TUN RAZAK EXCHANGE (TRX) LIFESTYLE

QUARTER
Work Method of Statements for Liquid Floor
Hardener Application
WCT Berhad
TP02 – SUPERSTRUCTURE, FAÇADE AND
BLOCKWORKS

DOCUMENT NUMBER: WCT_TP02_MS_AR_0003


REVISION NO: 05 | Revision Date: 25/10/2019

SUBMISSION
PREPARED REVIEWED APPROVED
Signature Signature Signature

Name: Sitti Julaiha Binti Jindang Name: Jeffrey yong Name: Ng Eng Beng
Position: QAQC Engineer Position: Manager- Achitectural Position: Senior Project Manager
Company: WCT Berhad Company: WCT Berhad Company: WCT Berhad
Date: 25/10/2019 Date: 25/10/2019 Date: 25/10/2019
REVIEW & APPROVAL
LLPM’s REVIEW CONSULTANT’s REVIEW APPROVAL (LLPM)
Signature Signature Signature

Name: Name: Name:


Position: Position: Position:
Company: Company: Company:
Date: Date: Date:
Comments: Comments: Comments:

A- Approved. B- Approved with Comment. C- Rejected.

Tun Razak Exchange (TRX) Lifestyle Quarter MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019

RESPONSE SHEET

NO. CONSULTANT’s COMMENT TRADE CONTRACTOR’s RESPONSE


1 To state type of product (manufacturer) to be Fosroc
used
2 To attach manufacturer’s method of Attached, Appendix C
application
3 To include method of rectification to damage Noted,
areas
4 Organization chart Attached, Appendix D
5

NO. LLPM’s COMMENT TRADE CONTRACTOR’s RESPONSE


Unauthorized modification of controlled Noted and comply.
1 template (MS & ITP)
2 Checklist to include for post-application and Noted and comply. Refer ITP
reflecting the works stated in ITP & MS.
3 What are the curing time between each coat. Noted and comply. Refer item 6.3

Tun Razak Exchange (TRX) Lifestyle Quarter 2 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019

REVISION CONTROL

Rev. No. Rev. Date Details of Amendment

00 25/08/2018 First issue

01 04/10/2018 Second issue

02 20/03/2019 Third issue

03 13/05/2019 Fourth issue

04 13/07/2019 Fifth issue

05 25/10/2019 Sixth issue

Tun Razak Exchange (TRX) Lifestyle Quarter 3 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019

TABLE OF CONTENT

1.0 PURPOSE AND SCOPE ........................................................................................................................... 5

2.0 REFERENCES......................................................................................................................................... 5

3.0 RESOURCE PLANNING .......................................................................................................................... 5


3.1 PERSONNEL/ MANPOWER ..................................................................................................................... 5
3.2 PLANT AND MACHINERY ....................................................................................................................... 6
3.3 TOOLS AND EQUIPMENT ....................................................................................................................... 6
3.4 MATERIAL ............................................................................................................................................ 6

4.0 DOCUMENT SUBMISSION & APPROVAL ................................................................................................ 6

5.0 HANDLING AND STORAGE .................................................................................................................... 6

6.0 CONSTRUCTION METHODOLOGY .......................................................................................................... 7


6.1 SUMMARY ........................................................................................................................................... 7
6.2 SITE ACCESS AND LOGISTIC .................................................................................................................... 7
6.3 TEMPORARY WORKS ............................................................................................................................. 7
6.4 SEQUENTIAL METHOD OF CONSTRUCTION ............................................................................................. 8

7.0 INSPECTION AND TESTING .................................................................................................................... 9

8.0 HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL ................................................................. 9

9.0 RECTIFICATION .................................................................................................................................. 10

10.0 APPENDICES ...................................................................................................................................... 11


10.1 APPENDIX A – SITE ORGANIZATION CHART .......................................................................................................6
10.2 APPENDIX B – ITP & INSPECTION CHECKLIST.....................................................................................................6
10.3 APPENDIX C – SWMS .........................................................................................................................................6
10.4 APPENDIX D – PLANT/ EQUIPMENT/ TOOLS CATALOGUE/ CERTIFICATION DETAILS........................................6
10.5 APPENDIX D – RELEVANT DRAWINGS ...............................................................................................................6

Tun Razak Exchange (TRX) Lifestyle Quarter 4 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019

1.0 PURPOSE AND SCOPE

This Method Statement describes the general procedures for method and construction for Floor
Hardener at project Site including descriptions of all preventive actions to be taken in order to
achieve good quality and safety.

