Beruflich Dokumente
Kultur Dokumente
1
An Introduction to Dosco
Contents Page
History
Dosco Overseas Engineering Limited is UK based and since 1995 a member of the Amco
Corporation plc group. Located in Tuxford, Nottinghamshire, the company was founded in
the early 1950's by the Dominion Steel and Coal Company of Canada to market the Dosco
Miner in the UK coal mining industry.
minerals.
From its inception, the company has pursued a policy of using specialist sub-contract
companies to manufacture Dosco designed parts, with final assembly and testing being
undertaken at the Tuxford site.
Design & manufacture
The Engineering Department employs a strong team of
qualified designers and support staff using the very latest
computer aided design and drafting equipment, including
three-dimensional solid modelling. Each new machine
design is in the hands of an experienced Project Manager,
backed by a pool of qualified design and detail staff.
Similarly, the Purchasing Department employ buyers
responsible for the purchase of proprietary items and the
outside manufacture of Dosco designed components. High
standards are demanded from suppliers, and professionally
trained staff ensures that, while negotiating the keenest prices, quality and delivery are to the
required standards.
Quality
Dosco is an ISO9001 registered company, and as such maintains an
independent Quality Assurance Department, responsible for
inspection of goods inwards, both Dosco design and proprietary parts.
The department also inspects component manufacture on suppliers'
premises. As well as component inspection, the department carries
out a final machine inspection to ensure the quality of the product and
traceability of all components.
Spares back up
Sales support
Mineral Mining
Civil Tunnelling
The rock cutting capability of Dosco equipment was quickly recognised by the construction
industry as an alternative to drill and blast in tunnelling operations, and a range of machines has
been developed for this purpose, including boom in shields and full face tunnel boring
machines for soft to medium ground.
Dosco has built an enviable reputation in the civil construction industry, providing machines for
rail and metro links in major cities around the UK, including Liverpool and Newcastle as well
as the underground link to Heathrow Airport's Terminal Four.
Following these earlier successes in the field,
Dosco extended its capability to the extent not
only of supplying the cutting element but the
complete tunnelling system including shield,
conveyor, segment transport and segment erector.
In the Materials Handling field, Dosco has a manufacturing and sales agreement with
Bridgestone of Japan for the unique pipe conveyor.
The wide range of belt materials includes food quality grade. Conveyor diameters range from
150mm to 850mm diameters. This gives volume flows of 95m3/hr up to 7,300m3/hr
respectively.
Special Engineering Projects form a key part of the Dosco product range. The specification of
work that can be done seems endless. Just some of projects to date range from sub sea vehicles
for diamond mining through to a tuyere cutter for cleaning out smelting furnaces. Projects of all
sizes are carried out. Dosco offers a range of services from feasibility studies, design,
installation and commissioning right through to full turnkey supply.
World-wide support
Dosco's ability to satisfy world demand is based on the early recognition of the importance of
sound engineering, reliable after-sales service, and a constant presence in the field.
To this end, the company has established a world-wide network of distributors and agents. As
part of the drive for market penetration in certain world markets, licence agreements have been
signed allowing indigenous manufacture of Dosco products, in India and in Poland.
To offer the best possible support Russian approvals have been obtained for four key models of
Dosco Roadheaders.
• Mk2B
• MD1100
• LH1300
• MK3
Iranian based engineers trained by Dosco personnel will be available for on site support.
Experienced Dosco Service Engineers are also able to offer back up on site, including
commissioning, training and machine maintenance.
The second machine to be built in the new facilities is another civil tunnelling machine, this
time for a project on the Heathrow High Speed Rail Link Extension, London, UK. The machine
is due for delivery January 2004.
To date, Dosco has manufactured almost 3,000 machines and recognises that machinery
working under constant production pressures requires a constant commitment from the
manufacturer. That is exactly what Dosco aims to provide. By consultation, collaboration,
innovation, excellent engineering and service, Dosco continues to break new ground and
production records.
2. Dosco – worldwide
The table below shows the countries where Dosco machines have been supplied:
Shields with hydraulic or electrical cutting booms to cope with soft to medium rock
conditions.
Shields fitted with manual digging stations and/or back hoe combinations for use in soft
ground conditions
Full face EPB machines for unstable natural ground
Pipe jacking machines with a variety of cutter options
Full face TBM’s for hard and soft ground
Multidrill – percussive for straight line percussive drilling of small bore pipelines
Special purpose tracked machines
Shaft sinking machines
Roadheaders with a variety of boom options
Complete back up system
abcdef abcdef
The list below shows a selection of the applications where Dosco Civil Tunnelling machines
have been utilised:
Dosco have designed and supplied two off pipe conveyors for handling cement at the RMC
owned Chelm Cement Plant located in Chelm, Poland.
