EELO UNIVERSITY

Storage Design

Estimation of storage in Jail Design (14.4m x 10.6 m)

 
storage  
Ite Description of works Un Spec. QTY Unit Total Cost
m it Cost
N0
.
1 Substructure work
1. Allow for clearing the M2 15*11 165 0.50 82.50
1 site from any debris,
trees, roots etc, filling
hollows and leveling.
1. Excavation of found M3 57.1*0.4*0.6 13.704 7.00 95.93
2 trench 0.4m x 0.6m
depth.
1. Mass concrete in 50 mm M3 57.1*0.4*0.05 1.142 70.00 79.94
3 thick blinding layer
(1:4:8 mix) under the
foundation wall.
1. Rubble stone foundation M3 57.1*0.4*0.8 18.272 45.00 822.24
4 wall in cement & sand
mortar 1:4 ( 0.8 m x
0.4m wide) min. 20cm
above ground level.
1. R.C (1:2:4 mix) in ground M3 57.1*0.4*0.15 3.426 300.00 1027.80
5 beam (0.4m x0.15m ),
with 4N0. Y12 re-bars &
R6 links @ 300 mm c/c.
1. 15cm thick murram or M3 ((14.4*10.6)- 19.47 10.00 194.70
6 other approved backfill (57.1*0.4))*0.15
material, well
compacted and leveled.
1. 15 cm thick stone M3 ((14.4*10.6)- 19.47 12.00 233.64
7 hardcore filling well (57.1*0.4))*0.15
compacted and leveled.
A  SUB-TOTAL A $
2,536.75
2 Superstructure works including conc. floor slab
2. Mass concrete (1:3:6 M3 ((14.4*10.6)- 12.98 70 908.60
1 mix ) in conc. floor slab (57.1*0.4))*0.1
10cm thick.
2. 20cm thick cement M2 42.1*3.1 130.51 15 1957.65
2 block walling laid in
cement & sand mortar
1:4 mix ( rate to include
making of blocks)
2. R.C (1:2:4 mix) in lintel M3 42.1*0.2*0.15 1.263 280 353.64
3 beam(0.2m*0.15m)
with 4N0. Y12 re-bars &
R6 links @ 250 mm c/c.
2. R.C (1:2:3 mix) in slab m3 ((14.4*10.6)*0.3*2 91.584 300 27475.20
4 concrete 0.3 mm with
5NO. Y12 re-bars & R10
upper @ 300mm c/c
B SUB-TOTAL A $
30,695.09
3 Superstructure works including conc. floor slab +1
3. 20cm thick cement M2 42.1*3.1 130.51 15 1957.65
1 block walling laid in
cement & sand mortar
1:4 mix ( rate to include
making of blocks)
3. R.C (1:2:4 mix) in lintel M3 42.1*0.3*0.15 1.8945 280 530.46
2 beam(0.2m*0.15m)
with 4N0. Y12 re-bars &
R6 links @ 250 mm c/c.
3. R.C (1:2:3 mix) in slab m3 ((14.4*10.6)*0.3 45.792 300 13737.60
3 concrete 0.3 mm with
5NO. Y12 re-bars & R10
upper @ 300mm c/c
C SUB-TOTAL A $
16,225.71
4 Plastering and other finishing and G+1
4. External & internal M2 (42.1*3.1)*2*2 522.04 7.00 3654.28
1 plastering, 25 mm thick,
cement / sand mix 1:5,
with wood float finish.
4. Apply two coats white M2 (42.1*3.1)*2*2 522.04 5.00 2610.20
2 wash and distemper
paint to the ceiling and
plastered wall surface.
4. Laying floor tiles with M2 42.1*2 84.2 8.00 673.60
3 cement screed 1:2
cement/sand floor
screed including 100mm
skirting.
D  SUB-TOTAL D $
6,938.08
5 Doors & Windows
5. Supply and fix metal No Number 3 150 450.00
1 doors (2m x 2.1m) .
complete with frame,
hinges & locks and to
include two coats of
gloss paint.
5. Supply and fix wooden No Number 1 180 180.00
2 imported doors .
(1x2.1m) complete with
frame, hinges & locks
and to include two coats
of gloss paint.
5. Supply and fix Allumium No 6 50 300.00
3 windows (1.5 x 1.5) .
complete with burglar
bars, hinges, locks and
to include two coats of
paint. Number
E  SUB-TOTAL E $
930.00
6 Concrete design
6. Footing Size (0.8m x No Number 6 350 2100.00
1 0.8m) with 2NO: Y12 in .
@400
  Beam size(0.45x0.25)   Number 15 350 5250.00
with 4NO: Y12 in R8
6. Column size (0.3 x 0.3) No Number 15 350 5250.00
2 with 4NO: Y12 in R8 .
@200
6. Staircase size (3mx4.8m) No Number 1 1280 1280.00
3 with 5NO: Y10 R6 @150 .
F  SUB-TOTAL E $
13,880.00
7 Roof work
7. Roof with timber trusses M2 14.4 14.4 30 432.00
1 covered with N0. 30 GCI
sheets with two coats
anti- rust paint
7. 20cm thick cement M2 57.1*1 57.1 15 856.50
2 block walling laid in
cement & sand mortar
1:4 mix ( rate to include
making of blocks)
G  SUB-TOTAL E $
1,288.50
8 Provisional Items (includes materials & labour )
8. Electrical and water LS LS 1 300 300.00
1 installation works
H SUB-TOTAL F $
300.00
 
  GRAND TOTAL = (A+B+C+D+E+F+G+H) $
72,794.13