2.0 REFERENCES

Specification

1. Specification for Paving and Screeds DPA_AR_SPE_3210_00.GO REV A

3.0 RESOURCE PLANNING

3.1 PERSONNEL/ MANPOWER

No. Position Responsibility


1 Construction Manager Construction Manager responsible to ensure a project is
completed safely, making sure the project runs on time and
within the allocated budget allowance
2 Site Engineer Site engineer responsible to offers advice in the planning,
coordination and supervision of technical aspects of
construction projects, validates work upon completion and
other activities that are carried out at the construction site
3 QAQC Engineer To ensure quality assurance at site, Inspection and validate of
work completed and progress at site on QA/ QC matters
4 Site Safety Supervisor To ensure all the safety, health and environmental legal
requirement implemented during the work
5 Site Supervisor Completes construction projects by planning, organizing, and
controlling projects; completing quality inspections;
supervising sub-contractors and staff
6 Skilled Workers Installation works

Tun Razak Exchange (TRX) Lifestyle Quarter 5 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019

3.2 PLANT AND MACHINERY

No. Plant/ Machinery


1 Light Buffing Machine
2 Vacuum cleaner
3 Grinder

3.3 TOOLS AND EQUIPMENT

No. Tool/ Equipment


1 Hand broom
2 Hand mop

3.4 MATERIAL

No. Material
1 Approved Liquid Floor Hardener (FOSROC- NITOFLOR LITHURIN)

4.0 DOCUMENT SUBMISSION & APPROVAL

No Description
1 WCT_TP02_SMES_AR_0001 - SMES LIQUID HARDENER (NITOFLOR LITHURIN – FOSROC
SDN BHD

5.0 HANDLING AND STORAGE

For this work package TP02, WCT lay down area located at off site and this place able to support
adequate amount of materials and all materials needed to be deliver were able to reach site on
time.

Material shall not store in excess 1.5 meters in height and must be stored in racks or on wheels.
Besides, material shall not store within 3 meters from any edge or opening.

All materials shall be properly stored and well maintain so that it is in neat and clean condition
throughout the construction period. materials need to have proper handling and storage from
weather and any source of water. The cement bags shall be laid on a dry platform made of
wooden planks resting over.

Delivery of material to the site shall be subjected to weekly and monthly reviews.

Tun Razak Exchange (TRX) Lifestyle Quarter 6 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019

6.0 CONSTRUCTION METHODOLOGY

6.1 SITE ACCESS AND LOGISTIC

Gate 2 will be available for access for entire construction period, it will be used for ingress
and egress of the site along Jalan Utara and Jalan Barat, Therefore, the construction
materials and other resources can be supplied to the site using the access provided.

Flag man will control the traffic flow at ingress, egress and within the proposed project site
to ensure that the traffic flow is within the safety requirement.

Upon commencement of works, the public traffic flow will remain the same as the current
traffic flow where no heavy vehicle is allowed to be on the city roads during peak hours as
mention in the specification.

6.2 Surface Preparation

i. The new concrete shall be cured for seven days or longer before application of liquid
floor hardener.

ii. Curing compound to be removed by light buffing without damaged the substrate
surface before application of liquid hardener. failure to follow these preparation
steps will prevent full penetration of liquid floor hardener, drastically reducing the
effectiveness.

iii. Before application of liquid floor hardener, concrete slurry/debris on slab surface to
be removed. Visible defects such as puddle/chipped off surface, cracks must be
rectified.

iv. Before application of liquid floor hardener, make sure dust, water stagnant, oil stain
and loose particle to be clear.

6.3 Application of Floor Hardening Materials

i. Liquid floor hardener ready to use.

ii. Air temperature during application must be between 2˚C and 38˚C.

iii. In hot and windy conditions, the reaction may take less than the normal 30 minutes
period. In hot weather, the concrete should be pre-dampened.

iv. Apply liquid floor hardener when all standing water has disappeared.