The pipe conveyors are both 300m diameter and 200m long. They are part of a dual system
each carrying up to 325 tonnes/hour of cement, 14 hours per day.
The new pipe conveyors, which are part of an investment to improve and upgrade the plant
were erected by Polish main contractors EZO. Other mechanical parts were procured in Poland
by Dosco’s Polish office. The design work was carried out in the UK at Dosco’s head office in
Tuxford. Sourcing products locally in Poland enabled Dosco’s UK skills and engineering
expertise to be combined with the economies of local manufacture.
The pipe conveyor system has replaced an old conventional troughed belt conveyor. It has
already proved to be an efficient and cleaner system with lower maintenance costs.
The system incorporates variable speed drives to adjust the conveyors’ fill rate and velocity and
is automatically controlled by a belt weigher on the incoming conventional feed belts. The set
up gives optimum efficiency and operational savings.
The layout includes curves and inclines – both vertical and horizontally, which negotiates a
complex route through the site at Steti. Many structural supports and mountings from existing
plant were utilised. The conveyors discharge at heights of 38m (line 1) and 50m (line 2).
As main contractor, FMW procured the steelwork locally and erected the system utilising the
Dosco designs and specifications. From receipt of order the equipment was designed,
manufactured, installed and commissioned by Dosco Engineers within 6 months.
Tabas mine located in the Parvadeh coalfield in the north eastern part of IRAN, will be the first
fully mechanised underground mine in the country. The new mine is scheduled to produce
750,000 tonnes of saleable coking coal each year. The coal will be used by the mines owners
and operators the National Iranian Steel Corporation (NISCO), to feed its steel making
operations at Esfehan. Throughout the project Dosco will be working closely with Cementation
Skanska who are the contractor responsible for providing specialist mining services for main
contractor IRITEC/IRASCO.
(KNJV).
Weighing in excess of 250 tonnes and over 50m long Gertrude was taken in sections from
Tuxford to her launch site in London. Gertrude starts her underground journey from King Cross
Station in August 2003, and will excavate the 650m twin-tube tunnels as part of the Thameslink
2000 project.
The on-board bolting system for Roadheaders was designed by Dosco in conjunction with UK
Coal Mining Ltd and the bolter manufacturers, Hydramatic Engineering Ltd.
The clever design enables the rigs and mounts to fold out of the way during cutting operations.
They are then powered forwards hydraulically for the bolting operation.
UK Coal now has a fleet of Dosco Roadheading machines with on-board roof and rib bolters
fitted. Other machines have been modified to enable on-board bolters to be fitted underground
at a later date if required.
Project details
The tunnel was worked from a shaft sunk on an island between taxiways in the middle of the
airport apron.
Throughout the project steady progress of 16m/day was maintained through the very consistent
clay.
The tunnel was approximately 25m below the runway level. Settlement to the runways and
taxiways had to be kept below 20mm. Even more sensitive was the Piccadilly line, where the
bore passed just 4m below the London Underground Tunnel.
By keeping the boring shield moving continuously day and night, plus some very skilful work
at the head, surface movement figures of around 10mm to 15mm were returned, which were
well inside permitted tolerances.
The tunnel was noted throughout its progress for its extreme cleanliness, much of which was
attributed to the efficient muck away process.
Machine information
Boom
A Dosco model TM1800S boom was utilised This comprised a 65kW electrically driven boom
cutter mounted onto a pedestal frame. The mounting allows the boom to arc and lift sufficiently
to cover the whole tunnel face. The pedestal was mounted onto a slew ring bearing, which is
mounted on a sliding bracket. This enables the boom to move longitudinally in/out from the
tunnel face sufficiently to excavate a minimum of one ring depth forwards of the shield cutting
edge.
All boom functions were controlled by manual lever valves. Additionally all functions were
fully protected against hose burst, system failure and intensification.
Shield
Housed in the shield were 14 off 180mm bore x 1600mm stroke shove rams. Each shove ram
could be individually selected for either shove or retract.
Erector
A heavy duty 3600 ring erector with vacuum pads was utilised. A heavy duty slide enabled the
accurate positioning of the erector.
