Project Central park requires pressurization of the lift well. Calculations show a total air quantity leakage of 8.7 cubic meters per second through the 20 open lift doors and cracks on other floors. A pressurization fan with a capacity of 22,579 cubic feet per minute is required to maintain positive pressure in the lift well.
Project Central park requires pressurization of the lift well. Calculations show a total air quantity leakage of 8.7 cubic meters per second through the 20 open lift doors and cracks on other floors. A pressurization fan with a capacity of 22,579 cubic feet per minute is required to maintain positive pressure in the lift well.
Project Central park requires pressurization of the lift well. Calculations show a total air quantity leakage of 8.7 cubic meters per second through the 20 open lift doors and cracks on other floors. A pressurization fan with a capacity of 22,579 cubic feet per minute is required to maintain positive pressure in the lift well.
1 Calculation of air quantity leakage through open lift well door Total No. of door 20 Door Area(mXm) 1.2 2.1 Area of each door 2.52 m² Air velocity(m/s) 0.75 m/s As Per EN 12101-6-2005 Q(Flow) With 5% extra 2.0 m3 /s Safety factor 2 Calculation of air quantity leakage through lift well doors and cracks on other floors Perimeter of Door(m) 6.6 Assumed Crake length 8 meter As Per EN 12101-6-2005 0.06 leakage area (m2) (As per ASHRAE handbook 0.065) Total no. of leakaged door 19 Total Leakage area(m2) 1.14 Differential pressure(Pa) 50
Q (Flow) (m3 /s) (0.827 X Total Leakage areaX (Differential pressure)^.5)
6.7 Q= Kf *Al*(DP) 1/2 CFM required for Lift well Pressurisation(m3/s) of a lift 8.7 Pressurization Fan Capacity (CFM) 22579