270P&ID Design
ReviewNormalFS[16]
MS-1040Project Effective Date for EPC PhaseStart
milestoneDE-GN-1010Review of SOW, Existing data and
inputsNormalFF[3]
MS-1040Project Effective Date for EPC PhaseStart
milestonePR-MM-1010PO AcceptanceFinish milestoneFS[16]
DE-MC-2850Incorporate Comments & Issue for
ApprovalNormalDE-MC-2880Issued for ConstructionNormalFS[9]
DE-MC-2820Prepare & Issue for ReviewNormalDE-MC-2850Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-MC-2820Prepare & Issue for ReviewNormalMS-1210HAZOP
WorkshopFinish milestoneFS[5]
DE-MC-2820Prepare & Issue for ReviewNormalKMS-3180HAZOP
WorkshopFinish milestoneFS[5]
DE-MC-2860Issued for ConstructionNormalDE-MC-2870Issued for
ConstructionNormalFF[5]
DE-MC-2830Incorporate Comments & Issue for
ApprovalNormalDE-MC-2860Issued for ConstructionNormalFS[9]
DE-MC-2830Incorporate Comments & Issue for
ApprovalNormalDE-MC-2840Incorporate Comments & Issue for
ApprovalNormalFF[5]
DE-MC-2800Prepare & Issue for ReviewNormalDE-MC-2830Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-MC-2800Prepare & Issue for ReviewNormalDE-MC-2810Prepare & Issue
for ReviewNormalFF[5]
DE-MC-2800Prepare & Issue for ReviewNormalDE-MC-2810Prepare & Issue
for ReviewNormalSS[5]
DE-MC-2840Incorporate Comments & Issue for
ApprovalNormalDE-MC-2870Issued for ConstructionNormalFS[9]
DE-MC-2810Prepare & Issue for ReviewNormalDE-MC-2840Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-MC-2810Prepare & Issue for ReviewNormalDE-MC-2820Prepare & Issue
for ReviewNormalFF[5]
DE-MC-2810Prepare & Issue for ReviewNormalDE-MC-2820Prepare & Issue
for ReviewNormalSS[5]
DE-PR-2340Incorporate Comments & Issue for
ApprovalNormalDE-PR-2410Issued for ConstructionNormalFS[9]
DE-PR-2240Prepare & Issue for ReviewNormalDE-PR-2340Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2280Incorporate Comments & Issue for
ApprovalNormalDE-PR-2380Issued for ConstructionNormalFS[9]
DE-PR-2130Prepare & Issue for ReviewNormalDE-PR-2280Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2130Prepare & Issue for ReviewNormalDE-PR-2180Prepare & Issue
for ReviewNormalSS[4]
DE-PR-2130Prepare & Issue for ReviewNormalDE-PR-2240Prepare & Issue
for ReviewNormalFF[5]
DE-PR-2130Prepare & Issue for ReviewNormalDE-PR-2240Prepare & Issue
for ReviewNormalSS[16]
DE-PR-2450Incorporate Comments & Issue for
ApprovalNormalDE-PR-2540Issued for ConstructionNormalFS[9]
DE-PR-2200Prepare & Issue for ReviewNormalDE-PR-2450Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2510Issued for ConstructionNormalDE-PR-2530Issued for
ConstructionNormalFF[5]
DE-PR-2420Incorporate Comments & Issue for
ApprovalNormalDE-PR-2510Issued for ConstructionNormalFS[9]
DE-PR-2120Prepare & Issue for ReviewNormalDE-PR-2420Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2120Prepare & Issue for ReviewNormalDE-PR-2270P&ID Design
ReviewNormalFS[5]
DE-PR-2120Prepare & Issue for ReviewNormalDE-PR-2200Prepare & Issue
for ReviewNormalSS[4]
DE-PR-2080Incorporate Comments & Issue for
ApprovalNormalDE-PR-2170Issued for ConstructionNormalFS[9]
DE-PR-2080Incorporate Comments & Issue for
ApprovalNormalDE-PR-2100Incorporate Comments & Issue for
ApprovalNormalFF[2]
DE-PR-2000Prepare & Issue for ReviewNormalDE-PR-2010Hydraulics and
Process SimulationsNormalSS[9]
DE-PR-2000Prepare & Issue for ReviewNormalDE-3P-8000Prepare & Issue
for Review SoW for 3rd Party HSEStudiesNormalSS[11]
DE-PR-2000Prepare & Issue for ReviewNormalDE-ME-5010Prepare & Issue
for ReviewNormalSS[5]
DE-PR-2000Prepare & Issue for ReviewNormalDE-PL-4080Prepare & Issue
for ReviewNormalSS[11]
DE-PR-2000Prepare & Issue for ReviewNormalDE-PR-2080Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2000Prepare & Issue for ReviewNormalDE-PL-4010Prepare & Issue
for ReviewNormalSS[8]
DE-PR-2000Prepare & Issue for ReviewNormalDE-MC-2810Prepare & Issue
for ReviewNormalSS[5]
DE-PR-2000Prepare & Issue for ReviewNormalDE-PR-2050Prepare & Issue
for ReviewNormalSS[9]
DE-PR-2000Prepare & Issue for ReviewNormalDE-PI-3000BOD: Prepare &
Issue for ReviewNormalSS[5]
DE-PR-2000Prepare & Issue for ReviewNormalDE-ST-9000Prepare & Issue
for ReviewNormalSS[16]
DE-PR-2000Prepare & Issue for ReviewNormalDE-EL-6000Prepare & Issue
for ReviewNormalSS[11]
DE-PR-2000Prepare & Issue for ReviewNormalDE-IC-7000Prepare & Issue
for ReviewNormalSS[11]
DE-PR-2000Prepare & Issue for ReviewNormalDE-ME-5000Prepare & Issue
for ReviewNormalSS[11]
DE-PR-2000Prepare & Issue for ReviewNormalDE-PR-2020Prepare & Issue
for ReviewNormalSS[5]
DE-PR-2430Incorporate Comments & Issue for
ApprovalNormalDE-PR-2580Issued for ConstructionNormalFS[9]
DE-PR-2260Prepare & Issue for ReviewNormalDE-PR-2430Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2260Prepare & Issue for ReviewNormalDE-SR-8250Prepare & Issue
for ReviewNormalFF[5]
DE-PR-2010Hydraulics and Process SimulationsNormalDE-PR-2060Prepare
& Issue for ReviewNormalSS[6]
DE-PR-2480Incorporate Comments & Issue for
ApprovalNormalDE-PR-2560Issued for ConstructionNormalFS[9]
DE-PR-2190Prepare & Issue for ReviewNormalDE-PR-2270P&ID Design
ReviewNormalFS[5]
DE-PR-2190Prepare & Issue for ReviewNormalDE-PR-2350Issue for
HAZOPNormalFS[9]
DE-PR-2100Incorporate Comments & Issue for
ApprovalNormalDE-PR-2220Issued for ConstructionNormalFS[9]
DE-PR-2050Prepare & Issue for ReviewNormalDE-PR-2100Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2470Incorporate Comments & Issue for
ApprovalNormalDE-PR-2570Issued for ConstructionNormalFS[9]
DE-PR-2230Prepare & Issue for ReviewNormalDE-PR-2470Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2230Prepare & Issue for ReviewNormalDE-3P-1140HAZOP
WorkshopNormalFS[5]
DE-PR-2460Incorporate Comments & Issue for
ApprovalNormalDE-PR-2550Issued for ConstructionNormalFS[9]
DE-PR-2210Prepare & Issue for ReviewNormalDE-PR-2460Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2210Prepare & Issue for ReviewNormalDE-EL-6100Prepare & Issue
for ReviewNormalSS[9]
DE-PR-2210Prepare & Issue for ReviewNormalDE-EL-6140Prepare & Issue
for ReviewNormalSS[13]
DE-PR-2520Incorporate Comments & Issue for
ApprovalNormalDE-PR-2600Issued for ConstructionNormalFS[9]
DE-PR-2360Prepare & Issue for ReviewNormalDE-PR-2520Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2590Incorporate Comments & Issue for
ApprovalNormalDE-PR-2610Issued for ConstructionNormalFS[9]
DE-PR-2500Prepare & Issue for ReviewNormalDE-PR-2590Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2320Incorporate Comments & Issue for
ApprovalNormalDE-PR-2440Issued for ConstructionNormalFS[9]
DE-PR-2320Incorporate Comments & Issue for
ApprovalNormalDE-GN-1240Prepare & Issue for ReviewNormalFS[21]
DE-PR-2090Prepare & Issue for ReviewNormalDE-PR-2320Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2090Prepare & Issue for ReviewNormalDE-PR-2180Prepare & Issue
for ReviewNormalSS[10]
DE-PR-2090Prepare & Issue for ReviewNormalDE-3P-1140HAZOP
WorkshopNormalFS[16]
DE-PR-2310Incorporate Comments & Issue for
ApprovalNormalDE-PR-2370Issued for ConstructionNormalFS[9]
DE-PR-2040Prepare & Issue for ReviewNormalDE-PR-2310Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2160Issued for ConstructionNormalDE-ME-5140Issued for
PurchaseNormalFF[2]
DE-PR-2070Incorporate Comments & Issue for
ApprovalNormalDE-PR-2160Issued for ConstructionNormalFS[9]
DE-PR-2020Prepare & Issue for ReviewNormalDE-PR-2070Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2020Prepare & Issue for ReviewNormalDE-ME-5030Prepare & Issue
for ReviewNormalSS[4]
DE-PR-2630Site Visit Report Issued for InfoNormalDE-PR-2640Site
Visit-3NormalFS[13]
DE-PR-2140Site Visit Report Issued for InfoNormalDE-PR-2620Site
Visit-2NormalFS[13]
DE-PR-2150Incorporate Comments & Issue for
ApprovalNormalDE-PR-2250Issued for ConstructionNormalFS[9]
DE-PR-2030Prepare & Issue for ReviewNormalDE-PR-2150Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2330Issue for HAZOPNormalDE-3P-1140HAZOP WorkshopNormalFS[5]
DE-PR-2270P&ID Design ReviewNormalDE-3P-1140HAZOP
WorkshopNormalFS[5]
DE-PR-2530Issued for ConstructionNormalDE-PR-2560Issued for
ConstructionNormalFF[5]
DE-PR-2530Issued for ConstructionNormalDE-PR-2570Issued for
ConstructionNormalSS[6]
DE-PR-2530Issued for ConstructionNormalDE-PR-2570Issued for
ConstructionNormalFF[6]
DE-PR-2400Incorporate Comments & Issue for
ApprovalNormalDE-PI-3600Incorporate Comments & Issue for
ApprovalNormalSS[6]
DE-PR-2400Incorporate Comments & Issue for
ApprovalNormalDE-PR-2530Issued for ConstructionNormalFS[9]
DE-PR-2180Prepare & Issue for ReviewNormalDE-PI-3120Prepare & Issue
for ReviewNormalSS[6]
DE-PR-2180Prepare & Issue for ReviewNormalDE-PR-2190Prepare & Issue
for ReviewNormalSS[5]
DE-PR-2180Prepare & Issue for ReviewNormalDE-PR-2190Prepare & Issue
for ReviewNormalFF[5]
DE-PR-2180Prepare & Issue for ReviewNormalDE-PR-2230Prepare & Issue
for ReviewNormalFF[11]
DE-PR-2180Prepare & Issue for ReviewNormalDE-IC-7280Prepare & Issue
for ReviewNormalSS[6]
DE-PR-2180Prepare & Issue for ReviewNormalDE-PR-2270P&ID Design
ReviewNormalFS[13]
DE-PR-2180Prepare & Issue for ReviewNormalDE-PI-3120Prepare & Issue
for ReviewNormalFF[5]
DE-PR-2180Prepare & Issue for ReviewNormalDE-PI-308030% Modeling
WorksNormalFF[16]
DE-PR-2180Prepare & Issue for ReviewNormalDE-PI-3050Prepare & Issue
for ReviewNormalFF[5]
DE-PR-2180Prepare & Issue for ReviewNormalDE-3P-1140HAZOP
WorkshopNormalFS[5]
DE-PR-2180Prepare & Issue for ReviewNormalDE-3P-1090HAZOP Terms of
ReferenceNormalFS[5]
DE-PR-2180Prepare & Issue for ReviewNormalDE-3P-1170SIL Study &
Verification WorkshopNormalFS[5]
DE-PR-2180Prepare & Issue for ReviewNormalDE-3P-1100SIL Study
ProcedureNormalFS[5]
DE-PR-2390Incorporate Comments & Issue for
ApprovalNormalDE-PR-2490Issued for ConstructionNormalFS[9]
DE-PR-2390Incorporate Comments & Issue for
ApprovalNormalDE-MC-2830Incorporate Comments & Issue for
ApprovalNormalFF[5]
DE-PR-2490Issued for ConstructionNormalDE-MC-2860Issued for
ConstructionNormalFF[5]
DE-PR-2290Issue for HAZOPNormalDE-3P-1140HAZOP WorkshopNormalFS[5]
DE-PR-2060Prepare & Issue for ReviewNormalDE-PR-2180Prepare & Issue
for ReviewNormalSS[5]
DE-PR-2060Prepare & Issue for ReviewNormalDE-3P-1030HAZID / ENVID /
OHRA WorkshopNormalFS[5]
DE-PR-2060Prepare & Issue for ReviewNormalDE-PR-2290Issue for
HAZOPNormalFS[9]
DE-PR-2060Prepare & Issue for ReviewNormalDE-MC-2800Prepare & Issue
for ReviewNormalSS[5]
DE-PR-2060Prepare & Issue for ReviewNormalDE-MC-2800Prepare & Issue
for ReviewNormalFF[5]
DE-PR-2060Prepare & Issue for ReviewNormalDE-SR-8100Prepare & Issue
for ReviewNormalFS[11]
DE-PR-2060Prepare & Issue for ReviewNormalDE-SR-8270Prepare & Issue
for ReviewNormalFS[16]
DE-PR-2060Prepare & Issue for ReviewNormalDE-3P-1020Award
Sub-contractNormalFS[11]
DE-EL-6400Incorporate Comments & Issue for
ApprovalNormalDE-EL-6570Issued for ConstructionNormalFS[9]
DE-EL-6240Prepare & Issue for ReviewNormalDE-EL-6400Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6020Incorporate Comments & Issue for
ApprovalNormalDE-EL-6040Issued for ConstructionNormalFS[9]
DE-EL-6000Prepare & Issue for ReviewNormalDE-EL-6020Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6000Prepare & Issue for ReviewNormalDE-EL-6010Prepare & Issue
for ReviewNormalFS[5]
DE-EL-6160Incorporate Comments & Issue for
ApprovalNormalDE-EL-6300Issued for ConstructionNormalFS[9]
DE-EL-6080Prepare & Issue for ReviewNormalDE-EL-6160Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6510Intermediate MTONormalDE-EL-6670Final MTONormalFS[9]
DE-EL-6380Preliminary MTONormalDE-EL-6510Intermediate MTONormalFS[9]
DE-EL-6460Issued for ConstructionNormalDE-EL-6490Issued for
ConstructionNormalFF[5]
DE-EL-6290Incorporate Comments & Issue for
ApprovalNormalDE-EL-6460Issued for ConstructionNormalFS[9]
DE-EL-6140Prepare & Issue for ReviewNormalDE-EL-6290Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6140Prepare & Issue for ReviewNormalDE-EL-6170Prepare & Issue
for ReviewNormalSS[5]
DE-EL-6140Prepare & Issue for ReviewNormalDE-EL-6170Prepare & Issue
for ReviewNormalFF[5]
DE-EL-6350Incorporate Comments & Issue for
ApprovalNormalDE-EL-6490Issued for ConstructionNormalFS[9]
DE-EL-6170Prepare & Issue for ReviewNormalDE-EL-6350Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6660Issued for ConstructionNormalDE-EL-6670Final
MTONormalFF[2]
DE-EL-6560Incorporate Comments & Issue for
ApprovalNormalDE-EL-6660Issued for ConstructionNormalFS[9]
DE-EL-6340Prepare & Issue for ReviewNormalDE-EL-6560Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6600Incorporate Comments & Issue for
ApprovalNormalDE-EL-6650Issued for ConstructionNormalFS[9]
DE-EL-6330Prepare & Issue for ReviewNormalDE-EL-6600Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6590Incorporate Comments & Issue for
ApprovalNormalDE-EL-6620Issued for ConstructionNormalFS[9]
DE-EL-6440Prepare & Issue for ReviewNormalDE-EL-6590Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6550Incorporate Comments & Issue for
ApprovalNormalDE-EL-6630Issued for ConstructionNormalFS[9]
DE-EL-6220Prepare & Issue for ReviewNormalDE-EL-6550Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6470Incorporate Comments & Issue for
ApprovalNormalDE-EL-6640Issued for ConstructionNormalFS[9]
DE-EL-6320Prepare & Issue for ReviewNormalDE-EL-6470Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6210Incorporate Comments & Issue for
ApprovalNormalDE-EL-6430Issued for ConstructionNormalFS[9]
DE-EL-6100Prepare & Issue for ReviewNormalDE-EL-6210Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6100Prepare & Issue for ReviewNormalDE-EL-6140Prepare & Issue
