CARBON PORTFOLIO - PERU 2010

Energy, Industry and Others

PORTILLO GRANDE landfill Gas Recovery Project WM1

Description: The project consists of the installation of a methane collection and flare system, to be placed in the cells of Portillo Grande landfill. Por-
tillo Grande landfill has an area of 307 hectares that currently receive 30% of the Municipal Solid Waste (MSW) of Lima around 1,500 tones per day.
It will be developed by Metropolitan Municipality of Lima.
Current Status: Projects Benefits:
Earliest project start date: 2009. Number of direct and indirect jobs generated:
Operation start date: 2011. It generates 10 new jobs.
Project lifetime: 30 years. Sustainable development contribution:
Current Status: Identification and pre-selection phase. Letter of Appro- It will decrease the pollution at local and global level, which would not
val of DNA is in process. The municipality of Lima is evaluating how to happen in absence of the project.
develop the projects and is taking conversations with several carbon It will allow attending the demand of the municipalities with minor re-
buyers in order to find the best deal. sources, which up to the date deposit their residues in the public via or
in clandestine places.
Estimated Annual Emission Reductions (tCO2/year): It will improve the wellbeing of some of the poorest areas of the city.
An average of 151,646 tCO2-equivalent per year.
CER´s negotiation: Open.
Project Participant and Financing
Total project cost: US$ 1,600,000
Contact Information:
Name: Juan Blest
Sources of finance to be sought or already identified: Company: Municipality of Lima
Equity: NA. Title: President of CDM Steering Committee
Debt: NA . Phone: (51-1) 3151300
E-mail: jblest@munlima.gob.pe

EL ZAPALLAL Landfill Gas Recovery Project WM2

Description: The project consists of the installation of a methane collection and flare system, to be placed in the cells of El Zapallal landfill. Portillo
Grande landfill has an area of 350, currently 40 hectares has been used to waste disposal. It will be developed by Metropolitan Municipality of Lima.

Current Status: Projects Benefits:


Earliest project start date: 2009. Number of direct and indirect jobs generated:
Operation start date: 2011. It generates 10 new jobs.
Project lifetime: 30 years. Sustainable development contribution:
Current Status: Identification and pre-selection phase. The municipality It will decrease the pollution at local and global level, which would not
of Lima is evaluating how to develop the projects and is taking conver- happen in absence of the project.
sations with several carbon buyers in order to find the best deal. It will allow attending the demand of the municipalities with minor re-
sources, which up to the date deposit their residues in the public via or
Estimated Annual Emission Reductions (tCO2/year): in clandestine places.
An average of 54,213 tCO2-equivalent per year. It will improve the wellbeing of some of the poorest areas of the city.

CER´s negotiation:
Project Participant and Financing Open.
Total project cost: US$ 1,600,000

Contact Information:
Sources of finance to be sought or already identified:
Name: Juan Blest
Equity: NA Company: Municipality of Lima
Debt: NA Title: President of CDM Steering Committee
Phone: (51-1) 3151300