Beruflich Dokumente
Kultur Dokumente
Answer:
Files/Information given are from my former company with a project in Clark.
Project Delivery Method: Design and Build
Contract Type: Lump Sum Contract
Project Scope:
Civil, structural and Architectural of a Nine (9) Storey Commercial and BPO
Building with Roof Deck composed of Five (5) Towers including Cinema.
Building 1 to 5 is typical with the addition of steel structures at Building 3 and
Helipad at Building 5
Project Duration: 1094 calendar days
a) How long did it take to complete the schedule?
Answer:
At least 2 to 4 weeks to established but continuous updating for
considerations of actual dates and changes on plan vs implementation
in the project.
I. Pre-Construction Phase
II. Construction Phase
i. Structural Works
ii. Wet works
iii. EXGA Works
iv. Dry works
v. Architectural Works
vi. Testing and Commissioning
vii. Final Punch listing and Handover
In that 7 phases, it is further subdivided per level and per area on each level
d) How is the schedule coded? By contract? By responsibility?
Answer:
Both. The schedule is established or made thru the pattern in WBS/BOQ
but further broken down to certain level that is “schedulable” and that
the per line item on the BOQ can be given a certain time to finish.
(classroom activity)