ECSS‐M‐ST‐10‐01C
15 November 2008
Foreword
This Standard is one of the series of ECSS Standards intended to be applied together for the
management, engineering and product assurance in space projects and applications. ECSS is a
cooperative effort of the European Space Agency, national space agencies and European industry
associations for the purpose of developing and maintaining common standards. Requirements in this
Standard are defined in terms of what shall be accomplished, rather than in terms of how to organize
and perform the necessary work. This allows existing organizational structures and methods to be
applied where they are effective, and for the structures and methods to evolve as necessary without
rewriting the standards.
This Standard has been prepared by the ECSS‐M‐ST‐10‐01 Working Group, reviewed by the ECSS
Executive Secretariat and approved by the ECSS Technical Authority.
Disclaimer
ECSS does not provide any warranty whatsoever, whether expressed, implied, or statutory, including,
but not limited to, any warranty of merchantability or fitness for a particular purpose or any warranty
that the contents of the item are error‐free. In no respect shall ECSS incur any liability for any
damages, including, but not limited to, direct, indirect, special, or consequential damages arising out
of, resulting from, or in any way connected to the use of this Standard, whether or not based upon
warranty, business agreement, tort, or otherwise; whether or not injury was sustained by persons or
property or otherwise; and whether or not loss was sustained from, or arose out of, the results of, the
item, or any services that may be provided by ECSS.
Published by: ESA Requirements and Standards Division
ESTEC, P.O. Box 299,
2200 AG Noordwijk
The Netherlands
Copyright: 2008 © by the European Space Agency for the members of ECSS
2
ECSS‐M‐ST‐10‐01C
15 November 2008
Change log
ECSS‐M‐30‐01A First issue
ECSS‐M‐30‐01B Never issued
ECSS‐M‐ST‐10‐01C Second issue
15 November 2008 Significant changes between ECSS‐M‐30‐01A and this version are:
‐ Definition of review entities and their roles and activities in project reviews.
‐ Update and rationalization of requirements.
‐ Document restructuring to maintain correspondences between the
descriptive section (clause 4) and requirement section (clause 5).
‐ Addition of DRDs to specify the content of expected documentation.
3
ECSS‐M‐ST‐10‐01C
15 November 2008
Table of contents
1 Scope.......................................................................................................................6
4 Fundamentals of reviews.....................................................................................10
4.1 Basic principles ........................................................................................................ 10
4.2 Review tasks ............................................................................................................ 10
4.2.1 Initiation of the review................................................................................. 10
4.2.2 Preparation and distribution of the review data-package ........................... 10
4.2.3 Review of the documentation ..................................................................... 11
4.2.4 Review findings and conclusions................................................................ 11
5 Requirements........................................................................................................12
5.1 General..................................................................................................................... 12
5.2 Review bodies .......................................................................................................... 12
5.3 Roles and tasks........................................................................................................ 13
5.3.1 Review authority ......................................................................................... 13
5.3.2 Customer .................................................................................................... 13
5.3.3 Supplier ...................................................................................................... 14
5.3.4 Review team leader.................................................................................... 14
5.3.5 Review team............................................................................................... 14
5.4 Prerequisite conditions for holding the review .......................................................... 14
5.5 Review meetings ...................................................................................................... 15
5.5.1 Prerequisite key point ................................................................................. 15
5.5.2 Kick-off meeting.......................................................................................... 15
5.5.3 Coordination meeting ................................................................................. 15
4
ECSS‐M‐ST‐10‐01C
15 November 2008
5.5.4 Collocation meeting .................................................................................... 15
5.5.5 Review team close-out meeting ................................................................. 15
5.5.6 Review authority meeting ........................................................................... 16
5.6 RID processing and action item follow-up ................................................................ 16
Bibliography.............................................................................................................27
Figures
Figure 4-1: Review information flow ....................................................................................... 11
Figure B-1 : Example of RID form .......................................................................................... 20
Figure B-2 : Example of RID form (continued) ....................................................................... 21
Figure E-1 : Flow logic for the RID processing....................................................................... 25
5
ECSS‐M‐ST‐10‐01C
15 November 2008
1
Scope
This Standard provides means for identifying and structuring all of the
activities and information required in a project review. It identifies the
information outputs and activities necessary to complete the process. It also
provides a check–list of activities and information required for each of the
project reviews identified in the ECSS Management Standards.
This standard may be tailored for the specific characteristics and constraints of a
space project, in conformance with ECSS‐S‐ST‐00.
6
ECSS‐M‐ST‐10‐01C
15 November 2008
2
Normative references
7
ECSS‐M‐ST‐10‐01C
15 November 2008
3
Terms, definitions and abbreviated terms
8
ECSS‐M‐ST‐10‐01C
15 November 2008
NOTE See informative Annex F for example of
application of the above to different levels of a
space project
9
ECSS‐M‐ST‐10‐01C
15 November 2008
4
Fundamentals of reviews
10
ECSS‐M‐ST‐10‐01C
15 November 2008
Figure 4‐1: Review information flow
11
ECSS‐M‐ST‐10‐01C
15 November 2008
5
Requirements
5.1 General
a. The customer shall ensure the level of independent expertise in the
review team and provide access to the information identified in the
review procedure.
b. A project review shall provide the customer with advice and
recommendations aiming at the resolution of any deficiencies identified
during the process.
c. The activity specified in 5.1b shall typically cover the following aspects:
⎯ compliance with the mission objectives or applicable STS or SFS;
⎯ adequacy of the requirements;
⎯ credibility of the proposed design, development and verification;
⎯ risk assessment and mitigation;
⎯ credibility of plans and schedules.
d. The customer shall organize the review with the approval of the
consumer.
e. A project review shall be based on the examination of a data‐package
that:
1. is compliant with the list of documents to be delivered as specified
for the review
2. is sufficient to demonstrate achievement of the review objectives.