Back up
The first provided space for the hydraulic power pack and carried the feed magazine.
The second provided space for two segment bodies, segment off loading hoist (electric) on a
runway beam, 0.7m wide conveyor and space for shuttle car.
A closed water cooling package was incorporated into the backup system.
Tunnel lining
Machine Specification
Shield
Shield o/d 4800 mm
Shield length 3625 mm
Face rams 4 x 180 mm bore 1400 mm stroke
Shove rams 16 off
Capacity @ 345 kg/cm2 861 kN
Stroke 1200 mm
Total thrust (all rams) 13776 kN
TM1800S boom
Cutting head motor 65 kW
Lifting rams 2 No
Lifting Force 32 kN
Arcing rams 2 No
Arcing force 33 kN
Sumping ram 1 No
Sumping ram force 119 kN
Conveyor
Conveyor Troughed rubber belt
Drive Hydraulic
Rating 10 kW
Speed 1 m/s
Electric's
Shove, erector, magazine & conveyor pump 75 kW
TM1800S pump 55 kW
TM1800S cutter motor 65 kW
Lighting 8 kW
Spare capacity 26 kW
Total 229 kW
Installed power 300 kW
The project was to enable the untreated sewage to be pumped from existing sewer pipes
through a new connecting tunnel and into the new treatment plant.
Tunnel information
Tunnel diameter was 4.8m with a length of 475m, lined with concrete segments and pea gravel
to be injected for primary fill prior to grout injection. Substantial flows of water were expected
throughout (this reached 70 litres per second during tunnelling).
The strata was predominately fissured limestone which contained some sandstone and clay
deposits.
A 50m deep shaft was sunk in the corner of the quarry from where the machine was launched.
The machine was launched from the bottom of the shaft which was 7m diameter at the top
opening out to 10m diameter at the base.
A short back shunt was excavated to enable efficient launch and to facilitate pit bottom
equipment when muck loading.
Machine overview
Morgan Tunnelling had retained the Dosco tunnelling machine that they had used for the
“Baggage Tunnel” excavation under Heathrow International Airport in 1994 (full details are
given in Section 3).
After consultation with Dosco it was identified as suitable, with conversion, to carry out the
new project.
The original machine incorporated a Dosco TM1800 type cutting boom. As the new application
involved cutting through harder strata it was decided the boom should be converted to a SB400
type.
The work required involved a major reconfiguration of the cutting boom. The original boom
was mounted in the invert, whereas the new SB400 boom was a top mounted slide unit. A key
advantage of the reconfiguration was that it allowed for greater capacity for loading muck and
gave much greater access within the shield.
Dosco proposed the use of their profile guidance system, which would ensure that overcuts
were controlled by the driver thereby controlling the amount of pea gravel/grout used. The
system also ensures that the driver has complete knowledge of the position of the boom
especially whilst it is buried in the invert muck pile.
It was decided that during the rebuild process a secondary provision should be designed for the
drilling of ground found to be harder than the boom capability.
Machine Specification
SB400U boom
Cutting head motor 142 kW
Cutting head speed 27 or 50 rpm
Lifting rams 2 No
Lifting Force 110 kN
Lifting ram stroke 370 mm
Arcing rams 2 No
Arcing force 130 kN
Arcing ram stroke 330 mm
Sumping ram 1 No
Sumping ram force 234 kN
Sumping ram stroke 750 mm
Electric's
Existing power pack motor 90 kW D.O.L
SB400U Boom 142 kW D.O.L
Hoist 7 kW D.O.L
Lighting 8 kW D.O.L
Conveyor 11 kW D.O.L
Vacuum Pump 1.1 kW D.O.L
Total installed power 259.1 kW
Transformer rating 300 kVA
For the first 18 km, the route follows the Great Western Main line to Airport Junction, near
Hayes. Here, Heathrow Express trains leave the main line to enter the tunnel that sweeps
underneath the heart of the airport.
A Dosco model SB400 shield type tunnelling machine was designed for construction of the
7.5km tunnel and two identical “Station shields” for the new underground stations.
Tunnel lining
• Sledge number 1 consisted of an upper and lower deck. Space for the hydraulic pumps is on
the lower level and hydraulic oil tank on the upper level. The segment feed magazine was
located under the lower deck level. Mounted centrally is a hydraulically indexed ladder. The
ladder carried a series of sprung loaded pawls which push each individual segment forward
through the magazine. The magazine was able to hold seven segments.
