Beruflich Dokumente
Kultur Dokumente
the loss of the cargo for its negligence in its duty Costs against the defendant.
SO ORDERED.”
as a common carrier. Dispositively, the decision
In time, Delsan appealed to the CA whereat its
reads:
“WHEREFORE, judgment is hereby rendered: recourse was docketed as CA-G.R. CV No. 40951.
In the herein challenged decision, the CA affirmed
3
1. A).In Civil Case No. 85-30559: the findings of the trial court. In so ruling, the CA
declared that Delsan failed to exercise the
1. (1)Ordering the defendant (petitioner Delsan) to extraordinary diligence of a good father of a
pay plaintiff (respondent AHAC) the sum of family in the handling of its cargo. Applying Article
P1,939,575.37 with interest thereon at the 1736 of the Civil Code, the CA ruled that since the
4
legal rate from November 21, 1984 until fully discharging of the diesel oil into Caltex bulk depot
paid and satisfied; and had not been completed at the time the losses
2. (2)Ordering defendant to pay plaintiff the sum of occurred, there was no reason to imply that there
P10,000.00 as and for attorney’s fees. For lack was actual delivery of the cargo to Caltex, the
of merit, the counterclaim is hereby dismissed.
consignee. We quote the fallo of the CA decision:
“WHEREFORE, premises considered, the appealed
1. B). In Civil Case No. 85-29357: Decision of the Regional Trial Court of Manila, Branch
09 in Civil Case Nos. 85-29357 and 85-30559 is hereby
1. (1)Ordering defendant to pay plaintiff the sum of AFFIRMED with a modification that attorney’s fees
P479,262.57 with interest thereon at the legal awarded in Civil Case Nos. 85-29357 and 85-30559 are
rate from February 6, 1985 until fully paid and hereby DELETED.
satisfied; SO ORDERED.”
Delsan is now before the Court raising
_______________
substantially the same issues proffered before the
Rollo, pp. 103-107.
2 CA.
608 Principally, Delsan insists that the CA
608 SUPREME COURT REPORTS ANNOTATED committed reversible error in ruling that Article
Delsan Transport Lines, Inc. vs. American Home Assurance 1734 of the Civil Code cannot
_______________
Corporation
Supra note 1.
3
4
Art. 1736. The extraordinary responsibility of the common
goods transported by them. They are presumed to
carrier lasts from the time the goods are unconditionally placed
in the possession of, and received by the carrier for
have been at fault or to have acted negligently if
transportation until the same are delivered, actually or the goods are lost, destroyed or deteriorated. To 6
backflow occurred when the diesel oil was already Prudential Guarantee And Assurance, Inc., G.R. No. 147246,
completely delivered to Caltex. August 19, 2003, 409 SCRA 340.
610
We are not persuaded.
In resolving this appeal, the Court reiterates the 610 SUPREME COURT REPORTS ANNOTATED
oft-stated doctrine that factual findings of the CA, Delsan Transport Lines, Inc. vs. American Home Assurance
affirmatory of those of the trial court, are binding Corporation
on the Court unless there is a clear showing that Art. 1734. Common carriers are responsible for the
such findings are tainted with arbitrariness, loss, destruction, or deterioration of the goods, unless
capriciousness or palpable error. 5
the same is due to any of the following causes only:
Delsan would have the Court absolve it from
1. 1)Flood storm, earthquake, lightning, or other
liability for the loss of its cargo on two
natural disaster or calamity;
grounds. First, the loss through spillage was partly 2. 2)Act of the public enemy in war, whether
due to the contributory negligence of Caltex; international or civil;
and Second, the loss through backflow should not 3. 3)Act or omission of the shipper or owner of the
be borne by Delsan because it was already goods;
delivered to Caltex’s shore tank. 4. 4)The character of the goods or defects in the
Common carriers are bound to observe packing or in the containers;
extraordinary diligence in the vigilance over the 5. 5)Order or act of competent public authority.
Both the trial court and the CA uniformly ruled VOL. 498, AUGUST 15, 2006 611
that Delsan failed to prove its claim that there was Delsan Transport Lines, Inc. vs. American Home Assurance
a contributory negligence on the part of the owner Corporation
of the goods—Caltex. We see no reason to depart vessel should have exerted utmost effort to
therefrom. As aptly pointed out by the CA, it had immediately inform the shore tender that the port
been established that the proximate cause of the bow mooring line was severed.
spillage and backflow of the diesel oil was due to To be sure, Delsan, as the owner of the vessel,
the severance of the port bow mooring line of the was obliged to prove that the loss was caused by
vessel and the failure of the shore tender to close one of the excepted causes if it were to seek
the storage tank gate valve even as a check on exemption from responsibility. Unfortunately, it
7
the drain cock showed that there was still a miserably failed to discharge this burden by the
product on the pipeline. To the two courts below, required quantum of proof.
the actuation of the gauger and the escort Delsan’s argument that it should not be held
surveyor, both personnel from the Caltex Bulk liable for the loss of diesel oil due to backflow
Depot, negates the allegation that Caltex was because the same had already been actually and
remiss in its duties. As we see it, the crew of the legally delivered to Caltex at the time it entered
vessel should have promptly informed the shore the shore tank holds no water. It had been settled
tender that the port mooring line was cut off. that the subject cargo was still in the custody of
However, Delsan did not do so on the lame excuse Delsan because the discharging thereof has not
that there was no available banca. As it is, yet been finished when the backflow occurred.
Delsan’s personnel signaled a “red light” which Since the discharging of the cargo into the depot
was not a sufficient warning because such signal has not yet been completed at the time of the
only meant that the pumping of diesel oil had spillage when the backflow occurred, there is no
been finished. Neither did the blowing of whistle reason to imply that there was actual delivery of
suffice considering the distance of more than 2 the cargo to the consignee. Delsan is straining the
kilometers between the vessel and the Caltex Bulk issue by insisting that when the diesel oil entered
Depot, aside from the fact that it was not the into the tank of Caltex on shore, there was legally,
agreed signal. Had the gauger and the escort at that moment, a complete delivery thereof to
surveyor from Caltex Bulk Depot not gone aboard Caltex. To be sure, the extraordinary responsibility
the vessel to make inquiries, the shore tender of common carrier lasts from the time the goods
would have not known what really happened. The are unconditionally placed in the possession of,
crew of the and received by, the carrier for transportation
611
until the same are delivered, actually or
constructively, by the carrier to the consignee, or obliged to prove that the damage to its cargo was
to a person who has the right to receive caused by one of the excepted causes if it were to
them. The discharging of oil products to Caltex
8
seek exemption from responsibility. Having failed
11
Bulk Depot has not yet been finished, Delsan still to do so, Delsan must bear the consequences.
has the duty to guard and to preserve the cargo. WHEREFORE, petition is DENIED and the
The carrier still has in it the responsibility to guard assailed decision of the CA is AFFIRMED in toto.
and preserve the goods, a duty incident to its Cost against petitioner.
having the goods transported. SO ORDERED.
To recapitulate, common carriers, from the Puno (Chairperson), Sandoval-Gutierrez, C
nature of their business and for reasons of public orona and Azcuna, JJ., concur.
policy, are bound to observe Petition denied, assailed decision affirmed in
_______________ toto.
Notes.—Upon the happening of the accident,
Martini Limited v. Macondray and Co., 39 Phil. 934 (1919).
7
——o0o——