for ReviewNormalFF[5]
DE-EL-6100Prepare & Issue for ReviewNormalDE-EL-6110Site
VisitNormalSS[5]
DE-EL-6540Issued for UseNormalPR-BK-2050PO AcceptanceFinish
milestoneFS[2]
DE-EL-6390Prepare & Issue for Review /
ApprovalNormalDE-EL-6540Issued for UseNormalFS[9]
DE-EL-6130Incorporate Comments & Issue for
ApprovalNormalDE-EL-6270Issued for PurchaseNormalFS[9]
DE-EL-6050Prepare & Issue for ReviewNormalDE-EL-6130Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6610Issued for UseNormalPR-MM-1470PO AcceptanceFinish
milestoneFS[2]
DE-EL-6480Prepare & Issue for Review /
ApprovalNormalDE-EL-6610Issued for UseNormalFS[9]
DE-EL-6410Incorporate Comments & Issue for
ApprovalNormalDE-EL-6530Issued for PurchaseNormalFS[9]
DE-EL-6260Prepare & Issue for ReviewNormalDE-EL-6410Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6370Incorporate Comments & Issue for
ApprovalNormalDE-EL-6500Issued for PurchaseNormalFS[9]
DE-EL-6190Prepare & Issue for ReviewNormalDE-EL-6370Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6030Incorporate Comments & Issue for
ApprovalNormalDE-EL-6090Issued for PurchaseNormalFS[9]
DE-EL-6010Prepare & Issue for ReviewNormalDE-EL-6030Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9120Incorporate Comments & Issue for
ApprovalNormalDE-ST-9210Issued for ConstructionNormalFS[9]
DE-ST-9040Prepare & Issue for ReviewNormalDE-ST-9120Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9540Incorporate Comments & Issue for
ApprovalNormalDE-ST-9610Issued for ConstructionNormalFS[9]
DE-ST-9350Prepare & Issue for ReviewNormalDE-ST-9540Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9510Incorporate Comments & Issue for
ApprovalNormalDE-ST-9600Issued for ConstructionNormalFS[9]
DE-ST-9300Prepare & Issue for ReviewNormalDE-ST-9510Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9500Incorporate Comments & Issue for
ApprovalNormalDE-ST-9590Issued for ConstructionNormalFS[9]
DE-ST-9270Prepare & Issue for ReviewNormalDE-ST-9500Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9270Prepare & Issue for ReviewNormalDE-ST-9350Prepare & Issue
for ReviewNormalFS[5]
DE-ST-9460Incorporate Comments & Issue for
ApprovalNormalDE-ST-9580Issued for ConstructionNormalFS[9]
DE-ST-9190Prepare & Issue for ReviewNormalDE-ST-9460Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9190Prepare & Issue for ReviewNormalDE-ST-9270Prepare & Issue
for ReviewNormalSS[5]
DE-ST-9190Prepare & Issue for ReviewNormalDE-ST-9300Prepare & Issue
for ReviewNormalSS[5]
DE-ST-9190Prepare & Issue for ReviewNormalDE-ST-9300Prepare & Issue
for ReviewNormalFS[5]
DE-ST-9450Incorporate Comments & Issue for
ApprovalNormalDE-ST-9570Issued for ConstructionNormalFS[9]
DE-ST-9250Prepare & Issue for ReviewNormalDE-ST-9450Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9250Prepare & Issue for ReviewNormalDE-ST-9270Prepare & Issue
for ReviewNormalFF[5]
DE-ST-9410Incorporate Comments & Issue for
ApprovalNormalDE-ST-9550Issued for ConstructionNormalFS[9]
DE-ST-9150Prepare & Issue for ReviewNormalDE-ST-9410Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9150Prepare & Issue for ReviewNormalDE-ST-9170Site
Visit-1NormalSS[11]
DE-ST-9030Incorporate Comments & Issue for
ApprovalNormalDE-ST-9080Issued for ConstructionNormalFS[9]
DE-ST-9000Prepare & Issue for ReviewNormalDE-ST-9030Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9490Intermediate MTONormalDE-ST-9620Final MTONormalFS[9]
DE-ST-9490Intermediate MTONormalCN-PF-1000Pre-Fabrication of
Structural Steel Works, Piping Spools for Offshore
HookupNormalFS[32]
DE-ST-9400Preliminary MTONormalDE-ST-9490Intermediate MTONormalFS[9]
DE-ST-9400Preliminary MTONormalPR-BK-2030PO AcceptanceFinish
milestoneFS[2]
DE-ST-9390Incorporate Comments & Issue for
ApprovalNormalDE-ST-9520Issued for ConstructionNormalFS[9]
DE-ST-9260Prepare & Issue for ReviewNormalDE-ST-9390Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9440Issued for ConstructionNormalDE-ST-9480Issued for
ConstructionNormalFF[5]
DE-ST-9310Incorporate Comments & Issue for
ApprovalNormalDE-ST-9440Issued for ConstructionNormalFS[9]
DE-ST-9160Prepare & Issue for ReviewNormalDE-ST-9310Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9160Prepare & Issue for ReviewNormalDE-ST-9240Prepare & Issue
for ReviewNormalSS[5]
DE-ST-9160Prepare & Issue for ReviewNormalDE-ST-9240Prepare & Issue
for ReviewNormalFF[5]
DE-ST-9050Incorporate Comments & Issue for
ApprovalNormalDE-ST-9110Issued for ConstructionNormalFS[9]
DE-ST-9010Prepare & Issue for ReviewNormalDE-ST-9050Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9010Prepare & Issue for ReviewNormalDE-ST-9020Prepare & Issue
for ReviewNormalFF[5]
DE-ST-9010Prepare & Issue for ReviewNormalDE-ST-9020Prepare & Issue
for ReviewNormalSS[5]
DE-ST-9530Issued for ConstructionNormalDE-ST-9560Issued for
ConstructionNormalFF[5]
DE-ST-9370Incorporate Comments & Issue for
ApprovalNormalDE-ST-9530Issued for ConstructionNormalFS[9]
DE-ST-9280Prepare & Issue for ReviewNormalDE-ST-9370Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9480Issued for ConstructionNormalDE-ST-9520Issued for
ConstructionNormalFF[5]
DE-ST-9330Incorporate Comments & Issue for
ApprovalNormalDE-ST-9480Issued for ConstructionNormalFS[9]
DE-ST-9240Prepare & Issue for ReviewNormalDE-ST-9330Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9230Incorporate Comments & Issue for
ApprovalNormalDE-ST-9360Issued for ConstructionNormalFS[9]
DE-ST-9230Incorporate Comments & Issue for
ApprovalNormalDE-ST-9410Incorporate Comments & Issue for
ApprovalNormalFF[5]
DE-ST-9090Prepare & Issue for ReviewNormalDE-ST-9230Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9090Prepare & Issue for ReviewNormalDE-ST-9100Prepare & Issue
for ReviewNormalSS[5]
DE-ST-9090Prepare & Issue for ReviewNormalDE-ST-9160Prepare & Issue
for ReviewNormalFS[4]
DE-ST-9090Prepare & Issue for ReviewNormalDE-ST-9260Prepare & Issue
for ReviewNormalSS[21]
DE-ST-9090Prepare & Issue for ReviewNormalDE-ST-9260Prepare & Issue
for ReviewNormalFS[16]
DE-ST-9090Prepare & Issue for ReviewNormalDE-ST-9440Issued for
ConstructionNormalSF[42]
DE-ST-9090Prepare & Issue for ReviewNormalDE-ST-9440Issued for
ConstructionNormalFF[37]
DE-ST-9070Incorporate Comments & Issue for
ApprovalNormalDE-ST-9140Issued for ConstructionNormalFS[9]
DE-ST-9020Prepare & Issue for ReviewNormalDE-ST-9070Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9220Incorporate Comments & Issue for
ApprovalNormalDE-ST-9380Issued for ConstructionNormalFS[9]
DE-ST-9220Incorporate Comments & Issue for
ApprovalNormalDE-ST-9410Incorporate Comments & Issue for
ApprovalNormalFF[5]
DE-ST-9100Prepare & Issue for ReviewNormalDE-ST-9220Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9100Prepare & Issue for ReviewNormalDE-ST-9150Prepare & Issue
for ReviewNormalFF[11]
DE-ST-9430Incorporate Comments & Issue for
ApprovalNormalDE-ST-9560Issued for ConstructionNormalFS[9]
DE-ST-9320Prepare & Issue for ReviewNormalDE-ST-9430Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3340Site Visit Report-2 Issued for InfoNormalDE-PI-3700Site
Visit-3NormalFS[32]
DE-PI-3070Site Visit Report-1 Issued for InfoNormalDE-PI-308030%
Modeling WorksNormalFF[11]
DE-PI-3070Site Visit Report-1 Issued for InfoNormalDE-PI-3330Site
Visit-2NormalFS[32]
DE-PI-3030BOD: Incorporate Comments & Issue for
ApprovalNormalDE-PI-3090BOD: Issued for ConstructionNormalFS[9]
DE-PI-3000BOD: Prepare & Issue for ReviewNormalDE-PI-3030BOD:
Incorporate Comments & Issue for ApprovalNormalFS[9]
DE-PI-3000BOD: Prepare & Issue for ReviewNormalDE-PI-3010Prepare &
Issue for ReviewNormalSS[11]
DE-PI-3800Issued for Construction (90% Model
Extracted)NormalDE-PI-3830Issued for Construction (90% Model
Extracted)NormalSS[5]
DE-PI-3800Issued for Construction (90% Model
Extracted)NormalDE-PI-3830Issued for Construction (90% Model
Extracted)NormalFF[8]
DE-PI-3670Intermediate MTONormalDE-PI-3840Final MTONormalFS[9]
DE-PI-3290Preliminary MTONormalDE-PI-3670Intermediate MTONormalFS[9]
DE-PI-3620Issued for ConstructionNormalDE-PI-366090% Modeling
WorksNormalFF[5]
DE-PI-3400Incorporate Comments & Issue for
ApprovalNormalDE-PI-3620Issued for ConstructionNormalFS[9]
DE-PI-3150Prepare & Issue for ReviewNormalDE-PI-3400Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3450Incorporate Comments & Issue for
ApprovalNormalDE-PI-3610Issued for ConstructionNormalFS[9]
DE-PI-3200Prepare & Issue for ReviewNormalDE-PI-3450Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3680Issued for ConstructionNormalDE-PI-366090% Modeling
WorksNormalFF[5]
DE-PI-3490Incorporate Comments & Issue for
ApprovalNormalDE-PI-3680Issued for ConstructionNormalFS[9]
DE-PI-3310Prepare & Issue for ReviewNormalDE-PI-3490Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3260Issue for HAZOPNormalDE-3P-1140HAZOP WorkshopNormalFS[5]
DE-PI-3260Issue for HAZOPNormalDE-ME-5190Prepare & Issue for
ReviewNormalFF[5]
DE-PI-3140Plot Plan ReviewNormalDE-3P-1140HAZOP WorkshopNormalFS[5]
DE-PI-3600Incorporate Comments & Issue for
ApprovalNormalDE-PI-3740Issued for ConstructionNormalFS[9]
DE-PI-3050Prepare & Issue for ReviewNormalDE-3P-1030HAZID / ENVID /
OHRA WorkshopNormalFS[5]
DE-PI-3050Prepare & Issue for ReviewNormalDE-PI-3140Plot Plan
ReviewNormalFS[9]
DE-PI-3050Prepare & Issue for ReviewNormalDE-ST-9060Piping /
Mechanical / Electrical / Instrument Load input to
StructuralNormalFS[5]
DE-PI-3760Incorporate Comments & Issue for
ApprovalNormalDE-PI-3810Issued for ConstructionNormalFS[9]
DE-PI-3720Prepare & Issue for ReviewNormalDE-PI-3760Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3570Issued for ConstructionNormalDE-PI-366090% Modeling
WorksNormalFF[5]
DE-PI-3570Issued for ConstructionNormalDE-PI-3620Issued for
ConstructionNormalFF[5]
DE-PI-3390Incorporate Comments & Issue for
ApprovalNormalDE-PI-3570Issued for ConstructionNormalFS[9]
DE-PI-3180Prepare & Issue for ReviewNormalDE-PI-3390Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3440Issued for ConstructionNormalDE-PI-366090% Modeling
WorksNormalFF[16]
DE-PI-3240Incorporate Comments & Issue for
ApprovalNormalDE-PI-3440Issued for ConstructionNormalFS[9]
DE-PI-3120Prepare & Issue for ReviewNormalDE-PI-3240Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-364060% Model ReviewNormalDE-PI-3620Issued for
ConstructionNormalFF[11]
DE-PI-364060% Model ReviewNormalDE-3P-1220Constructability Workshop
/ SIMOPS WorkshopNormalFS[5]
DE-PI-328060% Modeling WorksNormalDE-PI-3150Prepare & Issue for
ReviewNormalSS[27]
DE-PI-328060% Modeling WorksNormalDE-3P-1220Constructability
Workshop / SIMOPS WorkshopNormalFS[5]
DE-PI-308030% Modeling WorksNormalDE-PI-325030% Model
ReviewNormalFS[1]
DE-PI-3100Issued for ConstructionNormalDE-PI-308030% Modeling
WorksNormalFF[5]
DE-PI-3040Incorporate Comments & Issue for
ApprovalNormalDE-PI-3100Issued for ConstructionNormalFS[9]
DE-PI-3010Prepare & Issue for ReviewNormalDE-PI-3040Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-365060% Model Review ReportNormalDE-PI-375060% Model Review
Close-out ReportNormalFS[9]
DE-PI-327030% Model Review ReportNormalDE-PI-364060% Model
ReviewNormalFS[11]
DE-PI-327030% Model Review ReportNormalDE-PI-348030% Model Review
Close-out ReportNormalFS[9]
DE-PI-3230Incorporate Comments & Issue for
ApprovalNormalDE-PI-3430Issued for PurchaseNormalFS[9]
DE-PI-3110Prepare & Issue for ReviewNormalDE-PI-3130Prepare & Issue
for ReviewNormalSS[2]
DE-PI-3110Prepare & Issue for ReviewNormalDE-PI-3230Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3350Incorporate Comments & Issue for
ApprovalNormalDE-PI-3540Issued for PurchaseNormalFS[9]
DE-PI-3160Prepare & Issue for ReviewNormalDE-PI-3350Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3300Incorporate Comments & Issue for
ApprovalNormalDE-PI-3470Issued for PurchaseNormalFS[9]
DE-PI-3130Prepare & Issue for ReviewNormalDE-PI-3190Prepare & Issue
for ReviewNormalFF[5]
DE-PI-3130Prepare & Issue for ReviewNormalDE-PI-3190Prepare & Issue
for ReviewNormalSS[5]
DE-PI-3130Prepare & Issue for ReviewNormalDE-PI-3300Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3130Prepare & Issue for ReviewNormalDE-PI-3160Prepare & Issue
for ReviewNormalFF[5]
DE-PI-3130Prepare & Issue for ReviewNormalDE-PI-3160Prepare & Issue
for ReviewNormalSS[5]
DE-PI-3580Issued for PurchaseNormalPR-MM-1200PO AcceptanceFinish
milestoneFS[2]
DE-PI-3580Issued for PurchaseNormalPR-MM-1170PO AcceptanceFinish
milestoneFS[4]
DE-PI-3580Issued for PurchaseNormalCN-PF-1140Valve and Equipment
Installation before LoadoutNormalFS[2]
DE-PI-3460Prepare & Issue for ReviewNormalDE-PI-3580Issued for
PurchaseNormalFS[9]
DE-PI-3690Issued for PurchaseNormalPR-BK-2020PO AcceptanceFinish
milestoneFS[2]
DE-PI-3520Incorporate Comments & Issue for
ApprovalNormalDE-PI-3690Issued for PurchaseNormalFS[9]
DE-PI-3220Prepare & Issue for ReviewNormalDE-PI-3520Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3220Prepare & Issue for ReviewNormalPR-BK-2000PO
AcceptanceFinish milestoneFS[2]
DE-PI-3730Approved for PurchaseNormalPR-MM-1200PO AcceptanceFinish
milestoneFS[2]
DE-PI-3590Prepare & Issue for ReviewNormalDE-PI-3730Approved for
PurchaseNormalFS[9]
DE-PI-3500Incorporate Comments & Issue for
ApprovalNormalDE-PI-3630Approved for PurchaseNormalFS[9]
DE-PI-3320Prepare & Issue for ReviewNormalDE-PI-3500Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3410Incorporate Comments & Issue for
ApprovalNormalDE-PI-3550Approved for PurchaseNormalFS[9]
