SCOPE OF ELECTRICAL FOR MECHANICAL PACKAGES

Rev :R0
PROJECT : POWDER PLANT & ASSOCIATED RAW MATERIAL
FACILITIES OF PHWR FUEL FABRICATION FACILITY
PACKAGE / ITEM : TILTING AND DRUM TRANSFER SYSTEM Sheet:1 of 2

ATTACHMENT-1
Notes: 1) TPL’ Scope shall be indicated as ’T’, End Client’ Scope shall be indicated as ’C’ and Vendor/Bidder scope
shall be indicated as ‘V’, “

ATATCHMENT -1 : ELECTRICAL SCOPE OF WORK


Inputs for Remarks
Design &
design &
S.No Description Engg. Supply Erection
Engg. Commissioning

1 All motors, electrical V V V V V


equipment, MOV, actuators,
roller conveyor motor, Elevator
Electricals as per scope of
mechanical system

2 Power distribution Board (PDB) V V V V V Purchaser will


provide 1 No of
Note : Outgoing feeder quantity power supply at
in PDB shall be as per incoming terminal
requirement of bidder’s
supplied PDB
3 LPBS, Local starter panel and V V V V V
control panel

4 Electrical pertaining to Elevator, V V V V V All bidder supplied


Robot arm Electricals shall be
fed from bidder
supplied PDB
mentioned at
S.No.2
5 LT Power & Control cables with V V V V V Wherever both
terminations from Power end equipments
distribution panel to all are supplied by
equipments/ valves supplied by bidder
bidder
6 Cable tray, supports and V V V V V a. For machine
mounted
conduits
Electricals
b. Branch cable
tray
7 Trailing cables and special V V V V V
cables
8 Branch Cable tray/conduit with V V V V V
supports for all Electrical
cables supplied by bidders
9 Above ground earthing for all V V V V V
Equipments supplied by the
bidder
10 Earth mat below ground V T T T T Purchaser will
provide 2 Nos of
riser ( 1 no on
Engineering Group: Projects Group:
PRPD CHKD RVWD APPD REVIEWED APPROVED
AL VSR
Sign Sign
Name Name
Designation Designation
Date Date
Std Format No. Provisional No.21 Rev R0 Dt
SCOPE OF ELECTRICAL FOR MECHANICAL PACKAGES
Rev :R0
PROJECT : POWDER PLANT & ASSOCIATED RAW MATERIAL
FACILITIES OF PHWR FUEL FABRICATION FACILITY
PACKAGE / ITEM : TILTING AND DRUM TRANSFER SYSTEM Sheet:2 of 2

ATTACHMENT-1
Notes: 1) TPL’ Scope shall be indicated as ’T’, End Client’ Scope shall be indicated as ’C’ and Vendor/Bidder scope
shall be indicated as ‘V’, “

ATATCHMENT -1 : ELECTRICAL SCOPE OF WORK


Inputs for Remarks
Design &
design &
S.No Description Engg. Supply Erection
Engg. Commissioning

opposite corner)
11 Mandatory Spares V V V - -
12 Recommended Spares V V V - -
13 Start up and Commissioning V V V - -
Spares
14 Cable routing drawing as V V V V V
applicable

15 Datasheets and other V V V


documents related to the above
scope

16 All Engineering and As-built V V V V V


Documents pertaining to bidder
scope

17 Statutory approval if any V V V V V


required for Electrical
equipment
18 Construction Power V V V V V At the incoming
terminal of bidder
arrangement consisting of DB
supplied 415V
with its associated cables, construction
power DB
cable terminations etc

Engineering Group: Projects Group:


PRPD CHKD RVWD APPD REVIEWED APPROVED
AL VSR
Sign Sign
Name Name
Designation Designation
Date Date
Std Format No. Provisional No.21 Rev R0 Dt