SPConstruction SLAB DESIGNED 12/08/2021

Afghanistan Construction Engineering Group (ACEG)

Calculation of Dead Load for Internal Slab

2
Materials Unit γ Value Kg/m
Terrazzo Tile 2200.00 0.00
Gravel 1800.00 0.00
Isogam 0.01 1080.00 10.80
PCC 2400.00 0.00
Brant Brick 900.00 0.00
Mortar 0.03 2000.00 50.00
Plastic 8.00 0.00
Insulation 0.00
RCC 0.12 2500.00 300.00
Plaster 0.03 2000.00 50.00
Total DL: 410.80

Combination
Value Kg/m 2
1.4 DL = 575.12 1. Combination
1.2 DL + 1.6 LL = 652.96 2. Combination

One Way Slab Design

Input Data Output Result


Longer Shorter L/W Type of Slab
6.65 4.3 1.55 Two Way

Wu = 1430 Kg/m2 Length Span = 4.3 Coefficiant (L/S)


1/8
Calculation of Moment = Mcl2s Mid span moment = Positive moment

1/2*(E36)*(G40^2) = M = 1509.15 Ø = 0.9


Mu = M/Ø
Mu = 1676.84

Calculation of Bar

Fy = 2800 ρmin = 0.002


As = M/Fy*Z Asmin = ρmin (b*d)
Z = 0.9(d) Asmin = 2.4 Per Meter2 False
d = Depth 12
Z = 10.8 Asmin < As

As = 6.47

As = 6 Per Meter2 Ok Ø= 10 mm
asπd=2/4 = 0.79

Nos of Bars = As/as = 8


Spacing of Bars = 12 cm

Designed By: Mohammad Shoaib Perouz