Beruflich Dokumente
Kultur Dokumente
Prepared by
For
Masters Students offering Project and Organizational Change Management Course Unit
February 2010
1
Page
In their board meeting, which sat end of January 2010, the Makerere University new management
resolved to develop a centralized main Data Center (DC) for Makerere University. Securing for a
piece of land in the university to build this facility is part of the scope of this project. A redundant
data center (RDC) was approved to be installed in the existing FCIT’s new building, which must also
be developed to the same standard as the main data center and should work in mirrored mode.
Several Business Support Systems (BSS) were also approved.
The management team unanimously appointed Abdul Nsubuga, PMP as the project consultant to
advise them on how to go about with this project. The consultant’s first assignment was to present
to management a Project Management Plan within 2 Month. Based on the consultant’s experience
he decided to use Delphi technique to deliver as tasked. Subsequently, he assigned this task to you
and other project managers for action because of your previous knowledge exhibited in project
management.
1. Searching and approving for the land to take 30 days from the day the consultant was
assigned.
2. Architectural, structural and electro-mechanical design work is expected to take not more
than 30 days. Management review report of the designs is expected within 5 working days
to enable the architecture to implement the changes within 5 days. The final structural
designs and electro-mechanical design to be ready 10 days and 15 days respectively from
the day the final architectural work is completed. Two days are allowed for management to
approve/sign off the revised designs.
3. Submissions of all designs to local authorities have to be planned. Review and final approval
by KCC is expected to take 60 calendar days from the day of submission as per KCC
guidelines. However, provisional building certificate/permit can be acquired within 15 days
to enable civil works to resume. NEMA (Environmental Impact Assessment – EIA) certificate
is expected to be presented to KCC before a final building certificate is awarded. NEMA
certificate takes 10 days to process upon application; and provisional building permit is a
prerequisite.
4. The four floor building foundation completion is forecasted to be completed maximum 21
days. Completion of ground floor, which is also going to house the power transformer and
main Data Center (DC) should be completed 5 weeks after the foundation completion. First,
second and third floors to take the same time. Roofing of the building to take 15 days.
5. Commercial power application process takes 25 working days to be approved by Umeme.
Because a three phase high voltage connection is required, Umeme takes 10 days to extend
power to the nearest point to the building. Umeme’s scope of work excludes the supply
and installation of the required transformer; however it becomes Umeme’s infrastructure
after connecting it onto their grid. The transformer required is to be procured from South
Africa, management’s preferred supplier. Transformer manufacturing takes 12 days on
order; packaging and shipment by sea to Mombasa shall take 45 days FOB. Custom
2
clearance at Mombasa port takes 2 days while road transportation to URA’s warehouse
Page
takes maximum 3 days. Provided the manufacturer/ supplier had proper documentation
9. Networking and configuring of the two data centers shall take 10 working days and the data
Page
1. FCIT’s software innovation team was hired to design, develop and implement the system.
One month was allowed for them to collect user requirements and 2 days for management
to approve them.
2. The innovation team has committed to complete the system two weeks after
commissioning of the main DC. However the system requires 2 months of development
time, 5 days to train users on the test platform and 3 days to implement (including
configuring access rights) in the data center.
Assignment requirement.
In groups of not more than 5 students, study the given information and develop a detailed Project
Management Plan. All assumptions should be well stated.
NOTE: A project management plan is much more than a project schedule plan.
Document the roles played by each team members and % contribution on the assignment specified.
For example:
Team member Role % Contribution
Jane Project Leader 80%
Faridah Project Administrator 75%
John Analyst leader 10%
ETC
Submission of group members: 15 Feb; for any change of members, a formal change request must
be submitted to the consultant. No such changes shall be accepted after 15 March 2010.