Beruflich Dokumente
Kultur Dokumente
By
Supervisor
A REPORT SUBMITTED TO
University Of Khartoum
(POWER ENGINEERING)
Faculty of Engineering
October 2017
DECLARATION OF ORGINALITY
I declare this report entitled “OVERCURRENT PROTECTION COORDINATION
CASE STUDY: BALEELA OIL-FIELD NETWORK” is my own work except as cited in
references. The report has been not accepted for any degree and it is not being submitted
currently in candidature for any degree or other reward.
Signature: ____________________
Name: _______________________
Date: ________________________
ii | P a g e
Acknowledgement
To my mother and father, who grew me up, fed me and guided me through life.
Special thanks to my project partners for their hard work, support and cooperation. Besides, I
also want to thank Eng Abdallah Abdelmonem, and Eng Babikir Elnouman for their
significant assistance and help.
Many thanks to my colleagues and all the staff at the Department of Electrical and
Electronics Engineering for the pleasant working atmosphere and your friendship.
iii | P a g e
Abstract
Continuous and reliable power supply is the main goal and target for power system networks.
In this regard, many methods have been developed to enhance the performance of power
supply systems.
The present research is initiated to investigate Baleela power network, because this network
is faced by blackouts several times per year during last couple of years, this led to severe lack
of production during blackout times beside the maintenance and operation cost impact.
Using ETAP software as analysis tool, the network was drawn. The data for each component
in the network was collected from a site visit to Baleela. After running the simulator,
different fault scenarios were created to examine the existing protection system schemes and
different miss-operations results were obtained as a response of protection system to the
abnormal conditions. After studying this network, it is noticed that one of the main reasons
for blackouts is the relay setting miss-coordination caused by the use of only (DMT)
characteristics.
An optimum characteristic (IDMT) for the relays was chosen, and a completely new
coordination scheme is designed which starts first by coordinating the phase over-current
elements, for different paths from furthest downstream up to the generators. Next the earth
fault relays are coordinated for the same paths and finally the instantaneous element as a
backup protection was applied successfully.
The new relay setting coordination has been applied to all relays in the five main substations
as a result from this study. The sequence of operation is well improved and as a result the
total blackouts frequency is significantly decreased. Valuable recommendations were
suggested.
iv | P a g e
المستخلص
يعتبر إمداد الطالة بشكل مستمر وموثوق أحد أهم أهداف شبكات إمداد الطاله الكهربائية ,لذلن تم إبتكار أنظمة وطرق
من أجل تحسن أداء هذه الشبكات ألمداد الطالة بالصورة المطلوبة.
تم عمل هذا البحث لدراسة الشبكة الكهربائية لحمل بليلة ,تم إختيار هذه الشبكة بالتحديد نسبة لتكرر اإلنمطاع التام للتيار
الكهربائي خالل العام الواحد ,وذلن لألعوام المليلة الماضية مما أثر سلبا على اإلنتاج في الحمول بجانب تأثير التكاليف
الحالية للصيانة وإعادة التشغيل.
بإستخدام بزَبيــج ( )ETAPكأداة للدراسة والتحليل ,تم رسم وتمثيل شبكة بليلــــة ثم جمع البيانات الخاصة لجميع
عناصر الشبكة عن طريك زيـــارة المولع ,ثم تم إدخال هذه البيانات في برنامج المحاكاة (.)ETAP
تى إختببر أَظًة انحًبية انحبنية انخبصة بشبكة بهـــــيهة ػٍ طزيق ػًم سيُبريىهبت ألػطبل كهزببئية فتى انحصىل ػهى
بؼض اإلستجبببت انخبطئة يٍ َظبو انحًبية نهذِ األػطبل ,بؼذ دراسة وتحهيم انشبكة نىحظ أٌ أحذ أسببة إَقطبع إيذاد
انكهزببء هى فقذاٌ تُسيق وضبط يزحالت انحًبية َتيجة إلستخذاو طزيقة (.)DMT
في المرحلة الثانية تم تنسيك مرحالت حمياة األعطال للخطأ األرضي وذلن لنفس المسارات السابمة للشبكة ,وأخيراً تم
تنسيك العناصر اللحظية كعناصر إحتياطية للحماية.
تم تطبيك نظام ( )IDMTانسببق نجًيغ يزحالت انحًبية في انخًس يحطبت في انشبكة كُتيجة نهذراسة انسببقة.
نىحظ أٌ تسهسم عمل المرحالت لد تحسن بصورة كبيرة ,كنتيجة لذالن إنخفضت مرات إنمطاع اإلمداد الكهربائي
بصورة ملحوظة.
v|Page
Table of Contents
DECLARATION OF ORGINALITY ................................................................................ ii
Abstract .............................................................................................................................. iv
المستخلص.................................................................................................................................v
Introduction ................................................................................................................. 1
2 Literature Review........................................................................................................ 3
vi | P a g e
2.5.5 Sensitivity ......................................................................................................... 11
2.6 Protection components ............................................................................................. 11
2.6.1 Voltage transformers ......................................................................................... 11
2.6.2 Current transformers ......................................................................................... 12
2.6.3 Fuses ................................................................................................................. 12
2.6.4 Relays ................................................................................................................ 13
2.6.4.1 Electromechanical Relays.......................................................................... 13
2.6.4.2 Static Relays .............................................................................................. 14
2.6.4.3 Digital Relays ........................................................................................... 14
2.6.4.4 Numerical Relays ...................................................................................... 14
2.6.5 Circuit breakers ................................................................................................. 15
2.6.5.1 Purpose of circuit breakers ........................................................................ 15
2.6.5.2 Types of Circuit Breakers .......................................................................... 16
2.7 Over-current Protection ............................................................................................ 19
2.7.1 Co-ordination Procedure ................................................................................... 19
2.7.2 Principles of Time/Current Grading ................................................................. 19
2.7.2.1 Discrimination by Time ............................................................................. 20
2.7.2.2 Discrimination by Current ......................................................................... 20
2.7.2.3 Discrimination by both Time and Current ................................................. 20
2.7.3 Standard I.D.M.T. Overcurrent Relays ............................................................. 21
2.7.4 Combined IDMT and High Instantaneous Over-current Relays ................... 21
2.8 Generator protection ................................................................................................. 21
2.9 Feeder protection ...................................................................................................... 22
2.10 Transformer protection ............................................................................................. 22
2.11 Bus-bar protection .................................................................................................... 22
2.12 Primary and Back-up Protection .............................................................................. 23
2.13 Trip Circuit Supervision ........................................................................................... 24
CHAPTER THREE .......................................................................................................... 25
Conclusion ................................................................................................................ 65
Appendix A ....................................................................................................................... 68
ix | P a g e
NEW SETTING ........................................................................................................ 97
x|Page
List of Figures
Figure 2.1 Types of faults on a three-phase system: (A) Phase-to-earth fault; (B) Phase-to-
phase fault; (C) Phase-to phase- to-earth fault; (D) Three-phase fault; (E) Three-phase-to-
earth fault .............................................................................................................................5
Figure 2.2 Zones of protection............................................................................................ 7
Figure 2.3 Overlapping of zones ........................................................................................ 8
Figure 2.4 Application of principle of grading.................................................................. 10
Figure 2.5 Over current time grading ................................................................................ 10
Figure 2.6 Arc control circuit-breaker ............................................................................... 16
Figure 2.7 Oil circuit-breaker ............................................................................................ 17
Figure 2.8 Air break switchgear ......................................................................................... 18
Figure 3.1 Geographic description of BALEELA network............................................... 26
Figure 3.2 Baleela Oil-Field Network Single Line Diagram ............................................ 29
Figure 3.3 Three phase fault on JAKE (CH05 TR7802A) feeder ..................................... 30
Figure 3.4 sequence of operation for JAKE 11kV feeder ................................................. 31
Figure 3.5 Three phase fault at MOGA-JAKE transmission line ..................................... 32
Figure 3.6 sequence of operation for fault at MOGA-JAKE transmission line ................ 32
Figure 3.7 Three phase fault at CPF 33kV bus-bar (B) ..................................................... 33
Figure 3.8 sequence of operation for a fault on CPF 33kV bus-bar (B) ........................... 34
Figure 3.9 Line-to-Ground fault on KEYI 11kV feeder ................................................... 35
Figure 3.10 The sequence of operation for Line-to-Ground fault on KEYI 11kV feeder .. 35
Figure 3.11 Line -To-Ground fault at transmission line between CPF and KEYI ............ 36
Figure 3.12 Sequence of operation for Line-to-Ground fault at CPF-KEYI transmission
line .......................................................................................................................36
Figure 3.13 Definite time relay curve ................................................................................ 38
Figure 3.14 Inverse time relay curve ................................................................................. 38
Figure 4.1 The new phase [O/C] settings for JAKE-MOGA path relays ......................... 41
Figure 4.2 The new phase [O/C] settings for MOGA-CPF path relays........................... 42
Figure 4.3 The new phase [O/C] settings for FNE-CPF path relays ............................... 43
Figure 4.4 The new phase [O/C] settings for KEYI-CPF path relays .............................. 44
Figure 4.5 New earth fault settings for JAKE up to the secondary of its transformer .... 45
Figure 4.6 New earth fault settings from JAKE primary of the transformer up to CPF. 46
Figure 4.7 New earth fault settings For MOGA up to secondary of its transformer ...... 47
Figure 4.8 New earth fault settings from MOGA primary of the transformer up to CPF
...........................................................................................................................48
Figure 4.9 New earth fault settings for FNE up to secondary of its transformer ........... 49
Figure 4.10 New earth fault settings from FNE primary of the transformer up to CPF ... 50
Figure 4.11 New earth fault settings from KEYI up to secondary of its transformer ...... 51
Figure 4.12 New earth fault settings from KEYI primary of the transformer up to CPF . 52
Figure 4.13 New earth fault settings for CPF primary of its transformer up to 11kV bus
section .......................................................................................................................53
Figure 4.14 Three phase fault on JAKE 11kV (CH05 TR7802A) feeder ........................ 54
Figure 4.15 sequence of operation for a three phase fault on JAKE 11kV feeder ........... 55
Figure 4.16 Three phase fault at MOGA-JAKE transmission line ................................... 56
Figure 4.17 sequence of operation for a three phase fault at MOGA-JAKE line ............ 56
xi | P a g e
Figure 4.18 Three phase fault at CPF 33kV bus-bar (B) .................................................. 57
Figure 4.19 sequence of operation for three phase fault at CPF 33kV bus-bar (B) ......... 58
Figure 4.20 Line-to-Ground fault on KEYI 11kV feeder ................................................. 59
Figure 4.21 The sequence of operation for Line-to-Ground fault on KEYI 11kV feeder 60
Figure 4.22 Line -To-Ground fault at transmission line between CPF and KEYI ........... 61
Figure 4.23 sequence of operation for Line-to-Ground fault on CPF- KEYI transmission
line .......................................................................................................................62
xii | P a g e
List of Tables
Table 2.1 Fault Statistics With Reference to Type of Fault ..................................................... 5
Table 2.2 Fault Statistics With Reference to Power System Elements .................................... 6
Table 3.1: Real and reactive power for CPF loads at busbar A ............................................. 27
Table 3.2: Real and reactive power for CPF loads at busbar (B) ........................................... 27
Table 3.3: Real and reactive power for KEIY loads at busbar (A & B) ................................ 27
Table 3.4: Real and reactive power for FNE loads at busbar A & B ..................................... 28
Table 3.5: Real and reactive power for MOGA loads at busbar (A & B) ............................. 28
Table 3.6: real and reactive power for JAKE loads at busbar (A & B) ................................. 28
Table 3.7: Parameters for different types of inverse characteristic ........................................ 39
Table 4.1 Coordination status for each scenario .................................................................... 64
Table A.1 Power Transformers Technical Data ..................................................................... 68
Table A. 2 X/R ratio for each transformer using the transformer rated MVA and copper
losses ....................................................................................................................................... 69
Table A. 3 Transmission Lines Data ...................................................................................... 70
Table A. 4 The generators dynamic data................................................................................ 70
Table B. 1 11kV Feeders on 1stBusbar ................................................................................... 71
Table B. 2 11kV Feeders on 2ndBusbar .................................................................................. 72
Table B. 3 11kV Incomers ..................................................................................................... 72
Table B.4 33kV Transformer Feeders .................................................................................... 73
Table B. 5 33kV Bus coupler ................................................................................................. 73
Table B. 6 33kV Incomers ..................................................................................................... 74
Table B. 7 11kV Bus-section & 11kV two Incomers Directional Protection ........................ 74
Table B. 8 11 kV Feeders on 1st Busbar ................................................................................. 75
Table B. 9 11kV Feeders on 2nd Busbar ............................................................................... 75
Table B. 10 11kv Incomers .................................................................................................... 76
Table B. 11 11kV Bus-section & 11kV two incomers Directional Protection [the directional
Element is disabled = non-directional] ................................................................................... 77
Table B.712 33 kV Transformer Feeders ............................................................................... 77
Table B.13 33kV Bus coupler ................................................................................................ 78
Table B. 14 33kV incomers.................................................................................................... 79
Table B.15 33 kV Outgoings (to Jake Substation) ................................................................. 79
Table B. 16 11kV Feeders on 1st Busbar ................................................................................ 80
Table B.17 11kV Feeders on 2nd Busbar ................................................................................ 81
Table B. 18 11kV Incomers ................................................................................................... 82
Table B. 19 33kV Transformer Feeders ................................................................................. 82
Table B. 20 33kV Bus coupler ............................................................................................... 83
Table B. 21 33kV Incomers ................................................................................................... 83
Table B. 22 11 kV Bus-section & 11kV Two Incomers Directional Protection [the
directional Element is disabled = non-directional] ................................................................. 84
Table B. 23 11kV Feeders on 1st Busbar ................................................................................ 85
Table B. 24 11kV Feeders on 2nd Busbar ............................................................................... 86
Table B. 25 11kV Incomers ................................................................................................... 87
Table B. 26 33kV Transformer Feeders ................................................................................. 87
Table B. 27 33kV Bus coupler ............................................................................................... 88
Table B. 28 33kV Incomers ................................................................................................... 88
xiii | P a g e
Table B. 29 11kV Bus-section & 11kV Two Incomers Directional Protection [the directional
Element is disabled = non-directional] ................................................................................... 89
Table B. 30 11kV Substation Feeders ................................................................................... 90
Table B. 31 11Kv Substation New Added Feeders ............................................................... 92
Table B. 32 11 kV Bus-section & 11 kV Transformer feeders .............................................. 94
Table B. 33 33 kV Transformer Feeders ................................................................................ 94
Table B. 34 11 kV Bus-section & 11 kV Transformer feeders .............................................. 95
Table B. 35 33 kV Transformer Feeders ................................................................................ 95
Table B. 36 33kVBustie ......................................................................................................... 96
Table B. 37 33 kV outgoings ................................................................................................. 96
Table C.1 11kV FEEDERS on 1st Busbar.............................................................................. 97
Table C.2 11kV FEEDERS on 2nd Busbar............................................................................. 98
Table C.3 11kV incomers ...................................................................................................... 98
Table C.4 33kV Transformer Feeders.................................................................................... 99
Table C.5 33kV Bus coupler .................................................................................................. 99
Table C.6 33kV incomers ...................................................................................................... 99
Table C.7 11kV Bus-section & 11kV two incomers Directional Protection ....................... 100
Table C. 8 11kV FEEDERS on 1st Busbar .......................................................................... 101
Table C. 9 11kV FEEDERS on 2nd Busbar ........................................................................ 102
Table C.10 11kV incomers .................................................................................................. 103
Table C.11 33kV Transformer Feeders................................................................................ 103
Table C. 12 33kV Bus coupler ............................................................................................. 104
Table C. 13 33kV Incomers ................................................................................................. 104
Table C.14 11kV Bus-section & 11kV two incomers Directional Protection ..................... 104
Table C. 15 11kV FEEDERS on 1st Busbar ........................................................................ 105
Table C.16 11kV FEEDERS on 2nd Busbar ....................................................................... 106
Table C.17 11kV Incomers .................................................................................................. 106
table C. 18 33kV Transformer Feeders ................................................................................ 107
Table C. 19 33kV Bus coupler ............................................................................................. 107
Table C.20 33kV Incomers .................................................................................................. 107
Table C.21 11kV Bus-section & 11 kV two incomers Directional Protection .................... 108
Table C.22 11kV FEEDERS on 1st Busbar ........................................................................ 109
Table C.23 11kV FEEDERS on 2nd Busbar ....................................................................... 110
Table C. 24 11kV Incomers ................................................................................................. 110
Table C. 25 33kV Transformer Feeders............................................................................... 111
Table C.26 33kV Bus coupler .............................................................................................. 111
Table C. 27 11kV Bus-section & 11kV two incomers Directional Protection [the directional
Element is disabled = non-directional] ................................................................................. 112
Table C.28 NEW 11KV SUBSTATION FEEDERS .......................................................... 114
Table C.29 11kV Bus-section & 11kV Transformer feeders............................................... 116
Table C.30 33kV Transformer Feeders................................................................................ 116
Table C.31 33kV outgoings ................................................................................................. 117
xiv | P a g e
List of ABBREVIATIONS
MW Mega Watt
xv | P a g e
Chapter 1 [Introduction]
CHAPTER ONE
1 Introduction
1.1 Overview
This chapter is intended to give the reader an idea about the project‟s problem, background,
objectives. In addition, an overview of the report layout is given.