Tun Razak Exchange (TRX) Lifestyle Quarter 7 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019
v. Apply liquid floor hardener to the concrete surface by low pressure sprayer or by pouring
directly onto the surface and distributing evenly by broom or squeegee.

vi. With soft bristle hand brooms or brushes on an auto scrubber, work the liquid floor
hardener around the area to be treated and into the surface.

vii. The concrete must be kept wet with liquid floor hardener for at least thirty (30) minutes.
Add additional if necessary, to maintain a wet surface.

viii. When finish, completely remove/ vacuum all excess liquid floor hardener from the
surface with an automatic scrubber.

ix. In general coverage rates of 0.2 to 0.3 L/ m². are used.

x. 2 coats of liquid floor hardener will be applied

xi. Light traffic can be allowed after minimum 4 hours of hardener application.

xii. Heavy traffic can be allowed after minimum 24 hours of hardener application.

7.0 INSPECTION AND TESTING

The purpose of quality control is to provide a guide lines for a proper operational framework such
that the following targets will be attained

a) To achieve consistent high-quality standards of workmanship in all aspects of the work


b) To provide a safe working environment
c) To follow work procedures to ensure the quality construction
d) The work to be carried out using the Application for Inspection and Inspection Form Checklist
attached refer Appendix B and ensure the finishing quality of work be acceptable by Main
contractor

The QAQC manager shall review all the test reports based on the criteria set in the project
specification for all completed works and materials. All inspection and test record shall keep and
maintained. Refer Appendix for the Inspection and Test Plan

8.0 RECTIFICATION

8.1.1 The damage of power floated area will be rectified as per stated in Work Method of
Statement for powder float works.
8.1.2 The liquid floor hardener will be re-applying as per item 6.0 CONSTRUCTION
METHODOLOGY

Tun Razak Exchange (TRX) Lifestyle Quarter 8 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019

9.0 HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL

NO ACTIVITY POTENTIAL HAZARD


1 Application of liquid floor hardener Slippery condition, falling hazard
2 Application of liquid floor hardener Chemical hazard

10.0 APPENDICES

APPENDIX A – SITE ORGANIZATION CHART


APPENDIX B – ITP & INSPECTION CHECKLIST
APPENDIX C – SWMS
APPENDIX D – PLANT/ EQUIPMENT/ TOOLS CATALOGUE/ CERTIFICATION DETAILS
APPENDIX E – RELEVANT DRAWINGS

Tun Razak Exchange (TRX) Lifestyle Quarter 9 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019

APPENDIX A – SITE ORGANIZATION CHART

Tun Razak Exchange (TRX) Lifestyle Quarter 10 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
Senior Project Manager 1
Ng Eng Beng
019-387 0386

QA / QC 4 Architectural Works 5

QA/QC Architectural Project


Manager 1 Manager 1
Mohd Fauzi Bin Ujang Jeffry Yong
019-279 9316 019-260 8766

QA/QC
Engineer 2 Archi Coordinator 1
Sitti Julaiha Bt Jindang Nik Harisudin Bin Nik Mohamad
019-536 4612 018-358 4771
Syarul Hakimi Bin Mohd
019-980 5213 Sub Contractor 5

QA/QC Officer 1 Trade Manager 1


Nursyafiqah Bt Ismail TBA
013-527 3317

Skill Wokers 2

General Wokers 3
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019

APPENDIX B – ITP & INSPECTION CHECKLIST

Tun Razak Exchange (TRX) Lifestyle Quarter 11 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
MAIN CONTRACTOR : LEND LEASE PROJECTS (M) SDN BHD Page No. 1 of 2

TRX LQ : TP02 - SUPERSTRUCTURE, FAÇADE AND BLOCKWORKS Doc Ref. No. ITP_TP02_WCT_AR_0003

INSPECTION & TEST PLAN Revision No 04

APPLICATION OF LIQUID FLOOR HARDENER Date 25-Oct-19

Action by
Reference to Specification/ Frequency of Point of Inpection/
No Description of Work Characteristic Acceptance Criteria Verifying Document Trade
Standard/ Contract Document Inspection Test Design Commissioning
Contractor/ LLPM - PM&C
Consultant Consultant
Supplier

SELECTION OF TRADE CONTRACTOR/ SUPPLIER


Source of qualified Trade
Contractor / Supplier Trade Contractor/ Supplier as per Approved Trade
1 N/A Once Tender of work Verified via approved Trade Contractor/ Supplier List Trade Contractor/ Supplier List - - N/A A
Contractor/ Supplier List

Selection of succesful Trade Trade Contractor/ Supplier qualification as stated in the Before award of Trade Contractor/ Supplier - Fullfill the requirements for tender
2 N/A Once Letter of Award - - N/A A
Contractors / Supplier tender contract contract (i.e.Technical Proposal Evaluation)

