Sie sind auf Seite 1von 42

Testing and Commissioning of

Power Systems

Module 4
laying of UnderGround Cables

ELECTRONICS AND
ELECTRICAL ENGINEERING
Type to enter text

sandeep s r

SJB
I N S T I T U T E O F T E C H N O LO G Y
MODULE 4
laying of UnderGround Cables

The cable drums shall be stored on a well drained, hard surface, so that the drums do not sink in the ground causing rot and
damage to the cable drums. Paved surface is preferred, particularly for long term storage.

1
SECTION 1

Storage and Handling

Laying of Underground Cables: Inspection, Storage, Transportation and Han- Loose Neutral Connections, Provision of Proper Fuses on Service Lines and
dling of Cables, Cable Handing Equipment, Cable Laying Depths and Clear- Their Effect on System, Causes and Dim, and Flickering Lights.
ances from other Services such as Water Sewerage, Gas, Heating and other
Laying Of Underground Cables
Mains, Series of Power and Telecommunication Cables and Coordination with
these Services, Excavation of Trenches, Cable Jointing and Terminations Test- Underground cables are, of course, meant to be installed or laid under the
ing and Commissioning. Location of Faults using Megger, Effect of Open or ground. The reliability of underground cable network highly depends upon
proper laying of cables, quality of cable joints and branch connections etc.

2
There are three main methods of laying underground cables, which are - (i) di- Laying Procedure
rect laying, (ii) draw-in system and (iii) solid system. These three methods are
▪ A trench of about 1.5 meters deep and 45 cm wide is dug.
e x p l a i n e d b e l o w w i t h t h e i r a d v a n t a g e s a n d d r a w b a c k s .

▪ Then the trench is covered with a 10 cm thick layer of fine sand.

Direct Laying Of Underground Cables ▪ The cable is laid over the sand bed. The sand bed protects the ca-
ble from the moisture from the ground.
This method is the most popular as it is simple and cheap. The cables to be laid
using this method must have the serving of bituminised paper and hessian tape ▪ Then the laid cable is again covered with a layer of sand of about
so as to provide protection against corrosion and electrolysis. The direct laying 10 cm thick.
procedure is as follows.
▪ When multiple cables are to be laid in the same trench, a horizon-
tal or verticle spacing of about 30 cm is provided to reduce the effect of mutual
heating. Spacing between the cables also ensures a fault occurring on one cable
does not damage the adjacent cable.

▪ The trench is then covered with bricks and soil to protect the cable
from mechanical injury.

Advantages

▪ Simpler and cheaper than the other two methods

▪ Heat generated in cables is easily dissipated in the ground.

Disadvantages

▪ To install new cables for fulfilling an increased load demand, com-


pletely new excavation has to be done which costs as much as the new installa-
tion.

▪ Alterations in the cable network are not easy.

3
▪ Maintenance cost is higher. Advantages

▪ Identifying the location of a fault is difficult. ▪ Repairs, additions or alterations to the cable network can be easily
made from manholes without re-excavation.
▪ This method can not be used in congested areas such as metro cit-
ies where excavation is too expensive. ▪ In this method, as the cables need not be armoured, the cable joint-
ing procedure becomes simpler.
Draw-In System
▪ Maintenance cost is quite lower.
In this method, cast iron or concrete pipes or ducts are laid underground with
manholes at suitable positions along the cable route. The cables are then pulled ▪ Fewer chances of fault occurrence due to the strong mechanical
into the pipes from the manholes. Usually, an additional pipe/duct is also pro- protection provided by the system.
vided along with the three cable ducts for carrying relay protection connections
Disadvantages
and pilot wires. Distance between the manholes should be such that pulling in
the cables is easier. At corners or while changing the direction of route, radius ▪ The initial cost is very high.
of the corners must be longer. The cables that are to be laid in this way need
▪ Due to unfavourable conditions for dissipation of heat, current car-
not be armoured but must be provided with the serving of hessian and jute in
rying capacity of the cables is reduced.
order to protect them when being pulled.

Solid System

In this method, the cable is laid into troughing of cast iron, stoneware, asphalt
or treated wood. When the cable is laid into the position, the troughing is filled
with a bituminous of asphaltic compound and then covered over. Cables to be
laid in this manner could be just lead covered as the troughing provides a good
m e c h a n i c a l p r o t e c t i o n .

This method is very rarely used nowadays as it is more expensive and requires
skilled labour and favourable weather conditions.

4
Laying of underground cables 1 copper conductor, 2 plastic insulation, 3 common conductor covering, 4 ar-
mouring of steel strip, plastic sheath

The concentric conductor of the plastic cable in fig. 3.2. may be used as centre
conductor or protective conductor.

Consumers’ installations in the low-voltage range are very frequently con-


nected to the power supply networks by underground cables. In this, the tradi-
tional paper-insulated compound-impregnated cable is more and more replaced
by plastic-insulated dry cable.

At almost the same current-carrying capacity several advantages are offered


Fig. 3.2. Plastic cable with solid aluminium conductors
by plastic-insulated underground cables as compared to compound-
impregnated cables: 1 aluminium conductors, 2 plastic insulation. 3 common conductor cover, 4
concentric conductor of aluminium flat wires (armouring), 5 protection against
- o m i s s i o n o f t h e e x p e n s i v e l e a d s h e a t h i n g ,

corrosion, 6 plastic sheath
- the insulation value will not be reduced due to loss of compound.

- c o n s i d e r a b l y l o w e r w e i g h t .
 In lieu of the conductor material copper, becoming ever more expensive and
scarcer, more and more underground cable the conductor material of which con-
- s i m p l e r p r e p a r a t i o n ,

sists of aluminium is being applied.
- no problems in overcoming differences in height.
Power cables have standardized designations from which the construction and

type of cable may be seen!

3.1. Preparing cable laying

The first thing to be done before starting to lay the cable is to fix the cable
Fig. 3.1. Plastic sheathed cable with copper conductor route under consideration the tracts of land and rights of ownership and utiliza-

5
tion. On principle the same is valid here as when fixing the route of an over- In difficult terrain a provisional ramp may serve as an auxiliary. By allowing
head line. the cable drums to drop down damages to the cables and cable drums may be
caused.

Cable drums are to be moved only in rolling direction. The rolling direction is
marked on the cable drum.

Prior to processing, the cable is to be tested for current flow!

In case of the cables showing damages to the insulation, in particular the exter-
Fig. 3.3. Fixing the cable route prior to running out the cable nal insulation, such cables must not be used. If necessary a sleeve will have to
be fited to the faulty point.
1 building to be connected, 2 improper cable route since damage will be caused
to ways, ornamental shrubs and banks of waters, 3 proper cable route along a 3.2. Underground laying of power cables
way without mentionable damages to the property
The cable drum is firmly placed on cable jacks or a cable car. Care has to be
Underground cables are laid in cable ditches. Depending on the properties of taken to position the cable drum horizontally only a few centimeters above the
the soil and the degree of danger to damaging the cables these cable ditches are ground. This will prevent the cable drum from slipping off laterally during the
from 70 to 120 cm deep. The base of the cable ditch must be so wide as to offer cable is run out. A braking device is to be provided at the cable drum.
sufficient space for the cables to be laid. The distance between cables is to be
During reeling off the cable should continuously run out under tension from
approx. 20 cm. In order to prevent damage to the cables they are placed on
above
sand, fine gravel or screened soil. The excavated soil stays beside the cable
ditch. After completion of cable laying it will serve to back-fill the remaining The cable has to be pulled off the drum opposite to the rolling direction indi-
ditch. cated on the cable drum. The cable must neither be kinked, nor must there be
formed loops or curls!
Prior to laying the cable the required cable and auxiliaries for this activity will
have to be provided. During this, special attention will have to be paid to the
transport of the cable drums. Unloading the cable drums is preferably to be
done by mobile crane or from a special trailer. Under no circumstances must
cable drums be dropped from a transport vehicle.

6
cable laying is not feasable the cable will have to be pulled off manually. The
cable is carried with the arms spread downwards.