DE-PI-3190Prepare & Issue for ReviewNormalDE-PI-3410Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3370Incorporate Comments & Issue for
ApprovalNormalDE-PI-3530Approved for PurchaseNormalFS[9]
DE-PI-3170Prepare & Issue for ReviewNormalDE-PI-3370Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3170Prepare & Issue for ReviewNormalDE-PI-3190Prepare & Issue
for ReviewNormalSS[5]
DE-PI-3170Prepare & Issue for ReviewNormalDE-PI-3190Prepare & Issue
for ReviewNormalFF[5]
DE-IC-7730Issued for PurchaseNormalPR-MM-1600PO AcceptanceFinish
milestoneFS[2]
DE-IC-7550Prepare & Issue for ReviewNormalDE-IC-7730Issued for
PurchaseNormalFS[9]
DE-IC-7430Incorporate Comments & Issue for
ApprovalNormalDE-IC-7700Issued for PurchaseNormalFS[9]
DE-IC-7280Prepare & Issue for ReviewNormalDE-IC-7430Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7280Prepare & Issue for ReviewNormalDE-IC-7310Prepare & Issue
for ReviewNormalSS[5]
DE-IC-7510Issued for PurchaseNormalPR-BK-2080PO AcceptanceFinish
milestoneFS[2]
DE-IC-7510Issued for PurchaseNormalPR-MM-1440PO AcceptanceFinish
milestoneFS[2]
DE-IC-7340Prepare & Issue for ReviewNormalDE-IC-7510Issued for
PurchaseNormalFS[9]
DE-IC-7140Incorporate Comments & Issue for
ApprovalNormalDE-IC-7240Issued for PurchaseNormalFS[9]
DE-IC-7060Prepare & Issue for ReviewNormalDE-IC-7140Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7380Issued for PurchaseNormalPR-MM-1870PO AcceptanceFinish
milestoneFS[2]
DE-IC-7270Prepare & Issue for ReviewNormalDE-IC-7380Issued for
PurchaseNormalFS[9]
DE-IC-7160Incorporate Comments & Issue for
ApprovalNormalDE-IC-7600Issued for PurchaseNormalFS[9]
DE-IC-7110Prepare & Issue for ReviewNormalDE-IC-7160Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7040Incorporate Comments & Issue for
ApprovalNormalDE-IC-7050Issued for PurchaseNormalFS[9]
DE-IC-7040Incorporate Comments & Issue for
ApprovalNormalDE-IC-7060Prepare & Issue for ReviewNormalFS[11]
DE-IC-7010Prepare & Issue for ReviewNormalDE-IC-7090Prepare & Issue
for ReviewNormalSS[5]
DE-IC-7010Prepare & Issue for ReviewNormalDE-IC-7060Prepare & Issue
for ReviewNormalFS[11]
DE-IC-7010Prepare & Issue for ReviewNormalDE-IC-7040Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7120Incorporate Comments & Issue for
ApprovalNormalDE-IC-7520Issued for PurchaseNormalFS[9]
DE-IC-7090Prepare & Issue for ReviewNormalDE-IC-7120Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7590Incorporate Comments & Issue for
ApprovalNormalDE-IC-7740Issued for ConstructionNormalFS[9]
DE-IC-7410Prepare & Issue for ReviewNormalDE-IC-7590Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7790Incorporate Comments & Issue for
ApprovalNormalDE-IC-7800Issued for ConstructionNormalFS[9]
DE-IC-7800Issued for ConstructionNormalCN-TS-2010Jack-up Barge
Set-up, Operation isolation, spading, depressurization
etc.NormalFS[1]
DE-IC-7780Prepare & Issue for ReviewNormalDE-IC-7800Issued for
ConstructionNormalFS[9]
DE-IC-7780Prepare & Issue for ReviewNormalDE-IC-7790Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7660Incorporate Comments & Issue for
ApprovalNormalDE-IC-7760Issued for ConstructionNormalFS[9]
DE-IC-7440Prepare & Issue for ReviewNormalDE-IC-7660Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7480Incorporate Comments & Issue for
ApprovalNormalDE-IC-7650Issued for ConstructionNormalFS[9]
DE-IC-7260Prepare & Issue for ReviewNormalDE-IC-7480Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7460Incorporate Comments & Issue for
ApprovalNormalDE-IC-7610Issued for ConstructionNormalFS[9]
DE-IC-7310Prepare & Issue for ReviewNormalDE-IC-7460Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7170Incorporate Comments & Issue for
ApprovalNormalDE-IC-7290Issued for ConstructionNormalFS[9]
DE-IC-7100Prepare & Issue for ReviewNormalDE-IC-7170Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7030Incorporate Comments & Issue for
ApprovalNormalDE-IC-7080Issued for ConstructionNormalFS[9]
DE-IC-7000Prepare & Issue for ReviewNormalDE-IC-7030Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7000Prepare & Issue for ReviewNormalDE-IC-7010Prepare & Issue
for ReviewNormalSS[5]
DE-IC-7000Prepare & Issue for ReviewNormalDE-IC-7010Prepare & Issue
for ReviewNormalFF[5]
DE-IC-7320Incorporate Comments & Issue for
ApprovalNormalDE-IC-7630Issued for ConstructionNormalFS[9]
DE-IC-7210Prepare & Issue for ReviewNormalDE-IC-7500Preliminary
MTONormalSS[5]
DE-IC-7210Prepare & Issue for ReviewNormalDE-IC-7630Issued for
ConstructionNormalFS[9]
DE-IC-7210Prepare & Issue for ReviewNormalDE-IC-7320Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7530Incorporate Comments & Issue for
ApprovalNormalDE-IC-7710Issued for ConstructionNormalFS[9]
DE-IC-7370Prepare & Issue for ReviewNormalDE-IC-7530Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7680Issued for ConstructionNormalDE-IC-7720Issued for
ConstructionNormalFF[5]
DE-IC-7420Incorporate Comments & Issue for
ApprovalNormalDE-IC-7680Issued for ConstructionNormalFS[9]
DE-IC-7220Prepare & Issue for ReviewNormalDE-IC-7420Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7620Issued for ConstructionNormalDE-IC-7750Issued for
ConstructionNormalFF[5]
DE-IC-7390Incorporate Comments & Issue for
ApprovalNormalDE-IC-7620Issued for ConstructionNormalFS[9]
DE-IC-7390Incorporate Comments & Issue for
ApprovalNormalDE-IC-7420Incorporate Comments & Issue for
ApprovalNormalFF[5]
DE-IC-7180Prepare & Issue for ReviewNormalDE-IC-7390Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7690Intermediate MTONormalDE-IC-7770Final MTONormalFS[9]
DE-IC-7500Preliminary MTONormalDE-IC-7690Intermediate MTONormalFS[9]
DE-IC-7720Issued for ConstructionNormalDE-IC-7770Final
MTONormalFF[2]
DE-IC-7580Incorporate Comments & Issue for
ApprovalNormalDE-IC-7720Issued for ConstructionNormalFS[9]
DE-IC-7400Prepare & Issue for ReviewNormalDE-IC-7580Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7640Incorporate Comments & Issue for
ApprovalNormalDE-IC-7750Issued for ConstructionNormalFS[9]
DE-IC-7450Prepare & Issue for ReviewNormalDE-IC-7640Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7070AVEVA Database PopulationNormalDE-IC-7520Issued for
PurchaseNormalSS[32]
DE-IC-7570Issued for ConstructionNormalDE-IC-7620Issued for
ConstructionNormalFF[5]
DE-IC-7350Incorporate Comments & Issue for
ApprovalNormalDE-IC-7570Issued for ConstructionNormalFS[9]
DE-IC-7350Incorporate Comments & Issue for
ApprovalNormalDE-IC-7390Incorporate Comments & Issue for
ApprovalNormalFF[5]
DE-IC-7150Prepare & Issue for ReviewNormalDE-IC-7350Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7150Prepare & Issue for ReviewNormalDE-IC-7180Prepare & Issue
for ReviewNormalSS[5]
DE-IC-7670Issued for ConstructionNormalDE-IC-7720Issued for
ConstructionNormalFF[5]
DE-IC-7490Incorporate Comments & Issue for
ApprovalNormalDE-IC-7670Issued for ConstructionNormalFS[9]
DE-IC-7330Prepare & Issue for ReviewNormalDE-IC-7490Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8700Issued for PurchaseNormalPR-MM-1570PO AcceptanceFinish
milestoneFS[2]
DE-SR-8530Prepare & Issue for ReviewNormalDE-SR-8700Issued for
PurchaseNormalFS[9]
DE-SR-8490Incorporate Comments & Issue for
ApprovalNormalDE-SR-8670Issued for PurchaseNormalFS[9]
DE-SR-8370Prepare & Issue for ReviewNormalDE-SR-8490Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8430Incorporate Comments & Issue for
ApprovalNormalDE-SR-8690Issued for PurchaseNormalFS[9]
DE-SR-8300Prepare & Issue for ReviewNormalDE-SR-8430Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8360Incorporate Comments & Issue for
ApprovalNormalDE-SR-8660Issued for PurchaseNormalFS[9]
DE-SR-8240Prepare & Issue for ReviewNormalDE-SR-8360Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8380Prepare & Issue for ReviewNormalDE-SR-8520Issued for
ConstructionNormalFS[13]
DE-SR-8050Site VisitNormalDE-SR-8060Site Visit Report issued for
infoNormalFS[2]
DE-SR-8420Incorporate Comments & Issue for
ApprovalNormalDE-SR-8510Issued for ConstructionNormalFS[9]
DE-SR-8250Prepare & Issue for ReviewNormalDE-SR-8420Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8070Incorporate Comments & Issue for
ApprovalNormalDE-SR-8140Issued for ConstructionNormalFS[9]
DE-SR-8020Prepare & Issue for ReviewNormalDE-SR-8070Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8400Incorporate Comments & Issue for
ApprovalNormalDE-SR-8620Issued for ConstructionNormalFS[9]
DE-SR-8230Prepare & Issue for ReviewNormalDE-SR-8400Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8030Incorporate Comments & Issue for
ApprovalNormalDE-SR-8090Issued for ConstructionNormalFS[9]
DE-SR-8010Prepare & Issue for ReviewNormalDE-SR-8030Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8220Incorporate Comments & Issue for
ApprovalNormalDE-SR-8330Issued for ConstructionNormalFS[9]
DE-SR-8100Prepare & Issue for ReviewNormalDE-SR-8220Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8310Incorporate Comments & Issue for
ApprovalNormalDE-SR-8560Issued for ConstructionNormalFS[9]
DE-SR-8180Prepare & Issue for ReviewNormalDE-SR-8310Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8460Incorporate Comments & Issue for
ApprovalNormalDE-SR-8580Issued for ConstructionNormalFS[9]
DE-SR-8320Prepare & Issue for ReviewNormalDE-SR-8460Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8320Prepare & Issue for ReviewNormalMS-1250Participate in
PHSER-III WorkshopFinish milestoneFS[11]
DE-SR-8170Incorporate Comments & Issue for
ApprovalNormalDE-SR-8550Issued for ConstructionNormalFS[9]
DE-SR-8080Prepare & Issue for ReviewNormalDE-SR-8170Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8260Incorporate Comments & Issue for
ApprovalNormalDE-SR-8610Issued for ConstructionNormalFS[9]
DE-SR-8160Prepare & Issue for ReviewNormalDE-SR-8260Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8640Issued for ConstructionNormalDE-SR-8660Issued for
PurchaseNormalFF[2]
DE-SR-8210Incorporate Comments & Issue for
ApprovalNormalDE-SR-8640Issued for ConstructionNormalFS[9]
DE-SR-8130Prepare & Issue for ReviewNormalDE-SR-8210Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8130Prepare & Issue for ReviewNormalDE-SR-8230Prepare & Issue
for ReviewNormalSS[9]
DE-SR-8390Incorporate Comments & Issue for
ApprovalNormalDE-SR-8680Issued for ConstructionNormalFS[9]
DE-SR-8270Prepare & Issue for ReviewNormalDE-SR-8390Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8470Incorporate Comments & Issue for
ApprovalNormalDE-SR-8590Issued for ConstructionNormalFS[9]
DE-SR-8340Prepare & Issue for ReviewNormalDE-SR-8470Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8190Incorporate Comments & Issue for
ApprovalNormalDE-SR-8540Issued for ConstructionNormalFS[9]
DE-SR-8110Prepare & Issue for ReviewNormalDE-SR-8190Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8410Incorporate Comments & Issue for
ApprovalNormalDE-SR-8630Issued for ConstructionNormalFS[9]
DE-SR-8280Prepare & Issue for ReviewNormalDE-SR-8410Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8200Incorporate Comments & Issue for
ApprovalNormalDE-SR-8570Issued for ConstructionNormalFS[9]
DE-SR-8120Prepare & Issue for ReviewNormalDE-SR-8200Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8650Prepare & Issue for ReviewNormalDE-SR-8710Issued for
ConstructionNormalFS[9]
DE-SR-8290Incorporate Comments & Issue for
ApprovalNormalDE-SR-8450Issued for ConstructionNormalFS[9]
DE-SR-8150Prepare & Issue for ReviewNormalDE-IC-7070AVEVA Database
PopulationNormalFF[21]
DE-SR-8150Prepare & Issue for ReviewNormalDE-SR-8450Issued for
ConstructionNormalFS[9]
DE-SR-8150Prepare & Issue for ReviewNormalDE-SR-8290Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4800Award Sub ContractNormalPR-BK-2130Material Submittal /
Fabrication Drawing Approvals for the Concrete SleepersNormalFS[3]
DE-PL-4800Award Sub ContractNormalMS-1280Subcontract for Concrete
Sleepers PlacedFinish milestoneFS[2]
DE-PL-4670Prepare & Issue for Review Sub
contractNormalDE-PL-4800Award Sub ContractNormalFS[5]
DE-PL-4860Issued for PurchaseNormalPR-MM-1650PO AcceptanceFinish
milestoneFS[2]
DE-PL-4830Prepare & Issue for ReviewNormalDE-PL-4860Issued for
PurchaseNormalFS[9]
DE-PL-4710Incorporate Comments & Issue for
ApprovalNormalDE-PL-4820Issued for PurchaseNormalFS[9]
DE-PL-4570Prepare & Issue for ReviewNormalDE-PL-4710Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4570Prepare & Issue for ReviewNormalDE-PL-4660RFQ / Receive
Bids from VendorNormalFS[5]
DE-PL-4650Incorporate Comments & Issue for
ApprovalNormalDE-PL-4750Issued for PurchaseNormalFS[9]
DE-PL-4500Prepare & Issue for ReviewNormalDE-PL-4650Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4560Incorporate Comments & Issue for
ApprovalNormalDE-PL-4700Issued for PurchaseNormalFS[9]
DE-PL-4410Prepare & Issue for ReviewNormalDE-PL-4560Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4690Incorporate Comments & Issue for
ApprovalNormalDE-PL-4810Issued for ConstructionNormalFS[9]
DE-PL-4490Prepare & Issue for ReviewNormalDE-PL-4690Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4490Prepare & Issue for ReviewNormalPR-BK-2130Material
Submittal / Fabrication Drawing Approvals for the Concrete
SleepersNormalFS[22]
DE-PL-4490Prepare & Issue for ReviewNormalMS-1280Subcontract for
Concrete Sleepers PlacedFinish milestoneFS[21]
DE-PL-4550Incorporate Comments & Issue for
ApprovalNormalDE-PL-4680Issued for ConstructionNormalFS[9]
DE-PL-4400Prepare & Issue for ReviewNormalDE-PL-4550Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4400Prepare & Issue for ReviewNormalDE-PL-4440Prepare & Issue
