UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (EXCAVATE TO REDUCED LEVEL) PAGE NO: 1/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
1.
Excavate to reduce level; 13m2 1 Excavator 1 Site Excavator 1 days
commencing from supervisor output =
formation level; cart 9.25m³
away, excess earth, 1 machine
deposit, spread and operator (13 m³/
levelled where directed 9.25m³)/8hour
within the site = 0.17 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (EXCAVATE PIT) PAGE NO: 2/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
2. Excavate pit starting from
reduced level including 15m3 1 Excavator 1 Site Excavator 1 days
backfilling with approved supervisor output = 37m3
excavated material,
compaction in layers and 1 machine (15m3/
disposal of surplus operator 37m3)/8hour =
excavated material where 0.50 days
directed within the site.
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (EXCAVATE TRENCH) PAGE NO: 3/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
3. Excavate trench starting
from reduced level; 12m3 1 Excavator 1 Site Excavator 1 days
including backfill with supervisor output =
approved excavated 9.25m³
material, compaction in 1 machine
layers and disposal of operator (12 m³/
surplus excavated 9.25m³)/8hour
material where directed = 0.16 days
within the site.
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF(HARDCORE 150mm) PAGE NO: 4/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
4. 150mm Thick bed
hardcore as described 26m2 1 compacter 1 Site Compacter 1 days
spread, levelled and supervisor output = 15m³
compacted to receive
concrete slab. 1 machine (26 m³/
operator 15m³)/8hour =
0.22 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (HARDCORE 100mm) PAGE NO: 5/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
5. 100mm to receive apron
slab 76m2 1 compacter 1 Site Compacter 1 days
supervisor output = 15m³

1 machine (76 m³/


operator 15m³)/8hour =
0.63 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (LEAN CONCRETE) PAGE NO: 6/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
6. Lean Concrete (Grade
15) as specified; as 13m2 1 Mixer 1 Skill labour Mixer output = 1 day
blinding screed laid on 2.25m²/h
earth or hardcore 50mm 4 General
thick under Pile cap. labour (13 m²/
2.25m²)/ 8hour
= 0.72 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (LEAN CONCRETE) PAGE NO: 8/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
8. Lean Concrete (Grade
15) as specified; as 26m2 1 Mixer 1 Skill labor Mixer output = 2 days
blinding screed laid on 2.25m²/h
earth or hardcore 50mm 4 General
thick under ground beam. labor (26 m²/
2.25m²)/ 8hour
= 1.44 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (LEAN CONCRETE) PAGE NO: 9/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
9. Lean Concrete (Grade
15) as specified; as 237m2 1 Mixer 1 Skill labor Mixer output = 14 days
blinding screed laid on 2.25m²/h
earth or hardcore 50mm 4 General
thick under ground floor labor (237 m²/
slab. 2.25m²)/ 8hour
= 13.16 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (LEAN CONCRETE) PAGE NO: 10/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
10. Lean Concrete (Grade
15) as specified; as 76m2 1 Mixer 1 Skill labor Mixer output = 5 days
blinding screed laid on 2.25m²/h
earth or hardcore 50mm 4 General
thick under apron slab. labor (76 m²/
2.25m²)/ 8hour
= 4.22 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (REINFORCED CONC G30) PAGE NO11/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
11. Reinforced Concrete
(Grade 30) as specified 6m3 1 Mixer 1 Skill labour Mixer output = 1 day
in pile caps. 2.25m²/h
2 General
labour (6 m²/ 2.25m²)/
8hour

= 0.33 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (REINFORCED CONC G30) PAGE NO: 12/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
12. Reinforced Concrete
(Grade 30) as specified 1m3 1 Mixer 1 Skill labour Mixer output = 1 day
in column stump. 2.25m²/h
2 General
labour (1 m²/ 2.25m²)/
8hour

= 0.05 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (REINFORCED CONC G30) PAGE NO: 13/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
13. Reinforced Concrete
(Grade 30) as specified 185m2 1 Mixer 1 Skill labour Mixer output = 11 days
in ground beams. 2.25m²/h
2 General
labour (185 m²/
2.25m²)/ 8hour

= 10.27 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (REINFORCED CONC G30) PAGE NO: 14/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
14. Reinforced Concrete
(Grade 30) as specified 237m2 1 Mixer 1 Skill labour Mixer output = 14 days
in floor slab. 2.25m²/h
2 General
labour (237 m²/
2.25m²)/ 8hour

= 13.17 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (REINFORCED CONC G30) PAGE NO: 15 /27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
15. Reinforced Concrete
(Grade 30) as specified 76m2 1 Mixer 1 Skill labour Mixer output = 5 days
in apron slab. 2.25m²/h
2 General
labour (78 m²/
2.25m²)/ 8hour

