Beruflich Dokumente
Kultur Dokumente
c. Caps on/limitation of liability A commonly held misconception is that loss of profit will always
be an indirect or consequential loss. On the contrary, English courts
Obviously, there are rules applicable to types of loss and/or
can and have held that loss of profits can be a direct loss. Limiting
damage that are recoverable under or in connection with a contract
liability by reference to indirect or consequential loss alone is,
(e.g. in the law of tort), including consideration of issues such as
therefore, risky (at best) and it is recommended that when seeking to
remoteness, causation and foreseeability. All that is outside the
limit liability for any type of financial loss, that these are specifically
scope of this note, but assuming there is a liability, the use of
considered and excluded rather than by using generic terms.
clauses which attempt to cap/limit liability are fairly common in
England and Wales and are, generally speaking, enforceable. Successfully excluding indirect and consequential loss, whilst not
uncommon in process and engineering contracts, is a task that
Indeed, many of the standard forms of contract include caps on
requires special thought and consideration before putting words
liability for contractors/professionals. Depending on the nature
down on paper.
of the construction or engineering project, they may, for example,
relate to: Negligence
• Caps on liquidated damages for delay – whether per section or When considering clauses purporting to exclude or limit liability
for the whole of the works – which may be linked to termination for negligence, the court’s general starting position is that as it is
rights “inherently improbable” that one party would want to allow the
other party to exclude his liability for negligence.
• Caps on liquidated damage for failure to achieve certain KPI’s or
deliverables – which may be linked to termination rights However, even if wording specifically pertaining to negligence is
not included in the contract, the courts have still held that some
• Overall caps on general damages
phrases may be interpreted widely enough so as to allow liability
• Caps arising on a termination scenario for negligence to be excluded. The cases turn on the wording on
It is less common to see caps in favour of the Employer on the basis the relevant contracts. If it is the intention of the parties to exclude
that there is typically a Contract Sum and more limited grounds for liability for negligence, it is advised to expressly do so. Uncertainty
loss and expense/compensation event type claims. That said, it is is not a desirable state of affairs for negotiating parties particularly
not uncommon in more sophisticated contracts to cap the Employer’s given the importance of the issue.
liability in relation to termination for convenience or Employer A note for those reading from other jurisdictions, unlike numerous civil
default scenarios, particularly where there is a funding element to law jurisdictions, gross negligence is not generally recognised as a
the overall transaction. separate legal concept from “ordinary” negligence in English law.
e. Use of indemnities g. Statutory restrictions
Indemnity provisions are fairly common in construction and UCTA
engineering contracts and typical examples relate to damage to
Exclusion or limitation of liability clauses, which can take on various
property or intellectual property infringement but may also cover
forms, have been the subject of various legislative interventions.
interference with other party rights.
UCTA regulates the extent to which business-to-business contracts
Readers should note that the use of the term “indemnity” or can exempt liability where one party has contracted on the other’s
“indemnify” can give rise to different limitation periods and despite standard terms of business. In such a situation, an exclusion or
what may be perceived to be a common understanding, may not limitation clause will only apply to the extent that such a clause is
actually result in all losses (however remote) being recoverable reasonable.
on a “pound for pound” basis and may also not avoid the so called
The reasonableness test is set out at s.11(1) of UCTA:
“duty to mitigate” losses. As with all things, precision of drafting is
crucial. “In relation to a contract term, the requirement of reasonableness
for the purposes of this Part of this Act, is that the term shall have
As well as indemnifying for breach, an indemnity clause may
been a fair and reasonable one to be included having regard to the
constitute a promise by one party to bear the financial risk or pay
circumstances which were, or ought reasonably to have been, known
an amount to the other in respect of an event occurring. In such
to or in the contemplation of the parties when the contract was
circumstances, no breach of contract is required.
made.”
Indemnities can also be capped (or carved out of caps), so it is
Further guidance in respect of reasonableness is provided for by five
recommended that this is considered on a contract-by-contract basis,
guidelines laid down in UCTA:
alongside the extent of any insurance coverage and who should
bear, for example, responsibility for any shortfall or underinsurance a. The strength of the bargaining positions of the parties relative to
or failure to notify claims. each other, taking account (among other things) alternative means
by which the customer’s requirements could have been met –
f. Use of time bar provisions/conditions supplemented material
precedent b. Whether the customer received an inducement to agree to the
Notice provisions as a condition precedent to successful claims term, or in accepting it had an opportunity of entering into a
are fairly common in construction and engineering contracts in similar contract with other persons, but without having to accept
the UK or applying English law. For example, the FIDIC imposes an a similar term
obligation on a contractor to submit a notice within 28 days and the c. Whether the customer knew or ought reasonably to have known
NEC requirement is for a compensation event to be notified within of the existence and extent of the term (having regard, among
eight weeks. Many standard form contracts expressly state what the other things, to any custom of the trade and any course of dealing
consequences will be for failure to notify within the stipulated time, between the parties)
e.g. that the contractor will not be entitled to an extension of time or
loss and expense or cost. Some standard forms are not quite so well d. Where the term excludes or restricts any relevant liability if some
defined. In the UK, clearly drafted time-bar provisions are generally condition is not complied with, whether it was reasonable at the
enforced. time of the contract to expect that compliance with that condition
would be practicable – supplemented material
That said, there are, however, tales of caution with standard forms
and bespoke clauses alike since the triggers for commencement of e. Whether the goods were manufactured, processed or adapted to
the relevant timescale are often not always clear. They may link to the special order of the customer
subjective knowledge of the contractor (which may be difficult to The time for determining the reasonableness of the term is the
prove), they may be linked to what a reasonable contractor should time at which the agreement was made. This is to ensure that the
have been aware of at the time (again difficult to prove) and they reasonableness of a clause is not decided by virtue of the damage
may allow more than “one bite of the cherry” since an event may not caused.
actually cause delay or disruption until a later date, particularly if
There is a wealth of case law providing illustration of the above
there are mitigation steps or other events or circumstances occurring
principles but these are based on the specific circumstances and the
at the same time or if the event is continuing. A clause may not,
particular contract in question.
therefore, have the effect intended. Some contracts also include
“look-ahead” provisions with the use of warning notices and risk
registers and reflect entitlement based on when a notice should
have been given. As with all contracts, precision is required.
For those serving notices, they should check the notice provisions in
the contract carefully – including the method of service and date of
deemed delivery as these are often overlooked in practice and may
create a barrier to recovery.
Take away points
• Managing potential liabilities should be a key
consideration for all businesses and should be considered
as part of the risk profile when considered contracts.
• There are a number of possible ways to manage and
control risk in a contract governed by English law.
• Contracts need to be precise in order to manage and
control such risks.
• Using shorthand terms such as “consequential loss” to
seek to avoid or exclude liability for loss of profit, revenue
and the like should be avoided.
• Contracts in the UK depend not just on what is written
in the contract, but also on an understanding of rules of
interpretation, the relevant case law and understanding of
statutory implied terms. These are all fluctuating.
• As always, parties should take particular care to ensure
they understand the impact of having contracts which
involve parties from different jurisdictions or where the
location of the project or services/works performed are in
a different country as this may have a significant impact
on the contract/risks regardless of the choice of governing
law.
Contact
Ray O’Connor
Partner, London
T +44 207 655 1422
E ray.oconnor@squirepb.com
The contents of this update are not intended to serve as legal advice related to individual situations or as legal opinions
concerning such situations, nor should they be considered a substitute for taking legal advice.
26515/03/17