for ReviewNormalSS[5]
DE-PL-4400Prepare & Issue for ReviewNormalDE-PL-4440Prepare & Issue
for ReviewNormalFF[5]
DE-PL-4250Incorporate Comments & Issue for
ApprovalNormalDE-PL-4340Issued for ConstructionNormalFS[9]
DE-PL-4140Prepare & Issue for ReviewNormalDE-PL-4250Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4740Issued for ConstructionNormalPR-BK-2130Material Submittal
/ Fabrication Drawing Approvals for the Concrete SleepersNormalFS[1]
DE-PL-4600Incorporate Comments & Issue for
ApprovalNormalDE-PL-4740Issued for ConstructionNormalFS[9]
DE-PL-4390Prepare & Issue for ReviewNormalDE-PL-4600Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4310Incorporate Comments & Issue for
ApprovalNormalDE-PL-4430Issued for ConstructionNormalFS[9]
DE-PL-4200Prepare & Issue for ReviewNormalDE-PL-4310Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4460Incorporate Comments & Issue for
ApprovalNormalDE-PL-4640Issued for ConstructionNormalFS[9]
DE-PL-4190Prepare & Issue for ReviewNormalDE-PL-4460Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4190Prepare & Issue for ReviewNormalDE-PL-4290Prepare & Issue
for ReviewNormalSS[4]
DE-PL-4270Incorporate Comments & Issue for
ApprovalNormalDE-PL-4380Issued for ConstructionNormalFS[9]
DE-PL-4130Prepare & Issue for ReviewNormalDE-PL-4270Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4240Incorporate Comments & Issue for
ApprovalNormalDE-PL-4330Issued for ConstructionNormalFS[9]
DE-PL-4120Prepare & Issue for ReviewNormalDE-PL-4240Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4230Incorporate Comments & Issue for
ApprovalNormalDE-PL-4320Issued for ConstructionNormalFS[9]
DE-PL-4110Prepare & Issue for ReviewNormalDE-PL-4230Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4160Incorporate Comments & Issue for
ApprovalNormalDE-PL-4280Issued for ConstructionNormalFS[9]
DE-PL-4060Prepare & Issue for ReviewNormalDE-PL-4160Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4060Prepare & Issue for ReviewNormalDE-PL-4170Site
Visit-1NormalFS[11]
DE-PL-4100Incorporate Comments & Issue for
ApprovalNormalDE-PL-4220Issued for ConstructionNormalFS[9]
DE-PL-4040Prepare & Issue for ReviewNormalDE-PL-4100Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4300Incorporate Comments & Issue for
ApprovalNormalDE-PL-4420Issued for ConstructionNormalFS[9]
DE-PL-4080Prepare & Issue for ReviewNormalDE-PL-4300Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4630Intermediate MTONormalDE-PL-4850Final MTONormalFF[11]
DE-PL-4480Preliminary MTONormalDE-PL-4630Intermediate MTONormalFS[9]
DE-PL-4050Incorporate Comments & Issue for
ApprovalNormalDE-PL-4150Issued for ConstructionNormalFS[9]
DE-PL-4010Prepare & Issue for ReviewNormalDE-PL-4050Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4010Prepare & Issue for ReviewNormalDE-PL-4350Issued for
ConstructionNormalFS[18]
DE-PL-4010Prepare & Issue for ReviewNormalDE-PL-4280Issued for
ConstructionNormalFF[18]
DE-PL-4620Incorporate Comments & Issue for
ApprovalNormalDE-PL-4730Issued for ConstructionNormalFS[9]
DE-PL-4470Prepare & Issue for ReviewNormalDE-PL-4620Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4590Incorporate Comments & Issue for
ApprovalNormalDE-PL-4790Issued for ConstructionNormalFS[9]
DE-PL-4450Prepare & Issue for ReviewNormalDE-PL-4590Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4540Incorporate Comments & Issue for
ApprovalNormalDE-PL-4720Issued for ConstructionNormalFS[9]
DE-PL-4370Prepare & Issue for ReviewNormalDE-PL-4540Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4530Incorporate Comments & Issue for
ApprovalNormalDE-PL-4780Issued for ConstructionNormalFS[9]
DE-PL-4360Prepare & Issue for ReviewNormalDE-PL-4530Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4260Incorporate Comments & Issue for
ApprovalNormalDE-PL-4350Issued for ConstructionNormalFS[9]
DE-PL-4070Prepare & Issue for ReviewNormalDE-PL-4260Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4580Incorporate Comments & Issue for
ApprovalNormalDE-PL-4840Issued for ConstructionNormalFS[9]
DE-PL-4440Prepare & Issue for ReviewNormalDE-PL-4580Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4440Prepare & Issue for ReviewNormalDE-PL-4470Prepare & Issue
for ReviewNormalFF[2]
DE-PL-4440Prepare & Issue for ReviewNormalDE-PL-4470Prepare & Issue
for ReviewNormalSS[5]
DE-PL-4440Prepare & Issue for ReviewNormalDE-PL-4480Preliminary
MTONormalFF[5]
DE-PL-4520Incorporate Comments & Issue for
ApprovalNormalDE-PL-4770Issued for ConstructionNormalFS[9]
DE-PL-4290Prepare & Issue for ReviewNormalDE-PL-4520Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4290Prepare & Issue for ReviewNormalDE-PL-4440Prepare & Issue
for ReviewNormalFF[5]
DE-ME-5180Issued for PurchaseNormalPR-MM-1080PO AcceptanceFinish
milestoneFS[2]
DE-ME-5150Prepare & Issue for Review /
ApprovalNormalDE-ME-5180Issued for PurchaseNormalFS[9]
DE-ME-5100Incorporate Comments & Issue for
ApprovalNormalDE-ME-5170Issued for PurchaseNormalFS[9]
DE-ME-5040Prepare & Issue for ReviewNormalDE-ME-5100Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ME-5140Issued for PurchaseNormalDE-ME-5170Issued for
PurchaseNormalFF[5]
DE-ME-5090Incorporate Comments & Issue for
ApprovalNormalDE-ME-5140Issued for PurchaseNormalFS[9]
DE-ME-5030Prepare & Issue for ReviewNormalDE-ME-5040Prepare & Issue
for ReviewNormalFF[2]
DE-ME-5030Prepare & Issue for ReviewNormalDE-ME-5090Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ME-5030Prepare & Issue for ReviewNormalDE-ME-5040Prepare & Issue
for ReviewNormalSS[2]
DE-ME-5060Incorporate Comments & Issue for
ApprovalNormalDE-ME-5120Issued for PurchaseNormalFS[9]
DE-ME-5010Prepare & Issue for ReviewNormalDE-ME-5060Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ME-5080Incorporate Comments & Issue for
ApprovalNormalDE-ME-5160Issued for ConstructionNormalFS[9]
DE-ME-5000Prepare & Issue for ReviewNormalDE-ME-5080Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ME-5200Incorporate Comments & Issue for
ApprovalNormalDE-ME-5210Issued for ConstructionNormalFS[9]
DE-ME-5190Prepare & Issue for ReviewNormalDE-ME-5200Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ME-5070Incorporate Comments & Issue for
ApprovalNormalDE-ME-5130Issued for ConstructionNormalFS[9]
DE-ME-5020Prepare & Issue for ReviewNormalDE-ME-5070Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ME-5020Prepare & Issue for ReviewNormalDE-ME-5040Prepare & Issue
for ReviewNormalFF[5]
DE-3P-1240Prepare & Issue for ReviewNormalDE-3P-1260Issued for
UseNormalFS[9]
DE-3P-1110Value Engineering WorkshopNormalDE-PI-328060% Modeling
WorksNormalFF[16]
DE-3P-1190Issued for UseNormalDE-PI-366090% Modeling
WorksNormalFF[16]
DE-3P-1120Prepare & Issue for Review ReportNormalDE-3P-1190Issued
for UseNormalFS[9]
DE-3P-1020Award Sub-contractNormalDE-3P-1060Prepare & Issue for
ReviewNormalFS[5]
DE-3P-1250Issued for UseNormalDE-PI-379090% Model UpdatedNormalFF[5]
DE-3P-1160Incorporate CommentsNormalDE-3P-1250Issued for
UseNormalFS[9]
DE-3P-1060Prepare & Issue for ReviewNormalDE-3P-1160Incorporate
CommentsNormalFS[9]
DE-3P-1060Prepare & Issue for ReviewNormalDE-SR-8130Prepare & Issue
for ReviewNormalSS[9]
DE-3P-1100SIL Study ProcedureNormalDE-3P-1170SIL Study &
Verification WorkshopNormalFS[5]
DE-3P-1230SIL Report: Issued for UseNormalDE-IC-7670Issued for
ConstructionNormalFF[5]
DE-3P-1180SIL Report: Prepare & Issue for ReviewNormalDE-3P-1230SIL
Report: Issued for UseNormalFS[13]
DE-3P-1170SIL Study & Verification
WorkshopNormalDE-3P-1220Constructability Workshop / SIMOPS
WorkshopNormalFS[5]
DE-3P-1090HAZOP Terms of ReferenceNormalDE-3P-1140HAZOP
WorkshopNormalFS[5]
DE-3P-1150HAZOP Report: Prepare & Issue for
ReviewNormalDE-3P-1210HAZOP Report: Issued for UseNormalFS[13]
DE-3P-1140HAZOP WorkshopNormalDE-3P-1170SIL Study & Verification
WorkshopNormalFS[5]
DE-3P-1140HAZOP WorkshopNormalDE-PR-2390Incorporate Comments & Issue
for ApprovalNormalFS[11]
DE-3P-1140HAZOP WorkshopNormalDE-PR-2400Incorporate Comments & Issue
for ApprovalNormalFS[11]
DE-3P-1140HAZOP WorkshopNormalDE-PR-2460Incorporate Comments & Issue
for ApprovalNormalFS[11]
DE-3P-1140HAZOP WorkshopNormalDE-PI-3600Incorporate Comments & Issue
for ApprovalNormalFS[5]
DE-3P-1140HAZOP WorkshopNormalDE-PR-2420Incorporate Comments & Issue
for ApprovalNormalFS[11]
DE-3P-1140HAZOP WorkshopNormalDE-PR-2450Incorporate Comments & Issue
for ApprovalNormalFS[11]
DE-3P-1140HAZOP WorkshopNormalDE-PR-2520Incorporate Comments & Issue
for ApprovalNormalFS[11]
DE-3P-1010HAZID / ENVID / OHRA Terms of
ReferenceNormalDE-3P-1030HAZID / ENVID / OHRA WorkshopNormalFS[2]
DE-3P-8040Award Sub-contractNormalDE-3P-1030HAZID / ENVID / OHRA
WorkshopNormalFS[5]
DE-3P-8040Award Sub-contractNormalDE-3P-1010HAZID / ENVID / OHRA
Terms of ReferenceNormalFS[2]
DE-3P-8040Award Sub-contractNormalDE-3P-1140HAZOP
WorkshopNormalFS[11]
DE-3P-8040Award Sub-contractNormalDE-3P-1090HAZOP Terms of
ReferenceNormalFS[11]
DE-3P-8040Award Sub-contractNormalDE-3P-1170SIL Study & Verification
WorkshopNormalFS[11]
DE-3P-8040Award Sub-contractNormalDE-3P-1100SIL Study
ProcedureNormalFS[11]
DE-3P-1040HAZID / ENVID / OHRA Report: Prepare & Issue for
ReviewNormalDE-3P-1130HAZID / ENVID / OHRA Report: Issued for
UseNormalFS[13]
DE-3P-1040HAZID / ENVID / OHRA Report: Prepare & Issue for
ReviewNormalDE-SR-8180Prepare & Issue for ReviewNormalFS[11]
DE-3P-1030HAZID / ENVID / OHRA WorkshopNormalDE-3P-1140HAZOP
WorkshopNormalFS[5]
DE-GN-1350Incorporate Comments & Issue for
ApprovalNormalDE-GN-1360Issued for ConstructionNormalFF[21]
DE-GN-1350Incorporate Comments & Issue for
ApprovalNormalDE-GN-1360Issued for ConstructionNormalSS[11]
DE-GN-1340Prepare & Issue for ReviewNormalDE-GN-1350Incorporate
Comments & Issue for ApprovalNormalFF[21]
DE-GN-1340Prepare & Issue for ReviewNormalDE-GN-1350Incorporate
Comments & Issue for ApprovalNormalSS[21]
DE-GN-1160Incorporate Comments & Issue for
ApprovalNormalDE-GN-1200Issued for ConstructionNormalFS[9]
DE-GN-1110Prepare & Issue for ReviewNormalDE-GN-1160Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-GN-1280Incorporate Comments & Issue for
ApprovalNormalDE-GN-1290Issued for ConstructionNormalFS[9]
DE-GN-1260Prepare & Issue for ReviewNormalDE-GN-1280Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-GN-1180Incorporate Comments & Issue for
ApprovalNormalDE-GN-1220Issued for ConstructionNormalFS[9]
DE-GN-1080Prepare & Issue for ReviewNormalDE-GN-1180Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-GN-1070Lessons Learnt W/S Report: Prepare & Issue for
ReviewNormalDE-GN-1120Lessons Learnt W/S Report: Issued for
UseNormalFS[9]
DE-GN-1090Risk Assessment W/S Report: Prepare & Issue for
ReviewNormalDE-GN-1140Risk Assessment W/S Report: Issued for
ConstructionNormalFS[9]
DE-GN-1250Incorporate Comments & Issue for
ApprovalNormalDE-GN-1270Issued for ConstructionNormalFS[9]
DE-GN-1240Prepare & Issue for ReviewNormalDE-GN-1250Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-GN-1170Incorporate Comments & Issue for
ApprovalNormalDE-GN-1230Issued for ConstructionNormalFS[9]
DE-GN-1060Prepare & Issue for ReviewNormalDE-GN-1170Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-GN-1100Initial Site Visit, Data Collection & Alignment with
OperationsNormalDE-GN-1080Prepare & Issue for ReviewNormalFF[5]
DE-GN-1010Review of SOW, Existing data and inputsNormalDE-PI-30203D
Model Set-upNormalFS[11]
DE-GN-1010Review of SOW, Existing data and
inputsNormalDE-3P-8000Prepare & Issue for Review SoW for 3rd Party
HSEStudiesNormalSS[2]
DE-GN-1150Incorporate Comments & Issue for
ApprovalNormalDE-GN-1210Issued for ConstructionNormalFS[9]
DE-GN-1040Prepare & Issue for ReviewNormalDE-GN-1150Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-GN-1040Prepare & Issue for ReviewNormalDE-GN-1080Prepare & Issue
for ReviewNormalFF[5]
MS-2570Overall RFSU Duration (From Award date until last
RFSU)HammockAS-GN-1300As-bulit PackageNormalFS[1]
MS-2570Overall RFSU Duration (From Award date until last
RFSU)HammockMS-2580Issue PACFinish milestoneFS[1]
KMS-3540RFSU for All Facilities CompleteFinish milestoneMS-2580Issue
PACFinish milestoneFS[1]
KMS-3550Project Effective Date for EPC PhaseStart
milestoneDE-GN-1010Review of SOW, Existing data and
inputsNormalFF[3]
KMS-3550Project Effective Date for EPC PhaseStart
milestonePR-MM-1010PO AcceptanceFinish milestoneFS[16]
Negative lags ("leads")
A negative lag is an overlap in the logic between two tasks � often it is
used to represent a task starting earlier, with sufficient time allow some
other work to happen. Lags cannot have risk or uncertainty. In reality it
is likely that the negative lag represents an necessary overlap, whose
duration is uncertain. Consider replacing a negative lag with another kind
of link that does not need the lag. For example: � Replace a negative lag
on a Finish-to-Start link with a positive lag on a Start-to-Start link. �
Split the tasks so that the overlap is explicitly represented by a task.
None found.
Positive lags on Finish-to-Start links
A lag is a gap in the logic between two tasks � a delay after one task
finishes before the next one starts. Lags cannot have risk or uncertainty.
In reality it is likely that the lag represents either work or a delay,
whose duration is uncertain. Consider replacing the lag with a task, so
that uncertainty and risks can be assessed against it. Use the Convert
Lags to Tasks tool when a project contains a large number of long lags.
