Activity ID Activity Name Original Start Finish Duration % Total 2 2019

Duration Complete Float Jan Feb Mar Apr May Jun Jul Aug Sep
TIA-200.1 Open West K3 Loading Dock per Plant Constraint & Owner to Approve PIR 14 04-Feb-19* 17-Feb-19 0% -61
SPS1220 Sawcut & Excavate for 18" STM-DI between Influent MH and Existing MH-16-7 2 19-Feb-19 20-Feb-19 0% -30
SPS1250 Install Stone Bedding and 18" STM-DI Piping 2 21-Feb-19 22-Feb-19 0% -30
SPS1260 Backfill and Compact 18" STM-DI Pipe Excavation 1 26-Feb-19 26-Feb-19 0% -30
SPS1280 Excavate & Demolish MH-16-7 3 27-Feb-19 05-Mar-19 0% -30
SPS1300 Install New MH-16-7 3 06-Mar-19 12-Mar-19 0% -30
SPS1440 Tie-In 18" S TM-DI to New MH-16-7 2 13-Mar-19 14-Mar-19 0% -30
TIA-200.2 Open East K3 Loading Dock per Plant Constraint & Owner to Approve PIR 0 15-Mar-19 15-Mar-19 0% -58
K1-1000 Install Super-Silt Fence at K1 PS Area 1 19-Mar-19 19-Mar-19 0% -30
K1-1020 Excavate for K1 Bypass Manhole 3 20-Mar-19 22-Mar-19 0% -30
K1-1030 Install Stone Subgrade at K1 Bypass Manhole 1 26-Mar-19 26-Mar-19 0% -30
K1-1040 Install K1 Bypass Manhole 2 27-Mar-19 28-Mar-19 0% -30
K1-1050 Excavate and Expose Existing Utilities 4 29-Mar-19 04-Apr-19 0% -30
K1-1060 Install 8" Bypass Forcemain 3 09-Apr-19 11-Apr-19 0% -30
K1-1070 Install K1 Bypass Pump and Floats 2 16-Apr-19 17-Apr-19 0% -30
K1-1080 Install Underground Bypass Piping 3 18-Apr-19 23-Apr-19 0% -30
K1-1190 Tie-In 8" GSN-Clay Pipe t o Bypass Manhole 1 24-Apr-19 24-Apr-19 0% -30
K1-1210 Tie-In 12" GSN-PVC P ipe to B ypas s Manhole 1 25-Apr-19 25-Apr-19 0% -30
K1-1220 Tie-In 4" GSN-CI Pipe t o Bypass Manhole 1 26-Apr-19 26-Apr-19 0% -30
K1-1240 Tie-In 8" GD-CI and 12" CI P ipe to B ypas s Manhole 1 30-Apr-19 30-Apr-19 0% -30
K1-1250 Demolish Existing K1 Pump Station Control Panel 2 01-May-19 02-May-19 0% -30
K1-1260 Demolilsh Pumps and Piping at K1 PS and Vault 2 07-May-19 08-May-19 0% -30
K1-1270 Demolish K1 PS and Vault Top S labs , Support s and Hatc h 3 09-May-19 15-May-19 0% -30
K1-1280 Powerwash and Flush K1 PS 1 16-May-19 16-May-19 0% -30
K1-1290 Perform Pre-Coating Concrete Inspection at K1 PS 0 17-May-19 17-May-19 0% -42
K1-1300 Perform Concrete Repair at K1 PS 2 21-May-19 22-May-19 0% -30
K1-1310 Grout and Cure Bottom of K1 PS and Vault 2 23-May-19 24-May-19 0% -44
K1-1330 Install Valve Vault Piping, Valves and Supports 3 28-May-19 30-May-19 0% -30
K1-1350 Install K1 PS Discharge Piping, Supports 2 31-May-19 04-Jun-19 0% -30
K1-1360 Install K1 PS Pumps and Instruments 1 05-Jun-19 05-Jun-19 0% -30
K1-1380 Pull & Term Wire for K1 PS Pumps and Floats 1 06-Jun-19 06-Jun-19 0% -30
11306-PO3 Pre-Operational Component Inspection - K1 PS Pumps 2 07-Jun-19 10-Jun-19 0% -43
11306-CI3 Component Inspection - K1 PS Pumps 2 11-Jun-19 12-Jun-19 0% -43
11306-FT3 Functional and Performance Testing - K1 PS Pumps 3 13-Jun-19 17-Jun-19 0% -43
K1-1440 Owner to Approve PIR - 8" GSN-Clay Pipe 1 18-Jun-19 18-Jun-19 0% -62
K1-1480 Tie-In 8" GSN-Clay Pipe t o K1 PS 1 18-Jun-19 19-Jun-19 0% -29
K1-1490 Tie-In 12" GSN-PVC P ipe to K 1 PS 1 19-Jun-19 20-Jun-19 0% -29
K1-1500 Tie-In 4" GSN-CI Pipe t o K1 PS 1 20-Jun-19 25-Jun-19 0% -29
K1-1510 Tie-In 8" GD-CI and 12" CI P ipe to K 1 PS 1 25-Jun-19 26-Jun-19 0% -29
K1-1520 Demolish Underground Bypass Piping and Backfill 2 26-Jun-19 28-Jun-19 0% -29
K1-1530 Perform Asphalt Repair near K1 PS 3 28-Jun-19 09-Jul-19 0% -29
K1-1540 Seed and Restore K1 PS Area 3 09-Jul-19 12-Jul-19 0% -29
AD4000 Substantial Completion 0 12-Jul-19* 0% -63
AD5000 Punchlist and Final Cleanup 45 13-Jul-19 26-Aug-19 0% -63
AD6000 Final Completion 0 26-Aug-19* 0% -63

Remaining Level of Effort Actual Work EQ - PCO-036 TIA TASK filter: Longest Path.
Actual Level of Effort Remaining Work Analysis (Mitigation) © Oracle Corporation