Over current protection devices should also provide short-circuit as well as overload
protection for system components, such as bus, cables, motor controllers, ...etc.
To obtain reliable, coordinated operation and assure that system components are
protected from damage, it is necessary to first calculate the available fault current at various
critical points in the electrical system. Once the fault levels are determined, the
1|Page
Chapter 1 [Introduction]
electrical design professional can specify proper interrupting rating requirements, selectively
coordinate the system, and provide component protection.[6]
1.4 Objectives
The objectives of the project can be summarized as follows:
Simulate Baleela Oil-Field power Network using ETAP software.
Analyze Baleela Oil-Field power Network from the protection point of view
Point out the disadvantages of the currently used relay settings at Baleela power
Network.
Perform over-current phase (O/C) and earth fault protections on this network and
obtain its relays settings and co-ordination.
Apply instantaneous protection as a back-up protection.
Chapter three Baleela oil-field power network had been taken as case study, detailed
description about the system and different faults scenarios on the network had been
conducted.
Chapter four explains how to change the protection philosophy by using the more flexible
IDMT principle for over-current and earth fault. Different scenarios of faults on this network
had been conducted to assure that the protection scheme is operating adequately.
Appendix B contains the old protection relay settings as recorded directly from the
instruments interface.
Appendix C contains the new relay coordination settings for each substation.
2|Page
Chapter 2 [LITERATURE REVIEW]
CHAPTER TWO
2 Literature Review
2.1 Introduction
An electric power system is a network deployed to supply, transfer, and use electric power
with both reliability and economy .A power system is not only capable to meet the present
load but also has the flexibility to meet the future demands on a continuous basis.[1]
To ensure the maximum return on the large investment in the equipment, which goes to make
up the power system and to keep the users satisfied with reliable service, the whole system
must be kept in operation continuously without major breakdowns . This can be achieved in
two ways :
The first way is to implement a system adopting components, which should not fail and
requires the least or nil maintenance to maintain the continuity of service. By common
sense, implementing such a system is neither economical nor feasible, except for small
systems.
The second option is to foresee any possible effects or failures that may cause long-term
shutdown of a system.
The main idea is to restrict the disturbances during such failures to a limited area and
continue power distribution in the balance areas. Special equipment is normally installed to
detect such kind of failures (also called „faults‟) that can possibly happen in various sections
of a system, and to isolate faulty sections so that the interruption is limited to a localized area
in the total system covering various areas. The special equipment adopted to detect such
possible faults is referred to as „protective equipment or protective relay‟ and the system that
uses such equipment is termed as „protection system‟.[2]
3|Page
Chapter 2 [LITERATURE REVIEW]
A protective relay is the device, which gives instruction to disconnect a faulty part of the
system. This action ensures that the remaining system is still fed with power, and protects the
system from further damage due to the fault. Hence, use of protective apparatus is very
necessary in the electrical systems, which are expected to generate, transmit and distribute
power with least interruptions and restoration time. It can be well recognized that use of
protective equipment are very vital to minimize the effects of faults, which otherwise can kill
the whole system.[1]
Fault currents release an enormous amount of thermal energy, and if not cleared quickly may
cause fire hazards, extensive damage to equipment and risk to human life. Faults are
classified into two major groups: symmetrical and unbalanced (asymmetrical).Symmetrical
faults involve all three phases and cause extremely severe fault currents and system
disturbances. Unbalanced faults include phase-to-phase, phase-to-ground, and phase-to-
phase-to-ground faults. They are not as severe as symmetrical faults because not all three
phases are involved. The least severe fault condition is a single phase-to-ground fault with
the transformer neutral earthed through a resistor or reactor. However, if not cleared quickly,
unbalanced faults will usually develop into symmetrical faults. Switchgear need to be rated to
withstand and break the worst possible fault current ,which is a solid three-phase short-circuit
close to the switchgear.[4]
4|Page
Chapter 2 [LITERATURE REVIEW]
Power systems have been in operation for over a hundred years now. Accumulated
experience shows that all faults are not equally likely. Single line to ground faults (L-G)are
the most likely. Whereas the fault due to simultaneous short circuit between all the three
lines, known as the three-phase fault(L-L-L), is the least likely. This is depicted in Table
2.1[7] .
Line-to-line 8
Line-to-line-to-Ground 5
The probabilities of faults on different elements of the power system are different. The
transmission lines which are exposed to the vagaries of the atmosphere are the most likely to
5|Page
Chapter 2 [LITERATURE REVIEW]
be subjected to faults. Indoor equipment is least likely to be subjected to faults. The fault
statistics is shown in Table 2.2.
The severity of the fault can be expressed in terms of the magnitude of the fault current and
hence its potential for causing damage. In the power system, the three-phase fault is the most
severe whereas the single line-to-ground fault is the least severe. [7]
6|Page
Chapter 2 [LITERATURE REVIEW]
necessary to develop many types of relay that respond to various functions of the power
system quantities.
2.4.1 Overview
The basic function of electrical protection is to detect system faults and to clear them as soon
as possible. For any one particular application, there are many ways to do this function, with
varying degrees of effectiveness. The choice is influenced by the overall protection
philosophy of the plant, and the importance of the equipment or portion of the network to be
protected, weighing cost against performance. The general philosophy of applying protection
in a power network is to divide the network into protective zones, such that the power system
can be adequately protected with the minimum part of the network being disconnected during
fault conditions. The zones can either be very clearly defined, with the protection operating
exclusively for that zone only as in differential protection, illustrated in Figure 2.2 or less
clearly defined ,with overlapping of the protection function between zones for example, over-
current protection, as illustrated in Figure 2.3.
7|Page
Chapter 2 [LITERATURE REVIEW]
These requirements are necessary, firstly for early detection and localization of faults, and
secondly for prompt removal of faulty equipment from service. In order to carry out the
above duties, protection must have the following qualities.
Unit protection can only be achieved when the following essentials are satisfied :
8|Page
Chapter 2 [LITERATURE REVIEW]
The most common form of unit protection is current differential protection, whereby current
values at each end of the protected equipment is measured and compared, and a trip signal is
issued when the difference in measured values is more than a predefined threshold value.
i. Only the faulted equipment or part of the network is disconnected, with minimum
disruption to the power network.
ii. Unit protection operates very fast, limiting damages to equipment and danger to
human life. Fast operation is possible because the presence or absence of a fault is a
very clear-cut case.
iii. Unit protection is very stable
iv. Unit protection is very reliable (provided the communication path is intact).
v. Unit protection is very sensitive.
The discrimination qualities of non-unit protection are not absolute, as the relay functions
independently and will generally operate whenever it sees a fault, no matter where the fault is
located. Therefore, to achieve proper discrimination for non-unit protection schemes, the
principle of grading is applied. Consider the example, as illustrated in figure 2.4 where the
protection consists of only over-current relays. If the relays in figure 2.4 were all of the
same type, and no lower or upper restrictions were placed on the grading, it would be quite
simple, and the time–current would look something like the graph in figure 2.5 .
9|Page
Chapter 2 [LITERATURE REVIEW]
10 | P a g e
Chapter 2 [LITERATURE REVIEW]
2.5.2 Stability
Stability, also called security, is the ability of the protection to remain inoperative for normal
load conditions (including normal transients like motor starting).Most stability problems
arise from incorrect application of relays and lack of maintenance.
2.5.3 Reliability
Reliability, or dependability, is the ability of the protection to operate correctly in case of a
fault . Reliability is probably the most important quality of a protection system.
2.5.5 Sensitivity
The term sensitivity refers to the magnitude of fault current at which protection operation
occurs. A protection relay is said to be sensitive when the primary operating current is very
low. Therefore, the term sensitivity is normally used in the context of electrical protection for
expensive electronic equipment, or sensitive earth leakage equipment.
i. Electromagnetic type.
ii. Capacitor type.
11 | P a g e
Chapter 2 [LITERATURE REVIEW]
Electromagnetic voltage transformers may be connected inter phase or between phase and
earth. However, capacitor voltage transformers can only be connected phase-to-earth.[1]
To prevent secondary circuits from reaching dangerous potential, the circuits should be
earthed. Earthing should be made at only one point of a VT secondary circuit or galvanically
interconnected circuits. A VT with the primary connected phase-to-earth shall have the
secondary earthed at terminal n. A VT with the primary winding connected across two-
phases, shall have that secondary terminal earthed which has a voltage lagging the other
terminal by 120°. Windings not under use shall also be earthed .
The wound primary is used for the smaller currents, but it can only be applied on low fault
level installations due to thermal limitations as well as structural requirements due to high
magnetic forces. For currents greater than 100 A, the bar primary type is used. If the
secondary winding is evenly distributed around the complete iron core, its leakage reactance
eliminated .[1]
2.6.3 Fuses
Fuse is the most common and widely used protective device in electrical circuits
12 | P a g e
Chapter 2 [LITERATURE REVIEW]
Rewire able type as the name indicates the fuse can be replaced or „rewired‟ once it fails.
Fusible wire used to be contained in an asbestos tube to prevent splashing of volatile metal.
Advantages
i. Correct rating and characteristic fuse always fitted to a circuit-not open to abuse as
rewire able type.
ii. Arc and fault energy contained within insulating tube-prevents damage.
iii. Normally sealed therefore not affected by atmosphere hence gives more stable
characteristic-reliable grading.
iv. Can operate considerably faster, suitable for higher short-circuit duty (Cartridge type
can handle 100 000 A & Semi-open type can handle 4000 A).