DOCUMENT ISSUANCE/ SUBMISSION & APPROVAL


Issuance of Approved Prior to
Issuance of Construction Drawings to Trade Once every revision of Construction drawings to comply with the technical specification and
3 Construction Drawings to Trade commencement of CS& & AFC Drawings - P N/A R, A, I
Contractor/ Supplier prior to start work on the Contract submission contract requirements
Contractor/ Supplier physical work at site

Four weeks prior to starting work on the Contract


the Contractor shall submit for approval details of the
proposed sources of all materials, together with full
CSF & Method Statement - A (Approved)/ B
documentary evidence that the materials will comply
Submission of Method (Approved with Comments) Status
with the specification.
Statement, Inspection & Test Prior to
Once every revision of Method statement to comply with the technical specification and
4 Plan (ITP), Inspection Checklist DPA_AR_SPE_3210_00.G0 commencement of B - Status : works allowed to proceed subject to all P R N/A R, A
The Contractor shall submit method statements for submission construction drawings
& Safe Work Method Statements physical work at site works carried out as per comments. Revise MS/
approval indicating full detailed proposals of the
(SWMS) for approval ITP/ Inspection Checklist/ SWMS to be submitted
method of placing, finishing and curing the concrete.
for Status A approval.
The method statement shall cover all principle types of
floor hardener e.g. non-metallic pigmented floor
hardener, non-metallic liquid floor hardener.

Contractor to submit to Engineer the design Prior to


Once every revision of Shop drawings to comply with the technical specification, design,
5 Submission of Shop Drawings DPA_AR_SPE_3210_00.G0 calculations and shop drawing. E.g.formwork for his commencement of CSF & AFC Drawings P R N/A R, A
submission construction drawings and contract requirements
approval. physical work at site

CSF & Design Calculations - A (Approved)/ B


(Approved with Comments) Status
Prior to
Submission of Design Contractor to submit to Engineer the design Once every revision of Design Calculations to comply with the technical specification, design,
6 DPA_AR_SPE_3210_00.G0 commencement of B - Status : works allowed to proceed subject to all P R N/A R, A
Calculation (if any) calculations and shop drawing. submission construction drawings and contract requirements
physical work at site works carried out as per comments. Revise MS/
ITP/ Inspection Checklist/ SWMS to be submitted
for Status A approval.

Submission of SMES for


7 DPA_AR_SPE_3210_00.G0
Approval CSF & SMES - A (Approved)/ B (Approved with
Comments) Status
Use chemical hardeners that are non toxic, biodegradable and have
zero or low VOCs that bonds chemically with the concrete to B - Status : works allowed to proceed subject to all
Prior to strengthen and harden floors that are porous, readily absorptive, and works carried out as per comments. Revise SMES
DPA_AR_SPE_3210_00.G0 Once every revision of to be submitted for Status A approval.
a) Floor Hardener Liquid floor hardener commencement of only moderately hard. These hardeners shall have dust proofing P (Supplier) R, A,H N/A R, A,H
Clause 2.06 & 2.07 submission
physical work at site properties and in accordance technical performance.
Sample Tag to be provided upon approval Status
A.

MOCK-UP/ PROTOTYPE/ BENCHMARK PREPARATION & APPROVAL

Surface preparation and application shall be in


accordance with the manufacturer’s recommendation, Once or as per
8 Application of Floor Hardener DPA_AR_SPE_3210_00.G0 Surface of product Material to comply and approved to Engineer spesification. As per specify in AFI P, AFI W,V, A N/A V, AC
printed literature, and applicable codes, standards and instructed by Enginner
statutory requirements.

MATERIAL RECEIVE, HANDLING & STORAGE

Receiving of Material

9 Every delivery material Material delivered to be checked as per approved material submission Delivery order
Floor Hardener DPA_AR_SPE_3210_00.G0 Received in good condition Type, Quantity P W, A N/A V, AC
on site approval Material Receiving Inspection Checklist Form

Note: P = Prepare; R = Review; A = Approved; H = Hold; W = Witness; V = Verified; AC = Acknowledge; I = Issuance; AFI = Application for Inspection; CSF = Contractor Submission Form; ER = Client/ Employer's Representative; N/A = Not Applicable; CCS = Concrete Characteristic Strength
Prepared By: Reviewed & Verified By: Approved By:
Initial: Initial: Initial:
Name: Sitti Julaiha Binti Jindang Mohd Fauzi Bin Ujang Name: Name:
Designation: QAQC Engineer QAQC Manager Designation: Designation:
(Trade Contractor/ Supplier) WCT Berhad WCT Berhad (Consultant) (LLPM)