From TaskTo Task
Bookmark ID Description Type Bookmark ID Description Type
Link
DE-3P-9040Award Sub-contractNormalDE-PL-4060Prepare & Issue for
ReviewNormalFS[14]
DE-3P-9040Award Sub-contractNormalCN-PL-3000Mobilization of Team /
Application & Receipt of Security Passes, Preparation of
ProceduresNormalFS[127]
KMS-3180HAZOP WorkshopFinish milestoneDE-3P-1170SIL Study &
Verification WorkshopNormalFS[5]
KMS-3180HAZOP WorkshopFinish milestoneDE-PR-2390Incorporate Comments
& Issue for ApprovalNormalFS[11]
KMS-3180HAZOP WorkshopFinish milestoneDE-PR-2400Incorporate Comments
& Issue for ApprovalNormalFS[11]
KMS-3180HAZOP WorkshopFinish milestoneDE-PR-2460Incorporate Comments
& Issue for ApprovalNormalFS[11]
KMS-3180HAZOP WorkshopFinish milestoneDE-PI-3600Incorporate Comments
& Issue for ApprovalNormalFS[5]
KMS-3180HAZOP WorkshopFinish milestoneDE-PR-2420Incorporate Comments
& Issue for ApprovalNormalFS[11]
KMS-3180HAZOP WorkshopFinish milestoneDE-PR-2450Incorporate Comments
& Issue for ApprovalNormalFS[11]
KMS-3180HAZOP WorkshopFinish milestoneDE-PR-2520Incorporate Comments
& Issue for ApprovalNormalFS[11]
KMS-3200Constructability / SIMOPS Workshop CompletedFinish
milestoneMS-1250Participate in PHSER-III WorkshopFinish
milestoneFS[5]
KMS-321090% Model Review ConductedFinish milestoneMS-1310Completion
of Major EngineeringFinish milestoneFS[18]
KMS-321090% Model Review ConductedFinish milestoneKMS-3010Completion
of Major EngineeringFinish milestoneFS[18]
KMS-319060% Model Review ConductedFinish milestoneMS-1310Completion
of Major EngineeringFinish milestoneFS[42]
KMS-319060% Model Review ConductedFinish milestoneKMS-3010Completion
of Major EngineeringFinish milestoneFS[42]
KMS-317030% Model Review ConductedFinish milestoneDE-3P-1110Value
Engineering WorkshopNormalFS[5]
KMS-3040ESD Valve DeliveredFinish milestoneCN-TS-2010Jack-up Barge
Set-up, Operation isolation, spading, depressurization
etc.NormalFS[1]
KMS-3000KOM CompletedFinish milestoneMS-1070Conduct Lessons Learnt
WorkshopFinish milestoneFS[5]
CN-TS-2550Commence Offshore Top-side modification WorksStart
milestoneCN-TS-2490Jack-up Barge Mobilization Set-up, Operation
isolation, spading, depressurization etc.NormalFS[1]
PR-MM-1870PO AcceptanceFinish milestonePR-MM-1890Vendor Data
ReviewNormalFS[9]
DE-PL-5090Prepare & Issue for ReviewNormalDE-PL-5100Issued for
PurchaseNormalFS[4]
DE-PL-5070Incorporate Comments & Issue for
ApprovalNormalDE-PL-5080Issued for PurchaseNormalFS[9]
DE-PL-5060Prepare & Issue for ReviewNormalDE-PL-5070Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-5060Prepare & Issue for ReviewNormalDE-PL-5110RFQ / Receive
Bids from VendorNormalFS[9]
DE-PL-5040Incorporate Comments & Issue for
ApprovalNormalDE-PL-5050Issued for PurchaseNormalFS[9]
DE-PL-5030Prepare & Issue for ReviewNormalDE-PL-5040Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-5010Incorporate Comments & Issue for
ApprovalNormalDE-PL-5020Issued for PurchaseNormalFS[9]
DE-PL-5000Prepare & Issue for ReviewNormalDE-PL-5010Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4970Issued for PurchaseNormalPR-MM-1000PO AcceptanceFinish
milestoneFS[2]
DE-PL-4960Prepare & Issue for ReviewNormalDE-PL-4970Issued for
PurchaseNormalFS[4]
DE-PL-4940Incorporate Comments & Issue for
ApprovalNormalDE-PL-4950Issued for PurchaseNormalFS[9]
DE-PL-4930Prepare & Issue for ReviewNormalDE-PL-4940Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4930Prepare & Issue for ReviewNormalDE-PL-4980RFQ / Receive
Bids from VendorNormalFS[5]
DE-PL-4910Incorporate Comments & Issue for
ApprovalNormalDE-PL-4920Issued for PurchaseNormalFS[9]
DE-PL-4900Prepare & Issue for ReviewNormalDE-PL-4910Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4880Incorporate Comments & Issue for
ApprovalNormalDE-PL-4890Issued for PurchaseNormalFS[9]
DE-PL-4870Prepare & Issue for ReviewNormalDE-PL-4880Incorporate
Comments & Issue for ApprovalNormalFS[9]
GN-1280-A10Management ApprovalNormalGN-1280-10EPC ITT to Award Of
EPC ContractNormalFS[3]
KMS-1030Complete FEED ServicesFinish milestoneGN-1280-A10Management
ApprovalNormalFS[1]
KMS-3130Overall EPC completionFinish milestoneKMS-3440Overall
Project completion by CompanyFinish milestoneFS[13]
CN-PL-3130Submission of Final ReportNormalCN-PL-3110Mobilization of
DP-2 Vessel for Sleeper InstallationNormalFS[67]
CN-PL-3090Processing and Submission of Report for
ReviewNormalKMS-3220Commencement of Pipeline Sleeper
InstallationStart milestoneFS[7]
CN-PL-3090Processing and Submission of Report for
ReviewNormalCN-PL-3110Mobilization of DP-2 Vessel for Sleeper
InstallationNormalFS[7]
CN-TS-2090Piping Modification Works, Valve/Equipment
InstallationNormalCN-TS-2600Touch painting /Removal of
ScafoldingNormalFS[1]
PR-BK-2000PO AcceptanceFinish milestonePR-BK-2020PO AcceptanceFinish
milestoneFS[2]
PR-BK-2080PO AcceptanceFinish milestonePR-BK-2120Vendor Data
ReviewNormalFS[9]
PR-BK-2050PO AcceptanceFinish milestonePR-BK-2090Vendor Data
ReviewNormalFS[9]
PR-MM-1800Delivery & ClearanceNormalCN-TS-2010Jack-up Barge Set-up,
Operation isolation, spading, depressurization etc.NormalFS[1]
PR-MM-1570PO AcceptanceFinish milestonePR-MM-1610Vendor Data
ReviewNormalFS[9]
PR-MM-1170PO AcceptanceFinish milestonePR-MM-1250Vendor Data
ReviewNormalFS[9]
PR-MM-1200PO AcceptanceFinish milestonePR-MM-1260Vendor Data
ReviewNormalFS[9]
PR-MM-1150PO AcceptanceFinish milestonePR-MM-1230Vendor Data
ReviewNormalFS[9]
PR-MM-1470PO AcceptanceFinish milestonePR-MM-1580Vendor Data
ReviewNormalFS[9]
PR-MM-1470PO AcceptanceFinish milestonePR-MM-1390PO AcceptanceFinish
milestoneFS[2]
PR-MM-1810Delivery & ClearanceNormalCN-TS-2010Jack-up Barge Set-up,
Operation isolation, spading, depressurization etc.NormalFS[1]
PR-MM-1390PO AcceptanceFinish milestonePR-MM-1550Vendor Data
ReviewNormalFS[9]
PR-MM-1860Delivery & ClearanceNormalCN-TS-2520Electrical and
instrumentation worksNormalFS[13]
PR-MM-1860Delivery & ClearanceNormalCN-TS-2010Jack-up Barge Set-up,
Operation isolation, spading, depressurization etc.NormalFS[1]
PR-MM-1760Delivery & ClearanceNormalCN-TS-2010Jack-up Barge Set-up,
Operation isolation, spading, depressurization etc.NormalFS[1]
PR-MM-1440PO AcceptanceFinish milestonePR-MM-1560Vendor Data
ReviewNormalFS[9]
PR-MM-1270PO AcceptanceFinish milestonePR-MM-1400Vendor Data
ReviewNormalFS[9]
PR-MM-1270PO AcceptanceFinish milestonePR-MM-1870PO AcceptanceFinish
milestoneFS[2]
PR-MM-1080PO AcceptanceFinish milestonePR-MM-1130Vendor Data
ReviewNormalFS[9]
PR-MM-1650PO AcceptanceFinish milestonePR-MM-1710Vendor Data
ReviewNormalFS[9]
PR-MM-14603LPP and Concrete Coating of Line Pipe and Induction
BendsNormalCN-PL-3170Mobilization of LaybargeNormalFS[1]
PR-MM-1000PO AcceptanceFinish milestonePR-MM-1040Vendor Data
ReviewNormalFS[9]
MS-1380RFSU for All Facilities CompleteFinish
milestoneAS-GN-1300As-bulit PackageNormalFS[1]
MS-1380RFSU for All Facilities CompleteFinish milestoneMS-2580Issue
PACFinish milestoneFS[1]
MS-1360ESD Valve DeliveredFinish milestoneCN-TS-2010Jack-up Barge
Set-up, Operation isolation, spading, depressurization
etc.NormalFS[1]
MS-1070Conduct Lessons Learnt WorkshopFinish milestoneMS-1130Plot
Plans Issued for ReviewFinish milestoneFS[5]
MS-1070Conduct Lessons Learnt WorkshopFinish milestoneMS-1080Conduct
Risk Assessment WorkshopFinish milestoneFS[5]
MS-1130Plot Plans Issued for ReviewFinish milestoneDE-PI-3140Plot
Plan ReviewNormalFS[11]
MS-1120PFD, HMB Issued for ReviewFinish milestoneDE-PR-2290Issue for
HAZOPNormalFS[11]
MS-1210HAZOP WorkshopFinish milestoneDE-3P-1170SIL Study &
Verification WorkshopNormalFS[5]
MS-1210HAZOP WorkshopFinish milestoneDE-PR-2390Incorporate Comments
& Issue for ApprovalNormalFS[11]
MS-1210HAZOP WorkshopFinish milestoneDE-PR-2400Incorporate Comments
& Issue for ApprovalNormalFS[11]
MS-1210HAZOP WorkshopFinish milestoneDE-PR-2460Incorporate Comments
& Issue for ApprovalNormalFS[11]
MS-1210HAZOP WorkshopFinish milestoneDE-PI-3600Incorporate Comments
& Issue for ApprovalNormalFS[5]
MS-1210HAZOP WorkshopFinish milestoneDE-PR-2420Incorporate Comments
& Issue for ApprovalNormalFS[11]
MS-1210HAZOP WorkshopFinish milestoneDE-PR-2450Incorporate Comments
& Issue for ApprovalNormalFS[11]
MS-1210HAZOP WorkshopFinish milestoneDE-PR-2520Incorporate Comments
& Issue for ApprovalNormalFS[11]
MS-1250Participate in PHSER-III WorkshopFinish
milestoneDE-SR-8650Prepare & Issue for ReviewNormalFS[16]
MS-1090Process BOD Issued for reviewFinish
milestoneDE-PR-2080Incorporate Comments & Issue for
ApprovalNormalFS[11]
MS-1110Planning Package Issued for ReviewFinish
milestoneDE-GN-1170Incorporate Comments & Issue for
ApprovalNormalFS[11]
MS-1060KOM CompletedFinish milestoneMS-1070Conduct Lessons Learnt
WorkshopFinish milestoneFS[5]
MS-1240Constructability / SIMOPS Workshop CompletedFinish
milestoneMS-1250Participate in PHSER-III WorkshopFinish
milestoneFS[5]
MS-1050Mobilization and Allocation of Key Resources CompletedFinish
milestoneDE-PR-2270P&ID Design ReviewNormalFS[18]
MS-1050Mobilization and Allocation of Key Resources CompletedFinish
milestoneDE-PL-4220Issued for ConstructionNormalFS[18]
MS-1050Mobilization and Allocation of Key Resources CompletedFinish
milestoneDE-PL-4350Issued for ConstructionNormalFS[18]
MS-127090% Model Review ConductedFinish milestoneMS-1310Completion
of Major EngineeringFinish milestoneFS[18]
MS-127090% Model Review ConductedFinish milestoneKMS-3010Completion
of Major EngineeringFinish milestoneFS[18]
MS-123060% Model Review ConductedFinish milestoneMS-1310Completion
of Major EngineeringFinish milestoneFS[42]
MS-123060% Model Review ConductedFinish milestoneKMS-3010Completion
of Major EngineeringFinish milestoneFS[42]
MS-118030% Model Review ConductedFinish milestoneDE-3P-1110Value
Engineering WorkshopNormalFS[5]
MS-1150P&ID Issued for ReviewFinish milestoneDE-PR-2270P&ID Design
ReviewNormalFS[16]
MS-1040Project Effective Date for EPC PhaseStart
milestonePR-MM-1010PO AcceptanceFinish milestoneFS[16]
DE-MC-2850Incorporate Comments & Issue for
ApprovalNormalDE-MC-2880Issued for ConstructionNormalFS[9]
DE-MC-2820Prepare & Issue for ReviewNormalDE-MC-2850Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-MC-2820Prepare & Issue for ReviewNormalMS-1210HAZOP
WorkshopFinish milestoneFS[5]
DE-MC-2820Prepare & Issue for ReviewNormalKMS-3180HAZOP
WorkshopFinish milestoneFS[5]
DE-MC-2830Incorporate Comments & Issue for
ApprovalNormalDE-MC-2860Issued for ConstructionNormalFS[9]
DE-MC-2800Prepare & Issue for ReviewNormalDE-MC-2830Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-MC-2840Incorporate Comments & Issue for
ApprovalNormalDE-MC-2870Issued for ConstructionNormalFS[9]
DE-MC-2810Prepare & Issue for ReviewNormalDE-MC-2840Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2340Incorporate Comments & Issue for
ApprovalNormalDE-PR-2410Issued for ConstructionNormalFS[9]
DE-PR-2240Prepare & Issue for ReviewNormalDE-PR-2340Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2280Incorporate Comments & Issue for
ApprovalNormalDE-PR-2380Issued for ConstructionNormalFS[9]
DE-PR-2130Prepare & Issue for ReviewNormalDE-PR-2280Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2450Incorporate Comments & Issue for
ApprovalNormalDE-PR-2540Issued for ConstructionNormalFS[9]
DE-PR-2200Prepare & Issue for ReviewNormalDE-PR-2450Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2420Incorporate Comments & Issue for
ApprovalNormalDE-PR-2510Issued for ConstructionNormalFS[9]
DE-PR-2120Prepare & Issue for ReviewNormalDE-PR-2420Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2120Prepare & Issue for ReviewNormalDE-PR-2270P&ID Design
ReviewNormalFS[5]
DE-PR-2080Incorporate Comments & Issue for
ApprovalNormalDE-PR-2170Issued for ConstructionNormalFS[9]
DE-PR-2000Prepare & Issue for ReviewNormalDE-PR-2080Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2430Incorporate Comments & Issue for
ApprovalNormalDE-PR-2580Issued for ConstructionNormalFS[9]
DE-PR-2260Prepare & Issue for ReviewNormalDE-PR-2430Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2480Incorporate Comments & Issue for
ApprovalNormalDE-PR-2560Issued for ConstructionNormalFS[9]
DE-PR-2190Prepare & Issue for ReviewNormalDE-PR-2270P&ID Design
ReviewNormalFS[5]
DE-PR-2190Prepare & Issue for ReviewNormalDE-PR-2350Issue for
HAZOPNormalFS[9]
DE-PR-2100Incorporate Comments & Issue for
ApprovalNormalDE-PR-2220Issued for ConstructionNormalFS[9]
DE-PR-2050Prepare & Issue for ReviewNormalDE-PR-2100Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2470Incorporate Comments & Issue for
ApprovalNormalDE-PR-2570Issued for ConstructionNormalFS[9]
DE-PR-2230Prepare & Issue for ReviewNormalDE-PR-2470Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2230Prepare & Issue for ReviewNormalDE-3P-1140HAZOP
WorkshopNormalFS[5]
DE-PR-2460Incorporate Comments & Issue for
ApprovalNormalDE-PR-2550Issued for ConstructionNormalFS[9]
DE-PR-2210Prepare & Issue for ReviewNormalDE-PR-2460Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2520Incorporate Comments & Issue for
ApprovalNormalDE-PR-2600Issued for ConstructionNormalFS[9]
DE-PR-2360Prepare & Issue for ReviewNormalDE-PR-2520Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2590Incorporate Comments & Issue for
ApprovalNormalDE-PR-2610Issued for ConstructionNormalFS[9]
DE-PR-2500Prepare & Issue for ReviewNormalDE-PR-2590Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2320Incorporate Comments & Issue for
ApprovalNormalDE-PR-2440Issued for ConstructionNormalFS[9]
DE-PR-2320Incorporate Comments & Issue for
ApprovalNormalDE-GN-1240Prepare & Issue for ReviewNormalFS[21]
DE-PR-2090Prepare & Issue for ReviewNormalDE-PR-2320Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2090Prepare & Issue for ReviewNormalDE-3P-1140HAZOP
WorkshopNormalFS[16]
DE-PR-2310Incorporate Comments & Issue for
ApprovalNormalDE-PR-2370Issued for ConstructionNormalFS[9]
DE-PR-2040Prepare & Issue for ReviewNormalDE-PR-2310Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2070Incorporate Comments & Issue for
ApprovalNormalDE-PR-2160Issued for ConstructionNormalFS[9]
DE-PR-2020Prepare & Issue for ReviewNormalDE-PR-2070Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2630Site Visit Report Issued for InfoNormalDE-PR-2640Site
Visit-3NormalFS[13]
DE-PR-2140Site Visit Report Issued for InfoNormalDE-PR-2620Site
Visit-2NormalFS[13]
DE-PR-2150Incorporate Comments & Issue for
ApprovalNormalDE-PR-2250Issued for ConstructionNormalFS[9]
