UNIVERSITY OF THE EAST

COLLLEGE OF ENGINEERING - CALOOCAN CAMPUS


MECHANICAL ENGINEERING DEPARTMENT

Progress Report for Mini Hydroelectric Dynamo

IN PARTIAL FULFILLMENT OF THE


REQUIREMENTS IN
M.E. ELECTIVE 3
NME 513 – 1ME

GROUP LEADER:
Villanueva, Shiela

MEMBERS:
Canilao, Raven
David, Cedrick
Edep, Ashlie
Francisco, Matthew
Gatpandan, Ian
Guimbaolibot, Tyron
Sibayan, Adrianne Carl
Taloyo, Niño Dennis

SUBMITTED TO:
ENGR. Rizalito Tavares
October 01, 2018
MINI
HYDROELECTRIC 2
DYNAMO

CONTENTS

I. Activity Progress
Purchasing Of Materials…………………………………...………………………………… 3
Completed Activities………………….…………………………..…………………………….4

II. Project Schedule


Activity Planning ….…………….……………….……………………………………………. 6
Deliverables ………………………………………………….…………………………..………8

TABLE/S

Table 1.0: Materials Needed ….……..……………………………………………………………… 3


Table 2.0: Gantt Chart……… ………………………………………………………………………… 4
Table 3.0: List of Deliverable ………………………………………………………………………… 8

FIGURE/S

Figure: 1 Impeller Blade……… ………………………………………………………………………. 4


Figure: 1.1 Shaft……………………………………….……….……………………………..…………. 4
Figure: 1.2 Bearing……………………………………….……….………………………..…………. 5
MINI
HYDROELECTRIC 3
DYNAMO

I. Activity Progress

PURCHASING OF THE MATERIALS

Quantit Materials Specification Price 1/0


y
1 Alternator 12 Volts, IC Type, 2,000ph 1
Belt Driven p
1 Inverter 500 Watts 900php 1
DC 12V to AC
230V
1 Impeller Blades Diameter = 8” 1400php 1
12 blades
1.Shaft
2. Bearings 1. L=6in
3. 6002 Ball D=15mm
Bearing inside 2. D=1.75in
4. Oil Seal H=1.50in
3. 2 pcs
4. Di=15mm
Do=32mm
T=7mm

1 Battery - 0
1 Gear Box Ratio: 1:10 3500php 1
X10 Multiplier
1 Pump and - 0
Accessories

Legend:
1 – Ok
0 – Not Okay
Table 1.0: MATERIALS NEEDED

The table 1 shows what material is needed for the project. Last Saturday, 29 th of September,
the assigned member of the group successfully fabricated the impeller blades with the help of
known person who has an idea of creating it.
MINI
HYDROELECTRIC 4
DYNAMO

COMPLETED ACTIVITIES
Every Saturday the assigned members of the group have a task which is to buy the components
needed for the project. Last 29th of September, the impeller blade was successfully fabricated
with the help of a mechanic person. Also, our group bought a shaft with a length and diameter
of 6in and 15mm respectively and a bearing with diameter and height of 1.75in and 1.5in
respectively.

Figure 1.0: IMPELLER BLADE

Figure 1.1: SHAFT


MINI
HYDROELECTRIC 5
DYNAMO

Figure 1.2: BEARING


MINI
HYDROELECTRIC 6
DYNAMO

II. Project Schedule


ACTIVITY PLANNING

% Complete Actual Days


On Going
Planned Days

% Completion

18-Jun-18
20-Jun-18
22-Jun-18
25-Jun-18
27-Jun-18
29-Jun-18

18-Jul-18
23-Jul-18
25-Jul-18
27-Jul-18
30-Jul-18
1-Aug-18
11-Jul-18
13-Jul-18
16-Jul-18

3-Aug-18
4-Jul-18

9-Jul-18
2-Jul-18

6-Jul-18
ACTIVITY
START END PLANNED ACTUAL
DATE DATE DAYS DAYS
PROJECT PROPOSAL 18-Jun-18 22-Jun-18
CONSULTATION 25-Jun-18 27-Jun-18
REVISION 2-Jul-18 4-Jul
DRAFT DETAILED ENGINEERING DESIGN (SHOP
9-Jul-18 13-Aug
DRAWINGS)
MATERIAL FINALIZATION 25-Jul-18 6-Aug
PROGRESS REPORT 15-Aug-18 15-Aug-18
CANVASSING OF MATERIALS 10-Aug-18 19-Aug-18

SUBMISSION OF FINAL DED AND PLANS FOR APPROVAL 15-Aug-18 20-Aug-18

PURCHASING OF MATERIALS 22-Aug-18 28-Sep-18

DESIGN AND FABRICATON OF PROTOTYPE STRUCTURE 22-Aug-18 29-Aug-18

INSTALLATION OF DYNAMO 31-Aug-18 7-Sep-18


INSTALLATION OF PUMP 10-Sep-18 17-Sep-18
FINISHING OF THE PROTOTYPE 1-Oct-18 5-Oct-18
TESTING OF THE PROTOTYPE 8-Oct-18 12-Oct-18

SUBMISSION OF THE PROTOTYPE 17-Oct-18 17-Oct-18


Table 2.0: GANTT CHART
DELIVERABLES
The milestones and major deliverables with corresponding submission dates for the project is
given in Table 2. Note that the table below will be updated based on the activity progress of the
group.

No Deliverables 1/0
.
1 Project Proposal 1
2 Draft Detailed Engineering Design (Shop Drawings) 1
3 Finalization of List of Materials 1
4 Canvassing Of Materials 0
5 Purchasing of Materials 0
6 1st Progress Report 1
7 Design And Fabrication of Prototype Structure 0
8 Installation of Dynamo 0
9 2nd Progress Report 1
10 Installation of Pump 0
11 3rd Progress Report 1
12 Fabrication of Impeller Blade 1
13 4th Progress Report 1
14 Submission of “As-Built Plans” and DED 0
15 Fabrication of Gear Box 1
16 5th Progress Report 1
17 6th Progress Report 1
18 7th Progress Report 1
19 Final Presentation 0
Legend:
1 – Ok
0 – Not Okay
Table 3.0: LIST OF DELIVERABLES