Q7) Derive an expression for base width of elementary profile of gravity dam for no tension condition when the
reservoir is full.
Q8) Derive an expression for base width of elementary profile of gravity dam for no sliding condition when the
reservoir is full.
Q9) A concrete gravity dam has the following features:
Top of dam – RL 200m
Top width @top – 6m
RL of bottom of dam – 116m
RL of tail water level – 122m
RL of full reservoir level – 196m
Upstream face is vertical. Downstream face is vertical upto RL 191m and thereafter downstream face slopes
2H:3V. Drainage holes are located 8m away from upstream face, unit weight of concrete 23.5 kN/m3. Calculate
maximum vertical stress at the toe and heel
Q10) Define gravity dam. Explain forces that act on a gravity dam
Q11) Explain step by step the analytical procedure to be adopted for analyzing the stability of gravity dams.
Q12) Discuss briefly forces acting on a gravity dam with the help of a neat sketch.
Q13) Explain the various modes of failure of gravity dam and mention their remedies.
UNIT-3: EARTHEN DAMS
Q1) Explain with neat sketches different types of earth dams.
Q2) What are the causes of failure of earth dams. Explain them along with relevant sketches.
Q3) Briefly explain the method of drawing a phreatic line for a homogeneous earthen dam section.
Q4) A flow net is plotted for a homogenous earthen dam of 22m and free board 2.0m. The results obtained are,
No. of potential drops – 10
No. of flow channels – 4
The dam has a horizontal filter of 30m length at the downstream end and the coefficient of permeability of the
dam material is 5 x 10-4 cm/sec. Calculate the discharge per m run of the dam.
Q5) What are the precautions to be taken to avoid failure of earthen dam during the design procedure.
Q6) In order to find the factor of safety of the downstream slope of 2:1 during steady seepage, the section of the earth
dam was drawn. A possible slip circular arc passing through the toe of the dam was drawn. The soil mass was
divided into nine slices, each of 5m width. The end ordinates of the slices are 2.5, 4.5, 6, 7, 7.5, 6 and 4.5m
respectively from toe towards upstream. Assuming all the slices are dry, find the factor of safety. Take
i) Dry weight of soil dam – 18 kN/m3
ii) Length of arc – 54m
iii) Cohesion of soil of dam – 24kN/m2
iv) Angle of internal friction of soil in dam - 25°.
Q7) Draw a section of an earth dam of 20m height indicating the various parts of the dam.
Q8) How would you proceed to determine the phreatic line through homogeneous earthen dams provided with
horizontal filter.
Q9) Explain the method of stability analysis of upstream slope during sudden drawdown by Swedish slip circle method.
PART – B – IRRIGATION DESIGN - DRAWING
Q1) Design a tank surplus weir for a major tank connected with tanks in series.
1. Field data
Combined catchment area of group of tanks -29.5km2
Intercepted catchment area – 22.8km2
General ground level at proposed site – 15.8m
Level at which good foundation soil is available – 14m
Slope at the proposed surplus works from its centerline reaches 14.8m in a distance of 10m
2. Construction details
Full tank level :17.5m
Max water level :18.3m
Tank bund level :19.5m
Top width of bund : 2.2m
Side slopes :2:1
3. Other details
Make provision to store water up to MWL. Proper abutments, wing walls and returns are to be designed.
Assume a hydraulic gradient of 1 in 5 and Ryves coefficient =9.
Draw to a suitable scale
1) Half plan at top and half plan at foundation
2) Half elevation and half sectional elevation
3) Cross section across the weir.
Q2) Design a canal drop (Notch type) for the following data
Particulars U/s canal D/s canal
Full supply discharge 10m3/s 10m3/s
Bed level +20.00 +18.00
Full supply level +21.50 +19.50
Bed width 8.0 8.0
Top level of embarkment +22.50 +20.50
Top width of embarkment 2.0m 2.0m
Side slopes 1:1(cut) 1.5:1(fill)
Average ground level 20.50 12.50
Hand soil available@ 18.50
Draw to a suitable scale
1) Half plan@top and half of foundation
2) Half elevation & half longitudinal section
3) Cross section along the canal
Q3) Design the details of a canal regulator with the following particulars
Particulars Upstream Downstream
Full supply discharge (FSQ)(m3/s) 18.0 15.0
Bed width (m) 12 12
Bed level (m) +50.00 +50.00
Full Supply Level (FSL) (m) +52.00 +51.75
Top level of Bank (m) +53.00 +52.75
Top width of Bank (m) 2.0 2.0
Side slopes (H:V) 2:1 2:1
Canal:
Full supply discharge 30m3/s
Full supply level +213.5m
Canal Bed level +212.0m
Canal Bed width 20m
Trapezoidal canal section 1.5H:1V slopes
Canal water depth 1.5m
Drainage:
High flood discharge 300m3/s
Drainage bed level +207.5m
High flood level +210.0m
General ground level +212.5m
Q6) Design a tank surplus weir for a major tank connected with tanks in series.
1. Field data
Combined catchment area of group of tanks -25km2
Intercepted catchment area – 20km2
General ground level at proposed site – 15m
Level at which good foundation soil is available – 13.5m
Slope at the proposed surplus works from its centerline reaches 14m in a distance of 10m
2. Construction details
Full tank level :17m
Max water level :17.8m
Tank bund level :19m
Top width of bund : 2.2m
Side slopes :2:1
3. Other details
Make provision to store water up to MWL. Proper abutments, wing walls and returns are to be designed.
Assume a hydraulic gradient of 1 in 5 and Ryves coefficient =9.
Draw to a suitable scale
1) Half plan at top and half plan at foundation
2) Half elevation and half sectional elevation
3) Cross section across the weir.
Q7) Design a canal drop (Notch type) for the following data
Particulars U/s canal D/s canal
Full supply discharge 8m3/s 8m3/s
Bed level +19.00 +17.00
Full supply level +20.50 +18.50
Bed width 8.0 8.0
Top level of embarkment +21.50 +19.50
Top width of embarkment 2.0m 2.0m
Side slopes 1:1(cut) 1.5:1(fill)
Average ground level 19.50 11.50
Hand soil available@ 17.50
Draw to a suitable scale
1) Half plan@top and half of foundation
2) Half elevation & half longitudinal section
3) Cross section along the canal
Q8) Design the details of a canal regulator with the following particulars
Particulars Upstream Downstream
Full supply discharge (FSQ)(m3/s) 19.0 16.0
Bed width (m) 12 12
Bed level (m) +55.00 +55.00
Full Supply Level (FSL) (m) +57.00 +56.75
Top level of Bank (m) +58.00 +57.75
Top width of Bank (m) 2.0 2.0
Side slopes (H:V) 2:1 2:1
Q9) Design a tank sluice for an earthen dam (Tank bund) with the following particulars
Q10) Design a suitable cross-drainage work, given the following data at the crossing of a canal and a drainage
Canal:
Full supply discharge 25m3/s
Full supply level +211.5m
Canal Bed level +210.0m
Canal Bed width 20m
Trapezoidal canal section 1.5H:1V slopes
Canal water depth 1.5m
Drainage:
High flood discharge 270m3/s
Drainage bed level +205.5m
High flood level +208.0m
General ground level +210.5m