Disadvantages
2.6.4 Relays
Types of relays
i attracted armature
ii moving coil
iii induction
iv thermal
13 | P a g e
Chapter 2 [LITERATURE REVIEW]
v motor operated
vi mechanical
14 | P a g e
Chapter 2 [LITERATURE REVIEW]
The input analogue signals are converted into a digital representation and processed
according to the appropriate mathematical algorithm. Processing is carried out using a
specialized microprocessor that is optimized for signal processing applications, known as a
digital signal processor or DSP for short. Digital processing of signals in real time requires a
very high power microprocessor. In addition, the continuing reduction in the cost of
microprocessors and related digital devices (memory, I/O, etc.) naturally leads to an
approach where a single item of hardware is used to provide a range of functions („one-box
solution‟ approach). By using multiple microprocessors to provide the necessary
computational performance, a large number of functions previously implemented in separate
items of hardware can now be included within a single item.[3]
These should also be capable of breaking a live circuit under normal switching OFF
conditions as well as under fault conditions carrying the expected fault current until
completely isolating the fault side (rupturing/breaking capacity) Under fault conditions, the
breakers should be able to open by instructions from monitoring devices like relays. The
relay contacts are used in the making and breaking control circuits of a circuit breaker, to
prevent breakers getting closed or to trip breaker under fault conditions as well as for some
other interlocks .[1]
15 | P a g e
Chapter 2 [LITERATURE REVIEW]
A breaker consists of moving and fixed contact, and during the breaker operation, the
contactse broken and the arc created during such separation needs to be controlled. The
breaker is shown in figure 2.6.
16 | P a g e
Chapter 2 [LITERATURE REVIEW]
Advantages
i Ability of cool oil to flow into the space after current zero and arc goes out.
ii Cooling surface presented by oil.
iii Absorption of energy by decomposition of oil.
iv Action of oil as an insulator lending to more compact design of switchgear.
Disadvantages
In the initial stages, the use of high-volume (bulk) oil circuit breakers was more common, In
this type, the whole breaker unit is immersed in the oil. This type had the disadvantage of
production of higher hydrogen quantities during arcing and higher maintenance
requirements. Subsequently these were replaced with low oil (minimum oil) types, where the
arc and the bubble are confined into a smaller chamber, minimizing the size of the unit.[1]
17 | P a g e
Chapter 2 [LITERATURE REVIEW]
18 | P a g e
Chapter 2 [LITERATURE REVIEW]
i. A one-line diagram of the power system involved, showing the type and rating of the
protection devices and their associated current transformers .
ii. The impedances in ohms, per cent or per unit, of all power transformers, rotating
machine and feeder circuits .
iii. The maximum and minimum values of short circuit currents that are expected to flow
through each protection device .
iv. The maximum load current through protection devices .
v. The starting current requirements of motors and the starting and locked rotor/stalling
times of induction motors .
vi. The transformer inrush, thermal withstand anddamage characteristics .
vii. Decrement curves showing the rate of decay of the fault current supplied by the
generators.
viii. Performance curves of the current transformers .
The relay settings are first determined to give the shortest operating times at maximum fault
levels and then checked to see if operation will also be satisfactory at the minimum fault
current expected .[3]
19 | P a g e
Chapter 2 [LITERATURE REVIEW]
Each protection unit comprises a definite-time delay overcurrent relay in which the operation
of the current sensitive element simply initiates the time delay element. each relay time
setting must be long enough to ensure that the upstream relays do not operate before the
circuit breaker at the fault location has tripped and cleared the fault. The main disadvantage
of this method of discrimination is that the longest fault clearance time occurs for faults in
the section closest to the power source, where the fault level (MVA) is highest.[3]
There are two important practical points that affect this method of co-ordination:
i. it is not practical to distinguish between a fault at F1 and a fault at F2, since the
distance between these points may be only a few meters, corresponding to a change in
fault current of approximately 0.1% .
ii. in practice, there would be variations in the source fault level .
Discrimination by current is therefore not a practical proposition for correct grading between
the circuit breakers at two points. [3]
Illustrates the characteristics of two relays given different current/time settings. For a large
variation in fault current between the two ends of the feeder, faster operating times can be
achieved by the relays nearest to the source, where the fault level is the highest. The
disadvantages of grading by time or current alone are overcome .[3]
20 | P a g e
Chapter 2 [LITERATURE REVIEW]
One of the advantages of the high set instantaneous elements is to reduce the operating time
of the circuit protection by the shaded area below the 'discriminating curves'. If the source
impedance remains constant, it is then possible to achieve highspeed protection over a large
section of the protected circuit. The rapid fault clearance time achieved helps to minimize
damage at the fault location. a further important advantage gained by the use of high set
instantaneous elements. Grading with the relay immediately behind the relay that has the
instantaneous elements enabled is carried out at the current setting of the instantaneous
elements and not at the maximum fault level.[3]
21 | P a g e
Chapter 2 [LITERATURE REVIEW]
multi-function relays like a generator protection relay is quite involved and is usually done
by the relay supplier, preferably on a factory test-set before installation.[4]
An over-current and earth fault relay will generally be installed on each feeder cubicle in a
distribution substation, often supporting or as a backup for other specific types of protection,
like differential protection or transformer protection.
The feeder protection relay functions independently and in a very straightforward manner. It
is this characteristic, together with the fact that it is so commonly used, that made this relay.
The ideal candidate to be developed into a versatile, flexible intelligent relay, with powerful
control functions and advanced communications capabilities.[4]
Supplementary protection devices will usually be interfaced to the transformer, e.g. Buchholz
protection, oil temperature,... etc. [4]
22 | P a g e
Chapter 2 [LITERATURE REVIEW]
which is normally a very expensive piece of equipment as well as a crucial part of the
distribution network, can be extensive if the fault is not cleared quickly. Therefore, bus-bar
protection needs to operate very fast and reliably.[4]
Back-up protection may be considered as either being „local‟ or „remote‟. Local back-up
protection is achieved by protection which detects an un-cleared primary system fault at its
own location and which then trips its own circuit breakers, e.g. time graded over-current
relays.
The extent and type of back-up protection applied will naturally be related to the failure risks
and relative economic importance of the system. For distribution systems where fault
clearance times are not critical, time delayed remote back-up protection may be adequate.
For EHV systems, where system stability is at risk unless a fault is cleared quickly, multiple
primary protection systems, operating in parallel and possibly of different types (e.g. distance
and unit protection), will be used to ensure fast and reliable tripping.
23 | P a g e
Chapter 2 [LITERATURE REVIEW]
Back-up over-current protection may then optionally be applied to ensure that two separate
protection systems are available during maintenance of one of the primary protection
systems.
Back-up protection systems should, ideally, be completely separate from the primary
systems.[3]
These interconnections, coupled with the importance of the circuit, result in a requirement in
many cases to monitor the integrity of the circuit. This is known as trip circuit supervision.
The simplest arrangement contains a healthy trip lamp. The resistance in series with the lamp
prevents the breaker being tripped by an internal short circuit caused by failure of the lamp.
This provides supervision while the circuit breaker is closed, a simple extension gives pre-
closing supervision.
Schemes using a lamp to indicate continuity are suitable for locally controlled installations,
but when control is exercised from a distance it is necessary to use a relay system.[3]
24 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
CHAPTER THREE
3.1 Introduction
In power systems, the analysis of the network is an important step to determine the
performance, both under normal operation and during faults conditions.
Fault levels at different parts of the network, as well as protection coordination are some of
the many important parameters that define the performance of the network. Calculating these
measures and simulation of the system is invaluable in terms of identifying network
problems and suggesting modifications.
3.2 Overview
A site visit was conducted to Baleela Oil-Field network in order to collect the data of the
existing network, collect the uploaded settings of the protection system and investigate the
defects of the existing settings.
25 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
Table 3.1 shows real and reactive power for CPF loads at busbar (A).
26 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
Table 3.1: Real and reactive power for CPF loads at busbar A
Table 3.2 shows real and reactive power for CPF loads at busbar (B).
Table 3.2: Real and reactive power for CPF loads at busbar (B)
Table 3.3 shows real and reactive power for KEIY loads at busbar (A & B)
Table 3.3: Real and reactive power for KEIY loads at busbar (A & B)
Table 3.4 shows real and reactive power for FNE loads at busbar (A & B)
27 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
Table 3.4: Real and reactive power for FNE loads at busbar A & B
Table 3.5 shows real and reactive power for MOGA loads at busbar (A & B)
Table 3.5: Real and reactive power for MOGA loads at busbar (A & B)
Table 3.6 shows real and reactive power for JAKE loads at busbar (A & B)
Table 3.6: real and reactive power for JAKE loads at busbar (A & B)
28 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
The ETAP Single-Line Diagram is used to create and visually manage the electrical
schematics and electrical drawings of Baleela network. It will also be used to perform
multiple simultaneous scenario simulations.
29 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
The reason behind taking CPF-JAKE line as a case study is that it is the longest line, and
gives many faulty operations of relays.
30 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
The sequence of operation for three phase fault on JAKE 11kV feeder is shown in figure 3.4.
From figure 3.4, it's clear that the bus section relay (relay 32) and the two relays at the
primary side of the two transformers (relay 44 and relay 45) tripped at the same time as the
faulted feeder relay (relay 47),which means that the whole substation is out for a single three
phase fault at the downstream feeder.
Also the two relays of the two feeders (relay 46 and relay 56) tripped at the same time (300
milliseconds) due to the high reverse currents of the motors.
The correct sequence of operation is that the feeder relay (relay 47) must trip first followed
by the bus section relay (relay 32) delayed by at least 150 millisecond then the two 11 kv
incomers (relay 33 & 43) also delayed by at least 150 millisecond, then the two relays of the
primary side of the transformer.
31 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
The sequence of operation for three phase fault at MOGA-JAKE line is shown in figure 3.6
32 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
From figure 3.6, it's clear that the two relays of the two parallel transmission lines going from
CPF to MOGA (relay 217 and relay 230) tripped instantaneously at zero second. Hence
MOGA substation will totally blackout for any fault that occur at the transmission line
going to Jake substation .hence protection scheme is miss-coordinated.
The correct sequence of operation is that the sending end of the two transmission line (going
to JAKE) relay (relay 250( must trip first followed by the bus section relay (relay 57) delayed
by at least 150 millisecond then the receiving end of the transmission line (coming from
CPF) relay (relay 249) also delayed by 150 millisecond.
33 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
The sequence of operation for three phase fault at CPF 33kV bus-bar B is shown in figure
3.8.
Figure 3.8 sequence of operation for a fault on CPF 33kV bus-bar (B)
From the figure 3.8, is clear that all relays of the feeders in CPF (bus-bar A & B 11kV)
tripped due to the reverse current before the bus section.
Also the tripping of the bus section was delayed (after 500 millisecond), also 33kv incomer
relay did not trip. Hence protection scheme is miss-coordinated.
The correct sequence of operation is that the bus section relay (relay 171) must trip first then
the two 33kv incomers of CPF relays delayed by at least 150 millisecond then the two relays
of the primary side of the transformer.
34 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
Figure 3.10 shows the sequence of operation for Line-to-Ground fault on KEYI 11kV feeder
Figure 3.10 The sequence of operation for Line-to-Ground fault on KEYI 11kV feeder
35 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
From figure 3.10, it is clear that the bus-section relay (relay 98) is disabled which means that
the two 11kv bus-bars will be lost if the feeder relay failed to operate .also the earth fault
element of the two 11kv incomers is delayed by 600 milliseconds.
3.5.3.2 Line -To-Ground fault at transmission line between CPF and KEYI
Line -To-Ground fault was simulated at transmission line between CPF and KEYI as shown
in figure 3.11
Figure 3.11 Line -To-Ground fault at transmission line between CPF and KEYI
Figure 3.12 shows the sequence of operation for Line -To-Ground fault at CPF- KEYI line
36 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
From figure 3.12, the earth fault of the sending end relay of the transmission line (Relay 178)
operates instantaneously at Zero millisecond. However, it is clear that the earth fault element
of the bus-coupler relay is disabled and this will cause both transformers to be tripped when
the transmission line relay didn‟t operate. In addition, the earth fault element of the two 33kV
incomers was delayed by 1500 millisecond. This delay at fault current of 1260A will damage
the electrical equipments.
After investigation of the above fault scenarios, we found that the major cause of miss
coordination behavior of the relays was due to the use of the definite minimum time
philosophy.
The operation rules for definite-time-delayed over current relays can be expressed in the
following equation:
2𝑇𝑠
𝑇= 3.1
1+𝑠𝑔𝑛 (𝐼−𝐼𝑆 )
37 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
To enhance the protection scheme performance we must use a more flexible philosophy of
the current- time characteristic such as inverse definite minimum time philosophy.
38 | P a g e
Chapter 3 [Case Study: Baleela Oil-Field Network]
According to IEC and IEEE standards, the characteristic of inverse-time over current relays
can be depicted by the following expression:
𝑪
𝑻= 𝑰
𝜶 3.2
𝑰𝑺
−𝟏
Where:
T: relay operation time
C: constant for relay characteristic, proportional to the time multiplier setting
Is: current setting threshold
I: current detected by relay (after relay filtering), I>Is
α: constant representing inverse-time type, α>0
By assigning different values to α and C, there are different types of inverse characteristics.
Table 3.7 shows the definitions of various types by IEC and IEEE respectively.
α C
Curve Type IEC IEEE IEC IEEE
Standard Inverse (SI) 0.02 0.02 0.14 0.0515
Very Inverse (VI) 1 2 13.5 19.61
Extreme Inverse (EI) 2 2 80 28.2
Long Inverse (LI) 1 - 120 -
39 | P a g e
Chapter 4 [Implementation and Results]
CHAPTER FOUR
4.1 Introduction
This chapter introduces the results obtained from Relay coordination study. and the new
settings will be used to obtain a well coordinated network.
The entire definite-minimum-time (DMT) scheme was replaced with the more flexible
inverse-definite-minimum-time (IDMT) scheme philosophy for first stage of both over-
current and earth fault.
The result is that the new philosophy and settings provide a backup over current and earth
fault system that is streamlined and does not result in some gross miss-operations such as
loss of 33kV feeders in CPF due to a fault on the 11kV bus of JAKE. For all substations, the
pickup settings for earth fault were coordinated by taking thirty percent of the normal full
load current.
