Beruflich Dokumente
Kultur Dokumente
58DECEMBER 2013 | HydrocarbonProcessing.com
Plant Design, Engineering and Construction
mended to have a total load of nearly half of the flare capacity. Ac- flaring load is reduced below 65,000 kg/h. Step 2 has an addi-
cording to this methodology, isolatable sections can be accom- tional load of 80,000 kg/h and can be started at 6 min. The time
modated in the depressurization steps, as outlined in TABLE 3. delay for further steps is determined in a similar manner. The
Depressurization steps can have sections with more than one flaring load time profile during staggered depressurization is
level of priority. For example, in Step 1 of depressurization, sec- also displayed in FIG. 2.
tions of Priority 1, Priority 2 and Priority 3 are included based on
flare capacity. Similarly, isolatable sections of the same priority Implementation aspects. For successful implementation of
can be divided into more than one depressurization step. For ex- a staggered depressurization system, a number of detailed de-
ample, the Priority 3 sections are divided into Step 1 and Step 2. sign features must be implemented. These features should be
Determine the time delay between each step. The time de- included to avoid the simultaneous opening of all EDVs, which
lays are selected to ensure that the flaring load never exceeds the would cause the flare load to exceed the design capacity and,
flare system capacity. To determine the appropriate time delay, ultimately, lead to a catastrophic failure.
the flow profile should be generated for each depressurization Secured instrument air system. Each EDV valve should be
valve. The exponent coefficient factor can be calculated using provided with a secured instrument air (SIA) buffer vessel. To
Eq. 2. The exponent coefficient factor for each isolatable section ensure the workability of the EDV upon instrument air supply
is described in TABLE 4. failure, the SIA system should be designed to maintain suffi-
The flow profile for each isolatable section can be generated cient pressure in the buffer vessel for at least three valve strokes.
using the initial depressurization load and the exponent coeffi- To indicate low air pressure in the SIA, a low-pressure alarm is
cient factor θ in Eq. 1. The next step is to evaluate the time delay, provided. To prevent backflow from the SIA system during the
which can create sufficient ullage for the following step. Step 1 loss of instrument air header pressure, two non-return valves are
begins with a peak load of 140,000 kg/h, while Step 2 must ac- recommended. Bleeding devices, such as regulators, should not
commodate an additional 80,000 kg/h. be used downstream of the non-return valves.
Therefore, Step 2 can begin when the flaring load is reduced
from 140,000 kg/h to 65,000 kg/h. As described in TABLE 5, af-
ter 6 min. from the start of the depressurization sequence, the TABLE 2. Depressurization priority of isolatable section
Priority of depressurization Isolatable section
160,000
Priority 1 Gas inlet manifold
140,000
Priority 2 Gas separator
Blowdown load to flare
120,000
Mass flowrate to flare, kg/h
Solenoid valves. The use of normally energized solenoid sections with lower depressurization priority are depressurized
valves with a 1oo1 or 1oo2 configuration is recommended. If with a time delay.
normally de-energized valves are used, then the solenoid valve With proper design of a staggered depressurization route,
configuration will be 1oo2 (i.e., if one solenoid valve fails to the entire plant can be depressurized without exceeding the
energize or fails to open on energization, then the depressur- flare capacity, thereby preserving the safety of the facility.
izing valve still opens).
RAHUL DOLE is a process engineering manager with L&T-Chiyoda Ltd. in India.
Solenoid valves should be controlled from the instrument- He has over 16 years of experience in process design for oil and gas refineries and
ed protective system (IPS). The uninterruptable power sup- petrochemical facilities. Mr. Dole holds a bachelor’s degree in chemical engineering
ply backup of the IPS should be sized for 30 min. or longer, from Mumbai University in India. He is also a registered member of the UK’s
depending on the overall depressurization cycle time. The Institution of Chemical Engineers and the Indian Institute of Chemical Engineers.
exhaust port of the solenoid valve should be provided with SOHAN BHATT is a senior process engineer with L&T-Chiyoda Ltd. in India. He
port protectors, such as bug screens. Solenoid valves should holds a bachelor’s degree in chemical engineering from the Maharaja Sayajirao
be provided with resilient disc/seat material that gives a tight University of Baroda in India, where he also received three gold medals for
academic excellence. Mr. Bhatt is an active member of the Indian Institute of
shutoff feature. Chemical Engineers, and he is experienced in the process safety design of gas
processing plants, oil refineries and petrochemical plants.
Takeaway. For a situation where the flare system is inadequate
S. SRIDHAR is the head of process engineering at L&T-Chiyoda Ltd. He has
for handling the plant’s entire depressurization load, staggered more than 30 years of experience in process design. Mr. Sridhar holds a master’s
depressurization is a practical solution to avoid modification of degree in chemical engineering and has served as vice chairman for the Indian
the flare system. During staggered depressurization, isolatable Institute of Chemical Engineers’ Baroda Center.
60DECEMBER 2013 | HydrocarbonProcessing.com