• Sledge number 2 housed the segment off-loading hoist and monorail, which enabled a
segment to be off-loaded from the segment bogie and placed in the segment feed magazine.
Space is provided for two segment and one grout bogie.
• Sledges number 3 to 7 provided space for the electrical control console, transformer and
isolator.
Space was provided for 5 off 14m3 muck skips. These ran on the wagon wheel flanges whilst
within the back up sledges. This facility allowed permanent rail to be laid loose inside the
sledges. The loose rail was connected to the permanent rail in the tunnel, so as the machine
advanced it pulled off the rear sledge, where sleepers were placed under it. This method gives
continual railing up, allowing for a much quicker machine advance.
The soil was removed from the shield by a belt conveyor, which was elevated 170 to the crown
of the tunnel. It then turned horizontal for 30m and then discharged into the muck skips.
Advance rates
Advances of up to 60m/day were recorded during the work. The efficient muck away system
was a significant contributor to this effectiveness.
Machine specification
Shield
Outer diameter 6115 mm
Overall length 7770 mm
Cutting edge thickness 60 mm
Diaphragm thickness 50 mm
Shove rams 19 No
Stroke 1400 mm
Capacity 87 tonnes
Total thrust @ 345 kg/cm2 1673 tonnes
Shove time – extend 8 minutes
- retract 3 minutes
SB400 boom
Cutting head speed 50 rpm
Cutting head power 142 kW
Lift rams 2 No
Lifting force 110 kN
Stroke 370 mm
Working pressure 140 kg/cm2
Sumping ram 1 No
Sumping force at cutting edge 234 kN
Stroke 750 mm
Working pressure 140 kg/cm2
Cutting rate (average) 110 m3/hr
Erector
Type Rotary ring
Maximum rotation +- 2000
Speed of rotation (variable) 0-1 rpm
Ram capacity 26.4 kN
Stroke 400 mm
Number of pick-up head rams 1 No
Ram capacity 26.4 kN
Stroke 100 mm
Number of deflecting rams 2 No
Ram capacity 16.6 kN
Stroke 100 mm
Erector hydraulic system pressure 140 kg/m2
Segment magazine
Number of index rams 1 No
Ram capacity 253 kN
Stroke 1300 mm
Maximum working pressure 210 kg/cm2
Belt conveyor
Type 1000 mm wide troughed rubber belt
Type of drive Electric drum
Rating 20 kW
Capacity 350 tonnes/hour
Speed 1-10 m/sec
HYDRAULICS
Shield
Shield shove and face rams, and erector 1 No
Capacity 90 l/min
Working pressure 350 kg/cm2
Electric motor rating 55 kW
Boom
Arcing, lifting and sumping 1 No
Capacity 65 l/min
Working pressure 210 kg/cm2
Electric motor rating 30 kW
Electrics
Shield 55 kW
Boom 30 kW
Filler pump 190 kW
Hoist 3 kW
Lighting 7.3 kW
Belt conveyor 11 kW
Spare capacity:
1 @ 7.5 kW 7.5 kW
3 @ 10 kW 30 kW
Underground stations
The project was to drive a 2.64m (104”) diameter, 2.2km tunnel out to sea through the
following strata:
The flints were found to be up to 700mm diameter (the forecast predicted 150mm diameter).
Most of the length of the tunnel was subject to hydrostatic pressure from the North Sea at a
minimum of 5.3m above the tunnel.
Schematic of tunnel
Sewer main 32m deep shaft 7.5m min cover between 2 x tunnel bore dia Skin of TBM
chalkhead and crown of between left in place
bore in tidal range chalkhead & crown
Sea Level of bore
2.64m OD
outfall tunnel
Machine information
A Dosco full face TBM with three cutter arms equipped with tungsten carbide tipped cutting
tools was supplied. The three openings were fitted with hydraulically operated flood inundation
doors for control or shut off of the excavated material. The shield body was articulated and
housed eight shove rams and a rotary segment erector.
The machine was designed to operate in two modes – EPB mode and open mode:
EPB mode – the cutter head chamber was sealed off from the main tunnel by a bolted-
on bulkhead adapter. A hydraulically driven screw conveyor passed through to the
cutting head chamber and controlled the rate of material discharge.
Open mode – by removing the screw conveyor and extending the belt conveyor into the
excavation chamber the TBM could operate in open non-pressurised mode. The cut soil
was lifted and discharged onto a 500mm wide belt conveyor, which discharged into
2.5m3 dirt wagons.