DE-PR-2030Prepare & Issue for ReviewNormalDE-PR-2150Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PR-2330Issue for HAZOPNormalDE-3P-1140HAZOP WorkshopNormalFS[5]
DE-PR-2270P&ID Design ReviewNormalDE-3P-1140HAZOP
WorkshopNormalFS[5]
DE-PR-2400Incorporate Comments & Issue for
ApprovalNormalDE-PR-2530Issued for ConstructionNormalFS[9]
DE-PR-2180Prepare & Issue for ReviewNormalDE-PR-2270P&ID Design
ReviewNormalFS[13]
DE-PR-2180Prepare & Issue for ReviewNormalDE-3P-1140HAZOP
WorkshopNormalFS[5]
DE-PR-2180Prepare & Issue for ReviewNormalDE-3P-1090HAZOP Terms of
ReferenceNormalFS[5]
DE-PR-2180Prepare & Issue for ReviewNormalDE-3P-1170SIL Study &
Verification WorkshopNormalFS[5]
DE-PR-2180Prepare & Issue for ReviewNormalDE-3P-1100SIL Study
ProcedureNormalFS[5]
DE-PR-2390Incorporate Comments & Issue for
ApprovalNormalDE-PR-2490Issued for ConstructionNormalFS[9]
DE-PR-2290Issue for HAZOPNormalDE-3P-1140HAZOP WorkshopNormalFS[5]
DE-PR-2060Prepare & Issue for ReviewNormalDE-3P-1030HAZID / ENVID /
OHRA WorkshopNormalFS[5]
DE-PR-2060Prepare & Issue for ReviewNormalDE-PR-2290Issue for
HAZOPNormalFS[9]
DE-PR-2060Prepare & Issue for ReviewNormalDE-SR-8100Prepare & Issue
for ReviewNormalFS[11]
DE-PR-2060Prepare & Issue for ReviewNormalDE-SR-8270Prepare & Issue
for ReviewNormalFS[16]
DE-PR-2060Prepare & Issue for ReviewNormalDE-3P-1020Award
Sub-contractNormalFS[11]
DE-EL-6400Incorporate Comments & Issue for
ApprovalNormalDE-EL-6570Issued for ConstructionNormalFS[9]
DE-EL-6240Prepare & Issue for ReviewNormalDE-EL-6400Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6020Incorporate Comments & Issue for
ApprovalNormalDE-EL-6040Issued for ConstructionNormalFS[9]
DE-EL-6000Prepare & Issue for ReviewNormalDE-EL-6020Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6000Prepare & Issue for ReviewNormalDE-EL-6010Prepare & Issue
for ReviewNormalFS[5]
DE-EL-6160Incorporate Comments & Issue for
ApprovalNormalDE-EL-6300Issued for ConstructionNormalFS[9]
DE-EL-6080Prepare & Issue for ReviewNormalDE-EL-6160Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6510Intermediate MTONormalDE-EL-6670Final MTONormalFS[9]
DE-EL-6380Preliminary MTONormalDE-EL-6510Intermediate MTONormalFS[9]
DE-EL-6290Incorporate Comments & Issue for
ApprovalNormalDE-EL-6460Issued for ConstructionNormalFS[9]
DE-EL-6140Prepare & Issue for ReviewNormalDE-EL-6290Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6350Incorporate Comments & Issue for
ApprovalNormalDE-EL-6490Issued for ConstructionNormalFS[9]
DE-EL-6170Prepare & Issue for ReviewNormalDE-EL-6350Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6560Incorporate Comments & Issue for
ApprovalNormalDE-EL-6660Issued for ConstructionNormalFS[9]
DE-EL-6340Prepare & Issue for ReviewNormalDE-EL-6560Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6600Incorporate Comments & Issue for
ApprovalNormalDE-EL-6650Issued for ConstructionNormalFS[9]
DE-EL-6330Prepare & Issue for ReviewNormalDE-EL-6600Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6590Incorporate Comments & Issue for
ApprovalNormalDE-EL-6620Issued for ConstructionNormalFS[9]
DE-EL-6440Prepare & Issue for ReviewNormalDE-EL-6590Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6550Incorporate Comments & Issue for
ApprovalNormalDE-EL-6630Issued for ConstructionNormalFS[9]
DE-EL-6220Prepare & Issue for ReviewNormalDE-EL-6550Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6470Incorporate Comments & Issue for
ApprovalNormalDE-EL-6640Issued for ConstructionNormalFS[9]
DE-EL-6320Prepare & Issue for ReviewNormalDE-EL-6470Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6210Incorporate Comments & Issue for
ApprovalNormalDE-EL-6430Issued for ConstructionNormalFS[9]
DE-EL-6100Prepare & Issue for ReviewNormalDE-EL-6210Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6540Issued for UseNormalPR-BK-2050PO AcceptanceFinish
milestoneFS[2]
DE-EL-6390Prepare & Issue for Review /
ApprovalNormalDE-EL-6540Issued for UseNormalFS[9]
DE-EL-6130Incorporate Comments & Issue for
ApprovalNormalDE-EL-6270Issued for PurchaseNormalFS[9]
DE-EL-6050Prepare & Issue for ReviewNormalDE-EL-6130Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6610Issued for UseNormalPR-MM-1470PO AcceptanceFinish
milestoneFS[2]
DE-EL-6480Prepare & Issue for Review /
ApprovalNormalDE-EL-6610Issued for UseNormalFS[9]
DE-EL-6410Incorporate Comments & Issue for
ApprovalNormalDE-EL-6530Issued for PurchaseNormalFS[9]
DE-EL-6260Prepare & Issue for ReviewNormalDE-EL-6410Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6370Incorporate Comments & Issue for
ApprovalNormalDE-EL-6500Issued for PurchaseNormalFS[9]
DE-EL-6190Prepare & Issue for ReviewNormalDE-EL-6370Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-EL-6030Incorporate Comments & Issue for
ApprovalNormalDE-EL-6090Issued for PurchaseNormalFS[9]
DE-EL-6010Prepare & Issue for ReviewNormalDE-EL-6030Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9120Incorporate Comments & Issue for
ApprovalNormalDE-ST-9210Issued for ConstructionNormalFS[9]
DE-ST-9040Prepare & Issue for ReviewNormalDE-ST-9120Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9540Incorporate Comments & Issue for
ApprovalNormalDE-ST-9610Issued for ConstructionNormalFS[9]
DE-ST-9350Prepare & Issue for ReviewNormalDE-ST-9540Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9510Incorporate Comments & Issue for
ApprovalNormalDE-ST-9600Issued for ConstructionNormalFS[9]
DE-ST-9300Prepare & Issue for ReviewNormalDE-ST-9510Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9500Incorporate Comments & Issue for
ApprovalNormalDE-ST-9590Issued for ConstructionNormalFS[9]
DE-ST-9270Prepare & Issue for ReviewNormalDE-ST-9500Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9270Prepare & Issue for ReviewNormalDE-ST-9350Prepare & Issue
for ReviewNormalFS[5]
DE-ST-9460Incorporate Comments & Issue for
ApprovalNormalDE-ST-9580Issued for ConstructionNormalFS[9]
DE-ST-9190Prepare & Issue for ReviewNormalDE-ST-9460Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9190Prepare & Issue for ReviewNormalDE-ST-9300Prepare & Issue
for ReviewNormalFS[5]
DE-ST-9450Incorporate Comments & Issue for
ApprovalNormalDE-ST-9570Issued for ConstructionNormalFS[9]
DE-ST-9250Prepare & Issue for ReviewNormalDE-ST-9450Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9410Incorporate Comments & Issue for
ApprovalNormalDE-ST-9550Issued for ConstructionNormalFS[9]
DE-ST-9150Prepare & Issue for ReviewNormalDE-ST-9410Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9030Incorporate Comments & Issue for
ApprovalNormalDE-ST-9080Issued for ConstructionNormalFS[9]
DE-ST-9000Prepare & Issue for ReviewNormalDE-ST-9030Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9490Intermediate MTONormalDE-ST-9620Final MTONormalFS[9]
DE-ST-9490Intermediate MTONormalCN-PF-1000Pre-Fabrication of
Structural Steel Works, Piping Spools for Offshore
HookupNormalFS[32]
DE-ST-9400Preliminary MTONormalDE-ST-9490Intermediate MTONormalFS[9]
DE-ST-9400Preliminary MTONormalPR-BK-2030PO AcceptanceFinish
milestoneFS[2]
DE-ST-9390Incorporate Comments & Issue for
ApprovalNormalDE-ST-9520Issued for ConstructionNormalFS[9]
DE-ST-9260Prepare & Issue for ReviewNormalDE-ST-9390Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9310Incorporate Comments & Issue for
ApprovalNormalDE-ST-9440Issued for ConstructionNormalFS[9]
DE-ST-9160Prepare & Issue for ReviewNormalDE-ST-9310Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9050Incorporate Comments & Issue for
ApprovalNormalDE-ST-9110Issued for ConstructionNormalFS[9]
DE-ST-9010Prepare & Issue for ReviewNormalDE-ST-9050Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9370Incorporate Comments & Issue for
ApprovalNormalDE-ST-9530Issued for ConstructionNormalFS[9]
DE-ST-9280Prepare & Issue for ReviewNormalDE-ST-9370Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9330Incorporate Comments & Issue for
ApprovalNormalDE-ST-9480Issued for ConstructionNormalFS[9]
DE-ST-9240Prepare & Issue for ReviewNormalDE-ST-9330Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9230Incorporate Comments & Issue for
ApprovalNormalDE-ST-9360Issued for ConstructionNormalFS[9]
DE-ST-9090Prepare & Issue for ReviewNormalDE-ST-9230Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9090Prepare & Issue for ReviewNormalDE-ST-9160Prepare & Issue
for ReviewNormalFS[4]
DE-ST-9090Prepare & Issue for ReviewNormalDE-ST-9260Prepare & Issue
for ReviewNormalFS[16]
DE-ST-9070Incorporate Comments & Issue for
ApprovalNormalDE-ST-9140Issued for ConstructionNormalFS[9]
DE-ST-9020Prepare & Issue for ReviewNormalDE-ST-9070Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9220Incorporate Comments & Issue for
ApprovalNormalDE-ST-9380Issued for ConstructionNormalFS[9]
DE-ST-9100Prepare & Issue for ReviewNormalDE-ST-9220Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ST-9430Incorporate Comments & Issue for
ApprovalNormalDE-ST-9560Issued for ConstructionNormalFS[9]
DE-ST-9320Prepare & Issue for ReviewNormalDE-ST-9430Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3340Site Visit Report-2 Issued for InfoNormalDE-PI-3700Site
Visit-3NormalFS[32]
DE-PI-3070Site Visit Report-1 Issued for InfoNormalDE-PI-3330Site
Visit-2NormalFS[32]
DE-PI-3030BOD: Incorporate Comments & Issue for
ApprovalNormalDE-PI-3090BOD: Issued for ConstructionNormalFS[9]
DE-PI-3000BOD: Prepare & Issue for ReviewNormalDE-PI-3030BOD:
Incorporate Comments & Issue for ApprovalNormalFS[9]
DE-PI-3670Intermediate MTONormalDE-PI-3840Final MTONormalFS[9]
DE-PI-3290Preliminary MTONormalDE-PI-3670Intermediate MTONormalFS[9]
DE-PI-3400Incorporate Comments & Issue for
ApprovalNormalDE-PI-3620Issued for ConstructionNormalFS[9]
DE-PI-3150Prepare & Issue for ReviewNormalDE-PI-3400Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3450Incorporate Comments & Issue for
ApprovalNormalDE-PI-3610Issued for ConstructionNormalFS[9]
DE-PI-3200Prepare & Issue for ReviewNormalDE-PI-3450Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3490Incorporate Comments & Issue for
ApprovalNormalDE-PI-3680Issued for ConstructionNormalFS[9]
DE-PI-3310Prepare & Issue for ReviewNormalDE-PI-3490Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3260Issue for HAZOPNormalDE-3P-1140HAZOP WorkshopNormalFS[5]
DE-PI-3140Plot Plan ReviewNormalDE-3P-1140HAZOP WorkshopNormalFS[5]
DE-PI-3600Incorporate Comments & Issue for
ApprovalNormalDE-PI-3740Issued for ConstructionNormalFS[9]
DE-PI-3050Prepare & Issue for ReviewNormalDE-3P-1030HAZID / ENVID /
OHRA WorkshopNormalFS[5]
DE-PI-3050Prepare & Issue for ReviewNormalDE-PI-3140Plot Plan
ReviewNormalFS[9]
DE-PI-3050Prepare & Issue for ReviewNormalDE-ST-9060Piping /
Mechanical / Electrical / Instrument Load input to
StructuralNormalFS[5]
DE-PI-3760Incorporate Comments & Issue for
ApprovalNormalDE-PI-3810Issued for ConstructionNormalFS[9]
DE-PI-3720Prepare & Issue for ReviewNormalDE-PI-3760Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3390Incorporate Comments & Issue for
ApprovalNormalDE-PI-3570Issued for ConstructionNormalFS[9]
DE-PI-3180Prepare & Issue for ReviewNormalDE-PI-3390Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3240Incorporate Comments & Issue for
ApprovalNormalDE-PI-3440Issued for ConstructionNormalFS[9]
DE-PI-3120Prepare & Issue for ReviewNormalDE-PI-3240Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-364060% Model ReviewNormalDE-3P-1220Constructability Workshop
/ SIMOPS WorkshopNormalFS[5]
DE-PI-328060% Modeling WorksNormalDE-3P-1220Constructability
Workshop / SIMOPS WorkshopNormalFS[5]
DE-PI-308030% Modeling WorksNormalDE-PI-325030% Model
ReviewNormalFS[1]
DE-PI-3040Incorporate Comments & Issue for
ApprovalNormalDE-PI-3100Issued for ConstructionNormalFS[9]
DE-PI-3010Prepare & Issue for ReviewNormalDE-PI-3040Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-365060% Model Review ReportNormalDE-PI-375060% Model Review
Close-out ReportNormalFS[9]
DE-PI-327030% Model Review ReportNormalDE-PI-364060% Model
ReviewNormalFS[11]
DE-PI-327030% Model Review ReportNormalDE-PI-348030% Model Review
Close-out ReportNormalFS[9]
DE-PI-3230Incorporate Comments & Issue for
ApprovalNormalDE-PI-3430Issued for PurchaseNormalFS[9]
DE-PI-3110Prepare & Issue for ReviewNormalDE-PI-3230Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3350Incorporate Comments & Issue for
ApprovalNormalDE-PI-3540Issued for PurchaseNormalFS[9]
DE-PI-3160Prepare & Issue for ReviewNormalDE-PI-3350Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3300Incorporate Comments & Issue for
ApprovalNormalDE-PI-3470Issued for PurchaseNormalFS[9]
DE-PI-3130Prepare & Issue for ReviewNormalDE-PI-3300Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3580Issued for PurchaseNormalPR-MM-1200PO AcceptanceFinish
milestoneFS[2]
DE-PI-3580Issued for PurchaseNormalPR-MM-1170PO AcceptanceFinish
milestoneFS[4]
DE-PI-3580Issued for PurchaseNormalCN-PF-1140Valve and Equipment
Installation before LoadoutNormalFS[2]
DE-PI-3460Prepare & Issue for ReviewNormalDE-PI-3580Issued for
PurchaseNormalFS[9]
DE-PI-3690Issued for PurchaseNormalPR-BK-2020PO AcceptanceFinish
milestoneFS[2]
DE-PI-3520Incorporate Comments & Issue for
ApprovalNormalDE-PI-3690Issued for PurchaseNormalFS[9]
DE-PI-3220Prepare & Issue for ReviewNormalDE-PI-3520Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3220Prepare & Issue for ReviewNormalPR-BK-2000PO
AcceptanceFinish milestoneFS[2]
DE-PI-3730Approved for PurchaseNormalPR-MM-1200PO AcceptanceFinish
milestoneFS[2]
DE-PI-3590Prepare & Issue for ReviewNormalDE-PI-3730Approved for
PurchaseNormalFS[9]
DE-PI-3500Incorporate Comments & Issue for
ApprovalNormalDE-PI-3630Approved for PurchaseNormalFS[9]
DE-PI-3320Prepare & Issue for ReviewNormalDE-PI-3500Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3410Incorporate Comments & Issue for
ApprovalNormalDE-PI-3550Approved for PurchaseNormalFS[9]
DE-PI-3190Prepare & Issue for ReviewNormalDE-PI-3410Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PI-3370Incorporate Comments & Issue for
ApprovalNormalDE-PI-3530Approved for PurchaseNormalFS[9]
DE-PI-3170Prepare & Issue for ReviewNormalDE-PI-3370Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7730Issued for PurchaseNormalPR-MM-1600PO AcceptanceFinish
milestoneFS[2]
DE-IC-7550Prepare & Issue for ReviewNormalDE-IC-7730Issued for
PurchaseNormalFS[9]
DE-IC-7430Incorporate Comments & Issue for
ApprovalNormalDE-IC-7700Issued for PurchaseNormalFS[9]
DE-IC-7280Prepare & Issue for ReviewNormalDE-IC-7430Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7510Issued for PurchaseNormalPR-BK-2080PO AcceptanceFinish