40 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.1 The new phase [O/C] settings for JAKE-MOGA path relays
41 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.2 The new phase [O/C] settings for MOGA-CPF path relays
42 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.3 The new phase [O/C] settings for FNE-CPF path relays
43 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.4 The new phase [O/C] settings for KEYI-CPF path relays
44 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.5 New earth fault settings for JAKE up to the secondary of its transformer
45 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.6 New earth fault settings from JAKE primary of the transformer up to CPF
46 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.7 New earth fault settings For MOGA up to secondary of its transformer
47 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.8 New earth fault settings from MOGA primary of the transformer up to CPF
48 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.9 New earth fault settings for FNE up to secondary of its transformer
49 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.10 New earth fault settings from FNE primary of the transformer up to CPF
50 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.11 New earth fault settings from KEYI up to secondary of its transformer
51 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.12 New earth fault settings from KEYI primary of the transformer up to CPF
52 | P a g e
Chapter 4 [Implementation and Results]
4.4.2.9 Settings from CPF primary of its transformer up to 11kV bus section
The coordination is shown in figure 4.11
Figure 4.13 New earth fault settings for CPF primary of its transformer up to 11kV bus
section
53 | P a g e
Chapter 4 [Implementation and Results]
4.5.1 Overview
Now when applying the new settings mentioned in above section into ETAP to simulate the
sequence of operations for the same type of faults as mentioned in Chapter three, the results
showed that almost all the problems associated with the old settings has been resolved and
the network is well coordinated.
Figure 4.14 Three phase fault on JAKE 11kV (CH05 TR7802A) feeder
54 | P a g e
Chapter 4 [Implementation and Results]
The sequence of operation for three phase fault on JAKE 11kV feeder is shown in figure 4.15
Figure 4.15 sequence of operation for a three phase fault on JAKE 11kV feeder
from figure 4.15 it is clearly that the feeder relay (relay 47) was tripped first at Zero second
by instantaneous element followed by the bus section relay (relay 32) delayed after 170
millisecond then the two 11kV incomers (relay 33 & 43) after 370 millisecond. After that the
two relays of the primary side of the transformers (relay 44 & 45) were tripped. Now this is
the correct sequence of operation, also grading margin between relays is maintained above
150 millisecond. Hence, miss-coordination will not occur as demonstrated in section
(3.5.2.1).
From above sequence of operation, the discrimination was conducted correctly which was
not achieved at the old setting as shown in section (3.5.2.1).
55 | P a g e
Chapter 4 [Implementation and Results]
The sequence of operation for three phase fault at MOGA-JAKE transmission line is shown
in figure 4.17
Figure 4.17 sequence of operation for a three phase fault at MOGA-JAKE line
56 | P a g e
Chapter 4 [Implementation and Results]
Comparing figure 4.17 with that of chapter three (figure 3.6), it's clearly that the correct
sequence of operation is now achieved. Also, the grading margin between relays is
maintained above 150 millisecond.
Another point to shed the light on here, is the benefits of using the instantaneous current at
the beginning of the line (or on the transformer primary) to isolate the faults on the line as
quickly as possible. In this case, the instantaneous element enabled relay 250 to trip the line
at Zero seconds.
57 | P a g e
Chapter 4 [Implementation and Results]
The sequence of operation for three phase fault at CPF 33kV bus-bar (B) is shown in figure
4.19
Figure 4.19 sequence of operation for three phase fault at CPF 33kV bus-bar (B)
Comparing this sequence of operation , for three phase fault on CPF 33kV bus-bar (B), with
the old setting, it's obvious that the correct sequence of operation is now achieved. However,
the bus coupler relay (Relay 171) had operated after a long period of time (1.185s) and this is
a situation that needs improving.
One possible and necessary solution is to install bus-bar differential protection on CPF 33kV
bus-bars to isolate this type of fault quickly.
58 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.21 shows the sequence of operation for earth fault on KEYI 11kV feeder
59 | P a g e
Chapter 4 [Implementation and Results]
Figure 4.21 The sequence of operation for Line-to-Ground fault on KEYI 11kV feeder
From figure 4.21 it is clear that the feeder relay (relay 102) tripped instantanously at zero
millisecond followed by the bus-section relay (relay 98) at 170 millisecond then the two 11kv
incomers (relay 97 and relay 107 ) tripped at 340 millisecond.
60 | P a g e
Chapter 4 [Implementation and Results]
4.5.3.2 Line -To-Ground fault at transmission line between CPF and KEYI
Line -To-Ground fault was simulated at transmission line between CPF and KEYI is shown
in figure 4.22
Figure 4.22 Line -To-Ground fault at transmission line between CPF and KEYI
61 | P a g e
Chapter 4 [Implementation and Results]
Figure 3.12 shows the sequence of operation for fault at transmission line between CPF and
KEYI
Figure 4.23 sequence of operation for Line-to-Ground fault on CPF- KEYI transmission
line
From figure 4.2 it is clear that the feeder relay (relay 178) tripped instantanously at zero
millisecond followed by the buscoupler relay (relay 171) at 821 millisecond then the two
33kv incomers (relay 8and relay 10 ) tripped after 1 second.
62 | P a g e
Chapter 4 [Implementation and Results]
4.6 Summery
Now and after this study for all substations the coordination has been achieved as follows:
The coordination of the over current settings starts at far downstream of the JAKE 11
kV feeder relay with IDMT delay curve and minimum time multiplier setting (TMS)
= 0.025.
The next relay is the bus section relay which was coordinated using pickup above the
rated current passing through the secondary side of the transformer, with a TMS=
0.05 , in order to isolate the healthy load from the faulty side.
Then 11 kV incomer relay with pickup above the rated current on low voltage side of
33/11 kV main transformer with a TMS = 0.1. Also 33 kV transformer feeders were
coordinated with a slightly higher pickup than the low voltage side of 33/11 kV main
transformer, but with the same TMS to ensure that the two relays will operate at the
same time in order to completely isolate the main transformer (i.e. reacts as a
differential protection).
Also, instantaneous element was implemented on the high voltage side of 33/11 kV
main transformer as a back-up protection to ensure fast adequate operation of the
relay.
The bus coupler on normal operation is opened, but for worst case scenario it‟s
coordinated with a pickup = 0.4 and TMS = 0.15.
The 33 kV incomer is coordinated with pickup = 0.75 and TMS = 0.2.
Then the sending end of the transmission line is coordinated with a pickup slightly
higher than the receiving end but with the same TMS = 0.2 to isolate both ends of the
line in almost the same time.
An instantaneous element was implemented at the sending end of the transmission
line as a back-up protection to ensure fast adequate operation of the relay.
Then the bus coupler of the 33kv bus bar of MOGA is coordinated with TMS = 0.72.
Then the outgoing is coordinated with pickup = 0.9 for the receiving end and 1.15 for