12
ECSS‐M‐ST‐10‐01C
15 November 2008
d. The review team shall include representatives of the consumer
organization having no direct involvement in the project activities.
5.3.2 Customer
a. The customer shall propose a procedure for the review conforming to the
DRD of Annex A for review authority approval.
b. The customer shall ensure the practical organization of the following
review events:
1. Prerequisite keypoint
2. Kick‐off meeting
3. Intermediate coordination meetings
4. Collocation meeting between the review team and the supplier
5. Final meeting with the review authority.
c. The customer shall provide the review team with a data management
system for distribution and storage of:
1. Review data‐package
2. Additional technical documentation as required
3. Review item discrepancies and action items.
13
ECSS‐M‐ST‐10‐01C
15 November 2008
5.3.3 Supplier
a. The supplier shall support the customer in providing all facilities and
logistics for the review meetings and sessions as required by the
customer.
b. The supplier shall support the customer in ensuring that all necessary
means, information and documentation specified in the procedure are
available and current for the review.
c. The supplier shall support the customer in preparing responses to RIDs
and proposing a schedule for the identified actions as required by the
customer.
14
ECSS‐M‐ST‐10‐01C
15 November 2008
15
ECSS‐M‐ST‐10‐01C
15 November 2008
1. synthesize the results of the collocation meeting;
2. provide inputs for the review team report;
3. agree on major issues requiring the attention of the review
authority.
16
ECSS‐M‐ST‐10‐01C
15 November 2008
Annex A (normative)
Review procedure - DRD
<1> Introduction
a. The review procedure shall provide an overview of the status of the
project under review and the purpose and scope of the review.
<2> Applicable documents
a. The review procedure shall list the applicable documents for the review
evaluation.
<3> Review prerequisite, objectives and success criteria
a. The review procedure shall define the:
1. Prerequisites for the go‐ahead of the review as planned
2. Review objectives
3. Success criteria.
<4> Organization and responsibilities
a. The review procedure shall define the:
17
ECSS‐M‐ST‐10‐01C
15 November 2008
1. Review entities
NOTE For example, authority and review panels.
2. Participants in the review entities and their responsibilities
3. Implementation of the review data management system for
documentation, RIDs and action items
4. Review schedule including the following milestones:
o Prerequisite key point
o Kick‐off meeting
o Coordination meeting
o Collocation meeting
o Review team close‐out meeting
o Issue of panel reports
o Review authority meeting.
<5> Review data‐package
b. The review procedure shall define the list of the documents required to
be delivered for the review.
18
ECSS‐M‐ST‐10‐01C
15 November 2008
Annex B (normative)
Review item discrepancy (RID) - DRD
19
ECSS‐M‐ST‐10‐01C
15 November 2008
SHEET A
CONSUMER Project
REVIEW ITEM DISCREPANCY
Organisation Review
(A) TITLE: RID No:
Originator ID No:
reference:
Originator: Assoc. RID:
(B) REF. AND DOCUMENT TITLE:
Page/Section/Para: of the document under review
(C) DISCREPANCY:
(D)INITIATOR RECOMMENDED SOLUTION:
Originatorʹ Signature
(E) REVIEW TEAM RECOMMENDATIONS:
Status: Classification: Panel Chairmanʹ Signature
(accepted/rejected/withdrawn) (Major/Minor)
Figure B‐1: Example of RID form
SHEET B
CONSUMER Project
REVIEW ITEM DIPOSITION
Organisation Review
(A) TITLE: RID No:
‐ ‐ ID No:
‐ ‐ Assoc. RID:
(G) SUPPPLIER POSITION:
20
ECSS‐M‐ST‐10‐01C
15 November 2008
Status Responsible: Supplierʹ Signature
(H) REVIEW TEAM DISPOSTION:
Signature Consumer Published: Signature Supplier
Accepted with Closed To Pre‐Board To Postponed
action Board
(I) REVIEW TEAM CLOSEOUT:
Signature Consumer Signature Supplier
(K) CLOSE OUT REFERENCES: Closed: Date:
SIGNATURE
Figure B‐2: Example of RID form (continued)
21
ECSS‐M‐ST‐10‐01C
15 November 2008
Annex C (normative)
Review team report - DRD
22
ECSS‐M‐ST‐10‐01C
15 November 2008
(b) RIDs related to significant findings
(c) RIDs for resolution by the review authority
(d) Action item list.
23
ECSS‐M‐ST‐10‐01C
15 November 2008
Annex D (normative)
Review authority report - DRD
24
ECSS‐M‐ST‐10‐01C
15 November 2008
Annex E (informative)
Logic diagram for RID processing
Figure E‐1: Flow logic for the RID processing
25
ECSS‐M‐ST‐10‐01C
15 November 2008
Annex F (informative)
Examples for defined terms
26
ECSS‐M‐ST‐10‐01C
15 November 2008