= 4.33 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (FORMWORK) PAGE NO: 16/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
16. Formwork to sides of pile
caps. 51m2 4 hammers 1 Carpenter Workers 1 day
output = 1.5
4 General m²/h
labor
1.5m² x 5 =
7.5m²

(51 m²/
7.5m²)/8hour =
0.85 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (FORMWORK) PAGE NO: 17/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT


TOOL LABOUR
17. Formwork to sides of
column stump. 151m2 2 hammers 1 Carpenter Workers
output = 0.67
2 General m²
labor
0.67m² x 3 =
2.01m²

(151 m²/
2.01m²)/8hour
= 9.39 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (FORMWORK) PAGE NO: 18/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
18. Formwork to sides of
ground beam. 185m2 1 hammer 1 Carpenter Workers 8 days
output = 1.5
1 General m²
labour
1.5m² x 2 =
3m²

(185 m²/
3m²)/8hour =
7.71 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (FORMWORK) PAGE NO: 19/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
19. Formwork to sides of
edge of apron slab 83m 1 hammer 1 Carpenter Workers 4 days
100mm thick output = 1.5
1 General m²
labour
1.5m² x 2 =
3m²

(83 m²/
3m²)/8hour =
3.45 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (HIGH TENSILE ROD) PAGE NO: 20/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
20. High tensile/Mild steel
rod reinforcement in pile 768kg Bar bender 1 bar bender workers output 4 days
caps. machine = 0.04kg/h
3 generals
labor (768 kg x
0.04kg)/ 8hour
= 3.84 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (HIGH TENSILE ROD) PAGE NO: 21/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
21. High tensile/Mild steel
rod reinforcement in 250kg Bar bender workers output 2 days
column stump. machine 1 bar bender = 0.04kg/h

2 generals (250 kg x
labor 0.04kg)/ 8hour
= 1.25 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (HIGH TENSILE ROD) PAGE NO: /27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
22. High tensile/Mild steel
rod reinforcement in 1896kg Bar bender 1 bar bender workers output 10 days
ground beam. machine = 0.04kg/h
2 generals
labor (1896 kg x
0.04kg)/ 8hour
= 9.48 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (HIGH TENSILE ROD) PAGE NO: 23/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
23. High tensile/Mild steel
rod reinforcement in floor 3240kg Bar bender 1 bar bender Workers 17 days
slab and apron slab. machine output =
2 generals 0.04kg/h
labor
(3240 kg x
0.04kg)/ 8hour
= 16.2 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (DPM) PAGE NO: 24/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
24. A layer of 0.125mm
heavy duty polythene 237m2 1 Site Labor output = 3 days
sheet as described laid supervisor 4 m²
below concrete bed
2 General 4m² x 3 =
labor 12m²

(237m²/
12m²)/8hour =
2.46 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (ANTI-TERMITE TREATMENT) PAGE NO:25 /27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
25. Supply and apply anti-
termite treatment to 237m2 Anti-termite 1 Site Labor output = 4 days
ground floor area with 5 spray supervisor 4 m²
years warranty all as per
S.O approval. 1 General 4m² x 2 = 8m²
labor
(237m²/
8m²)/8hour =
3.70 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (MS GRATING) PAGE NO: 25/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
25. Supply and install Mild
steel grating to engineer 81m Welder 1 Site Welder output 5 days
details as per drawing supervisor = 2.5 m²

2 General (81m²/
labor 2.5m²)/8hour =
4.05 days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (RAMP) PAGE NO: 26/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
26. To construct and
complete reinforced 2 nos’ Labor output = 6 days
concrete 1500mm x 1 Site 2.50m²
1000mm ramp with supervisor
concrete grade 30, fabric 2.50m² x 2 =
reinforcement, formwork, 1 General 5m²
pebble wash and labor
including all necessary (237m²/
accessories and work all 5m²)/8hour =
as per Architect's 5.93 days
drawings and approval.
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI, SERI ISKANDAR, PERAK.
PREPARED BY: SHARIFAH NUR ATIQAH DATE: 08/11/2019
ELEMENT: WBLFF (PERIMETER DRAIN) PAGE NO: 27/27

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
27. 230mm diameter precast
concrete as specified half 81m Labor output = 2 days
round drain, finished fair 1 Site 2.00m²
or exposed surfaces, supervisor
bedded, jointed and 2.00m² x 3 =
pointed in cement mortar 2 General 6m²
(1:3) to engineer detail labor
including disposal of (81m²/
surplus excavated 6m²)/8hour =
material and all the entire 1.67 days
satisfaction of the S.O.