the sending end with the same TMS= 0.3.
63 | P a g e
Chapter 4 [Implementation and Results]
The earth fault settings were coordinated in the same way as for over-current in TMS
setting, furthermore the pickup settings were coordinated by taking thirty percent
from over-current pickup settings.
This coordination was performed to all substations (KEYI, FNE, MOGA, and JAKE)
except the feeders of the CPF main station because these feeders are directly
connected to the generation side.
In all 11 kV feeders of the CPF main station the pickup was raised up to avoid the
inrush current of the big motors, and the proposed settings is given in Appendix C.
64 | P a g e
Chapter 5 [Conclusion and Recommendations]
CHAPTER FIVE
5 Conclusion
Furthermore, the pickup settings for earth fault were coordinated by taking thirty percent of
the normal full load current. Also, an instantaneous element was performed successfully as a
back-up protection
65 | P a g e
Chapter 5 [Conclusion and Recommendations]
5.3 Recommendations
It‟s recommended to replace the currently installed DMT settings with the new
IDMT settings for both overcurrent and earth faults into all relays at Baleela network.
It‟s recommended to install busbar differential protection at CPF and MOGA 33KV
busbars to isolate the faults on them as quickly as possible. Because both the new and
old settings showed a high operating time for such faults.
Relay Settings coordination for both phase and earth faults in all substations should be re-
assessed on regular basis, because the nature of loads are dynamically changed.
It's recommended that all transformers and transmission lines relays to trip the two
breakers in order to entirely isolate the faulty transformer or transmission line.
It‟s recommended to re-calculate all the spare feeders‟ normal current before they are
connected to any load.
66 | P a g e
References
[2]J. Lewis Blackburn and Thomas J. Domain, “Protective Relaying Principles and
Applications”, Third Edition 2007.
[3] Areva, “Network Protection and Automation Guide”, First edition july 2002.
67 | P a g e
6 Appendix A
68 | P a g e
A.2 X/R Ratio for each transformer
Table A.1 shows X/R ratio for each transformer using the transformer rated MVA and
copper losses.
Table A. 2 X/R ratio for each transformer using the transformer rated MVA and copper
losses
69 | P a g e
A.3 Transmission Lines Data
Table A.3 shows transmission lines data
Table A. 3 Transmission Lines Data
70 | P a g e
Appendix B
7 OLD SETTINGS
BH04: 150/1 D I > 0.5 0.02 I >>0.5𝐼𝑛 0s 50 D I> 0.05 I >> 0.2 𝐼𝑒 0s Tamco
1#RMUFeed M 𝐼𝑛 /1 M 0.1𝐼𝑒 MicomP
er T I >>>0.6𝐼𝑛 0s T I>>0.2 𝐼𝑒 0s 123
SI
71 | P a g e
BH05: TR- 100/1 D I> 2 I >>0.98 𝐼𝑛 0. 50 ID I> 0.5 I > 0.4 𝐼𝑒 0s Tamco
8802A M 0.76𝐼𝑛 3s /1 M 0.2𝐼𝑒 Micom
T I >>>3.01 𝐼𝑛 T P123
0s SI
BH12: TR-8802B 100/ DM I> 0.02 I >>0.98𝐼𝑛 0.3 s 50/1 DMT I> 0.5 I > 0.4 𝐼𝑒 0s Tamco
1 T 0.76 𝐼𝑛 0.2𝐼𝑒 Micom
I >>>3.01𝐼𝑛 0s P123
BH13: Spare 100/ DM I> 0.025 I >>1.08𝐼𝑛 0s 50/1 DMT I> 0.025 I > 0.4 𝐼𝑒 0s Tamco
Feeder 1 T 0.75𝐼𝑛 0.2𝐼𝑒 Micom
I >>>16.41𝐼𝑛 0s P123
BH14: Spare 40/1 DM I> 0.025 I >>1.08𝐼𝑛 0s 50/1 DMT I> 0.025 I > 0.4 𝐼𝑒 0s Tamco
Feeder T 0.75 𝐼𝑛 0.2𝐼𝑒 Micom
I >>>16.40𝐼𝑛 0s P123
BH15: 1# RMU 150/ DM I > 0.4 0.025 I >>0.6𝐼𝑛 0s 50/1 DMT I> 0.025 I > 0.4 𝐼𝑒 0s Tamco
Feeder 1 T 𝐼𝑛 0.2𝐼𝑒 Micom
I >>>0.9𝐼𝑛 0s P123
BH16: Spare 100/ DM I> 0.025 I >>4.43𝐼𝑛 0s 50/1 DMT I> 0.025 I > 0.4 𝐼𝑒 0s Tamco
Feeder 1 T 0.75 𝐼𝑛 0.2𝐼𝑒 Micom
I >>5.01𝐼𝑛 0s P123
72 | P a g e
BH07: 1# 200/1 DMT I> 2 I >>1.5𝐼𝑛 0.5 s 200/1 DMT I> 0.1 s. I >> 0.15 𝐼𝑒 0.6 s Tamco
Incomer 0.8 𝐼𝑛 0.1𝐼𝑒 I >>> 0.4 𝐼𝑒 0.1 s Micom
I >>>2.5𝐼𝑛 0.1s P121
BH10: 2# 200/1 DMT I> 2 I >>1.5𝐼𝑛 0.5 s 200/1 DMT Disabled Tamco
Incomer 0.8 𝐼𝑛 Micom
I >>>2.5𝐼𝑛 0.1s P121
6# Bus 150/1 DMT I> 0.125 Disabled 150/1 Disabled Disabled Schneider
coupler 0.4𝐼𝑛 P143
73 | P a g e
Table B. 6 33kV Incomers
4# 150/1 DMT I> 0.15 Disabled 50/1 DMT I> 0.15 Disabled Schneider
Incoming 0.5𝐼𝑛 1.14𝐼𝑒 P143
1
7# 150/1 DMT I> 0.15 Disabled 50/1 DMT I> 0.15 Disabled Schneider
Incoming 0.5𝐼𝑛 1.14𝐼𝑒 P143
2
BH07: 1# 200/ DMT I 0.0 Disabled 40/1 DMT I> 0.1 Disabled Tamco
Incomer 1 >0.85𝐼𝑛 75 0.8𝐼𝑒 P127
BH10: 2# 200/ DMT I> 0.0 Disabled 40/1 DMT I> 0.1 Disabled Tamco
Incomer 1 0.85𝐼𝑛 75 0.8 𝐼𝑒 P127
BH08: Bus 200/ DMT I> 0.0 Disabled 200/ Disabled Tamco
section 1 0.6𝐼𝑛 5 1 P127
74 | P a g e
B.2 OLD SETTINGS – MOGASUBSTATION
AH11: TR-2820B 100/ DMT I > 0.5 2 I >>1𝐼𝑛 0.3 s 50/1 DMT I > 0.2 0.2 I > 0.4 𝐼𝑒 0s Tamco
Feeder 1 𝐼𝑛 𝐼𝑒 Micom
P123
AH12: RMU-2830B 100/ DMT I> 0.5 I >>0.6 𝐼𝑛 0s 50/1 DMT I > 0.2 0.025 I > 0.4 𝐼𝑒 0s Tamco
1 0.6𝐼𝑛 𝐼𝑒 Micom
I >>>0.6 𝐼𝑛 0s P123
75 | P a g e
Overcurrent protection [50/51] Earth protection [50N/51N] Relay
Type
Feeder
C.T. Delay Current Time Instantaneou Ti C.T Delay Current Time Instantaneous Tim
ratio curve setting settin s protection me . curve setting setting protection e
type g rati type
(DMT) o (DMT)
AH01: Spare Feeder 40/1 DMT I > 0.5𝐼𝑛 2 I >>0.65 𝐼𝑛 0.3 50/ DMT I > 0.2 0.2 I > 0.4 𝐼𝑒 0s Tamco
s 1 𝐼𝑒
I >>>6.25 𝐼𝑛 Micom
0s P123
AH02: RMU-2830A 100/ DMT I > 0.4𝐼𝑛 0.2 I >>0.5 𝐼𝑛 0s 50/ DMT I > 0.1 0.05 I > 0.2 𝐼𝑒 0s Tamco
1 1 𝐼𝑒
I >>>0.6 𝐼𝑛 0s Micom
P123
AH03: Spare Feeder 40/1 DMT I > 0.5𝐼𝑛 2 I >>0.65 𝐼𝑛 0.3 50/ DMT I > 0.2 0.2 I > 0.4 𝐼𝑒 0s Tamco
s 1 𝐼𝑒
I >>>6.25 𝐼𝑛 Micom
0s P123
AH04: TR-2820A 100/ DMT I> 2 I >>1 𝐼𝑛 0.3 50/ DMT I > 0.2 0.2 I >> 0.4 𝐼𝑒 0s Tamco
Feeder 1 0.5 𝐼𝑛 s 1 𝐼𝑒
Micom
P123
76 | P a g e
Table B. 11 11kV Bus-section & 11kV two incomers Directional Protection [the directional Element is disabled =
non-directional]
AH06: 150/1 DMT I 0.075 Disabled 30/1 DMT I> 0.1 Disabled Tamco
1# >0.9𝐼𝑛 1.0 𝐼𝑒 P127
Incomer
AH09: 150/1 DMT I 0.075 Disabled 30/1 DMT I> 0.1 Disabled Tamco
2# >0.9 𝐼𝑛 1.0𝐼𝑒 P127
Incomer
77 | P a g e
Transformer Overcurrent protection [50/51] Earth protection [50N/51N] Relay
feeders Type
C.T. Delay Current Time Instantaneous Time C.T. Delay Current Time Instantaneous Time
ratio curve setting setting protection ratio curve setting setting protection
type (DMT) type (DMT)
3# 75/1 DMT I> 0.1 Disabled 50/1 DMT I> 0.025 Disabled Schneider
Transformer 0.6𝐼𝑛 0.4𝐼𝑒 P142
(TR 7801A)
10# 75/1 DMT I> 0.1 Disabled 50/1 DMT I> 0.025 Disabled Schneider
Transformer 0.6𝐼𝑛 0.4𝐼𝑒 P142
(TR 7801B)
78 | P a g e
Table B. 14 33kV incomers
5# 100/1 DMT I> 0.2 Disabled 50/1 DMT I> 0.2 Disabled Schneider
Incoming 0.75𝐼𝑛 1.32𝐼𝑒 P143
8# 100/1 DMT I> 0.2 Disabled 50/1 DMT I> 0.2 Disabled Schneider
Incoming 0.75𝐼𝑛 1.32𝐼𝑒 P143
2# JAKE 1 100 DM I> 0.175 Disabled 50/1 DMT I> 0.175 Disabled Schneider
/1 T 0.75𝐼𝑛 1.14𝐼𝑒 P123
11# JAKE 2 100 DM I> 0.175 Disabled 50/1 DMT I> 0.175 Disabled Schneider
/1 T 0.75 𝐼𝑛 1.14𝐼𝑒 P123
79 | P a g e
B.3 OLD SETTINGS – JAKE SUBSTATION
Feeder
C.T. Delay Current Time Instantaneous Time C.T. Delay Current Time Instantaneous Time
ratio curve setting setting protection ratio curve setting setting protection
type type
(DMT) (DMT)
CH01: 50/1 DMT I >0.8 0.200 I >>1 𝐼𝑛 0s 50/1 DMT I > 0.1 0.050 I>> 0.2 𝐼𝑒 0s Tamco
Spare 𝐼𝑛 𝐼𝑒 I>>> 2 𝐼𝑒 Micom
Feeder I >>>1.2 𝐼𝑛 0s P123
(OGM2)
CH02: 100/1 DMT I> 0.200 I >>0.5 𝐼𝑛 0s 50/1 DMT I > 0.1 0.050 I>> 0.2 𝐼𝑒 0s Tamco
Spare 0.4𝐼𝑛 𝐼𝑒 I>>> 0.2 𝐼𝑒 Micom
Feeder I >>>0.6 𝐼𝑛 0s P123
(Camp)
CH03: 40/1 DMT I > 2 𝐼𝑛 2 I >>3𝐼𝑛 0.3 s 50/1 DMT I > 0.2 0.500 I >> 0.4 𝐼𝑒 0s Tamco
P- 𝐼𝑒 Micom
7603C I >>>7𝐼𝑛 0s P123
Feeder
Water
Injection
Pump C
CH04: 40/1 DMT I > 2𝐼𝑛 2 I >>3𝐼𝑛 0.3 s 50/1 DMT I > 0.2 0.500 I > 0.4 𝐼𝑒 0s Tamco
P- 𝐼𝑒 MicomP123
7603B I >>>7 𝐼𝑛 0
Feeder s
Water
Injection
Pump B
CH05: 100/1 DMT I > 0.8 0.025 I >>1.3𝐼𝑛 0.1 s 50/1 DMT I > 0.2 0.025 I > 0.4 𝐼𝑒 0s Tamco
TR- 𝐼𝑛 𝐼𝑒 Micom
7802A I >>>3𝐼𝑛 0s P123
80 | P a g e
Table B.17 11kV Feeders on 2nd Busbar
CH12: TR- 100 DMT I > 0.8 0.02 I >>1.3 𝐼𝑛 0.1 s 50/ DMT I > 0.2 0.02 I > 0.4 𝐼𝑒 0s Tamco
7802B /1 𝐼𝑛 5 1 𝐼𝑒 5 Micom
I >>>3 𝐼𝑛 0s P123