milestoneFS[2]
DE-IC-7510Issued for PurchaseNormalPR-MM-1440PO AcceptanceFinish
milestoneFS[2]
DE-IC-7340Prepare & Issue for ReviewNormalDE-IC-7510Issued for
PurchaseNormalFS[9]
DE-IC-7140Incorporate Comments & Issue for
ApprovalNormalDE-IC-7240Issued for PurchaseNormalFS[9]
DE-IC-7060Prepare & Issue for ReviewNormalDE-IC-7140Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7380Issued for PurchaseNormalPR-MM-1870PO AcceptanceFinish
milestoneFS[2]
DE-IC-7270Prepare & Issue for ReviewNormalDE-IC-7380Issued for
PurchaseNormalFS[9]
DE-IC-7160Incorporate Comments & Issue for
ApprovalNormalDE-IC-7600Issued for PurchaseNormalFS[9]
DE-IC-7110Prepare & Issue for ReviewNormalDE-IC-7160Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7040Incorporate Comments & Issue for
ApprovalNormalDE-IC-7050Issued for PurchaseNormalFS[9]
DE-IC-7040Incorporate Comments & Issue for
ApprovalNormalDE-IC-7060Prepare & Issue for ReviewNormalFS[11]
DE-IC-7010Prepare & Issue for ReviewNormalDE-IC-7060Prepare & Issue
for ReviewNormalFS[11]
DE-IC-7010Prepare & Issue for ReviewNormalDE-IC-7040Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7120Incorporate Comments & Issue for
ApprovalNormalDE-IC-7520Issued for PurchaseNormalFS[9]
DE-IC-7090Prepare & Issue for ReviewNormalDE-IC-7120Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7590Incorporate Comments & Issue for
ApprovalNormalDE-IC-7740Issued for ConstructionNormalFS[9]
DE-IC-7410Prepare & Issue for ReviewNormalDE-IC-7590Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7790Incorporate Comments & Issue for
ApprovalNormalDE-IC-7800Issued for ConstructionNormalFS[9]
DE-IC-7800Issued for ConstructionNormalCN-TS-2010Jack-up Barge
Set-up, Operation isolation, spading, depressurization
etc.NormalFS[1]
DE-IC-7780Prepare & Issue for ReviewNormalDE-IC-7800Issued for
ConstructionNormalFS[9]
DE-IC-7780Prepare & Issue for ReviewNormalDE-IC-7790Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7660Incorporate Comments & Issue for
ApprovalNormalDE-IC-7760Issued for ConstructionNormalFS[9]
DE-IC-7440Prepare & Issue for ReviewNormalDE-IC-7660Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7480Incorporate Comments & Issue for
ApprovalNormalDE-IC-7650Issued for ConstructionNormalFS[9]
DE-IC-7260Prepare & Issue for ReviewNormalDE-IC-7480Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7460Incorporate Comments & Issue for
ApprovalNormalDE-IC-7610Issued for ConstructionNormalFS[9]
DE-IC-7310Prepare & Issue for ReviewNormalDE-IC-7460Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7170Incorporate Comments & Issue for
ApprovalNormalDE-IC-7290Issued for ConstructionNormalFS[9]
DE-IC-7100Prepare & Issue for ReviewNormalDE-IC-7170Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7030Incorporate Comments & Issue for
ApprovalNormalDE-IC-7080Issued for ConstructionNormalFS[9]
DE-IC-7000Prepare & Issue for ReviewNormalDE-IC-7030Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7320Incorporate Comments & Issue for
ApprovalNormalDE-IC-7630Issued for ConstructionNormalFS[9]
DE-IC-7210Prepare & Issue for ReviewNormalDE-IC-7630Issued for
ConstructionNormalFS[9]
DE-IC-7210Prepare & Issue for ReviewNormalDE-IC-7320Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7530Incorporate Comments & Issue for
ApprovalNormalDE-IC-7710Issued for ConstructionNormalFS[9]
DE-IC-7370Prepare & Issue for ReviewNormalDE-IC-7530Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7420Incorporate Comments & Issue for
ApprovalNormalDE-IC-7680Issued for ConstructionNormalFS[9]
DE-IC-7220Prepare & Issue for ReviewNormalDE-IC-7420Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7390Incorporate Comments & Issue for
ApprovalNormalDE-IC-7620Issued for ConstructionNormalFS[9]
DE-IC-7180Prepare & Issue for ReviewNormalDE-IC-7390Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7690Intermediate MTONormalDE-IC-7770Final MTONormalFS[9]
DE-IC-7500Preliminary MTONormalDE-IC-7690Intermediate MTONormalFS[9]
DE-IC-7580Incorporate Comments & Issue for
ApprovalNormalDE-IC-7720Issued for ConstructionNormalFS[9]
DE-IC-7400Prepare & Issue for ReviewNormalDE-IC-7580Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7640Incorporate Comments & Issue for
ApprovalNormalDE-IC-7750Issued for ConstructionNormalFS[9]
DE-IC-7450Prepare & Issue for ReviewNormalDE-IC-7640Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7350Incorporate Comments & Issue for
ApprovalNormalDE-IC-7570Issued for ConstructionNormalFS[9]
DE-IC-7150Prepare & Issue for ReviewNormalDE-IC-7350Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-IC-7490Incorporate Comments & Issue for
ApprovalNormalDE-IC-7670Issued for ConstructionNormalFS[9]
DE-IC-7330Prepare & Issue for ReviewNormalDE-IC-7490Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8700Issued for PurchaseNormalPR-MM-1570PO AcceptanceFinish
milestoneFS[2]
DE-SR-8530Prepare & Issue for ReviewNormalDE-SR-8700Issued for
PurchaseNormalFS[9]
DE-SR-8490Incorporate Comments & Issue for
ApprovalNormalDE-SR-8670Issued for PurchaseNormalFS[9]
DE-SR-8370Prepare & Issue for ReviewNormalDE-SR-8490Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8430Incorporate Comments & Issue for
ApprovalNormalDE-SR-8690Issued for PurchaseNormalFS[9]
DE-SR-8300Prepare & Issue for ReviewNormalDE-SR-8430Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8360Incorporate Comments & Issue for
ApprovalNormalDE-SR-8660Issued for PurchaseNormalFS[9]
DE-SR-8240Prepare & Issue for ReviewNormalDE-SR-8360Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8380Prepare & Issue for ReviewNormalDE-SR-8520Issued for
ConstructionNormalFS[13]
DE-SR-8050Site VisitNormalDE-SR-8060Site Visit Report issued for
infoNormalFS[2]
DE-SR-8420Incorporate Comments & Issue for
ApprovalNormalDE-SR-8510Issued for ConstructionNormalFS[9]
DE-SR-8250Prepare & Issue for ReviewNormalDE-SR-8420Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8070Incorporate Comments & Issue for
ApprovalNormalDE-SR-8140Issued for ConstructionNormalFS[9]
DE-SR-8020Prepare & Issue for ReviewNormalDE-SR-8070Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8400Incorporate Comments & Issue for
ApprovalNormalDE-SR-8620Issued for ConstructionNormalFS[9]
DE-SR-8230Prepare & Issue for ReviewNormalDE-SR-8400Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8030Incorporate Comments & Issue for
ApprovalNormalDE-SR-8090Issued for ConstructionNormalFS[9]
DE-SR-8010Prepare & Issue for ReviewNormalDE-SR-8030Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8220Incorporate Comments & Issue for
ApprovalNormalDE-SR-8330Issued for ConstructionNormalFS[9]
DE-SR-8100Prepare & Issue for ReviewNormalDE-SR-8220Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8310Incorporate Comments & Issue for
ApprovalNormalDE-SR-8560Issued for ConstructionNormalFS[9]
DE-SR-8180Prepare & Issue for ReviewNormalDE-SR-8310Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8460Incorporate Comments & Issue for
ApprovalNormalDE-SR-8580Issued for ConstructionNormalFS[9]
DE-SR-8320Prepare & Issue for ReviewNormalDE-SR-8460Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8320Prepare & Issue for ReviewNormalMS-1250Participate in
PHSER-III WorkshopFinish milestoneFS[11]
DE-SR-8170Incorporate Comments & Issue for
ApprovalNormalDE-SR-8550Issued for ConstructionNormalFS[9]
DE-SR-8080Prepare & Issue for ReviewNormalDE-SR-8170Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8260Incorporate Comments & Issue for
ApprovalNormalDE-SR-8610Issued for ConstructionNormalFS[9]
DE-SR-8160Prepare & Issue for ReviewNormalDE-SR-8260Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8210Incorporate Comments & Issue for
ApprovalNormalDE-SR-8640Issued for ConstructionNormalFS[9]
DE-SR-8130Prepare & Issue for ReviewNormalDE-SR-8210Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8390Incorporate Comments & Issue for
ApprovalNormalDE-SR-8680Issued for ConstructionNormalFS[9]
DE-SR-8270Prepare & Issue for ReviewNormalDE-SR-8390Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8470Incorporate Comments & Issue for
ApprovalNormalDE-SR-8590Issued for ConstructionNormalFS[9]
DE-SR-8340Prepare & Issue for ReviewNormalDE-SR-8470Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8190Incorporate Comments & Issue for
ApprovalNormalDE-SR-8540Issued for ConstructionNormalFS[9]
DE-SR-8110Prepare & Issue for ReviewNormalDE-SR-8190Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8410Incorporate Comments & Issue for
ApprovalNormalDE-SR-8630Issued for ConstructionNormalFS[9]
DE-SR-8280Prepare & Issue for ReviewNormalDE-SR-8410Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8200Incorporate Comments & Issue for
ApprovalNormalDE-SR-8570Issued for ConstructionNormalFS[9]
DE-SR-8120Prepare & Issue for ReviewNormalDE-SR-8200Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-SR-8650Prepare & Issue for ReviewNormalDE-SR-8710Issued for
ConstructionNormalFS[9]
DE-SR-8290Incorporate Comments & Issue for
ApprovalNormalDE-SR-8450Issued for ConstructionNormalFS[9]
DE-SR-8150Prepare & Issue for ReviewNormalDE-SR-8450Issued for
ConstructionNormalFS[9]
DE-SR-8150Prepare & Issue for ReviewNormalDE-SR-8290Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4800Award Sub ContractNormalPR-BK-2130Material Submittal /
Fabrication Drawing Approvals for the Concrete SleepersNormalFS[3]
DE-PL-4800Award Sub ContractNormalMS-1280Subcontract for Concrete
Sleepers PlacedFinish milestoneFS[2]
DE-PL-4670Prepare & Issue for Review Sub
contractNormalDE-PL-4800Award Sub ContractNormalFS[5]
DE-PL-4860Issued for PurchaseNormalPR-MM-1650PO AcceptanceFinish
milestoneFS[2]
DE-PL-4830Prepare & Issue for ReviewNormalDE-PL-4860Issued for
PurchaseNormalFS[9]
DE-PL-4710Incorporate Comments & Issue for
ApprovalNormalDE-PL-4820Issued for PurchaseNormalFS[9]
DE-PL-4570Prepare & Issue for ReviewNormalDE-PL-4710Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4570Prepare & Issue for ReviewNormalDE-PL-4660RFQ / Receive
Bids from VendorNormalFS[5]
DE-PL-4650Incorporate Comments & Issue for
ApprovalNormalDE-PL-4750Issued for PurchaseNormalFS[9]
DE-PL-4500Prepare & Issue for ReviewNormalDE-PL-4650Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4560Incorporate Comments & Issue for
ApprovalNormalDE-PL-4700Issued for PurchaseNormalFS[9]
DE-PL-4410Prepare & Issue for ReviewNormalDE-PL-4560Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4690Incorporate Comments & Issue for
ApprovalNormalDE-PL-4810Issued for ConstructionNormalFS[9]
DE-PL-4490Prepare & Issue for ReviewNormalDE-PL-4690Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4490Prepare & Issue for ReviewNormalPR-BK-2130Material
Submittal / Fabrication Drawing Approvals for the Concrete
SleepersNormalFS[22]
DE-PL-4490Prepare & Issue for ReviewNormalMS-1280Subcontract for
Concrete Sleepers PlacedFinish milestoneFS[21]
DE-PL-4550Incorporate Comments & Issue for
ApprovalNormalDE-PL-4680Issued for ConstructionNormalFS[9]
DE-PL-4400Prepare & Issue for ReviewNormalDE-PL-4550Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4250Incorporate Comments & Issue for
ApprovalNormalDE-PL-4340Issued for ConstructionNormalFS[9]
DE-PL-4140Prepare & Issue for ReviewNormalDE-PL-4250Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4740Issued for ConstructionNormalPR-BK-2130Material Submittal
/ Fabrication Drawing Approvals for the Concrete SleepersNormalFS[1]
DE-PL-4600Incorporate Comments & Issue for
ApprovalNormalDE-PL-4740Issued for ConstructionNormalFS[9]
DE-PL-4390Prepare & Issue for ReviewNormalDE-PL-4600Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4310Incorporate Comments & Issue for
ApprovalNormalDE-PL-4430Issued for ConstructionNormalFS[9]
DE-PL-4200Prepare & Issue for ReviewNormalDE-PL-4310Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4460Incorporate Comments & Issue for
ApprovalNormalDE-PL-4640Issued for ConstructionNormalFS[9]
DE-PL-4190Prepare & Issue for ReviewNormalDE-PL-4460Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4270Incorporate Comments & Issue for
ApprovalNormalDE-PL-4380Issued for ConstructionNormalFS[9]
DE-PL-4130Prepare & Issue for ReviewNormalDE-PL-4270Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4240Incorporate Comments & Issue for
ApprovalNormalDE-PL-4330Issued for ConstructionNormalFS[9]
DE-PL-4120Prepare & Issue for ReviewNormalDE-PL-4240Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4230Incorporate Comments & Issue for
ApprovalNormalDE-PL-4320Issued for ConstructionNormalFS[9]
DE-PL-4110Prepare & Issue for ReviewNormalDE-PL-4230Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4160Incorporate Comments & Issue for
ApprovalNormalDE-PL-4280Issued for ConstructionNormalFS[9]
DE-PL-4060Prepare & Issue for ReviewNormalDE-PL-4160Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4060Prepare & Issue for ReviewNormalDE-PL-4170Site
Visit-1NormalFS[11]
DE-PL-4100Incorporate Comments & Issue for
ApprovalNormalDE-PL-4220Issued for ConstructionNormalFS[9]
DE-PL-4040Prepare & Issue for ReviewNormalDE-PL-4100Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4300Incorporate Comments & Issue for
ApprovalNormalDE-PL-4420Issued for ConstructionNormalFS[9]
DE-PL-4080Prepare & Issue for ReviewNormalDE-PL-4300Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4480Preliminary MTONormalDE-PL-4630Intermediate MTONormalFS[9]
DE-PL-4050Incorporate Comments & Issue for
ApprovalNormalDE-PL-4150Issued for ConstructionNormalFS[9]
DE-PL-4010Prepare & Issue for ReviewNormalDE-PL-4050Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4010Prepare & Issue for ReviewNormalDE-PL-4350Issued for
ConstructionNormalFS[18]
DE-PL-4620Incorporate Comments & Issue for
ApprovalNormalDE-PL-4730Issued for ConstructionNormalFS[9]
DE-PL-4470Prepare & Issue for ReviewNormalDE-PL-4620Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4590Incorporate Comments & Issue for
ApprovalNormalDE-PL-4790Issued for ConstructionNormalFS[9]
DE-PL-4450Prepare & Issue for ReviewNormalDE-PL-4590Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4540Incorporate Comments & Issue for
ApprovalNormalDE-PL-4720Issued for ConstructionNormalFS[9]
DE-PL-4370Prepare & Issue for ReviewNormalDE-PL-4540Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4530Incorporate Comments & Issue for
ApprovalNormalDE-PL-4780Issued for ConstructionNormalFS[9]
DE-PL-4360Prepare & Issue for ReviewNormalDE-PL-4530Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4260Incorporate Comments & Issue for