The segment erector was a rotary ring type, mounted off the shield rear diaphragm by six
wheels. The bolted trapezoidal precast concrete rings comprised six segments that were fitted
with a hydrophilic water sealing gasket.
Tunnel lining
Back up Equipment
Sledge No 1 provided space for the transformer and isolator (mounted above the segment feed
magazine). The segment feed magazine comprised a curved section which had mounted on it a
hydraulically indexed ladder.
Mounted on the ladder were a series of spring loaded pawls, these could push individual
segments forward, eventually cantilevering them into the tail skin building area.
Sledge No 2 provided apace for the segment bogies. The segments were off loaded by a special
hoist which transported them to the load point of the segment magazine.
Sledges 3 to 5 provided space for the 4 No 2.5 m3 muck wagons and supported the 500mm
wide belt conveyor.
The belt conveyor was specially designed so that the load end could be articulated enabling it to
fit into the cutter chamber when the machine was in EPB mode.
To convert the machine from open to EPB mode the conveyor was retracted and the angle
changed.
Machine specification
Shield
Outer diameter 2642mm (104”)
Overall length 5125 mm
Articulation rams 8 No
Capacity 411 kN each
Stroke 125 mm
Shove rams 8 No
Capacity 520 kN each
Stroke 1400 mm
Maximum advance rate – open mode 20cm min
Maximum advance rate – EPB mode 7 cm/min
Cutter head
Drive Hydraulic
Speed Varaiable 1.73 to 3.25 rpm
Torque 360 kN @ 3.25 rpm, 676 Kn @ 1.73 rpm
Screw conveyor
Type of drive Hydraulic
Rating 20 kW
Capacity 0 to 40.5 m3/hr
Speed Variable 0 – 29 rpm
Conveyor
Type 500 mm wide troughed belt
Speed Variable 0 to 1.5 m/s
Capacity 200 tonnes/hour
Erector
Type Rotary ring
Rortation drive Hydraulic braked motor
Speed of rotation Variable 0 to 2.5 rpm
Index Ram 1 No
Capacity 161 kN
Tilt Ram 2 No
Ram capacity 58 kN each
Longitudinal travel ram 1 No
Capacity 161 kN
Electrics
Cutter head pump 185 kW
Shove/articulation/conveyor/erector pump 45 kW
Screw conveyor 22.5 kW
Lighting 8 kW
Spare capacity 30kW
Total power 290.5 kW
Transformer capacity 350 kVA
Additional information
The machine was designed, manufactured and delivered within 14 weeks of the order being
placed.
The 45 tonnes TBM was lowered in one piece nose first down the 32m deep entry shaft.
The tunnel was driven on a maximum 1 in 90 downhill drive. It would have been preferred to
drive the tunnel on a level or slightly uphill, but this would have meant a launch shaft twice the
depth.
9. Dosco Roadheaders
The performance of the cutting boom is directly related to the ground conditions. Whilst
material hardness is a key factor in determining efficiency the composition of the material e.g.
whether the material has fractures or is massive, the strata mix of the face to be cut and the
surrounding strata conditions are all crucial factors.
Popular models of Dosco Roadheaders for Civil Tunnelling applications include the following:
Typical specification:
Dosco Roadheaders can also be supplied complete with an on-board bolting facility, for both
roof and rib bolting. This rapidly speeds up developments using roof and rib bolts as the
method for tunnel lining.
The rigs and mounts have been cleverly designed so that they fold out of the way during cutting
operations. For the bolting operation they are then powered forwards hydraulically.
A recently developed tracked machine, ideally suited for the economic construction of Cross
Passages to link together twin tunnels.
The Cross Passage Machine is highly manoeuvrable versatile. It incorporates a quick hitch
facility to allow use of a rotary backhoe, cutting head, bucket or hydraulic impact hammer.
A single operator can perform all machine functions. The operator can either work from a cab
on the machine or control it remotely.
Cross Passage Machine with Rotary Backhoe fitted Cross Passage Machine with cutting head fitted
12. Contacts
Your local Dosco agent:
Mining Products
Materials Handling
Civil Tunnelling
Marketing
Directors
Contact address
Dosco Overseas Engineering Ltd, Ollerton Road, Tuxford, Newark, Nottinghamshire, NG22 0PQ, UK
Mr Al Leeming
Tel: + 1 604-535-7488
Fax: +1 604-535-7499
Email: al.leeming@ndcogroup.com
60