CH13: P-7603A 40/ DMT I > 2𝐼𝑛 2 I >>3 𝐼𝑛 0.3s 50/ DMT I > 0.2 0.50 I >> 0.4 𝐼𝑒 0s Tamco
Feeder Water 1 1 𝐼𝑒 0 Micom
Injection Pump I >>>7 𝐼𝑛 0s P123
A
CH14: Spare 40/ DMT I> 0.02 I >>3 𝐼𝑛 0.1 s 50/ DMT I> 0.02 I > 0.4 𝐼𝑒 0s Tamco
Feeder 1 1.2𝐼𝑛 5 1 0.2𝐼𝑒 5 Micom
I >>>5 𝐼𝑛 0s P123
CH15: Spare 40/ DMT I> 0.02 I >>3 𝐼𝑛 0.1 s 50/ DMT I> 0.02 I > 0.4 𝐼𝑒 0s Tamco
Feeder 1 1.2𝐼𝑛 5 1 0.2𝐼𝑒 5 Micom
I >>>5 𝐼𝑛 0s P123
CH16: Spare 40/ DMT I> 0.02 I >>3 𝐼𝑛 0.1 s 50/ DMT I> 0.02 I > 0.4 𝐼𝑒 0s Tamco
Feeder 1 1.2𝐼𝑛 5 1 0.2𝐼𝑒 5 Micom
I >>>5 𝐼𝑛 0s P123
CH17: Spare 40/ DMT I> 0.02 I >>2 𝐼𝑛 0.1 s 50/ DMT I > 0.1 0.05 I >> 0.2 𝐼𝑒 0s Tamco
Feeder 1 0.8𝐼𝑛 5 1 𝐼𝑒 0 Micom
I >>>3 𝐼𝑛 0s I >>> P123
(OGM1) 0.2 𝐼𝑒
81 | P a g e
Table B. 18 11kV Incomers
C.T. Delay Current Time Instantaneous Time C.T. Delay Current Time Instantaneous Time
ratio curve setting setting protection ratio curve setting setting protection
type (DMT) type
(DMT)
2# 75/1 DMT I> 0.1 Disabled 50/1 DMT I> 0.025 Disabled Schneider
Transformer 0.6𝐼𝑛 0.4𝐼𝑒 P142
(TR 7801A)
2# 75/1 DMT I> 0.1 Disabled 50/1 DMT I > 0.4 0.025 Disabled Schneider
Transformer 0.6𝐼𝑛 𝐼𝑒 P142
(TR 7801B)
82 | P a g e
Table B. 20 33kV Bus coupler
Bus 150/1 DMT I> 0.125 Disabled 150/1 Disabled Disabled Schneider
coupler 0.4 𝐼𝑛 P143
CH07: 1# 100/1 DMT I> 0.15 Disabled 50/1 DMT I> 0.15 Disabled Schneider
Incomer 0.75𝐼𝑛 1.14𝐼𝑒 P143
CH07: 2# 100/1 DMT I> 0.15 Disabled 50/1 DMT I 0.15 Disabled Schneider
Incomer 0.75𝐼𝑛 >1.14𝐼𝑒 P143
83 | P a g e
Table B. 22 11 kV Bus-section & 11kV Two Incomers Directional Protection [the directional
Element is disabled = non-directional]
CH07: 150/1 DMT I 0.075 Disabled 30/1 DMT I 0.1 Disabled Tamco
1# >0.9𝐼𝑛 >1.0𝐼𝑒 P127
Incomer
CH10: 150/1 DMT I 0.075 Disabled 30/1 DMT I> 0.1 Disabled Tamco
2# >0.9𝐼𝑛 1.0 𝐼𝑒 P127
Incomer
84 | P a g e
B.4 OLD SETTINGS – KEYI SUBSTATION
C.T. Delay Current Time Instantaneous Time C.T. Delay Current Time Instantaneous Time
ratio curve setting setting protection ratio curve setting setting protection
type type
(DMT) (DMT)
DH01: K13 40/1 DMT I> 0.200 I >>0.9𝐼𝑛 0s 50/1 DMT I > 0.1 0.05 I >>0.2 𝐼𝑒 0s Tamco
RMU 0.5𝐼𝑛 𝐼𝑒 Micom
I >>>1.2𝐼𝑛 0s P123
DH02: 100/1 DMT I> 0.200 I >>0.5 𝐼𝑛 0s 50/1 DMT I > 0.1 0 I >>0.2 𝐼𝑒 0s Tamco
OGM1 + 0.3𝐼𝑛 𝐼𝑒 Micom
CAMP + I >>>0.5 𝐼𝑛 0s P123
Unloading
Pumps
DH03: P- 40/1 DMT I> 0.200 I >>2.1 𝐼𝑛 0.1 s 50/1 IDMT I > 0.2 0.500 I >> 0.4 𝐼𝑒 0s Tamco
6603C 1.2𝐼𝑛 SI 𝐼𝑒 Micom
Feeder I >>>3 𝐼𝑛 0s P123
Water
injection
Pump C
DH04: P- 40/1 DMT I >1.2 0.200 I >>2.1 𝐼𝑛 0s 50/1 DMT I > 0.2 0.500 I >> 0.4 𝐼𝑒 0s Tamco
7603B 𝐼𝑛 𝐼𝑒 Micom
Feeder I >>>3 𝐼𝑛 0s P123
Water
injection
Pump B
DH05: TR- 100/1 DMT I> 0.200 I>>0.79 𝐼𝑛 0.3 s 50/1 DMT I> 0.500 I >> 0.4 𝐼𝑒 0s Tamco
7802A 0.5 𝐼𝑛 0.2 𝐼𝑒 Micom
I>>>4.49 𝐼𝑛 0s P123
85 | P a g e
Table B. 24 11kV Feeders on 2nd Busbar
DH12: TR-6802B 100/ DM I> 0.2 I>>0.84 3s 5 DMT I> 0.50 I >> 0s Tamco
1 T 0.5𝐼𝑛 𝐼𝑛 0/ 0.2𝐼𝑒 0 0.4 𝐼𝑒 Micom
0s 1 P123
I>>>4.4
9 𝐼𝑛
DH13: P-6603A 40/1 DM I 0.02 I>>2 0.1 s 5 DMT I > 0.2 0.02 I >> 0s Tamco
Feeder Water T >1.2𝐼𝑛 5 . 1 𝐼𝑛 0/ 𝐼𝑒 5 0.4 𝐼𝑒 Micom
injection Pump A 0s 1 P123
I>>>3
𝐼𝑛
DH14: Fire Fighter 40/1 DM I> 4 I>>5 𝐼𝑛 0. 5 DMT I> 0.50 I >> 0s Tamco
Pump T 1.2 𝐼𝑛 3 0/ 0.2 𝐼𝑒 0 0.4 𝐼𝑒 Micom
I>>>7 s 1 P123
𝐼𝑛
DH15: OGM 2-3- 100/ DM I 0.2 I>>0.5 0s 5 DMT I> 0.05 I >> 0s Tamco
4-5 1 T >0.3 𝐼𝑛 𝐼𝑛 0/ 0.1 𝐼𝑒 0.2 𝐼𝑒 Micom
0s 1 P123
I>>>0.5
𝐼𝑛
DH16: Spare 40/1 DM I 0.02 I>>2 𝐼𝑛 0.1 s 5 DMT I> 0.02 I> 0s Tamco
Feeder (Perkins) T >1.24 5 0/ 0.2𝐼𝑒 5 0.4 𝐼𝑒 Micom
𝐼𝑛 I>>>3 0s 1 P123
𝐼𝑛
86 | P a g e
Table B. 25 11kV Incomers
DH07: 1# 150/ DMT I>1.0 2 I>>2. 𝐼𝑛 600 150/ DMT I> 1.15 I >> 0.2 𝐼𝑒 0.6 s Tamco
Incomer 1 0𝐼𝑛 ms 1 0.15 𝐼𝑒 Micom
I>>>3.5 𝐼𝑛 P121
0
ms
DH11: 2# 150/ DMT I>1.0 2 I>>2. 𝐼𝑛 600 150/ DMT I> 1.15 I >> 0.2 𝐼𝑒 0.6 s Tamco
Incomer 1 0𝐼𝑛 ms 1 0.15 𝐼𝑒 Micom
I>>>3.5 𝐼𝑛 P121
0
ms
2# 75/1 DMT I> 0.1 Disabled 50/1 DMT I> 0.12 Disabled Schneider
Transformer 0.6 𝐼𝑛 0.3 𝐼𝑒 P142
(TR-6801A)
9# 75/1 DMT I> 0.1 Disabled 50/1 DMT I> 0.12 Disabled Schneider
Transformer 0.6𝐼𝑛 0.3 𝐼𝑒 P142
(TR-6801B)
87 | P a g e
Table B. 27 33kV Bus coupler
6# Bus 150/1 DMT I 0.125 Disabled 150/1 DMT I> 0.02 s Disabled Schneider
coupler >0.4𝐼𝑛 0.1 𝐼𝑒 P143
4# Incoming 150/ DMT I> 0.15 Disabled 50/1 DMT I> 0.8 Disabled Schneider
1 1 0.5𝐼𝑛 0.9𝐼𝑒 P143
7# Incoming 150/ DMT I> 0.15 Disabled 50/1 DMT I> 0.8 Disabled Schneider
2 1 0.5 𝐼𝑛 0.9𝐼𝑒 P143
88 | P a g e
Table B. 29 11kV Bus-section & 11kV Two Incomers Directional Protection [the
directional Element is disabled = non-directional]
C.T. Dela Curren Tim Instantane Tim C.T. Delay Current Time Instantaneous Time
ratio y t e ous e ratio curve setting setting protection
curv setting setti protection type
e ng (DMT) (DMT)
type
Disabled
89 | P a g e
B.5 OLD SETTINGS – CPF SUBSTATION
C.T. Delay Current Tim Instantaneou Ti C.T. Delay Current Time Instantane Ti
ratio curve setting e s protection me ratio curve setting setti ous me
type setti type ng protection
ng (DMT)
(DMT)
01: TR-1803A 100/ DMT I> 0.50 I >>2𝐼𝑛 0.1 50/5 DMT I 0.1 s I >>0.5𝐼𝑒 0.1 Alstom
5 0.85𝐼𝑛 0 s >0.25𝐼𝑒 s Micom
I >>> 3.8 𝐼𝑛 I >>> 1 𝐼𝑒 P123
0s 0s
04: TR-1805A 100/ DMT I > 1 𝐼𝑛 0.50 I >> 2 𝐼𝑛 0.1 100/ DMT I> 0.50 I >>0.25𝐼𝑒 0.1 Alstom
5 0 s 5 0.125𝐼𝑒 0 s Micom
I >>> 4 𝐼𝑛 I >>> 0.5 P122
0s 𝐼𝑒 0s
10: TR-1801B 100/ DMT I > 1 𝐼𝑛 0.50 I >> 2 𝐼𝑛 0.1 100/ DMT I> 0.50 I 0.1 Alstom
5 0 s 5 0.125 𝐼𝑒 0 >>0.25 𝐼𝑒 s Micom
I >>> 4 𝐼𝑛 P122
0s I >>> 0.5 0s
𝐼𝑒
13: TR-1801C 100/ DMT I >1.5 0.3 I >> 3 𝐼𝑛 0.1 50/5 DMT I >.4𝐼𝑒 0.07 I >>0.6𝐼𝑒 0.1 AREVA
5 𝐼𝑛 s 5 s MicomP
I >>> 1.2 122
0s 𝐼𝑒 0s
I >>> 6 𝐼𝑛
13: TR-1803B 100/ DMT I >1𝐼𝑛 0.50 I >> 2 𝐼𝑛 0.1 50/5 DMT I 0.50 I >>0.5𝐼𝑒 0.1 Alstom
5 0 s >0.25𝐼𝑒 0 s Micom
I >>> 4 𝐼𝑛 I >>> 1 𝐼𝑒 P123
0s 0s
15: Initial 100/ DMT I > 3𝐼𝑛 0.510 I >> 6 𝐼𝑛 0.1 50/5 I 0.075 I>>1.3 0.1s Alstom
substation -2 5 s DMT >0.67 𝐼𝑒 Micom
I >>> NO 𝐼𝑒 P122
0s I >>>
NO
16: RMU-2 200/ DMT I > 0.8 1.00 I >> 1.25 𝐼𝑛 0.3 200/ DMT I> 0.30 I >>0.2𝐼𝑒 0.1 Alstom
Micom
90 | P a g e
5 𝐼𝑛 I >>> 2 𝐼𝑛 s 5 0.1𝐼𝑒 0 I >>> 0.3 s P123
𝐼𝑒
0s 0s
18: FULA 200/ DMT I > 0.8 2.00 I >> 1.25 𝐼𝑛 0.1 50/5 DMT I > 0.25 0.30 I >> 0.4𝐼𝑒 0.1 Alstom
CENTRE -1-1 5 𝐼𝑛 s 𝐼𝑒 0 s Micom
& 1-2 I >>>2 𝐼𝑛 I P123
0.1 >>>0.8𝐼𝑒 0s
s
19: RMU-1 200/ DMT I > 0.8 1.00 I >> 1.25 𝐼𝑛 0.3 200/ DMT I> 0.30 I >>0.2 𝐼𝑒 0.1 Alstom
5 𝐼𝑛 s 5 0.1𝐼𝑒 0 s Micom
I >>> 2 𝐼𝑛 I >>> 0. 𝐼𝑒 P123
0s 0s
19: TR-1801E 100/ DMT I > 0.8 0.07 I >> 2 𝐼𝑛 0.1 50/5 DMT I > 0.25 0.07 I >>0.5𝐼𝑒 0.1 AREVA
5 𝐼𝑛 5 I >>>4 In s 𝐼𝑒 5 s MicomP
I >>> 1 𝐼𝑒 122
0s 0s
I >>> 4 𝐼𝑛
15: Initial The relay is not working and the switchgear is OFF
substation -2
TR-1801F 100/ DMT I > 0.8 0.07 I >> 2 𝐼𝑛 0.1 50/1 DMT I> 0.07 I >>0.5𝐼𝑒 0.1 AREVA
1 𝐼𝑛 5 s 0.25𝐼𝑒 5 s Micom
I >>> 4 𝐼𝑛 I >>> 1 𝐼𝑒 P122
0s 0s
TR-1801D 100/ DMT I > 1.5 0.3 I >> 3 𝐼𝑛 0.1 50/1 DMT I > 0.4 𝐼𝑒 0.07 I >>0.6𝐼𝑒 0.1 AREVA
1 𝐼𝑛 s 5 s Micom
I >>> 6 𝐼𝑛 I >>> 1.2 P122
0s 𝐼𝑒 0s
91 | P a g e
Table B. 31 11Kv Substation New Added Feeders
01: Spare Feeder 200 DM I 0.07 I >>1.5𝐼𝑛 0.1 50/1 DM I >0.25 0.07 I >>0.8𝐼𝑒 0.1 Tamco
/1 T >0.73 5 s T 𝐼𝑒 5 s Micom
𝐼𝑛 P141
02: Spare Feeder 300 DM I > 0.73 0.07 I >> 1.2 𝐼𝑛 0.1 50/1 DM I > 0.25 0.07 I >> 0.5 𝐼𝑒 0.1 Tamco
/1 T 𝐼𝑛 5 s T 𝐼𝑒 5 s Micom
I >>> 7.4 𝐼𝑛 P142
0.1
s
04: TR-1807A 150 DM I >0.65 0.07 I >>2𝐼𝑛 0.1 50/1 DM I > 0.25 0.07 I >>0.5 𝐼𝑒 0.1 Tamco
(AGR) /1 T 𝐼𝑛 5 s T 𝐼𝑒 5 s Micom
P142
05: Spare Feeder 300 DM I > 0.73 0.07 I >> 1 𝐼𝑛 0.1 50/1 DM I > 0.25 0.07 I >> 0.5 𝐼𝑒 0.1 Tamco
/1 T 𝐼𝑛 5 s T 𝐼𝑒 5 s Micom
P142
06: WIP Pump 75/ DM I 0.07 I >>4𝐼𝑛 0.1 50/1 DM I >0.25 0.07 I >>0.5 𝐼𝑒 0.1 Tamco
1605A 1 T >2.5𝐼𝑛 5 s T 𝐼𝑒 5 s Micom
P142
07: WIP Pump 75/ DM I 0.07 I >>4𝐼𝑛 0.1 50/1 DM I >0.25 0.07 I >> 0.5 𝐼𝑒 0.1 Tamco
1605B 1 T >2.5𝐼𝑛 5 s T 𝐼𝑒 5 s Micom
P142
08: Spare Feeder 300 DM I > 0.5 0.07 I >>1 𝐼𝑛 0.1 50/1 DM I > 0.25 0.07 I >> 0.5 𝐼𝑒 0s Tamco
/1 T 𝐼𝑛 5 s T 𝐼𝑒 5 Micom
P141
09: Spare Feeder 400 DM I >1.25 0.07 I >> 1.4 𝐼𝑛 0.1 50/1 DM I > 0.25 0.07 I >> 0.5 𝐼𝑒 0s Tamco
