Sie sind auf Seite 1von 1

CARBON PORTFOLIO - PERU 2010

Energy, Industry and Others

LA JOYA Hydroelectric Power Plant H9


Description: is a new hydropower project connected to the grid with 14.96 MW of installed capacity and will produce an average generation of 88.53
GWh. The project will be located in the department of Arequipa.

Current Status: Projects Benefits:


Earliest project start date: November 2006. Number of direct and indirect jobs generated:
Operation start date: October 2009. The project would create 250 new jobs during construction and 20
Project lifetime: 40 years. during the operation of the hydropower plant.
Current Status: Environmental Impact Assessment approved. Energy Sustainable development contribution:
and Water concessions were given. Letter of DNA approval was obtai- It improves the water quality for irrigation.
ned. Registered at the Executive Board. It will assist the education of children and young people of the project
site. It helps the commerce balance of hydrocarbons through the re-
Estimated Annual Emission Reductions (tCO2/year): duction of oil importation.
An average of 41,987 tCO2-equivalent per year. It enlarges agrarian land frontier in 3,000 Ha.
CER´s negotiation:
Project Participant and Financing Closed
Total project cost: US$ 17,556,552

Contact Information:
Sources of finance to be sought or already identified:
Name: Javier Lei Siucho
Equity: 70 % Company: Generadora de Energía del Perú S.A.
Debt: 30 % Title: General Manager
Phone: (51-1) 3650876/ 3659772
E-mail: jlei@gepsaperu.com.pe

El PLATANAL Hydropower Plant H10


Description: El Platanal is a new hydroelectric project with 220 MW of installed capacity; producing an average generation of 1,063 GWh that con-
nects to the national grid. It is located in the provinces of Cañete and Yauyos, in the department of Lima.
Current Status: Projects Benefits:
Earliest project start date: January 2006. Number of direct and indirect jobs generated: In the construction pe-
Operation start date: February 2010. riod the project generated 1,200 jobs and in the operation period will
Project lifetime: 40 years. permanently generate 150 jobs between direct and indirect labor.
Current Status: Registered at the EB in September 2009. Sustainable development contribution: It increases the under-supplied
In February 2010, the project obtained the Letter of Approval from national power generation, allowing Peru’s industrial development. It
the Environmental Ministry of Spain (DNA) that confirms the project promotes and implements sustainable agricultural and aquacultural
compliance with the guidelines for dam building of WCD in accordance projects and practices in the area. It also encourages and supports local
with the validation report. education as well as technical training opportunities. During the ope-
ration period it is estimated that the hydroelectric plant will inject an
Estimated Annual Emission Reductions (tCO2/year): estimated yearly amount of $US 2 million in social development, taxes
An average of 501,814 tCO2-equivalents per year. and canon to the Project’s area of influence.
CER´s negotiation: Open.
Project Participant and Financing
Total project cost: US$ 350,000,000 Contact Information:
Name: Pedro Lerner Rizo Patrón/ Ximena Gubbins
Sources of finance to be sought or already identified: Company: Compañía Eléctrica El Platanal S.A. - CELEPSA
Equity: NA. Title: General Manager / Administrative Manager
Debt: NA. Phone Number: (51-1) 6192800
E-mail: plerner@celepsa.com / xgubbins@celepsa.com

www.fonamperu.org

National Environmental Fund - Peru

Das könnte Ihnen auch gefallen