LLM_CN_TMP_3013_00.00 Revision No: 02


TRX LQ/ITP Template for LLPM.doc Revision Date: 22/03/2019
MAIN CONTRACTOR : LEND LEASE PROJECTS (M) SDN BHD Page No. 2 of 2

TRX LQ : TP02 - SUPERSTRUCTURE, FAÇADE AND BLOCKWORKS Doc Ref. No. ITP_TP02_WCT_AR_0003

INSPECTION & TEST PLAN Revision No 04

APPLICATION OF LIQUID FLOOR HARDENER Date 25-Oct-19

Action by
Reference to Specification Frequency of Point of Inpection Trade
No Description of Work Characteristic Acceptance Criteria Verifying Document Design Commissioning
(Contract Document) Inspection Test Contractor/ LLPM - PM&C
Consultant Consultant
Supplier

Material Handling & Storage (Site-


Storage Yard/ Working Area)
10
Prior to
Opened container store in secondary containment / Material Receiving Inspection Checklist, SMES
Floor Hardener DPA_AR_SPE_3210_00.G0 Storage on site commencement of Label on the material P W, A N/A V, AC
designated chemical storage Approval
physical work at site
DOCUMENTATION FOR INSPECTION
Details of Works Inspection e.g Location, Date and Once every AFI Subject to AFI
11 AFI submission AFI submitted earlier to the consultant, Complete Submission AFI form Application for Inspection form (AFI) P R.V,A N/A A, V, AC
time Issuance Submission
PRE-CONSTRUCTION STAGE
Surface preparation
Once before New concrete must be thoroughly dry and cured a minimum of 10 days
KTP_ST_SPE_0007_00.G0 Rev The concrete shall be cured for seven days or longer (Prior to
12 Curing process commencement of prior to application of liquid hardener; for best results cure for a full 28 Method Statement, AFI Checklist P V, A N/A V, AC
02 Clause 3.08 Part C (2) before application of liquid floor hardener. commencement of
work area days.
physical work at site)

i. Curing compound must be fully removed before Surface preparation


Once before Surfaces must be clean, dry, and free of all loose dirt, oil, wax, sealers,
KTP_ST_SPE_0007_00.G0 Rev applying liquid floor hardener. (Prior to
13 Surface cleaness commencement of curing and parting compounds, and other foreign matter or Method Statement, AFI Checklist P V, A N/A V, AC
02 Clause 3.08 Part C (3) ii. Dust, water stagnant, oil stain and loose particle to commencement of
work area carbonation, prior to application of liquid hardener.
be clear. physical work at site)

IN-PROCESS INSPECTION / ON-GOING CONSTRUCTION STAGE

Liquid Floor Hardener Prior to Liquid hardener shall be applied by roller, spray, brush, or squeegee.
Application of Liquid Floor KTP_ST_SPE_0007_00.G0 Rev
14 Surface preparation and application shall be in Once commencement of Distribute evenly and mop up excess solution or puddles, and allow to Method Statement, AFI Checklist P V, A N/A V, AC
Hardener 02 Clause 3.08 Part C (1)
accordance with the manufacturer’s recommendation, physical work at site dry.

POST-CONSTRUCTION STAGE

Material or works fails to meet specified requirement


DPA_AR_SPE_3210_00.G0 may be rejected by the Engineer whenever found at Finish product of
16 Post Inspection & Defects List Once Material or works to follow the requirement AFI, Method Statement of Repairing Works P V, A N/A V, AC
Clause 3.08 any time prior to final acceptance of the works concrete
regardless or previous inspection.

TESTING

N/A

Note: P = Prepare; R = Review; A = Approved; H = Hold; W = Witness; V = Verified; AC = Acknowledge; I = Issuance; AFI = Application for Inspection; CSF = Contractor Submission Form; ER = Client/ Employer's Representative; N/A = Not Applicable; CCS = Concrete Characteristic Strength
Prepared By: Reviewed & Verified By: Approved By:
Initial: Initial: Initial:
Name: Sitti Julaiha Binti Jindang Mohd Fauzi Bin Ujang Name: Name:
Designation: QAQC Engineer QAQC Manager Designation: Designation:
(Trade Contractor/ Supplier) WCT Berhad WCT Berhad (Consultant) (LLPM)