ApprovalNormalDE-PL-4350Issued for ConstructionNormalFS[9]
DE-PL-4070Prepare & Issue for ReviewNormalDE-PL-4260Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4580Incorporate Comments & Issue for
ApprovalNormalDE-PL-4840Issued for ConstructionNormalFS[9]
DE-PL-4440Prepare & Issue for ReviewNormalDE-PL-4580Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-PL-4520Incorporate Comments & Issue for
ApprovalNormalDE-PL-4770Issued for ConstructionNormalFS[9]
DE-PL-4290Prepare & Issue for ReviewNormalDE-PL-4520Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ME-5180Issued for PurchaseNormalPR-MM-1080PO AcceptanceFinish
milestoneFS[2]
DE-ME-5150Prepare & Issue for Review /
ApprovalNormalDE-ME-5180Issued for PurchaseNormalFS[9]
DE-ME-5100Incorporate Comments & Issue for
ApprovalNormalDE-ME-5170Issued for PurchaseNormalFS[9]
DE-ME-5040Prepare & Issue for ReviewNormalDE-ME-5100Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ME-5090Incorporate Comments & Issue for
ApprovalNormalDE-ME-5140Issued for PurchaseNormalFS[9]
DE-ME-5030Prepare & Issue for ReviewNormalDE-ME-5090Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ME-5060Incorporate Comments & Issue for
ApprovalNormalDE-ME-5120Issued for PurchaseNormalFS[9]
DE-ME-5010Prepare & Issue for ReviewNormalDE-ME-5060Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ME-5080Incorporate Comments & Issue for
ApprovalNormalDE-ME-5160Issued for ConstructionNormalFS[9]
DE-ME-5000Prepare & Issue for ReviewNormalDE-ME-5080Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ME-5200Incorporate Comments & Issue for
ApprovalNormalDE-ME-5210Issued for ConstructionNormalFS[9]
DE-ME-5190Prepare & Issue for ReviewNormalDE-ME-5200Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-ME-5070Incorporate Comments & Issue for
ApprovalNormalDE-ME-5130Issued for ConstructionNormalFS[9]
DE-ME-5020Prepare & Issue for ReviewNormalDE-ME-5070Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-3P-1240Prepare & Issue for ReviewNormalDE-3P-1260Issued for
UseNormalFS[9]
DE-3P-1120Prepare & Issue for Review ReportNormalDE-3P-1190Issued
for UseNormalFS[9]
DE-3P-1020Award Sub-contractNormalDE-3P-1060Prepare & Issue for
ReviewNormalFS[5]
DE-3P-1160Incorporate CommentsNormalDE-3P-1250Issued for
UseNormalFS[9]
DE-3P-1060Prepare & Issue for ReviewNormalDE-3P-1160Incorporate
CommentsNormalFS[9]
DE-3P-1100SIL Study ProcedureNormalDE-3P-1170SIL Study &
Verification WorkshopNormalFS[5]
DE-3P-1180SIL Report: Prepare & Issue for ReviewNormalDE-3P-1230SIL
Report: Issued for UseNormalFS[13]
DE-3P-1170SIL Study & Verification
WorkshopNormalDE-3P-1220Constructability Workshop / SIMOPS
WorkshopNormalFS[5]
DE-3P-1090HAZOP Terms of ReferenceNormalDE-3P-1140HAZOP
WorkshopNormalFS[5]
DE-3P-1150HAZOP Report: Prepare & Issue for
ReviewNormalDE-3P-1210HAZOP Report: Issued for UseNormalFS[13]
DE-3P-1140HAZOP WorkshopNormalDE-3P-1170SIL Study & Verification
WorkshopNormalFS[5]
DE-3P-1140HAZOP WorkshopNormalDE-PR-2390Incorporate Comments & Issue
for ApprovalNormalFS[11]
DE-3P-1140HAZOP WorkshopNormalDE-PR-2400Incorporate Comments & Issue
for ApprovalNormalFS[11]
DE-3P-1140HAZOP WorkshopNormalDE-PR-2460Incorporate Comments & Issue
for ApprovalNormalFS[11]
DE-3P-1140HAZOP WorkshopNormalDE-PI-3600Incorporate Comments & Issue
for ApprovalNormalFS[5]
DE-3P-1140HAZOP WorkshopNormalDE-PR-2420Incorporate Comments & Issue
for ApprovalNormalFS[11]
DE-3P-1140HAZOP WorkshopNormalDE-PR-2450Incorporate Comments & Issue
for ApprovalNormalFS[11]
DE-3P-1140HAZOP WorkshopNormalDE-PR-2520Incorporate Comments & Issue
for ApprovalNormalFS[11]
DE-3P-1010HAZID / ENVID / OHRA Terms of
ReferenceNormalDE-3P-1030HAZID / ENVID / OHRA WorkshopNormalFS[2]
DE-3P-8040Award Sub-contractNormalDE-3P-1030HAZID / ENVID / OHRA
WorkshopNormalFS[5]
DE-3P-8040Award Sub-contractNormalDE-3P-1010HAZID / ENVID / OHRA
Terms of ReferenceNormalFS[2]
DE-3P-8040Award Sub-contractNormalDE-3P-1140HAZOP
WorkshopNormalFS[11]
DE-3P-8040Award Sub-contractNormalDE-3P-1090HAZOP Terms of
ReferenceNormalFS[11]
DE-3P-8040Award Sub-contractNormalDE-3P-1170SIL Study & Verification
WorkshopNormalFS[11]
DE-3P-8040Award Sub-contractNormalDE-3P-1100SIL Study
ProcedureNormalFS[11]
DE-3P-1040HAZID / ENVID / OHRA Report: Prepare & Issue for
ReviewNormalDE-3P-1130HAZID / ENVID / OHRA Report: Issued for
UseNormalFS[13]
DE-3P-1040HAZID / ENVID / OHRA Report: Prepare & Issue for
ReviewNormalDE-SR-8180Prepare & Issue for ReviewNormalFS[11]
DE-3P-1030HAZID / ENVID / OHRA WorkshopNormalDE-3P-1140HAZOP
WorkshopNormalFS[5]
DE-GN-1160Incorporate Comments & Issue for
ApprovalNormalDE-GN-1200Issued for ConstructionNormalFS[9]
DE-GN-1110Prepare & Issue for ReviewNormalDE-GN-1160Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-GN-1280Incorporate Comments & Issue for
ApprovalNormalDE-GN-1290Issued for ConstructionNormalFS[9]
DE-GN-1260Prepare & Issue for ReviewNormalDE-GN-1280Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-GN-1180Incorporate Comments & Issue for
ApprovalNormalDE-GN-1220Issued for ConstructionNormalFS[9]
DE-GN-1080Prepare & Issue for ReviewNormalDE-GN-1180Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-GN-1070Lessons Learnt W/S Report: Prepare & Issue for
ReviewNormalDE-GN-1120Lessons Learnt W/S Report: Issued for
UseNormalFS[9]
DE-GN-1090Risk Assessment W/S Report: Prepare & Issue for
ReviewNormalDE-GN-1140Risk Assessment W/S Report: Issued for
ConstructionNormalFS[9]
DE-GN-1250Incorporate Comments & Issue for
ApprovalNormalDE-GN-1270Issued for ConstructionNormalFS[9]
DE-GN-1240Prepare & Issue for ReviewNormalDE-GN-1250Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-GN-1170Incorporate Comments & Issue for
ApprovalNormalDE-GN-1230Issued for ConstructionNormalFS[9]
DE-GN-1060Prepare & Issue for ReviewNormalDE-GN-1170Incorporate
Comments & Issue for ApprovalNormalFS[9]
DE-GN-1010Review of SOW, Existing data and inputsNormalDE-PI-30203D
Model Set-upNormalFS[11]
DE-GN-1150Incorporate Comments & Issue for
ApprovalNormalDE-GN-1210Issued for ConstructionNormalFS[9]
DE-GN-1040Prepare & Issue for ReviewNormalDE-GN-1150Incorporate
Comments & Issue for ApprovalNormalFS[9]
MS-2570Overall RFSU Duration (From Award date until last
RFSU)HammockAS-GN-1300As-bulit PackageNormalFS[1]
MS-2570Overall RFSU Duration (From Award date until last
RFSU)HammockMS-2580Issue PACFinish milestoneFS[1]
KMS-3540RFSU for All Facilities CompleteFinish milestoneMS-2580Issue
PACFinish milestoneFS[1]
KMS-3550Project Effective Date for EPC PhaseStart
milestonePR-MM-1010PO AcceptanceFinish milestoneFS[16]

Start-to-Finish links
Start-to-Finish links are used deliberately very rarely, because they have
the unusual effect that the successor happens before the predecessor.
Consider whether this logic might be a mistake, especially if it is
between tasks that are not milestones.
From TaskTo Task
Bookmark ID Description Type Bookmark ID Description Type
DE-ST-9090Prepare & Issue for ReviewNormalDE-ST-9440Issued for
ConstructionNormal

Lags between tasks with different calendars


Options selected:FS

A lag is a gap in the logic between two tasks � a delay between the dates
of two tasks that are linked together. When the two tasks have different
calendars, it is not clear which calendar the task will use � whether it
is the preceding task's or the succeeding task's calendar. Consider
replacing the lag with a task, so that its calendar can be explicitly
defined. Use the Convert Lags to Tasks tool when a project contains a
large number of long lags.
From Task To Task
Bookmark ID Description Type Predecessor Calendar Bookmark ID
Description Type Successor Calendar Link
DE-3P-9040Award
Sub-contractNormalC00987_5D_enggCN-PL-3000Mobilization of Team /
Application & Receipt of Security Passes, Preparation of
ProceduresNormalC00987_7D_ConstFS[127]
KMS-3040ESD Valve DeliveredFinish
milestoneC00987_5D_enggCN-TS-2510Piping Modification Works,
Valve/Equipment InstallationNormal* C00987_7D_ConstFF[12]
KMS-3040ESD Valve DeliveredFinish
milestoneC00987_5D_enggCN-TS-2010Jack-up Barge Set-up, Operation
isolation, spading, depressurization etc.NormalC00987_7D_ConstFS[1]
PR-MM-1890Vendor Data
ReviewNormalC00987_5D_enggPR-MM-1880ManufacturingNormal*
C00987_7D_procFF[21]
KMS-1030Complete FEED ServicesFinish
milestoneC00987_7D_ConstGN-1280-A10Management
ApprovalNormalC00987_7D_procFS[1]
CN-PF-1140Valve and Equipment Installation before LoadoutNormal*
C00987_6D_const[no-holidays]CN-TS-2550Commence Offshore Top-side
modification WorksStart milestoneC00987_7D_ConstSS[25]
CN-PF-1000Pre-Fabrication of Structural Steel Works, Piping Spools
for Offshore HookupNormal*
C00987_6D_const[no-holidays]CN-PF-1220Loadout & Transport
pre-fabricated modules and structures
ZW-100NormalC00987_7D_ConstSS[51]
PR-BK-2120Vendor Data
ReviewNormalC00987_5D_enggPR-BK-2100ManufacturingNormal*
C00987_7D_procFF[21]
PR-BK-2090Vendor Data
ReviewNormalC00987_5D_enggPR-BK-2070ManufacturingNormal*
C00987_7D_procFF[21]
PR-BK-2130Material Submittal / Fabrication Drawing Approvals for the
Concrete SleepersNormalC00987_5D_enggPR-BK-2140Preparation of
Pre-cast Moulds for the Concrete SleepersNormal*
C00987_6D_const[no-holidays]FF[11]
PR-MM-1800Delivery & ClearanceNormalC00987_7D_procCN-TS-2010Jack-up
Barge Set-up, Operation isolation, spading, depressurization
etc.NormalC00987_7D_ConstFS[1]
PR-MM-1610Vendor Data
ReviewNormalC00987_5D_enggPR-MM-1590ManufacturingNormal*
C00987_7D_procFF[21]
PR-MM-1250Vendor Data
ReviewNormalC00987_5D_enggPR-MM-1210ManufacturingNormal*
C00987_7D_procFF[32]
PR-MM-1260Vendor Data
ReviewNormalC00987_5D_enggPR-MM-1220ManufacturingNormal*
C00987_7D_procFF[21]
PR-MM-1580Vendor Data
ReviewNormalC00987_5D_enggPR-MM-1540ManufacturingNormal*
C00987_7D_procFF[32]
PR-MM-1810Delivery & ClearanceNormalC00987_7D_procCN-TS-2010Jack-up
Barge Set-up, Operation isolation, spading, depressurization
etc.NormalC00987_7D_ConstFS[1]
PR-MM-1550Vendor Data
ReviewNormalC00987_5D_enggPR-MM-1510ManufacturingNormal*
C00987_7D_procFF[32]
PR-MM-1860Delivery &
ClearanceNormalC00987_7D_procCN-TS-2520Electrical and
instrumentation worksNormalC00987_7D_ConstFS[13]
PR-MM-1860Delivery & ClearanceNormalC00987_7D_procCN-TS-2010Jack-up
Barge Set-up, Operation isolation, spading, depressurization
etc.NormalC00987_7D_ConstFS[1]
PR-MM-1660OEM Activities / Preparation of DocumentsNormal*
C00987_7D_procDE-IC-7780Prepare & Issue for
ReviewNormalC00987_5D_enggSS[30]
PR-MM-1660OEM Activities / Preparation of DocumentsNormal*
C00987_7D_procDE-GN-1260Prepare & Issue for
ReviewNormalC00987_5D_enggSS[21]
PR-MM-1760Delivery & ClearanceNormalC00987_7D_procCN-TS-2010Jack-up
Barge Set-up, Operation isolation, spading, depressurization
etc.NormalC00987_7D_ConstFS[1]
PR-MM-1560Vendor Data
ReviewNormalC00987_5D_enggPR-MM-1500ManufacturingNormal*
C00987_7D_procFF[21]
PR-MM-1400Vendor Data
ReviewNormalC00987_5D_enggPR-MM-1300ManufacturingNormal*
C00987_7D_procFF[53]
PR-MM-1130Vendor Data
ReviewNormalC00987_5D_enggPR-MM-1090ManufacturingNormal*
C00987_7D_procFF[32]
PR-MM-1830Delivery &
ClearanceNormalC00987_7D_procCN-PF-1010Pre-Fabrication of Riser with
SpoolsNormal* C00987_6D_const[no-holidays]FF[40]
PR-MM-1710Vendor Data
ReviewNormalC00987_5D_enggPR-MM-1670ManufacturingNormal*
C00987_7D_procFF[21]
PR-MM-14603LPP and Concrete Coating of Line Pipe and Induction
BendsNormal* C00987_6D_const[no-holidays]CN-PF-1240Loadout &
Transportation of the Pipeline Materials for ZW-100 to
WSPNormalC00987_7D_ConstSS[69]
PR-MM-14603LPP and Concrete Coating of Line Pipe and Induction
BendsNormalC00987_6D_const[no-holidays]CN-PL-3170Mobilization of
LaybargeNormalC00987_7D_ConstFS[1]
PR-MM-14603LPP and Concrete Coating of Line Pipe and Induction
BendsNormal* C00987_6D_const[no-holidays]CN-PL-3170Mobilization of
LaybargeNormalC00987_7D_ConstSS[51]
PR-MM-1010PO AcceptanceFinish
milestoneC00987_5D_enggPR-MM-1030ManufacturingNormal*
C00987_7D_procFF[41]
PR-MM-1040Vendor Data
ReviewNormalC00987_5D_enggPR-MM-1020ManufacturingNormal*
C00987_7D_procFF[32]
MS-1380RFSU for All Facilities CompleteFinish
milestoneC00987_7D_ConstAS-GN-1300As-bulit
PackageNormalC00987_5D_enggFS[1]
MS-1360ESD Valve DeliveredFinish
milestoneC00987_5D_enggCN-TS-2510Piping Modification Works,
Valve/Equipment InstallationNormal* C00987_7D_ConstFF[12]
MS-1360ESD Valve DeliveredFinish
milestoneC00987_5D_enggCN-TS-2010Jack-up Barge Set-up, Operation
isolation, spading, depressurization etc.NormalC00987_7D_ConstFS[1]
DE-ST-9490Intermediate
MTONormalC00987_5D_enggCN-PF-1000Pre-Fabrication of Structural Steel
Works, Piping Spools for Offshore
HookupNormalC00987_6D_const[no-holidays]FS[32]
DE-PI-3580Issued for PurchaseNormalC00987_5D_enggCN-PF-1140Valve and
Equipment Installation before
LoadoutNormalC00987_6D_const[no-holidays]FS[2]
DE-IC-7800Issued for
ConstructionNormalC00987_5D_enggCN-TS-2010Jack-up Barge Set-up,
Operation isolation, spading, depressurization
etc.NormalC00987_7D_ConstFS[1]
MS-2570Overall RFSU Duration (From Award date until last
RFSU)HammockC00987_7D_ConstAS-GN-1300As-bulit
PackageNormalC00987_5D_enggFS[1]

Links to / from summary tasks


Many people prefer not to put predecessors or successors against summary
tasks, because other project management tools (such as Primavera P6) do
not support them. Consider removing logic on a summary task, by using a
milestone to represent the start or finish of all the tasks in the summary
heading, and putting the link on the milestone instead of the summary
task.
None found.
Duration uncertainty distribution shape
Tasks identified where: Maximum - Most Likely duration divided by the Most
Likely - Minimum duration is greater than 2. The validation is only
applied to the following distributions:
Triangle
Trigen
BetaPert
The check also tells you whether the numbers entered for Min, Most Likely
and Max create a valid distribution.
A task's duration can have a "skewed" three-point estimate, which means it
is not symmetrical. Usually three-point estimates are skewed on the
"pessimistic" side, where the maximum is further away from the most likely
than the minimum. The ratio of (Maximum - Most Likely) to (Most Likely -
Minimum) is used to measure this skew. When the skew is significant (for
example minimum = 1, most likely = 10, maximum = 100), this may be an
indication that there are low-probability events that cause this
pessimism. Consider using the risk register to represent these risks
events, and reduce the amount of skew on the task's uncertainty.
None found.