Fig. 3.7. Position of workmen during running out the cable


Fig. 3.6. Support by idlers of cable being run out
1 workmen, 2 supervisor
When laying cable, preferably devices for mechanical cable laying wil
Cables must not be carried on the shoulder because the permissible minimum
l have to be employed. For that purpose winches and cable handling machinery
bending radius may be exceeded resulting possibly in ruptures of cable or insu-
are to be taken.
lation. Cables must not be dragged over the ground or other obstacles!
Cable handling machinery is to be employed in case of long and winding
During cable laying the permissible minimum bending radius will have to be
routes.
observed.At temperatures below 4°C cable is not to be laid any longer. Cables
When laying cable by means of a winch the cable will be joined to a pulling will become brittle at low temperatures and will be easily broken. In urgent
rope by means of a cable stocking of metal. cases also at low temperatures cable may be run out, if the cable is warmed up
beforehand, e.g. by means of a heater fan.
The pulling speed is to be slowly and flexibly adapted to the tensile force of the
cable, in which case Cables will be covered in cable ditches by bricks or concrete ducts resp. cable
covering hoods. Cables may also be laid into cable ditches embedded in sand
the permissible tensile forces must not be exceeded!
without cover. However, in this instance the route of the cable must be marked
In distances of 5 m idlers are to be positioned on which the cable runs. In by an approx. 10 cm wide yellow plastic tape, placed 30 cm above the cable.
curves angular idlers will have to be arranged. If application of machinery for This exemption holds, however, for cables with a concentric conductor only.

7
Cables being laid into the ground without cover must be dug in at least 1 m 1 bricks, 2 cable covering hoods
deep!
Also in the instance of crossing other cables, e.g. telecommunication cables,
If cable covering hoods are being employed the cable will have to be sur- both cables are to be protected mechanically. Each 3 to 5 m the laid cables will
rounded by sand. Existing cavities between cable and covering hood will ob- be marked. For that purpose plastic cable marking tape is being used.
struct heat dissipation from the cable to the soil.
Colour and printing on the cable marking tape will inform about
Beneath streets resp. roads cables are being passed, laid in cement ducts. There
- v o l t a g e

are cement ducts for 1 to 4 draughts. They are made of concrete and are to be
- c a b l e t y p e a n d n u m b e r o f c a b l e a s w e l l a s

put together without a gap between them.
- cross section.
Beneath railway tracks cables are to be laid in tubes 1.50 m deep. Alongside
Before cutting sheathed cable, the sheath of the cable will be tied on both sides
gas pipelines cables are being laid in a distance of approx. 25 cm.
of the cut. For that purpose “endless bindings” are made of firmly wound

 twine. The principle of such a binding may be seen from fig. 3.10. For cutting
hand hack saws or strength-saving cable shears are being employed.

Within buildings the outer jute cover of cables is to be completely removed for
reasons of fire protection!
Fig. 3.8. Cement duct with 3 draughts

Fig. 3.10. Cutting of a lead-sheathed cable with jute envelope and representa-
Fig. 3.9. Cable covers
tion of an endless binding at the cable

8
1 pull twine by flat pliers until the twine’s upper end is in the binding, thereaf- 3.3. Removal of insulation layers from cable
ter cut end at the binding
Prior to making conductive connections at the cable, the individual insulation
For drawing or correcting the cable layout plan, cables, cable joints, under- layers will have to be removed.
passes as well as particular crossings and exposures will have to be surveyed
Processing plastic insulated cable is quite simple. For a cable according to fig.
prior to back-filling the cable ditch. The cable ditch will be back-filled by 30
3.2. the following working steps will be taken:
cm thick layers of soil. Each layer will have to be compacted.
1. Removal of plastic sheath

Take measurements; by dismantling device make longitudinal incision in plas-
tic sheath; make the circular cut; pull off sheath.

2. Bringing out the concentric conductor

Deflect the individual armouring wires and bunch the wires

3. Cutting of sheet

Nick the sheet by triangular file just above the deflected armouring and tear off

4. Removal of the common conductor cover


Fig. 3.11. Simplified segment of a cable layout plan and cable marker with in-
Make longitudinal incision by dismantling device; make circular cut; fan out
formation on longitudinal extension
conductor; tear off common conductor cover; clean conductor’s plastic insula-
1 switchgear, 2 consumer’s installation, 3 cable, 4 site of cable laying machine, tion from adhering residues of plastic material.
5 sites for placing cable drums along the route, 6 direction of earth excavation,

7 crossing with pipeline, 8 street underpasses, 9 streets, 10 cable marker
Fig. 3.12. Removal of insulation layers from a cable with concentric conductor
The position of cables in ground without fixed reference points is marked by
1 plastic sheath, 2 cable fixing clamp, 3 concentric conductor, 4 common con-
cable markers.
ductor cover, 5 plastic insulation, 6 conductor, 7 clip 10 x 1 mm in a distance
They consist of ashlar or concrete and bear an abbreviation. of approx. 120 mm, 8 cable terminal

9
9. Tie off conductor insulation; remove conductor insulation; clean conductors;
finally deflect conductors.

For removal of the insulation layers from paper-insulated compound-


impregnated lead-sheathed cable the following working steps are to be taken:
(see fig. 3.13.)

1. Make tie and remove the external jute cover. Fig. 3.13. Working steps on removal of insulation layers at paper-insulated
lead-sheathed cable
2. Fit collar out of a piece of armouring sheet, cut the armouring by filing and
remove same. Special care has to be taken in soldering on the earthing strand. For this pur-
pose propane gas soldering devices or a blow lamp for soldering are being em-
3. Remove cushioning layer.
ployed. The lead sheath and the copper strand to be soldered on are to be
4. Clean lead sheathing by a non-inflammable dissolvent. cleaned from all oxides. The lead sheath may be cleaned by scraping with a
stripper. The copper strand is to be tautly placed around the lead sheath and the
5. Solder on copper strand to lead sheath.
soldering surface to be wetted by soldering flux. Solder tin stick is to be laid on
6. Make circular incision on lead sheath; make parallel incision in lead sheath; in pieces and to be shaped like a bulb by means of a dampened rag after thor-
roll-back the loose strip by flat pliers; tear off lead sheath along circular cut; oughly warming the soldering surface.
slightly widen the upper edge of the remaining lead sheath.
Caution! In case of too much warming of the lead sheath at one point, perfora-
7. Tie off the belt insulation; unwind and tear off belt insulation. tions of the lead sheath may result!

8. Spread conductors and cutt off fillers.

10

 For making the sleeve joint both ends of the cable must overlap each other for
approx. 50 cm and run towards the sleeve’s end as an s-shaped load reducing
curve.

Sleeve bodies of grey cast iron are split. The upper and lower parts of the
sleeve will be bolted together after accommodating the cable.

Fig. 3.14. Copper strand soldered onto lead sheath

1 lead sheath, 2 copper strand, 3 soldering surface 


3.4. Cable joints and terminations

For protecting cables from ingress of humidity into the insulation, for mechani-
cal protection as well as for preventing cable impregnating compound to
Fig. 3.15. Placement of cable in front of a connecting sleeve
emerge from compound-impregnated cables, conductor connections at cables
are being made by means of sleeves and cable terminations. 1 cable ditch, 2 working pit, 3 ends of cable, 4 cable sleeve, 5 flatly placed
brick
Sleeves serve for connecting cables to each other. Connecting sleeves and tee
joints are discerned. The outer cover of the cable extends into the inner end of the sleeve’s housing.
Each opening of the sleeve for entering the cable will be sealed by a bitumi-
Cable terminations are being installed at points of the cable where transition
nous felt batting wrapped around the cable.
from cables to open-ended line systems, e.g. bus bars takes place.
The lengths of the lead sheath and of the belt insulation in case of paper-
There are differences in respect to the construction of sleeves and terminations.
insulated lead-sheathed cables to be stripped are dependent on the cable cross
Practically sleeves and cable terminations of cast iron, plastic and cast resin are
section. The connection of the conductor ends to each other can be achieved by
being used.
stamping, soldering, welding or screwing. Stamped connections can be made in
Fitting of cable sleeves takes place in the cable ditch. For easing the work of a very simple and firm way by sliding a stamping tube on to the prepared con-
the cable fitter providing a work pit is recommended. ductor ends which will - similar as in case of stamped terminals - conductively
connect both conductor ends after stamping. Within the sleeve the conductors
are insulated and spaced by means of stems.