LLM_CN_TMP_3013_00.00 Revision No: 02


TRX LQ/ITP Template for LLPM.doc Revision Date: 22/03/2019
PM&C : Page No. : 1 of 1
LENDLEASE PROJECTS (MALAYSIA) SDN BHD Doc Ref. No. : WCT_TP02_CHK_AR_002
Project : TRX LQ THE EXCHANGE
TRADE CONTRACTOR/ SUPPLIER: Trade
: TP 02
WCT BERHAD Package

LIQUID FLOOR HARDENER INSPECTION CHECKLIST

Description of Works/ Elements/ Structure: AFI No. :

Location/ Zone/ Sub-Zone/ Level/ Block /Unit/ Area : Drawing Ref. No. :

Date of Inspection : Material : (Approved / Not Approved)


Time : Method Statement : (Approved / Not Approved)

Trade Contractor Consultant LLPM


Description of Works Remarks
(√ / X ) (√ / X ) (√ / X )

Surface preparation

i. Surface cured for adequate time ( 7 Days )

ii. Surface fully removed from curing compound by buffing machine

iii. Surface is clean and free from loose particle, oil and standing water

iv. Surface defects are rectified

Floor Hardener application

i. Material used as per approved Material Submission (SMES)

ii. Air temperature during application (between 2° C and 3° C)

Application liquid floor hardener in dry condition (all standing water has
iii.
disappeared)
Apply liquid floor hardener evenly by low pressure spray or by poring directly
iv.
using broom or squeegee

v. Concrete kept wet with liquid hardener (at least 30 minutes)

vi. Apply first coat layer liquid floor hardener

Apply second coat layer liquid floor hardener after 30 minutes first coat layer
vii.
application.

Post-Application Process

i. All areas has been applied with floor hardener

ii. Protect/Barricade the area for at least 24 hours from the traffic

STATUS OF INSPECTION
We have carried out all necessary inspections and verify that the above items/ activities conform to the contract specifications/ document
Checked By: Checked By: Checked By:

Initial : Initial : Initial :


Name : Name : Name :
Position : Position : Position :
Date : Date : Date :
NSC (if applicable) : Trade Contractor (if applicable) : Lendlease Projects (M) Sdn Bhd
Checked By: Approved By : Acknowledged by:

Initial : Initial : Initial :


Name : Name : Name :
Position : C.o.W/ ARE / ARA Position : RE / RA Position :
Date : Date : Date :
Client's Consultant : Client's Consultant : Lendlease Projects (M) Sdn Bhd
CHK_TP02_WCT_TP02_002 Rev: 04 Date : 25/10/2019

LLM_CN_TMP_3014_00.00 Revision No: 01


TRX LQ/ Inspection Checklist Template for Trade Contractor.doc Revision Date: 7/09/2018
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019

ATTACHMENT C –
SAFE WORKS METHOD STATEMENTS
SWMS related to this Method Statements to refer :

TITTLE : SWMS for Power Float & Floor Hardener


DOCUMENT REF. : WCT_TP02_SWMS_AR_0007
REVISION NO. : 00
REVISION DATE : 17/08/2018
ACONEX REF. : LLM-WTRAN-004500

Tun Razak Exchange (TRX) Lifestyle Quarter 12 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019

ATTACHMENT D –
PLANT/ EQUIPMENT/ TOOLS CATALOGUES/
CERTIFICATES DETAILS
SMES related to this Method Statements to refer :

TITTLE : SMES LIQUID HARDENER (NITOFLOR LITHURIN – FOSROC SDN


BHD
DOCUMENT REF. : WCT_TP02_SMES_AR_0001
REVISION NO. : 01
REVISION DATE : 01/06/2019
ACONEX REF. : LLM-WTRAN-006734

Tun Razak Exchange (TRX) Lifestyle Quarter 14 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
Tun Razak Exchange (TRX) Lifestyle Quarter 15 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
Tun Razak Exchange (TRX) Lifestyle Quarter 16 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
Tun Razak Exchange (TRX) Lifestyle Quarter 17 MC02 Method Statement Submission Template
LLM_CN_TMP_3049_00.00 (Rev 02) Revision Date: 27/09/2018
WORK METHOD STATEMENTS FOR
LIQUID FLOOR HARDENER Revision No.: 05
APPLICATION
Doc. No: WCT_TP02_MS_AR_0003 Rev. Date : 25/10/2019

APPENDIX E – RELEVANT DRAWINGS


(N/A)