Sie sind auf Seite 1von 4

Special Report Plant Design, Engineering and Construction

R. DOLE, S. BHATT and S. SRIDHAR,


L&T-Chiyoda Ltd., Vadodara, India

Design a staggered depressurization sequence


for flare systems
Emergency depressurization is one of the most impor- • High-pressure sections should be given depressurization
tant design provisions for safeguarding facilities in case of an priority over low-pressure sections.
emergency, such as a fire or an exothermic runaway reaction, • Depressurization priority can also be assigned based on the
that can cause catastrophic failure of equipment and loss of nature of the isolatable section. Rotating equipment (e.g.,
containment. Depressurization reduces failure potential by compressors) should be given higher priority. Vessels can
decreasing the internal stress, thereby extending vessel life at be assigned moderate priority. Isolatable sections contain-
a given temperature. By reducing vessel inventory, the depres- ing only piping can be given the lowest priority. Care should
surization of a pressurized vessel minimizes the impact of ves- be taken in determining timing for the centrifugal machine,
sel leakage and rupture. as keeping it under a pressurized shutdown for a prolonged
A gas processing plant is typically divided into various iso- time would require an external seal gas supply and, based on
latable sections (e.g., gas inlet manifolds, inlet separators, a gas its availability, the delay timing would need to be adjusted.
sweetening unit, a gas dehydration unit, etc.), each isolated by Number of depressurization steps. The depressurization
emergency shutdown valves (ESVs). Each section can be de- requirement is divided into steps to enable nearly uniform peak
signed as a separate fire zone that is depressurized by a dedi- load at each step. A higher number of steps is better for the utili-
cated emergency depressurization valve (EDV). zation of the flare system, but it also increases the complexity of
In general, during emergency shutdown conditions, the sequence implementation and its maintenance.
depressurization of only relevant isolatable sections is carried Time delay between each step. The time delay between
out to make those sections safe. However, during certain emer- each depressurization step is evaluated to create enough ullage
gency circumstances, the whole facility must be depressurized, for the next depressurization peak load. To calculate the time
thereby creating a large load discharge to the flare. delay between each step, the flow/time relationship for each de-
In certain situations, flare systems (including the flare head- pressurization valve must be known.
er, the flare knockout drum and the flare stack) may not be ade- The whole facility can be simulated using modern software
quate to handle the entire plant’s depressurization load at once. programs. Depressurization can be calculated using dynamic
This situation is typically encountered when facilities are re- features to develop the depressurization curves of flow, in
vamped over time without a major revamp of the flare systems. terms of pressure vs. time.
To overcome limitations of flare system capacity during The calculation can be simplified using Eq.1, which can
such a scenario, depressurization can be practiced in a sequen- provide reliable depressurization curves. An entire facility de-
tial manner. Presented here are the criteria and calculation pressurization model can be built in a spreadsheet, greatly sim-
methods for designing sequential depressurization, along with plifying the calculation.
guidelines for the implementation of recommended designs. The flowrate through the orifice significantly reduces with
time:
Design criteria. When designing the depressurizing se- F = F0 e–θt (1)
quence, several key guidelines must be considered:
• Priority of depressurization where:
• Number of steps t = Time from start of depressurization, minute
• Time delay between each step. F = Flow through orifice (depressurization load
Priority of depressurization. Based on the cause of de- at time t), kg/h
pressurization, priority for depressurization is assigned to each F0 = Initial flowrate through orifice (peak
isolatable section. The following guidelines can be utilized to depressurization load), kg/h
specify priority: θ = Exponent coefficient factor depending on
• If the cause of depressurization is fire or gas leakage, then orifice size, minute–1.
the section activating the fire or gas detector must be de- The exponent coefficient factor θ can be derived from:
pressurized immediately. Nearby areas are assigned later
priority for depressurization. P = P0 e–θt (2)