(PSI-2 Incoming /1 T 𝐼𝑛 5 s T 𝐼𝑒 5 Micom
Line) I >>> 1.6 𝐼𝑛 P142
0s
16: Spare Feeder 300 DM I > 0.73 0.07 I >> 1.5𝐼𝑛 0.1 50/1 DM I > 0.25 0.07 I >> 0.5 𝐼𝑒 0s Tamco
/1 T 𝐼𝑛 5 s T 𝐼𝑒 5 Micom
P142
92 | P a g e
17: Spare Feeder 300 DM I > 0.73 0.07 I >> 1 𝐼𝑛 50/1 DM I > 0.25 0.07 I >> 0.5 𝐼𝑒 0.1 Tamco
/1 T 𝐼𝑛 5 T 𝐼𝑒 5 s Micom
P141
19: TR-1807B 150 DM I > 0.65 0.07 I >> 2 𝐼𝑛 0.1 50/1 DM I > 0.25 0.07 I >>0.5 𝐼𝑒 0.1 Tamco
/1 T 𝐼𝑛 5 s T 𝐼𝑒 5 s Micom
P142
20: Spare Feeder 300 DM I > 0.73 0.07 I >> 1.08𝐼𝑛 0.1 50/1 DM I > 0.25 0.07 I >> 0.5 𝐼𝑒 0s Tamco
/1 T 𝐼𝑛 5 s T 𝐼𝑒 5 Micom
P142
21: Spare Feeder 200 DM I > 0.73 0.07 I >> 1.5𝐼𝑛 0.1 50/1 DM I > 0.25 0.07 I >> 0.5 𝐼𝑒 0s Tamco
/1 T 𝐼𝑛 5 s T 𝐼𝑒 5 Micom
P141
22: WIP Pump 75/ DM I 0.07 I >> 4𝐼𝑛 0.1 50/1 DM I >0.25 0.07 I >> 0.5 𝐼𝑒 0.1 Tamco
1605C 1 T >2.5𝐼𝑛 5 s T 𝐼𝑒 5 s Micom
P142
23: Spare Feeder 100 DM I > 0.73 0.07 I >> 1.08𝐼𝑛 0.1 50/1 DM I > 0.25 0.07 I >> 0.5 𝐼𝑒 0.1 Tamco
/1 T 𝐼𝑛 5 s T 𝐼𝑒 5 s Micom
P142
24: Spare Feeder 400 DM I > 1.25 0.07 I >> 1.4 𝐼𝑛 0.1 50/1 DM I > 0.25 0.07 I >> 0.5 𝐼𝑒 0.1 Tamco
(PSI-1 Incoming /1 T 𝐼𝑛 5 s T 𝐼𝑒 5 s Micom
Line) I >>> 1.6 𝐼𝑛 P142
0s
93 | P a g e
Table B. 32 11 kV Bus-section & 11 kV Transformer feeders
03: 800/1 DMT I> 0.275 Disabled 50/1 DMT I >1 𝐼𝑒 0.025 Disabled Tamco
Transformer 0.66𝐼𝑛 Micom
(TR-1806A) P142
18: 800/1 DMT I> 0.275 Disabled 50/1 DMT I > 1 𝐼𝑒 0.025 Disabled Tamco
Transformer 0.66𝐼𝑛 Micom
(TR-1806A) P142
DH08: Bus 1500/1 DMT I> 0.3 Disabled 50/1 Disabled Tamco
section 0.36𝐼𝑛 Micom
P143
Table B. 33 33 kV Transformer
Feeders
250/1 DMT I 0.25 Disabled 250/1 DMT I> 0.275 Disabled AREVA
>0.7 0.31 P142
𝐼𝑛 𝐼𝑒
250/1 DMT I 0.25 Disabled 250/1 DMT I > 0.31 0.275 Disabled AREVA
>0.7 P142
𝐼𝑛 𝐼𝑒
94 | P a g e
Table B. 34 11 kV Bus-section & 11 kV Transformer
feeders
03: 800/1 DMT I> 0.275 Disabled 50/1 DMT I >1 𝐼𝑒 0.025 Disabled Tamco
Transformer 0.66𝐼𝑛 Micom
(TR-1806A) P142
18: 800/1 DMT I> 0.275 Disabled 50/1 DMT I > 1 𝐼𝑒 0.025 Disabled Tamco
Transformer 0.66𝐼𝑛 Micom
(TR-1806A) P142
DH08: Bus 1500/1 DMT I> 0.3 Disabled 50/1 Disabled Tamco
section 0.36𝐼𝑛 Micom
P143
Table B. 35 33 kV Transformer
Feeders
250/1 DMT I 0.25 Disabled 250/1 DMT I> 0.275 Disabled AREVA
>0.7 0.31 P142
𝐼𝑛 𝐼𝑒
250/1 DMT I 0.25 Disabled 250/1 DMT I > 0.31 0.275 Disabled AREVA
>0.7 P142
𝐼𝑛 𝐼𝑒
95 | P a g e
Table B. 36 33kVBustie
H9: 200/1 DMT I> 0.225 Disabled 200/1 Disabled Disabled AREVA
Bus 0.85𝐼𝑛 P143
coupler
Table B. 37 33 kV outgoings
H1: FNE 1 150/ DMT I> 0.17 I >> 4𝐼𝑛 0s 50/1 DMT I> 0.175 Disabled Areva
1 0.5𝐼𝑛 5 1.14𝐼𝑒 P123
H3: KEYI 1 100/ DMT I > 0.75 0.17 I >> 4𝐼𝑛 0s 50/1 DMT I > 0.2𝐼𝑒 0.1 I > 0.25𝐼𝑒 0s Areva
1 𝐼𝑛 5 P123
H5: MOGA 150/ DMT I > 0.5 0.22 I >> 4𝐼𝑛 0s 50/1 DMT I> 0.225 Disabled Areva
1 1 𝐼𝑛 5 1.32𝐼𝑒 P123
H15: KEYI 100/ DMT I > 0.75 0.17 I >> 4𝐼𝑛 0s 50/1 DMT I > 0.2𝐼𝑒 0.1 I > 0.25𝐼𝑒 0s Areva
2 1 𝐼𝑛 5 P123
H13: 150/ DMT I > 0.5 0.22 I >> 4𝐼𝑛 0s 50/1 DMT I> 0.225 Disabled Areva
MOGA 2 1 𝐼𝑛 5 1.32𝐼𝑒 P123
H17: FNE 2 150/ DMT I > 0.5 0.17 I >> 4𝐼𝑛 0s 50/1 DMT I> 0.175 Disabled Areva
1 𝐼𝑛 5 1.14𝐼𝑒 P123
96 | P a g e
8 Appendix C
9 NEW SETTING
C.1 NEW RELAY COORDINATION SETTINGS – FNE
SUBSTATION
BH01: Spare Feeder 40/1 IDMT Disabled 50/1 IDMT Disabled Tamco
SI SI
Micom
P123
BH02: Spare Feeder 150/1 IDMT Disabled 50/1 IDMT Disabled Tamco
SI SI
Micom
P123
BH03: Spare Feeder 150/1 IDMT Disabled 50/1 IDMT Disabled Tamco
SI SI
Micom
P123
BH04: 1# 150/1 IDMT I >0.5𝐼𝑛 0.025 I >>1𝐼𝑛 0s 50/1 IDMT I > 0.1 0.025 I >> 0.2 𝐼𝑒 0s Tamco
RMUFeeder SI SI 𝐼𝑒
Micom
P123
BH05: TR-8802A 100/1 IDMT I > 0.2 0.025 I >>0.5𝐼𝑛 0s 50/1 IDMT I> 0.025 I >>0.8𝐼𝑒 0s Tamco
SI 𝐼𝑛 SI 0.4𝐼𝑒
Micom
P123
97 | P a g e
Table C.2 11kV FEEDERS on 2nd Busbar
BH12: TR-8802B 100/ IDM I > 2.5 0.025 I >> 5 𝐼𝑛 0s 50/1 IDM I> 0.025 I >>0.7𝐼𝑒 0s Tamco
1 T SI 𝐼𝑛 T SI 0.35𝐼𝑒 Micom
P123
BH13: Spare Feeder 100/ IDM Disabled 50/1 IDM Disabled Tamco
1 TSI T SI Micom
P123
BH14: Spare Feeder 40/1 IDM Disabled 50/1 IDM Disabled Tamco
SI T SI Micom
P123
BH16: Spare Feeder 100/ IDM Disabled 50/1 IDM Disabled Tamco
1 TSI T SI Micom
P123
BH07: 1# 200/1 IDMT I> 0.075 Disabled 200/1 IDMT I > 0.3𝐼𝑒 0.15 Disabled Tamco
Incomer SI 1.65𝐼𝑛 SI Micom
P121
BH10: 2# 200/1 IDMT I> 0.075 Disabled 200/1 IDMT I > 0.3𝐼𝑒 0.15 Disabled Tamco
Incomer SI 1.65𝐼𝑛 SI Micom
P121
98 | P a g e
Table C.4 33kV Transformer Feeders
2# TR-A 75/1 IDMT I> 0.075 I >> 9 𝐼𝑛 0s 50/1 IDMT I> 0.025 I >> 1.05𝐼𝑛 0 Schneider
SI 1.6𝐼𝑛 SI 0.35𝐼𝑒 P142
9# TR-B 75/1 IDMT I> 0.075 I >> 9 𝐼𝑛 0s 50/1 IDMT I> 0.075 I >> 1.05𝐼𝑛 0 Schneider
SI 1.6𝐼𝑛 SI 0.35𝐼𝑒 P142
Bus Coupler Overcurrent protection [50/51] Earth protection [50N/51N] Relay Type
C.T. Delay Current Time Instantaneous Time C.T. Delay Current Time Instantaneous Time
ratio curve setting setting protection ratio curve setting setting protection
type (DMT) type (DMT)
6# Bus 150/1 IDMT I> 0.1 Disabled 150/1 IDMT I> 0.075 Disabled Schneider
coupler SI 0.95𝐼𝑛 SI 0.15𝐼𝑛 P143
4# Incoming 150/1 IDMT I >1 𝐼𝑛 0.15 Disabled 50/1 IDMT I> 0.15 Disabled Schneider
1 SI SI 0.5𝐼𝑒
P143
7# Incoming 150/1 IDMT I >1 𝐼𝑛 0.15 Disabled 50/1 IDMT I> 0.15 Disabled Schneider
2 SI SI 0.5𝐼𝑒
P143
99 | P a g e
Table C.7 11kV Bus-section & 11kV two incomers Directional Protection
BH08: 200/1 IDMT I > 1.25 0.05 Disabled 200/1 IDMT I> 0.075 Disabled Tamco
SI 𝐼𝑛 SI 0.25𝐼𝑒
Bus P127
section
100 | P a g e
C.2 NEW RELAY COORDINATION SETTINGS – JAKE
SUBSTATION
CH01: 40/1 IDMT I >2.3𝐼𝑛 0.025 I >> 4 𝐼𝑛 0s 50/1 IDMT I > 0.2 0.025 I >> 0.4 𝐼𝑒 0s Tamco
Spare SI SI 𝐼𝑒 Micom
Feeder P123
(OGM2)
CH02: 100/1 IDMT I > 0.5 0.025 I >> 1 𝐼𝑛 0s 50/1 IDMT I > 0.2 0.025 I >> 0.4 𝐼𝑒 0s Tamco
Spare SI 𝐼𝑛 SI 𝐼𝑒 Micom
Feeder P123
(Camp)
CH03: P- 40/1 IDMT I > 3.3 0.025 I >> 5 𝐼𝑛 0s 50/1 IDMT I > 0.16 0.025 I >> 0.32 𝐼𝑒 0s Tamco
7603C SI 𝐼𝑛 SI 𝐼𝑒 Micom
Feeder P123
(Water
Injection
Pump C)
(Water
Injection
Pump B)
101 | P a g e
Table C. 9 11kV FEEDERS on 2nd Busbar
CH05: TR-7802B 100/ IDM I > 1 𝐼𝑛 0.025 I >> 2 𝐼𝑛 0s 50/1 IDM I > 0.2 Tamco
1 T SI 0s T SI 𝐼𝑒
Micom
P123
CH04: P-7603A
Feeder (Water
Injection Pump A)
CH14: Spare Feeder 40/1 IDM I > 1.24 0.025 I >> 20.21 𝐼𝑛 I 0s 50/1 IDM I > 0.8 0.025 I >> 0.16 𝐼𝑒 0s Tamco
SI 𝐼𝑛 >>> 34.2 𝐼𝑛 0s T SI 𝐼𝑒
Micom
P123
CH15: Spare Feeder 40/1 IDM I > 1.24 0.025 I >> 20.21 𝐼𝑛 I 0s 50/1 IDM I > 0.8 0.025 I >> 0.16 𝐼𝑒 0s Tamco
TSI 𝐼𝑛 >>> 34.2 𝐼𝑛 T SI 𝐼𝑒
0s Micom
P123
CH16: Spare Feeder 40/1 IDM I > 1.24 0.025 I >> 20.21 𝐼𝑛 0s 50/1 IDM I > 0.8 0.025 I >> 0.16 𝐼𝑒 0s Tamco
TSI 𝐼𝑛 T SI 𝐼𝑒
I >>> 34.2 𝐼𝑛 0s Micom
P123
CH17: Spare Feeder 40/1 IDM I >1.6𝐼𝑛 0.025 I >> 2.5 𝐼𝑛 0s 50/1 IDM I > 𝐼𝑒 0.025 I >> 0.4 𝐼𝑒 0s Tamco
T SI T SI
(OGM1) Micom
P123
102 | P a g e
Table C.10 11kV incomers
CH07: 150/1 IDMT I > 1 𝐼𝑛 0.1 Disabled 150/1 IDMT I> 0.05 Disabled
1# SI SI 0.17𝐼𝑒
Incomer Micom
P121
CH07: 150/1 IDMT I > 1 𝐼𝑛 0.1 Disabled 150/1 IDMT I> 0.05 Disabled Tamco
2# SI SI 0.17𝐼𝑒
Incomer Micom
P121
2# 75/1 IDMT I> 0.8 s I >> 8 0s 50/1 IDMT I > 0.2 0.075 I >> 0.4 0.05s Schneider
𝐼𝑛 𝐼𝑒
Transformer SI 0.8 SI P142
𝐼𝑛 𝐼𝑒
(TR 7801A)
2# 75/1 IDMT I> 0.8 s I >> 8 0s 50/1 IDMT I > 0.2 0.075 I >> 0.4 0.05s Schneider
𝐼𝑛 𝐼𝑒
Transformer SI 0.8 SI P142
𝐼𝑛 𝐼𝑒
(TR 7801B)
103 | P a g e
Table C. 12 33kV Bus coupler
Bus 150/1 IDMT I > 0.4 0.15 Disabled Disabled Disabled Schneider
coupler SI 𝐼𝑛 P143
CH07: 1# 100/1 IDMT I > 0.75 0.2 Disabled 50/1 IDMT I > 0.6 0.125 I >>1𝐼𝑒 0.1s Schneider
Incomer SI 𝐼𝑛 SI 𝐼𝑒 P143
CH07: 2# 100/1 IDMT I > 0.75 0.2 Disabled 50/1 IDMT I > 0.6 0.125 I >> 1 𝐼𝑒 0.1s Schneider
Incomer SI 𝐼𝑛 SI 𝐼𝑒 P143
Table C.14 11kV Bus-section & 11kV two incomers Directional Protection
CH07: 1# 150/1 SI Disabled 30/1 IDMT I > 1.6 0.05 Disabled Tamco
Incomer SI 𝐼𝑒 P127
104 | P a g e
CH10: 2# 150/1 IDMT Disabled 30/1 IDMT I > 1.1 0.05 Disabled Tamco
Incomer SI SI 𝐼𝑒 P127
CH08: Bus 200/1 IDMT I > 0.75 0.05 Disabled 200/1 Disabled Tamco
section SI 𝐼𝑛 P127
DH01: Spare 40/1 IDMT I 0.025 I >>9.8𝐼𝑛 0s 50/1 IDMT I> 0.025 I >> 0.5 𝐼𝑒 0s Tamco