11

 After approx. 10 minutes the sealing compound is to be poured carefully
through the lid of the sleeve. Since the sealing compound will shrink during the
cooling process, refilling will have to be done.

In case of cable terminations to be sealed by sealing compound the same proc-


ess will be applied as when preparing a cable sleeve.

In the instance of plastic-insulated cable sealing by cable termination is re-


Fig. 3.16. Sectional view of a connecting sleeve at a plastic cable with concen- quired only if ingress of humidity may take place!
tric conductor
Making cast-resin terminations is simpler than fitting cable terminations sealed
1 cable, 2 lower portion of sleeve, 3 upper portion of sleeve, 4 lid, 5 compres- by sealing compound.
sion clamps, 6 earthing socket, 7 bituminous felt batting, 8 flexible earthing
Also in this case it will be important to seal the cable when working with
strand, 9 stems, 10 sealing compound
paper-insulated lead-sheathed cable. This will be achieved if the conductor insu-
The concentric conductors and lead sheath of the cables are being connected to lation, the belt insulation and approx. 10 mm of the metal sheathing are being
each other. wrapped in two layers of PVC-tape. Each layer of PVC-tape with an overlap of
50% is provided with a coat of PVC-adhesive. For this termination no box
It is also very important to include the sleeve body into the earthing system.
body, but a mould only will be required. Into this mould, being arranged
When installing service tap boxes the main cable needs not be cut! around the cable and sealed, a mixture of synthetic resin and silica sand will be
poured.
Cable sealing compound by which the sleeve is completely sealed is easily
melted and highly insulating. It will have reached its processing temperature if The mould’s concentric position around the cable must be paid attention to!
bubbles do not raise any more in the melting container. Then further heating
If strictly observing the mixing ratio and the curing time the casting will be per-
must be stopped. If during heating the sealing compound foam is created on the
manently hardened after approx. 24 hours. Then the mould may be removed
surface it will have to be stirred until the foam subsides. Foam means humidity
and the casting be cleaned (de-burring).
in the sealing compound reducing the insulating capacity of the sealing com-
pound considerably. 

Fig. 3.17. Cable termination of cast resin

12
ceived special training only! The completed cables will be fixed by a double-
tongued mounting clip (see fig, 3.12.) or other mounting elements, e.g. an an-
gle iron, in front of the connection point.

3.5. Making of conductor connections

Conductor connections on cable terminations are quite frequently made via ca-
ble terminals.

In case of the traditional methods of connection like soldering, welding or


clamping of cable terminals to conductors no absolute safety for an unobjection-
able connection will be given.

Stamped connections have replaced these traditional types of connection.


Stamping is distinguished by reliability of the procedure, durability of the con-
nection also under unfavourable conditions as well as by uncomplicated han-
dling of the stamping tools. For the stamping of cable terminals mechanical
1 cast resin, 2 cast resin and silica sand, 3 conductor insulation covered by hand stampers, or in case of bigger cross sections, hydraulic stamping devices
PVC-tape, 4 belt insulation with binding (4 windings), 5 lower PVC-banding, 6 are being employed.
copper strand, 7 stamped cable terminal, 8 metal sheath, 9 external protective
1 stamping head, 2 safety valve, 3 pressure hose, 4 pressure reducing valve, 5
cover
pump lever, 6 pressure tank, 7 pump handle, 8 bearing grip
Synthetical resins are chemically aggressive. For protecting the skin and the
clothes, protective apparel will have to be worn when making terminations of
cast-resin. During this work the eyes are particularly endangered. They are to
be protected by safety goggles.

Fitting of Cable sleeves and cable terminations is a responsible work. Voca-


tional experience and special knowledge will be required. Due to this, cable
sleeves and terminations should in principle be mounted by experts having re-

13
1 Pressure tank of the stamping head, 2 space for stamping inserts, 3 hose con-
nection, 4 screw cap, 5 piston

Stamping inserts being matched to the type of cable and cross section of the
conductor will be fitted into the stamping tools.

There are two different types of stamping inserts:

- s t a m p i n g i n s e r t s f o r V- g r o o v i n g

- stamping inserts for hexagonal stamping.

V-grooving is on principle applied to copper conductors only!

Cable terminals are marked with information about the size of the diameter of
the connecting pin and the conductor’s diameter.

Fig. 3.20. Stamping inserts



1 V-grooving, 2 hexagonal stamping
Fig. 3.19. Stamping head of a hydraulic stamping tool
The stamping inserts for the cable terminal are in any case to match the cable
terminal.

14
The designations of suitable stamping inserts are to be taken from the tables in 2. Removal of the conductor’s insulation and cleaning of the contact surfaces.
the valid regulations.
The outside of the conductor and the inner contact surfaces of the terminal’s
When stamping on cable terminals the following fitting process is to be ad- barrel must be metallic-bright. Contaminated conductors and barrels of termi-
hered to: nals will have to be cleaned from adhering dirt and oxides by wire brush.

1. Cutting conductor lengthwise Every conductor has to be cleaned only just prior to the stamping process, max.
10 minutes beforehand!
The conductor is to be matched to the length of the cable terminal up to the con-
necting pin. It is to fill out the cable terminal. The elongation of the cable termi- 3. Entering the conductor into the barrel of the terminal
nal’s connection during hexagonal stamping has also to be considered. It has to
Difficulties which may arise in that process are best overcome by chamfering
be subtracted from the length of the conductor. Depending on the cross section
the conductor laterally or by fixing a taut wire binding adjacent to the cut sur-
in question this change of length may be between 3 and 5 mm.
face which will have to be removed after having entered the conductor into the

 cable terminal’s barrel. Segmental conductors are to stamped circularly by the
corresponding stamping inserts prior to putting on the cable terminal.


Fig. 3.22. Entering the conductor into the cable terminals barrel by means of a
wire binding

4. Stamping on the cable terminal

V-grooving is to be performed so as to have the local impression situated at the


upper or lower side of the terminal’s barrel aproximately in the centre. In par-
ticular, maintenance of the required stamping depth has to be observed. This
will be achieved when the stamping jaws of the stamping insert will have
Fig. 3.21. Cable terminal prior to and after stamping closed or corresponding markings have been reached.

15

 If after closing of the stamp jaws further pressure is exerted on the stamping
tool this will unconditionally lead to heavy damage at the stamp inserts or the
stamping device itself (risk of accident!)!

Stamp jaws which are not completely closed do not warrant a durable electrical
connection (restamping to be done!)!

Lapping the conductors, which has been dealt with in section 3.4. on process-
ing of paper-insulated lead-sheathed cables, takes place after fitting the cable
Fig. 3.23. V-grooving of the upper or lower sides
terminals.
In case of hexagonal stamping of aluminium conductors the stamping insert
For soldering of cable terminals there are some restrictions. Soldering of cable
has to be applied in between the stamping marks on the cable terminal. If two
terminals should be turned to only if stamped terminals cannot be applied.
stampings are to be made, stamping will be started at the point nearest to the
terminal lug. The burrs resulting from hexagonal stamping at the cable terminal
will have to be removed.

How to proceed when soldering cable terminal is to be taken from fig. 3.25.
and 3.26.Fig. 3.25. Soldering a cable terminal

Fig. 3.24. Connection to cable terminal of aluminium conductors with one or a) prepared conductor, b) conductor with cable terminal slid on, c) soldering on
two hexagonal stampings the cable terminal: 1 flame-proof batting, 2 solder, 3 heating nozzle, 4 cable ter-
minal

16
When soldering on cable terminals the connecting area around the lug of the 1.3.2 Short runs of cables laid in pipes, closed masonary trenches and similar
cable terminal is continued to be heated until the soldering tin laid on starts to protected or secured enclosures need not be armoured.
flow. So much solder is put on to the soldering surface that all parts of the con-
1.3.3 PVC and XLPE cables, when armoured, shall have galvanized steel wires
ductor in the total area are covered by tin which must show a mirror reflection.
(flat or round) for armouring.
In no case so much solder is to be brought on the soldering surface resp. heat-
1.3.4 Paper insulated cables shall have for armouring, a double layer of steel
ing is continued so long that the solder flows through the cable terminal into
tape for normal applications. Steel wire armouring is preferred where the ca-
the conductor!
bles are liable to tensile stresses in applications such as vertical runs, sus-
Soldering cable terminals requires extensive special skills and is therefore to be pended on brackets or laid in soil that is likely to subside.
carried out by especially qualified experts only.
1.3.5 Serving over armouring in paper insulated cables shall consist of a com-

 plete layer or layers of suitable compounded Hessian materials.