Hydrocarbon Processing | DECEMBER 201357


Plant Design, Engineering and Construction

where: sections is 290,000 kg/h. During the depressurization of the


P0 = Initial pressure (internal pressure at time t = 0), bara entire facility, staggered depressurization is required.
P = Final pressure (internal pressure at time t = t), bara. There are several scenarios that can lead to the depressuriza-
Depressurization criteria for each valve are determined by tion of the entire plant:
rupture time, rupture pressure, and vapor release due to rup- • Fire or gas leakage detection in common process areas,
ture. In a typical depressurization system design, the goal is such as the inlet manifold, the export manifold, etc.
to reduce the pressure to less than 50% of the design pressure • Instrument air failure
within 15 minutes (min.), or to reduce the internal pressure to • Low fuel gas supply pressure
7 barg from the design pressure in 15 min. • A power failure to the safeguarding system.
For example, depressurization of a system from design pres- Since the depressurization priority may vary for different
sure of 45 barg to 7 barg, in 15 min., would result in θ = 0.12 causes, individual depressurization sequences may need to be
min–1. A flow profile is described in FIG. 1, based on the applica- activated for each cause. The gas inlet manifold area is one place
tion of Eq. 1 to F 0 = 50,000 kg/h. where an entire-facility depressurization can be activated. To
design staggered depressurization for the gas inlet manifold,
Case study. For the sake of simplicity, this case study con- several steps were applied:
siders the depressurization of a single train in a gas processing Assign depressurization priority to each section. If fire is
plant to its dedicated flare system. Each process unit is consid- the cause of an emergency shutdown, priority will be assigned
ered as a single, isolatable system. The depressurization system to each isolatable section based on geographical area. The iso-
sizing criteria are summarized in TABLE 1. latable section of the gas inlet manifold is affected by fire; there-
The initial peak depressurization load can be evaluated fore, it should be depressurized immediately (i.e., Priority 1).
from the depressurization utility available in commercial simu- The next priority is assigned to adjacent areas.
lators. The initial peak load can be evaluated at the maximum The gas separator and depletion compressor are located ad-
upstream operating pressure instead of the design pressure, if jacent to the gas inlet manifold, so these units will be assigned
the cause of emergency shutdown is not a fire in that section. the next level of priority (i.e., Priority 2). Priority of depressur-
In this case study, the flare system capacity is pegged at ization is assigned to other isolatable sections in a similar man-
145,000 kg/h. Here, the total depressurization load of all the ner. Based on these guidelines, priority for depressurization is
assigned, as shown in TABLE 2.
Determine number of depressurization steps. Once the
60,000 priority of depressurization is assigned based on peak depres-
Flowrate, kg/h 80
50,000 Section pressure, barg surization load, the valves that can be accommodated at the
Section pressure, barg

40,000 60 depressurization step should be determined. The total flaring


Flowrate, kg/h

load during depressurization and the flare system capacity are


30,000
40 the major factors used to determine the number of steps.
20,000 At the first staggered depressurization step, the flaring load is
20
10,000 zero. Depressurization valves with a total peak load that is slightly
0 0 less than the flare capacity should be initiated. In the subsequent
0 10 20 30 40 50 60 steps, depressurization valves with a total peak load that is near
Depressurization time, min.
to half of the flare capacity should be initiated. The flaring load
FIG. 1. The flow profile of an individual depressurization valve used can be higher or lower than half of the flare capacity; however, to
for calculating the time delay between each step. have an optimum number of depressurization steps, it is recom-

TABLE 1. Depressurization data of isolatable section


Initial depressurization
Isolatable section Initial pressure, barg Final pressure, barg Depressurization time, min. load, kg/h
Gas inlet manifold 45 7 15 35,000
Gas separator 45 7 15 30,000
Depletion compressor 70 7 15 25,000
Acid gas removal 70 7 15 30,000
Dehydration 70 7 15 30,000
Mercury removal 70 7 15 20,000
Nitrogen rejection 70 7 15 30,000
NGL recovery 70 7 15 20,000
Fractionation train 60 7 15 25,000
Sweetening unit 60 7 15 20,000
Booster compressor 80 7 15 25,000