Feeder SI >4.9𝐼𝑛 SI 0.25 𝐼𝑒 Micom
(RMU) P123
DH02: Spare 100/1 IDMT I> 0.025 I >> 0.5𝐼𝑛 0s 50/1 IDMT I> 0.025 I >> 0.06 𝐼𝑒 0s Tamco
Feeder SI 0.1𝐼𝑛 SI 0.03 𝐼𝑒 Micom
(OGM1 + P123
CAMP +
Unloading
pumps)
DH05: TR- 100/1 IDMT I> 0.025 I >>1.2𝐼𝑛 0s 50/1 IDMT I> 0.025 I >>0.16𝐼𝑒 0s Tamco
7802A SI 0.6𝐼𝑛 SI 0.08𝐼𝑒 Micom
P123
105 | P a g e
Table C.16 11kV FEEDERS on 2nd Busbar
DH12: TR-6802B 100/1 IDM I > 0.35𝐼𝑛 0.02 I >>0.7𝐼𝑛 0s 50/1 IDM I> 0.025 I >>0.1𝐼𝑒 0s Tamcos
T SI 5 T SI 0.05 𝐼𝑒 Micom
P123
DH13: P-6603A Feeder 40/1 IDM Disabled 50/1 IDM Disabled Tamco
(Water injection Pump TSI T SI Micom
A) P123
DH14: Spare Feeder 40/1 IDM Disabled 50/1 IDM Disabled Tamco
(Fire Fighter) SI T SI Micom
P123
DH15: Spare Feeder 100/1 IDM I >0.45𝐼𝑛 0.02 I >>0.9𝐼𝑛 0s 50/1 IDM I> 0.025 I >> 0.2𝐼𝑒 0s Tamco
(OGM) TSI 5 T SI 0.1𝐼𝑒 Micom
P123
DH16: Spare Feeder 40/1 IDM Disabled 50/1 IDM Disabled Tamco
(Perkins) TSI T SI Micom
P123
DH07: 1# 150/1 IDMT I > 1.7𝐼𝑛 0.075 Disabled 150/1 IDMT I> 0.075 Disabled Tamco
Incomer SI SI 0.25𝐼𝑒 Micom
P121
DH11: 2# 150/1 IDMT I > 1.7𝐼𝑛 0.075 Disabled 150/1 IDMT I> 0.075 Disabled Tamco
Incomer SI SI 0.25𝐼𝑒 Micom
P121
106 | P a g e
table C. 18 33kV Transformer Feeders
2# 75/1 IDMT I > 1.2𝐼𝑛 0.075 I >>7𝐼𝑛 0s 50/1 IDMT I> 0.025 I >> 0.66𝐼𝑛 0s Schneider
Transformer SI SI 0.22𝐼𝑒 P142
(TR-6801A)
9# 75/1 IDMT I > 1.2𝐼𝑛 0.075 I >>7𝐼𝑛 0s 50/1 IDMT I> 0.025 I >> 0.66𝐼𝑛 0s Schneider
Transformer SI SI 0.22𝐼𝑒 P142
(TR-6801B)
Bus Coupler Overcurrent protection [50/51] Earth protection [50N/51N] Relay Type
C.T. Delay Current Time Instantaneous Time C.T. Delay Current Time Instantaneous Time
ratio curve setting setting protection ratio curve setting setting protection
type (DMT) type (DMT)
6# Bus 150/1 IDMT I> 0.1 I >> 2 𝐼𝑛 0.07s 150/1 IDMT I > 0.1𝐼𝑒 0.075s Disabled Schneider
coupler SI 0.7𝐼𝑛 SI P143
C.T. Delay Current Time Instantaneous Time C.T. Delay Current Time Instantaneous Time
ratio curve setting setting protection ratio curve setting setting protection
type (DMT) type (DMT)
4# Incoming 150/1 IDMT I >0.77𝐼𝑛 0.15 Disabled 50/1 IDMT I> 0.15 Disabled Schneider
1 SI SI 0.4𝐼𝑒 P143
7# Incoming 150/1 IDMT I >0.77𝐼𝑛 0.15 Disabled 50/1 IDMT I> 0.15 Disabled Schneider
2 SI SI 0.4𝐼𝑒 P143
107 | P a g e
Table C.21 11kV Bus-section & 11 kV two incomers Directional Protection
DH08: Bus 150/1 IDMT I > 1.3𝐼𝑛 0.05 Disabled 150/1 IDMT I> 0.075 Disabled Tamco
section SI SI 0.2𝐼𝑒 P127
108 | P a g e
C.4 NEW RELAY COORDINATION SETTINGS – MOGA
SUBSTATION
AH01: Spare Feeder Disabled 50/1 IDMT I > 0.2 0.025 I >> 0.4 𝐼𝑒 0s Tamco
SI 𝐼𝑒 Micom
P123
AH02: RMU-2830A 100/ IDMT I > 0.7𝐼𝑛 0.025 I >>1.4𝐼𝑛 0s 50/1 IDMT I > 0.2 0.025 I >> 0.4 𝐼𝑒 0s Tamco
1 SI SI 𝐼𝑒 Micom
P123
AH03: Spare Feeder Disabled 50/1 IDMT I > 0.2 0.025 I >> 0.4 𝐼𝑒 0s Tamco
SI 𝐼𝑒 Micom
P123
AH04: TR-2820A disable 50/1 IDMT I > 0.2 0.025 I >> 0.4 𝐼𝑒 0s Tamco
Feeder SI 𝐼𝑒 Micom
P123
109 | P a g e
Table C.23 11kV FEEDERS on 2nd Busbar
AH11: TR-2820A 100/ IDM disable 50/1 IDM I > 0.2 0.025 I >> 0.4 𝐼𝑒 0s Tamco
Feeder 1 T SI T SI 𝐼𝑒 Micom
P123
AH12: RMU-2830B 100/ IDM disable 50/1 IDM I > 0.2 0.025 I >> 0.4 𝐼𝑒 0s Tamco
1 T SI T SI 𝐼𝑒 Micom
P123
C.T. Delay Current Time Instantaneous Time C.T. Delay Current Time Instantaneous Time
ratio curve setting setting protection ratio curve setting setting protection
type (DMT) type (DMT)
AH07: 1# 150/1 IDMT I > 1.4 0.1 Disabled 150/1 IDMT I > 0.2 0.05 Disabled Tamco
𝐼𝑛
Incomer SI SI Micom P121
𝐼𝑒
AH09: 2# 150/1 IDMT I > 1.4 0.1 Disabled 150/1 IDMT I > 0.2 0.05 Disabled Tamco
𝐼𝑛
Incomer SI SI Micom P121
𝐼𝑒
110 | P a g e
Table C. 25 33kV Transformer Feeders
3# 75/1 IDMT I> 0.1 I >> 8 𝐼𝑛 0s 50/1 IDMT I> 0.05 I >> 0.8𝐼𝑒 0.05s Schneider
Transformer SI 1.1𝐼𝑛 SI 0.65𝐼𝑒 P142
8# 75/1 IDMT I> 0.1 I >> 8 𝐼𝑛 0s 50/1 IDMT I> 0.05 I >> 0.8𝐼𝑒 0.05s Schneider
Transformer SI 1.1𝐼𝑛 SI 0.65𝐼𝑒 P142
(TR 7801B)
111 | P a g e
Table C. 27 11kV Bus-section & 11kV two incomers Directional Protection [the directional
Element is disabled = non-directional]
AH07: 1# 150/1 IDMT Disabled 30/1 IDMT I > 0.8 0.05 Disabled Tamco
Incomer SI SI 𝐼𝑒 P127
AH09: 2# 150/1 IDMT Disabled 30/1 IDMT I > 0.8 0.05 Disabled Tamco
Incomer SI SI 𝐼𝑒 P127
CH08: Bus 150/1 IDMT I > 1.5 0.05 Disabled 1/1 Disabled Tamco
section SI 𝐼𝑛 P127
112 | P a g e
C.5 NEW RELAY COORDINATION SETTINGS – CPF
SUBSTATION
C.T. Dela Current Time Instantaneous Ti C.T. Delay Current Time Instantaneo Tim
rati y setting settin protection me ratio curve setting settin us e
o curv g type g protection
e (DMT)
type (DMT)
04: TR-1805A 100/ IDM I >1.2 𝐼𝑛 0.02 I >>2.4𝐼𝑛 0s 100/ IDM I > 0.07𝐼𝑒 0.025 I >>0.14 𝐼𝑒 0s Alstom
5 T SI 5 5 T SI Micom
P122
13: TR-1803B 100/ IDM I > 0.9 0.02 I >>1.8𝐼𝑛 0s 50/5 IDM I >0.1𝐼𝑒 0.025 I >>0.2 𝐼𝑒 0s Alstom
5 T SI 𝐼𝑛 5 T SI Micom
P123
15: Initial substation -2 The relay is not working and the switchgear is OFF
16: RMU-2 200/ IDM I > 1 𝐼𝑛 0.02 I >> 2 𝐼𝑛 0s 200/ IDM I > 0.06 0.025 I >> 0.12𝐼𝑒 0s Alstom
5 T SI 5 5 T SI 𝐼𝑒 Micom
P123
18: FULA CENTRE 1-1 200/ IDM I > 1.1 0.02 I >> 2.2 𝐼𝑛 0s 50/5 IDM I > 0.25 0.025 0s Alstom
& 1-2 5 T SI 𝐼𝑛 5 T SI 𝐼𝑒 Micom
P123
19: TR-1801E 100/ IDM I > 2.1 0.02 I >> 4.2 𝐼𝑛 0s 50/5 IDM I > 0.22 0.025 I >> 0.44𝐼𝑒 0s AREVA
5 T SI 𝐼𝑛 5 T SI 𝐼𝑒 Micom
113 | P a g e
P122
TR-1801F 100/ IDM I > 0.8 0.02 I >> 1.6 𝐼𝑛 0s 50/5 IDM I > 0.1 𝐼𝑒 0.025 I >> 0.2 𝐼𝑒 0s AREVA
1 T SI 𝐼𝑛 5 T SI Micom
P122
TR-1801D 100/ IDM I > 1.3 0.02 I >> 2.6 𝐼𝑛 0s 50/5 IDM I > 0.15 0.075 I >> 0.3 𝐼𝑒 0s AREVA
1 T SI 𝐼𝑛 5 T SI 𝐼𝑒 Micom
P122
Feeder
C.T Dela Current Tim Instantaneous Ti C.T. Delay Current Time Instantaneo Ti
. y setting e protection me ratio curve setting settin us me
rati curv setti type g protection
o e ng (DMT)
type (DMT)
06: WIP Pump 1605A 75/ IDM I 0.02 I >>2.7𝐼𝑛 0s 50/1 IDM I >0.12 𝐼𝑒 0.025 I >>0.24 𝐼𝑒 0s Tamco
1 T >1.35𝐼𝑛 5 T SI Micom
SI P142
114 | P a g e
09: Spare Feeder 400 IDM I > 0.75 0.02 I >>1.5 𝐼𝑛 0s 50/1 IDM I > 0.32 0.075 I >> 0.64 𝐼𝑒 0s Tamco
(PSI-2 Incoming Line) /1 T 𝐼𝑛 5 T SI 𝐼𝑒 Micom
SI P142
19: TR-1807B 150 IDM I > 0.6 0.02 I >> 1.2 𝐼𝑛 0s 100/ IDM I > 0.1 𝐼𝑒 0.025 I >> 0.2 𝐼𝑒 0s Tamco
/5 T 𝐼𝑛 5 5 T SI Micom
SI P142
24: Spare Feeder 400 IDM I > 0.5 0.02 I >>1 𝐼𝑛 0s 50/1 IDM I > 0.25 0.025 I >> 0.5 𝐼𝑒 0s Tamco
(PSI-1 Incoming Line) /1 T 𝐼𝑛 5 T SI 𝐼𝑒 Micom
SI P142
115 | P a g e
Table C.29 11kV Bus-section & 11kV Transformer feeders
03: 800/1 IDMT I > 0.7𝐼𝑛 0.35 Disabled 50/1 IDMT I 0.025 I > >10𝐼𝑒 0s Tamco
Transformer SI SI >3.2𝐼𝑒 Micom
(TR-1806A) P142
18: 800/1 IDMT I > 0.7 0.375 Disabled 50/1 IDMT I > 3.2 0.025 I > >10𝐼𝑒 0s Tamco
Transformer SI 𝐼𝑛 SI 𝐼𝑒 Micom
(TR-1806A) P142
DH08: Bus 1500/1 IDMT I> 0.325 Disabled 50/1 IDMT I > 3.4 0.075 Disabled Tamco
section SI 0.41𝐼𝑛 SI 𝐼𝑒 Micom
P143
H8: Transformer 250/1 IDMT I > 1.4 0.25 Disabled 75/1 IDMT I > 0.3 0.25 Disabled AREVA
(TR-1806A) SI 𝐼𝑛 SI 𝐼𝑒 P121
250/1 IDMT I > 1.4 0.25 Disabled 250/1 IDMT I > 0.1 0.25 Disabled AREVA
SI 𝐼𝑛 SI 𝐼𝑒 P142
H11:Transformer 250/1 IDMT I > 1.4 0.25 Disabled 75/1 IDMT I > 0.3 0.25 Disabled AREVA
( TR-1806B ) SI 𝐼𝑛 SI 𝐼𝑒 P121
250/1 IDMT I > 1.4 0.25 Disabled 250/1 IDMT I > 0.1 0.25 Disabled AREVA
SI 𝐼𝑛 SI 𝐼𝑒 P142
116 | P a g e
Table C.31 33kV outgoings
H1: FNE 150/1 IDMT I >1.2𝐼𝑛 0.15 I >>11.5𝐼𝑛 0s 50/1 IDMT I> 0.15 I >> 34𝐼𝑒 0s Areva
1 SI SI 0.6𝐼𝑒 P123
H3: 100/1 IDMT I> 0.15 I >> 14 𝐼𝑛 0s 50/1 IDMT I > 0.45 0.15 I >> 24 𝐼𝑒 0s Areva
KEYI 1 SI 1.3𝐼𝑛 SI 𝐼𝑒 P123
H5: 150/1 IDMT I > 0.9 0.3 I >> 11.2 𝐼𝑛 0s 50/1 IDMT I > 1 𝐼𝑒 0.3 I >> 28 𝐼𝑒 0s Areva
MOGA SI 𝐼𝑛 SI P123
1
H15: 100/1 IDMT I > 1.3 0.15 I >>14 𝐼𝑛 0s 50/1 IDMT I > 0.45 0.15 I >> 24 𝐼𝑒 0s Areva
KEYI 2 SI 𝐼𝑛 SI 𝐼𝑒 P123
H13: 150/1 IDMT I > 0.9 0.3 I >> 11.2𝐼𝑛 0s 50/1 IDMT I > 1𝐼𝑒 0.3 I >> 28 𝐼𝑒 0s Areva
MOGA SI 𝐼𝑛 SI P123
2
H17: 150/1 IDMT I > 1.2 0.15 I >> 11.5 𝐼𝑛 0s 50/1 IDMT I > 0.6 0.15 I >> 34 𝐼𝑒 0s Areva
FNE 2 SI 𝐼𝑛 SI 𝐼𝑒 P123
117 | P a g e