SELECTION OF CABLE SIZES

1.4.1 The cable sizes shall be selected by considering the voltage drop in the
case of MV (distribution) cables and Current carrying capacity in the case of
Fig. 3.26. Cable terminal finished by soldering
HV (feeder) cables. Due consideration should be given for the Prospective
1 plastic tube or tape short circuit current and the period of its flow, especially in the case of HV ca-
bles.

1.4.2 While deciding upon the cable sizes, derating factors for the type of cable
ARMOURING AND SERVING
and depth of laying, grouping, ambient temperature, ground temperature, and
All multicore cables liable for mechanical damage and all HV cabkes (irrespec- soil resistivity shall be taken into account.
tive of the situation of installation) shall be armoured. Where armouring is un-
1.4.3 Guidance for the selection of cables shall be served from relevant Indian
avoidable in dingle core cables, either the armour should be made of nonmag-
Standards such as IS:3961 (Part-1)-1967 for paper insulated lead sheathed ca-
netic material, or it should be ensured that the armouring is not shorted at termi-
bles, IS: 3961 (Part-2)-1967 for PVC insulated and PVC sheathed heavy duty
nations, thus preventing the flow of circulating currents therein.
cables, IS: 5819- 1970 for recommended short circuit ratings of high voltage

17
PVC cables, IS: 1255-1983 on code of practice for installation and mainte- pulled by means of ropes. Alternatively, they may be mounted on a trailer or on
nance of power cables upto and including 33KV rating etc. a suitable mechanical transport.

STORAGE AND HANDLING (iii) For loading into and unloading from vehicles, a crane or a suitable lifting
tackle should be used. Small sized cable drums can also be rolled down care-
(i) The cable drums shall be stored on a well drained, hard surface, so that the
fully on a suitable ramp or rails, for unloading, provided no damage is likely to
drums do not sink in the ground causing rot and damage to the cable drums.
be caused to the cable or to the drum.
Paved surface is preferred, particularly for long term storage.
INSTALLATION
(ii) The drums shall always be stored on their flanges, and not on their flat
sides. (i) Cables with kinks, straightened kinks or any other apparent defects like de-
fective armouring etc. shall not be installed.
(iii) Both ends of the cables especially of PILCA cables should be properly
sealed to prevent ingress/ absorption of moisture by the insulation during stor- (ii) Cables shall not be bent sharp to a small radius either while handing or in
age. installation. The minimum safe bending radius for PVC/XLPE (MV) cables
shall be 12 times the overall diameter of the cable. The minimum safe bending
(iv) Protection from rain and sun is preferable for long term storage for all
radius for PILCA/XLPE (HV) cables shall be as given in Table-II. At joints and
types of cables. There should also ventilation between cable drums.
terminations, the bending radius of individual cores of a multi core cable of
(v) During storage, periodical rolling of drums once in, say, 3 months through any type shall not be less than 15 times its overall diameter.
90 degrees shall be done, in the case of paper insulated cables. Rolling shall be
(iii) The ends of lead sheathed cables shall be sealed with solder immediately
done in the direction of the arrow marked on the drum.
after cutting the cables. In case of PVC cables, suitable sealing compound/tape
(vi) Damaged battens of drums etc. should be replaced as may be necessary. shall be used for this purpose, if likely exposed to rain in transit storage. Suit-
able heat shrinkable caps may also be used for the purpose.
1.5.2 Handling
Route
(i) When the cable drums have to be moved over short distances, they should
be rolled in the direction of the arrow marked on the drum. Before the cable laying work is undertaken, the route of the cable shall be de-
cided by the Engineer-in-Charge considering the following.
(ii) For manual transportation over long distances, the drum should be mounted
on cable drum wheels, strong enough to carry the weight of the drum and

18
(i) While the shortest practicable route should be preferred, the cable route Power and communication cables shall as far as possible cross each other at
shall generally follow fixed developments such as roads, foot paths etc. with right angles. The horizontal and vertical clearances between them shall not be
proper offsets so that future maintenance, identification etc. are rendered easy. less than 60cm.
Cross country run merely to shorten the route length shall not te adopted.
1.6.4 Railway crossing
(ii) Cable route shall be planned away from drains and near the property, espe-
Cables under railway tracks shall be laid in spun reinforced concrete, or cast
cially in the case of LV/MV cables, subject to any special local requirements
iron or steel pipes at such depths as may be specified by the railway authorities,
that may have to be necessarily complied with.
but not less than 1m, measured from the bottom of the sleepers to the top of the
(iii) As far as possible, the alignment of the cable route shall be decided after pipe. Inside railway station limits, pipes shall be laid upto the point of the rail-
taking into consideration the present and likely future requirements of other way station limits, pipes shall be laid upto a minimum distance of 3m from the
services including cables enroute, possibility of widening of roads/lanes etc. center of the nearest track on either side.

(iv) Corrosive soils, ground surrounding sewage effluent etc. shall be avoided 1.6.5 Way Leave
for the routes.
Way leave for the cable route shall be obtained as necessary, from the appropri-
( v ) R o u t e o f c a b l e s o f d i f f e r e n t v o l t a g e s .
 ate authorities, such as, Municipal authorities, Department of telecommunica-
(a) Whenever cables are laid along well demarcated or established roads, the tion, Gas Works, Railways, Civil Aviation authorities, Owners of properties etc.
In case of private property, Section 12/51 of the Indian Electricity Act shall be
LV/MV cables shall be laid farther from the kerb line than HV cables.
complied with.
(b) Cables of different voltages, and also power and control cables shall be
1.6.6 Methods of laying
kept in different trenches with adequate separation. Where available space is
restricted such that this requirement cannot be met, LV/MV cables shall be laid The cables shall be laid direct in ground, pipe, closed or open ducts, cable trays
above HV cables. or on surface of wall etc. The method(s) of laying required shall be specified in
the tender schedule of work.
(c) Where cables cross one another, the cable of higher voltage shall be laid at
a lower level than the cable of lower voltage. 1.6.7 Laying direct in ground 1.6.7.1 General

1.6.3 Proximity to communication cables This method shall be adopted where the cable route is through open ground,
along roads/lanes, etc. and where no frequent excavations are likely to be en-

19
countered and where re-excavation is easily possible without affecting other 1 . 1 K V .

services. (b) When more than one tier of cables is unavoidable and vertical formation

1.6.7.2 Trenching of laying is adopted, the depth of the trench in (ii) a above shall be increased by
30cm for each additional tier to be formed.
( i ) W i d t h o f t r e n c h

The width of the trench shall first be determined on the following basis Where no sand cushioning and protective covering are provided for the cables
as per 2.6.7.3(i)(b), 2.6.7.3(vii)(c) and 2.6.7.3(ix)(d) below, the depth of the
. (a) The minimum width of the trench for laying a single cable
trench as per (ii)(a) and (b) above shall be increased by 25cm.
s h a l l b e 3 5 c m

(iii) Excavation of trenches

. (b) Where more than one cable is to be laid in the same trench in (a) The trenches shall be excavated in reasonably straight lines. Wherever there

h o r i z o n t a l
 is a change in the direction, a suitable curvature shall be adopted complying


with the requirements of clause 2.6.1(ii).

formation, the width of the trench shall be increased such that the inter-axial (b) Where gradients and changes in depth are unavoidable, these shall be grad-

spacing between the cables, except where otherwise specified, shall be at least ual.

20cm. The bottom of the trench shall be level and free from stones, brick bats etc.

© There shall be a clearance of at least 15cm between axis of the end cables (d) The excavation should be done by suitable means-manual or mechanical.
and the sides of the trench. The excavated soil shall be stacked firmly by the side of the trench such that it

(ii) Depth of trench may not fall back into the trench.

The depth of the trench shall be determined on the following basis (Refer fig- (e) Adequate precautions should be taken not to damage any existing cable(s),

ure 1): - (a) Where the cables are laid in a single tier formation, the total depth pipes or any other such installations in the route during excavation. Wherever

of trench shall not be less than 75cm for cables upto 1.1KV and 1.2m for ca- trickd, tiles or protective covers or bare cables are encountered, further excava-

bles above tion shall not be carried out without the approval of the Engineer-in-Charge.