58DECEMBER 2013 | HydrocarbonProcessing.com
Plant Design, Engineering and Construction

mended to have a total load of nearly half of the flare capacity. Ac- flaring load is reduced below 65,000 kg/h. Step 2 has an addi-
cording to this methodology, isolatable sections can be accom- tional load of 80,000 kg/h and can be started at 6 min. The time
modated in the depressurization steps, as outlined in TABLE 3. delay for further steps is determined in a similar manner. The
Depressurization steps can have sections with more than one flaring load time profile during staggered depressurization is
level of priority. For example, in Step 1 of depressurization, sec- also displayed in FIG. 2.
tions of Priority 1, Priority 2 and Priority 3 are included based on
flare capacity. Similarly, isolatable sections of the same priority Implementation aspects. For successful implementation of
can be divided into more than one depressurization step. For ex- a staggered depressurization system, a number of detailed de-
ample, the Priority 3 sections are divided into Step 1 and Step 2. sign features must be implemented. These features should be
Determine the time delay between each step. The time de- included to avoid the simultaneous opening of all EDVs, which
lays are selected to ensure that the flaring load never exceeds the would cause the flare load to exceed the design capacity and,
flare system capacity. To determine the appropriate time delay, ultimately, lead to a catastrophic failure.
the flow profile should be generated for each depressurization Secured instrument air system. Each EDV valve should be
valve. The exponent coefficient factor can be calculated using provided with a secured instrument air (SIA) buffer vessel. To
Eq. 2. The exponent coefficient factor for each isolatable section ensure the workability of the EDV upon instrument air supply
is described in TABLE 4. failure, the SIA system should be designed to maintain suffi-
The flow profile for each isolatable section can be generated cient pressure in the buffer vessel for at least three valve strokes.
using the initial depressurization load and the exponent coeffi- To indicate low air pressure in the SIA, a low-pressure alarm is
cient factor θ in Eq. 1. The next step is to evaluate the time delay, provided. To prevent backflow from the SIA system during the
which can create sufficient ullage for the following step. Step 1 loss of instrument air header pressure, two non-return valves are
begins with a peak load of 140,000 kg/h, while Step 2 must ac- recommended. Bleeding devices, such as regulators, should not
commodate an additional 80,000 kg/h. be used downstream of the non-return valves.
Therefore, Step 2 can begin when the flaring load is reduced
from 140,000 kg/h to 65,000 kg/h. As described in TABLE 5, af-
ter 6 min. from the start of the depressurization sequence, the TABLE 2. Depressurization priority of isolatable section
Priority of depressurization Isolatable section
160,000
Priority 1 Gas inlet manifold
140,000
Priority 2 Gas separator
Blowdown load to flare
120,000
Mass flowrate to flare, kg/h

Total flare limit Depletion compressor


100,000 Priority 3 Acid gas removal
80,000 Dehydration unit
60,000 Mercury removal
40,000 Priority 4 Nitrogen rejection
20,000 NGL recovery
0
0 30 60 Priority 5 Fractionation unit
Depressurization time, min.
Sweetening unit
FIG. 2. Flaring load during staggered depressurization. Priority 6 Booster compressor

TABLE 3. Isolatable section accommodated in depressurization step


Initial depressurization
Depressurization step Isolatable section Priority of depressurization load, kg/h Flaring load added for step
Gas inlet manifold Priority 1 35,000
Gas separator Priority 2 30,000
Step 1 Depletion compressor Priority 2 25,000 140,000
Acid gas removal Priority 3 30,000
Mercury removal Priority 3 20,000
Dehydration Priority 3 30,000
Step 2 Nitrogen rejection Priority 4 30,000 80,000
NGL recovery Priority 4 20,000
Fractionation train Priority 5 25,000
Step 3 Sweetening unit Priority 5 20,000 70,000
Booster compressor Priority 6 25,000

Hydrocarbon Processing | DECEMBER 201359


Plant Design, Engineering and Construction

TABLE 4. Exponent coefficient factor for each isolatable section

Initial depressurization Final depressurization Depressurization time, Exponent coefficient