(f) Existing property, if any, exposed during trenching shall be temporarily sup-
ported adequately as directed by the Engineer-in-Charge. The trenching in such

20
cases shall be done in short lengths, necessary pipes laid for passing cables carry the weight of the drum without failure, and that the spindle is horizontal
therein and the trench refilled in accordance with clause 2.6.7.4. in the bearings so as to prevent the drum creeping to one side while rotating.

(g) It there is any danger of a trench collapsing or endangering adjacent struc- (iv) The cable shall be pulled over on rollers in the trench steadily and uni-
tures, the sides may be left in place when back filling the trench. formly without jerks and strain. The entire cable length shall as far as possible
be laid off in one stretch. PVC/XLPE cables less than 120sq.mm. size may be
(h)Excavation through lawns shall be done in consultation with the Department
removed by “Flaking” i.e. by making one long loop in the reverse direction.
concerned.
Note: - For short runs and sizes upto 50sq.mm. of MV cables, any other suit-
Laying of cable in trench
able method of direct handing and laying can be adopted without strain or ex-
(i) Sand cushioning cess bending of the cables.

(a) The trench shall then be provided with a layer of clean, dry sand cushion of (v) After the cable has been so uncoiled, it shall be lifted slightly over the roll-
not less than 8cm in depth, before laying the cables therein. ers beginning from one and by helpers standing about 10m apart and drawn
straight. The cable shall then be lifted off the rollers and laid in a reasonably
(b) However, sand cushioning as per (a) above need not be provided for MV
straight line.
cables, where there is no possibility of any mechanical damage to the cables
due to heavy or shock loading on the soil above. Such stretches shall be clearly (vi) Testing before covering
specified in the tender documents.
The cables shall be tested for continuity of cores and insulation resistance (Re-
© Sand cushioning as per (a) above shall however be invariably provided in fer clause 2.8.1) and the cable length shall be measured, before closing the
the case of HV cables. trench. The cable end shall be sealed /covered as per clause 2.6.1 (iii)

(ii) Testing before laying ( v i i ) S a n d c o v e r i n g



Cables laid in trenches in a single tier formation shall have a covering of dry
All the time of issue of cables for laying, the cables shall be tested for continu-
sand of not
ity and insulation resistance (See also clause 2.8.1)
less than 17cm above the base cushion of sand before the protective cover is
(iii) The cable drum shall be properly mounted on jacks, or on a cable wheel at
laid.
a suitable location, making sure that the spindle, jack etc. are strong enough to

21
In the case of vertical multi-tier formation, after the first cable has been laid, a (a) Mechanical protection to cables shall be laid over the covering in accor-
sand cushion of 30cm shall be provided over the base cushion before the sec- d a n c e w i t h

ond tier is laid. If additional tiers are formed, each of the subsequent tiers also
shall have a sand cushion of 30cm as stated above. Cables in the top most tiers
(b) and (c) below to provide warning to future excavators of the presence of
shall have final sand covering not less than 17cm before the protective cover is
laid. t h e c a b l e

and also to protect the cable against accidental mechanical damage by pick-axe
Sand covering as per (a) and (b) above need not be provided for MV cables blows etc.
where a decision is taken by the Engineer-in-Charge as per sub clause (i)(b)
above, but the inter tier spacing should be maintained as in (b) above with soft (b) Unless otherwise specified, the cables shall be protected by second class

soil instead of sand between tiers and for covering. brick of nominal size 22cmX11.4cmX7 cm or locally available size, placed on
top of the sand (or, soil as the case may be). The bricks shall be placed breadth-
Sand cushioning as per (a) and (b) above shall however be invariably provided wise for the full length of the cable. Where more than one cable is to be laid in
in the case of HV cables. the same trench, this protective covering shall cover all the cables and project

(viii) Extra loop cable at least 5cm over the sides of the end cables.

(a) At the time of original installation, approximately 3m of surplus cable shall © Where bricks are not easily available, or are comparatively costly, there is no

be left on each terminal end of the cable and on each side of the underground objection to use locally available material such as tiles or slates or stone/

joints. The surplus cable shall be left in the form of a loop. Where there are cement concrete slabs. Where such an alternative is acceptable, the same shall

long runs of cables such loose cable may be left at suitable intervals as speci- be clearly specified in the tender specifications.

fied by the Engineer-in-Charge. (d) Protective covering as per (b) and (c) above need not be provided only for

(b) Where it may not be practically possible to provide separation between ca- MV cables, in exceptional cases where there is normally no possibility of subse-

bles when forming loops of a number of cables as in the case of cables emanat- quent excavation. Such cases shall be particularly specified in the Tender speci-

ing from a substation, measurement shall be made only to the extent of actual fications.

volume of excavation, sand filling etc. and paid for accordingly. (e) The protective covering as per (b) and (c) above shall, however invariably

(ix) Mechanical protection over the covering be provided in the case of HV cables.

22
Back filling Laying of single core cables

(i) The trenches shall be then back-filled with excavated earth, free from stones (i) Three single core cables forming one three phase circuit shall normally be
or other sharp ended debris and shall be rammed and watered, if necessary in laid in close trefoil formation and shall be bound together at intervals of ap-
successive layers not exceeding 30cm depth. proximately 1m.

(ii) Unless otherwise specified, a crown of earth not less than 50mm and not (ii) The relative position of the three cables shall be changed at each joint at the
exceeding 100mm in the center and tapering towards the sides of the trench time of original installation, complete transposition being effected in every
shall be left three consecutive cable lengths.

to allow for subsidence. The crown of the earth however, should not exceed 10 Route markers
Cms so as not to be a hazard to vehicular traffic.
(i) Location
(iii) The temporary re-statements of roadways should be inspected at regular
Route markers shall be provided along the runs of cables at locations approved
intervals, particularly during wet weather and settlements should be made good
by the Engineer-in-Charge and generally at intervals not exceeding 100m.
by further filling as may be required.
Markers shall also be provided to identity change in the direction of the cable
(iv) After the subsidence has ceased, trenches cut through roadways or other route and at locations of underground joints.
paved areas shall be restored to the same density and materials as the surround-
(ii) (a) Plate type marker
ing area and –re-paved in accordance with the relevant building specifications
to the satisfaction of the Engineer-in-Charge. Route markers shall be made out of 100mm X 5mm GI/ aluminium plate
welded / bolted on 35mm X 35mm X 6mm angle iron, 60cm long. Such plate
(v) Where road beams or lawns have been cut out of necessity, or kerb stones
markers shall be mounted parallel to and at about 0.5m away from the edge of
displaced, the same shall be repaired and made good, except for turfing /as-
the trench.
phalting, to the satisfaction of the Engineer-in-Charge and all the surplus earth
or rock shall be removed to places as specified. (b) CC marker

Alternatively, cement concrete 1:2:4 (1 cement:2 coarse sand: 4 graded stone


aggregate of 20mm in size) as shown in figure 2 shall be laid flat and centered
over the cable. The concrete markers, unless otherwise instructed by the

23
Engineer-in-Charge, shall project over the surrounding surface so as to make cable enters and leaves the crossing. This is particularly important for HV ca-
the cable route easily identifiable. bles.

( c ) I n s c r i p t i o n
 (iii) When pipes are laid cutting an existing road, care shall be taken so that the
The words ‘CPWD-MV/HV CABLE’ as the case may be, shall be inscribed on soil filled up after laying the pipes is rammed well in layers with watering as
the marker. required to ensure proper compaction. A crown of earth not exceeding 10cm
should be left at the top. (iv) The temporary re-instatements of roadways
Laying in pipes / closed ducts
should be inspected at regular intervals, particularly after a rain, and any settle-
1.6.8.1 In locations such as road crossing, entry in to buildings, paved areas ment should be made good by further filling as may be required.
etc. cables shall be laid in pipes or closed ducts. Metallic pipe shall be used as
(v) After the subsidence has ceases, the top of the filled up trenches in road-
protection pipe for cables fixed on poles of overhead lines.
ways or other paved areas shall be restored to the same density and material as
1.6.8.2 the surrounding area in accordance with the relevant CPWD Building Specifica-
tions to the satisfaction of the Engineer-in-Charge.
(i) Stone ware pipes, GI, CI or spun reinforced concrete pipes shall be used for
cables in general; however only GI pipe shall be used as protection pipe on 1.6.8.5 Manholes shall be provided to facilitate feeding/drawing in of cables
p o l e s .
 with sufficient working space for the purpose. They shall be covered by suit-
(ii) The size of the pipe shall not be less than 10cm in diameter for a single ca- able manhole covers. Sizes and other details shall be indicated in the Schedule
ble and not less than 15cm for more than one cable. of work.

(iii) Where steel pipes are employed for protection of single core cable feeding Cable entry into the building
AC load, the pipe should be large enough to contain both cables in the case of
Pipes for cable entries to the building shall slope downwards from the building.
single phase system and all cables in the case of poly phase system.
 The pipes at the building end shall be suitably sealed to avoid entry of water,
(iv) Pipes for MV and HV cables shall be independent ones. after the cables are laid.

Road crossings 1.6.8.7 Cable-grip / draw-wires, winches etc. may be employed for drawing ca-

(i) The top surface of pipes shall be at a minimum depth of 1m from the pave- bles through pipes / closed ducts.

m e n t l e v e l w h e n l a i d u n d e r r o a d s , p a v e m e n t s e t c .

(ii) The pipes shall be laid preferably askew to reduce the angle of bend as the

24
1.6.8.8 Measurement for drawing/ laying cables in pipes/ closed duct shall be be fixed on the wall by bolts grouted into the wall in an approved manner at a
on the basis of the actual length of the pipe / duct for each run of the cable, irre- spacing of not less than 60cm.
spective of the length of cable drawn through.
Laying on cable tray
Laying in open ducts
This method may be adopted in places like indoor substations, air-conditioning
1.6.9.1 Open ducts with suitable removable covers (RCC slabs or chequered plant rooms, generator rooms etc. or where long horizontal runs of cables are
plates) are generally provided in sub-stations, switch rooms, plant rooms, work- required within the building and where it is not convenient to carry the cable in
shops etc. for taking the cables. The cable ducts should be of suitable dimen- open ducts. This method is preferred where heavy sized cables or a number of
sions for the number of cables involved. cables are required to be laid. The cable trays may be either of perforated sheet
type or of ladder type.
(i) Laying of cables with different voltage ratings in the same duct shall be
avoided. Where it is inescapable to take HV & MV cables same trench, they Perforated type cable tray
shall be laid with a barrier between them or alternatively, one of the two (HV
(i) The cable tray shall be fabricated out of slotted/perforated MS sheets as
&MV) cables may be taken through pipe(s).
channel sections, single or double bended. The channel sections shall be sup-
(ii) Splices or joints of any type shall not be permitted inside the ducts. plied in convenient lengths and assembled at site to the desired lengths. These
may be galvanished or painted as specified. Alternatively, where specified, the
(i) The cables shall be laid directly in the duct such that unnecessary crossing
cable tray may be fabricated by two angle irons of 50mmX50mmX6mm as two
of cables is avoided.
longitudinal members, with cross bracings between them by 50mmX5mm flats
(ii) Where specified, cables may be fixed with clamps on the walls of the duct welded/bolted to the angles at 1 m spacing. 2mm thick MS perforated sheet
or taken in hooks/brackets/troughs in ducts. shall be suitably welded/bolted to the base as well as on the two sides.

Where specified, ducts may be filled with dry sand after the cables are laid and (ii) Typically, the dimensions, fabrication details etc. are shown in figure 3A,B
covered as above, or finished with cement plaster, specially in high voltage ap- and C.
plications.
(iii) The jointing between the sections shall be made with coupler plates of the
The arrangement of laying the cables in cradles is permitted only in the case of same material and thickness as the channel section. Two coupler plates, each of
cables of 1.1KV grade of size exceeding 120sq.mm. In such cases, the cables minimum 200mm length, shall be bolted on each of the two sides of the chan-
may be suspended on MS flat cradles of size 50mmX5mm which in turn shall nel section with 8mm dia round headed bolts, nuts and washers. In order to

25
maintain proper earth continuity bond, the paint on the contact surfaces be- dirt and rust, and finished with two coats of spray paint of approved make syn-
tween the coupler plates and cable tray shall be scraped and removed before thetic enamel paint.
the installation.
(ix) The cable tray shall be bonded to the earth Terminal of the switch bonds at
(iv) The maximum permissible uniformly distributed load for various sizes of both ends.
cables trays and for different supported span are given in Table IV. The sizes
(x) The cable trays shall be measured on unit length basis, along the center line
shall be specified considering the same.
of the cable tray, including bends, reducers, tees, cross joints, etc. and paid for
(v) The width of the cable tray shall be chosen so as to accommodate all the accordingly.
cables in one tier, plus 30 to 50% additional width for future expansion. This
Ladder type cable tray
additional width shall be minimum 100mm. The overall width of one cable tray
shall be limited to 800mm. (i) The ladder type of cable tray shall be fabricated of double bended channel
section longitudinal members with single bended channel section rungs of
(vi) Factory fabricated bends, reducers, tee/cross junctions, etc. shall be pro-
cross members welded to the base of the longitudinal members at a center to
vided as per good engineering practice. (Details are typically shown in figure
center spacing of 250cm.
3). The radius of bends, junctions etc. shall not be less than the minimum per-
missible radius of bending of the largest size of cable to be carried by the cable (ii) Alternatively, where specified, ladder type cable trays may be fabricated
tray. out of 50mmX50mmX6mm (minimum) angle iron for longitudinal members,
and 30mmX6mm flat for rungs.
(vii) The cable tray shall be suspended from the ceiling slab with the help of
10mm dia MS rounds or 25mmX5mm flats at specified spacing (based on Ta- (iii) Typical details of fabrication and dimensions of both the types of trays are
ble III). Flat type suspenders may be used for channels upto 450mm width shown in figure 4A,B,C and D.
bolted to cable trays. Round suspenders shall be threaded and bolted to the ca-
(iv) The maximum permissible loading, jointing of channel sections, width of
ble trays or to independent support angles 50mmX50mmX5mm at the bottom
the cable tray, provision of elbows, bends, reducers, horizontal tee/ cross junc-
end as specified. These shall be grouted to the ceiling slab at the other end
tions etc. suspension of cable tray from the ceiling slab; painting and measure-
through an effective means, as approved by the Engineer-in-Charge, to take the
ment of the cable tray shall be as per sub-clauses (ii) to (x) below clause
weight of the cable tray with the cables.
2.6.11.2, except that the overall width of one cable tray may be limited to
(viii) The entire tray (except in the case of galvanized type) and the suspenders 800mm.
shall be painted with two coats of red oxide primer paint after removing the

26
1.6.11.4 Cables laid on cable trays shall be clamped on to the tray at suitable Safety precaution
intervals as per Table-III.
(i) A caution board indicating “CAUTION – CABLE JOINTING WORK IN
Cable identification tags PROGRESS” shall be displayed to warn the public and traffic where necessary.

Whenever more than one cable is laid / run side by side, marker tags as ap- (ii) Before jointing is commenced, all safety precautions like isolation, dis-
proved, inscribed with cable identification details shall be permanently at- charging, earthing, display of caution board on the controlling switchgear etc.
tached to al the cables in the manholes / pull pits / joint pits / entry points in shall be taken to ensure that the cable would not be inadvertently charged from
buildings / open ducts etc. These shall also be attached to cables laid direct in live supply. Metallic armour and external metallic bonding shall be connected
ground at specified intervals, before the trenches are backfilled. to earth. Where “Permit to work” system is in vogue, safety procedures pre-
scribed shall be complied with.
JOINTING
Jointing materials
(i) Before laying a cable, proper locations for the proposed cable joints, if any,
shall be decided, so that when the cable is actually laid, the joints are made in (i) Jointing materials and accessories like conductor ferrules, solder, flux, insu-
the most suitable places. As far as possible, water logged locations, carriage lating and protective tapes, filling compound, jointing boxes, heat shrinking
ways, pavements, proximity to telephone cables, gas or water mains, inaccessi- joint kit etc. of right quality and correct sizes, conforming to relevant Indian
ble places, ducts, pipes, racks etc. shall be avoided for locating the cable joints. Standards, wherever they exist, shall be used.