Isolatable section pressure, barg pressure, barg min. factor θ
Gas inlet manifold 45 7 15 0.1241
Gas separator 45 7 15 0.1241
Depletion compressor 70 7 15 0.1535
Acid gas removal 70 7 15 0.1535
Mercury removal 70 7 15 0.1535
Dehydration 70 7 15 0.1535
Nitrogen rejection 70 7 15 0.1535
NGL recovery 70 7 15 0.1535
Fractionation train 60 7 15 0.1432
Sweetening unit 60 7 15 0.1432
Booster compressor 80 7 15 0.1624

TABLE 5. Calculation of time delay between each step


Flaring load to depressurization valve, kg/h
Isolatable section Step 1 Step 2 Step 3
Time from start of depressurization sequence Peak load 0 min. 6 min. 6 min. 11 min. 11 min.
Gas inlet manifold 35,000 35,000 (0) 16,629 (6) 16,629 (6) 8,943 (11) 8,943 (11)
Gas separator 30,000 30,000 (0) 14,254 (6) 14,254 (6) 7,666 (11) 7,666 (11)
Depletion compressor 25,000 25,000 (0) 9,954 (6) 9,954 (6) 4,620 (11) 4,620 (11)
Acid gas removal 30,000 30,000 (0) 11,945 (6) 11,945 (6) 5,544 (11) 5,544 (11)
Mercury removal 20,000 20,000 (0) 7,963 (6) 7,963 (6) 3,696 (11) 3,696 (11)
Dehydration 30,000 30,000 (0) 13,925 (5) 13,925 (5)
Nitrogen rejection 30,000 30,000 (0) 13,925 (5) 13,925 (5)
NGL recovery 20,000 20,000 (0) 9,283 (5) 9,283 (5)
Fractionation train 25,000 25,000 (0)
Sweetening unit 20,000 20,000 (0)
Booster compressor 25,000 25,000 (0)
Total flaring load 140,000 60,746 140,746 67,603 137,603

Solenoid valves. The use of normally energized solenoid sections with lower depressurization priority are depressurized
valves with a 1oo1 or 1oo2 configuration is recommended. If with a time delay.
normally de-energized valves are used, then the solenoid valve With proper design of a staggered depressurization route,
configuration will be 1oo2 (i.e., if one solenoid valve fails to the entire plant can be depressurized without exceeding the
energize or fails to open on energization, then the depressur- flare capacity, thereby preserving the safety of the facility.
izing valve still opens).
RAHUL DOLE is a process engineering manager with L&T-Chiyoda Ltd. in India.
Solenoid valves should be controlled from the instrument- He has over 16 years of experience in process design for oil and gas refineries and
ed protective system (IPS). The uninterruptable power sup- petrochemical facilities. Mr. Dole holds a bachelor’s degree in chemical engineering
ply backup of the IPS should be sized for 30 min. or longer, from Mumbai University in India. He is also a registered member of the UK’s
depending on the overall depressurization cycle time. The Institution of Chemical Engineers and the Indian Institute of Chemical Engineers.
exhaust port of the solenoid valve should be provided with SOHAN BHATT is a senior process engineer with L&T-Chiyoda Ltd. in India. He
port protectors, such as bug screens. Solenoid valves should holds a bachelor’s degree in chemical engineering from the Maharaja Sayajirao
be provided with resilient disc/seat material that gives a tight University of Baroda in India, where he also received three gold medals for
academic excellence. Mr. Bhatt is an active member of the Indian Institute of
shutoff feature. Chemical Engineers, and he is experienced in the process safety design of gas
processing plants, oil refineries and petrochemical plants.
Takeaway. For a situation where the flare system is inadequate
S. SRIDHAR is the head of process engineering at L&T-Chiyoda Ltd. He has
for handling the plant’s entire depressurization load, staggered more than 30 years of experience in process design. Mr. Sridhar holds a master’s
depressurization is a practical solution to avoid modification of degree in chemical engineering and has served as vice chairman for the Indian
the flare system. During staggered depressurization, isolatable Institute of Chemical Engineers’ Baroda Center.

60DECEMBER 2013 | HydrocarbonProcessing.com

Das könnte Ihnen auch gefallen