(ii) Joints shall be staggered by 2m to 3m when joints are to be done for two or (ii) The design of the joint box and the composition of the filing compound
more cables laid together in the same trench. shall be such as to provide an effective sealing against entry of moisture in addi-
tion to affording proper electrical characteristic to joints.
Joints pits
(iii) Where special type of splicing connector kits or epoxy resin spliced joints
(i) Joint pits shall be of sufficient dimensions as to allow easy and comfortable
or heat shrinkable jointing kits are specified, materials approved for such appli-
working. The sides of the pit shall be well protected from loose earth falling
cation shall be used. Storing as well as jointing instructions of the manufacturer
into it. It shall also be covered by a tarpaulin to prevent dust and other foreign
of such materials shall be strictly followed.
matter being blown on the exposed joints and jointing materials.

(ii) Sufficient ventilation shall be provided during jointing operation in order to


disperse fumes given out by fluxing.

27
Jointer

Jointing work shall be carried out by a licensed/ experienced (where there is no


licensing system for jointers) cable jointer.

Cable work with joints

(i) About 3m long surplus cable shall be left on each side of joints as laid down
in clause 1.6.7.3 (viii).

(ii) Insulation resistance of cables to be jointed shall be tested as per clause


1.8.1. Unless the insulation resistance values are satisfactory, jointing shall
not be done.

(iii)(iii) Cores of the cables must be properly identified before jointing.



(iv) Where cable is to be jointed with the existing cable, the sequence
should be so arranged as to avoid crossing of cores wile jointing.

(v) Whenever the aluminium conductor is exposed to outside atmosphere, a


highly tenacious oxide film is formed which makes the soldering of aluminium
conductor difficult. This oxide film should be removed by using appropriate
type of flux.

(vi) The clamps for the armour shall be clean and tight.

Jointing procedure

While it would be necessary to follow strictly the instructions for jointing fur-
nished by the manufacturers of cables and joint kits, a brief on the jointing pro-
cedures is given for general guidance in Appendix F.

28
SECTION 2

Testing of Cables

T E S T I N G
 Testing before backfilling


Testing before laying
All cables shall be subjected to the above mentioned tests, before covering the
All cables, before laying, shall be tested with a 500V megger for cables of cables by protective covers and back filling and also before taking up any joint-
1.1KV grade, or with a 2500/5000V megger for cables of higher voltage. The ing operation.
cable cores shall be tested for continuity, absence of cross phasing, insulation
resistance from conductors to earth / armour and between conductors.

29
Testing after laying Step 3 - Cable tracing: When an underground cable is first laid, it rarely runs in
a straight line, but rather meanders in depth and direction. Cable tracing is done
(i) After laying and jointing, the cable shall be subjected to a 15 minutes pres-
to determine that the route of the cable is following the expected path.
sure test. The test pressure shall be as given in Table VI. DC pressure testing
may normally be preferred to AC pressure testing. Step 4 - Fault identification: The first major procedure is to determine the
phase on which the fault has occurred and if it is of low or high resistance. This
(ii) In the absence of facilities for pressure testing as above, it is sufficient to
test determines the correct technique, and therefore equipment, needed to diag-
test for one minute with 1000V megger for cables of 1.1KV grade and with
nose the fault. Typically, if the fault is found to be below 100 Ohms, a low volt-
2500/5000V megger for cables of higher voltages.
age pulse (eg: 40 V) from a TDR (time domain reflectometer) can be used. If
Cable fault location the fault is a higher resistance (> 100 Ohm), a low voltage pulse will likely not
see it. For these types of faults, an impulse generator (shock discharge) or
is required anywhere where the fault cannot be seen. This is a multi-step proc-
bridge, will be necessary.
ess that must be performed as safely and as quickly as possible to prevent cus-
tomers going without power. Step 5 – Fault prelocation: A reliable and precise pre-location method is neces-
sary to locate a cable fault quickly and efficiently. Good pre-location can deter-
Step 1 - Cable isolation and safety procedures: A cable fault is nearly always a
mine the fault position to within a few percent of the cable length and will re-
permanent fault. This means that the cable in question will be in a condition
duce pinpointing time to a few minutes.
where the protection devices at one or both ends of the cable will have tripped,
leaving the cable isolated but NOT earthed (grounded). Remember:

The first task is for the authorised person on the site to make the cable safe by a) If it is a low resistance fault, pre-location is likely to be the only means nec-
isolating and then earthing (grounding) one or both ends. Only after the appro- essary for location.
priate procedures have been carried out can any testing personnel be allowed to
b) For high resistance faults, ARM (arc reflection) or ICE (impulse current)
approach the cable and prepare for testing.
techniques on an SWG (surge wave generator) should be used. Alternatively,
Step 2 - Cable identification: Where multiple cables exist, cable identification the decay method with an HV DC tester (bridge) can be used for pre-location.
testing will identify the correct cable to work on. Clear identification before a
Step 6 - Pinpointing: The aforementioned test methods will get the operator
cable is cut is intrinsic to safe maintenance work. Any mistakes here can be fa-
within 5% distance of the fault. Acoustic pinpointing techniques must be em-
tal and may cause much longer outages for the connected customers.
ployed at this stage in order to narrow the margin of error to 0.1%. In most

30
cases, shock discharge generators are used for pinpointing in conjunction with predicted, a large long-lasting arc may occur. This can cause damage to the sur-
acoustic methods. The discharge creates a loud noise, which is pinpointed pre- roundings, and it can start a fire.
cisely using an acoustic pinpointing device. This device evaluates the time dif-
A resistive neutral is closely related to a loose neutral. A resistive neutral oc-
ference between the acoustic signal (speed of sound) and the electromagnetic
curs when the neutral is connected, but it’s not a very good connection. Good
(nearly the speed of light) impulse of the shock discharge. When the shortest
connections have extremely low electrical resistance, but a resistive neutral con-
time difference is indicated, the exact fault location is revealed.
dition has an intermediate resistance — its resistance is low enough to conduct
Step 7 - Re-energisation of the cable: Once all testing and repairs are com- some electricity, but too high to conduct as well as it’s supposed to. This poor
pleted, the Safety/Testing documentation is cancelled and the cable is handed connection has several damaging and dangerous effects.
back to the appropriate operators so they can reinstate it and re-energise the
One effect is that a loose or resistive neutral can cause abnormally high and
loads on the newly repaired cable.
low voltages to occur in the house wiring. For example, a cardinal sign of a re-
Effect of loose neutral connections: sistive neutral is that lights will get brighter than normal at odd times, such as
when another circuit is turned on, or when an appliance cycles on. A resistive
loose neutral wire can cause abnormal arcing around its point of connection, neutral won’t always cause the lights to get abnormally bright, but when it hap-
usually resulting in the neutral wire becoming unusually hot, burning its insula- pens, it’s a pretty reliable indication that you have a resistive neutral. If you are
tion off and even causing damage to its surroundings. aware of a situation in which the lights get abnormally bright when other cir-
cuits are used, you should call the power company and report that you believe
A loose neutral wire is also the cause of the majority of electrical fires.
that there is a problem with the neutral connection. They know this can be very
Arcing occurs because the loose wire does not make consistent contact. Some- dangerous, so they will likely treat it as a high-priority situation.

times it does make contact and sometimes it doesn’t. This can happen due to a Another effect of a resistive neutral connection is that the connection becomes
variety of factors, such as an outside supply wire swaying in the breeze (if the hot. As a result, it can overheat its surroundings and even start a fire. Even if it
wire or its connections are damaged), or it can happen inside due to changes in doesn’t do either of these right away, it will tend to get worse over time be-
temperature, electrical load, or mechanical disturbance. cause heat accelerates the aging of the wire, its insulation, and surrounding ma-

Every time the connection is made or broken, an arc forms. Usually this arc is terials.

very brief, but it is very hot and so it causes some damage every time. Thus the Another very dangerous effect of a loose or resistive neutral is that it can can
condition of the connection gets worse over time. At some time that can’t be lead to electrical shocks and even electrocution. The ways this can happen are

31
extremely unpredictable and depend on exactly how your house is wired and you would like to replace your old main fuse with a more up-to-date and reli-
the exact conditoin of the wiring. Here is a real example: if one resident of a able main fuse, with the same amperage;
certain house was in the shower when another resident used the garbage dis-
You want to transfer from a single-phase to a three-phase network connection.
posal, the first resident would feel a mild electrical tingle. No one else in the
house could feel it. This turned out to be due to neutral wire at the electrical I n c r e a s i n g t h e a m p e r a g e o f a m a i n f u s e

pole that was nearly broken. Only three strands of wire were still connected. The procedure for increasing the amperage of the main fuse is the same as for
Had the remaining strands been allowed to deteriorate further, someone would connecting to the power network. If the amperage at the place of consumption
have been electrocuted. This is just one example of why it’s important to get is too low, the amperage of the main fuse should be increased.

immediate attention for problems with neutral connections. When the amperage of a main fuse is increased, the fuse is changed at its exist-
ing location, while the supply point is not relocated. The prices for increasing
Fuses on service lines:
the main fuse amperage are listed on the network connection page.

Why do I need main fuse services? If the main fuse cannot be changed at its existing location, perhaps because

It is important for the rating of the main fuse in your place of consumption to there is no junction box or fuse base that meets the requirements or because the

be correct so that you can use electricity without any problems. The main fuse cables are old, you will have to upgrade your main fuse box and, if necessary,

has two functions – it provides fire protection by switching off in the event of a the electrical system inside your house. Once the required work has been done,

short circuit, and it determines how many household appliances you can use at we will install a main fuse of the amperage you have requested in the upgraded

any one time. The higher your main fuse rating, the more electrical appliances j u n c t i o n b o x .


you can use at the same time and the higher their wattage can be. If you plan to improve the electrical system in your house or are already doing
so, you can also ask us to relocate your supply point in addition to increase the
You will need our main fuse services if: amperage of the main fuse. We usually install a junction box at the border of

your fuses keep blowing, as this means that the main fuse amper- the property and install a main fuse of the amperage you have requested. A

age in your place of consumption is too low and you should increase it; cost-based fee of 1000–1500 euros will be charged for relocating the supply
p o i n t .

the main fuse amperage is higher than you need, meaning that you
How much does it cost to increase the amperage of the main fuse?

could save on costs by lowering the amperage of the main fuse if you are using
The fee depends on how many additional amperes you want to buy and on the
a package with a fixed fee;
distance between the supply point and the substation.

32
If the distance from a low voltage substation is up to 400 metres, one ampere A d d i n g m a i n f u s e s

costs 156.00 euros (including VAT). If you have two or more supply points on your property, they can be added or
m e r g e d .

If the connection point is more than 400 metres from the low voltage substa-
For example, when a house has a single-phase connection with a 16 A main
tion, we will calculate the fee for increasing the amperage of your main fuse
fuse and an ancillary building has a three-phase connection with a 16 A main
based on the actual costs of the main fuse replacement; there may be additional
fuse, these main fuses can be added to form a three-phase connection with a 32
costs for network renovation work.

There is no main fuse for medium voltage network connections. The cost of
increasing network transmission capacity is always based on actual costs. D i v i d i n g a m a i n f u s e


R e p l a c i n g m a i n f u s e s

You can replace your main fuse with one with higher nominal amperage, for The division of the nominal amperage of the existing main fuse with the con-

example you could replace a thermal fuse with a circuit breaker or an older sent of the owner between consumers on the same cadastral unit or between

type circuit breaker with a newer type. We do not change the location of the new cadastral units created by the division of a cadastral unit – for example, if
a new home or other building is built on a property or if an existing building is
supply point and main fuse when we replace the main fuse.

divided between co-owners who want separate network connections. When a

cadastral unit is split, there are two ways that a new property can obtain a net-
How much does it cost to replace a main fuse?
work connection:
The fee for replacing a main fuse of up to 63 A is 45.76 euros.
Connection of a new place of consumption
The fee for replacing a main fuse of over 63 A is cost-based and depends on the
Division of the main fuse of a cadastral unit being divided. This is an option if
cost of equipment, materials and work.
the existing main fuse amperage is too high. It is unreasonable to divide a main
A d d i n g a n d d i v i d i n g m a i n f u s e s
 fuse with an amperage under 32 A.
An existing main fuse can be divided when a property is divided. Main fuses
How much does it cost to add or divide the amperage of a main fuse?

o n t h e s a m e p r o p e r t y c a n b e a d d e d .

The price of the service depends on the actual cost of equipment, materials and

 work.

33
Causes of Dim and Flickering Lights: Problems with the Power Grid

It can be scary moving to a new house or apartment, especially if the establish- Has your area experienced some bad weather lately? A transformer may have
ment is old to the neighborhood. Sometimes the doors creak a little more than blown, or the service feed coming into your house may have been interrupted.
you’re used to, or the cabinets don’t shut all the way, or the appliances fail to Both are common occurrences during a storm. The problem may even be at the
operate correctly. When I first moved to my new/old apartment, I faced all of local utility substation. Brownouts (all-around dim lights) are not as common
these minor annoyances. However, none were as alarming as one peculiar phe- as blackouts, but they can happen when there is a city-wide power shortage or
nomenon: every time I used my microwave, the lights would flicker and dim an unusually high demand for power.
until my food was done cooking. While my meal was always properly warmed
Improper Wiring
and the lights always went back to normal, it was still a little unsettling. Was
this indicative of a larger problem? Below, we’ll review the cause of my situa- Another reason your lights could be dimming unexpectedly is because the wir-
tion, as well as some other common reasons house lights go dim (other than ing throughout your home is outdated or insufficient to handle the amount of
your light dimmer switch, of course!). current it uses. When the electrical service has a demand for too much current,
the voltage can drop, causing your lights to dim. Many older houses have this
Overloaded Circuit
problem; they simply weren’t built to handle the electrical loads of today’s
If your lights dim when you are running an appliance, such as a dryer, air condi- modern household, which typically features many devices or appliances that all
tioner, or microwave like in my case, check to see if the lights are on the same require large amounts of power. If this is the case, you may require new wiring
circuit as the appliance. You might be simply dealing with an overloaded cir- or a new service – ask an electrician.
cuit – meaning your circuit is outdated or wired to run more appliances than it
Loose or Corroded Neutral Wire
can handle. This is typically the case if you are living in an older abode. Al-
though annoying, overloaded circuits due to appliance usage are common and If the lights in your house are fluctuating between bright and dim, you could
not typically a danger. However, if you find that your lights are dimming be- have a more serious problem on your hands. You might have a loose or cor-
yond the use of the appliance, or if the appliance is tripping your circuit roded neutral wire in your circuit breaker. The circuit breaker contains three
breaker, another reason could be behind the dimming. It’s time to call an electri- wires: the first is red or black (the "hot" wire) the second is white (the "neutral"
cian. wire) and the third is a green or bare (the "ground” wire) which is only used for
safety purposes. The first two wires are responsible for providing power to
your household circuit. The neutral wire simply provides a return path to earth
ground in the electrical panel to complete the circuit. A broken neutral wire

34
means that the return path to the electrical panel is incomplete, which can
Interactive 1.1 Module 4
cause imbalances in the two main power wires. When your lights brighten they
are receiving too much voltage, and when they are dimming, they are receiving
too little. If this problem worsens, your electrical devices could end up receiv-
ing far too much or too little power and become damaged. Loose or bad connec-
tions are the major cause of fires and other safety hazards. Contact an electri-
cian as soon as possible.

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do tempor
incididunt ut labore et dolore magna aliqua.

35
Movie 1.1 Module 4 Review 1.1 Module 4

Question 1 of 5
If the length of a cable is increased, its capacitance

A. decreases.

B. increases.

C. remain same.

D. none of the above.

Check Answer

36
Grooving

! ! long, narrow cut or indentation in a surface, as the cut in a board to receive the
tongue of another board (tongue-and-groove joint), a furrow, or a natural indentation on an
organism.

Related Glossary Terms


Drag related terms here

Index Find Term


Paved surface

covered with a firm surface suitable for travel, as with paving stones or concrete. a small
paved courtyard. covered with a hard layer of something. shelves paved with marble.

Related Glossary Terms


Drag related terms here

Index Find Term


Trench

dig a trench or trenches in (the ground).

Related Glossary Terms


Drag related terms here

Index Find Term


Underground Cables

Cable designed to be place underground, either directly buried or in conduit. Underground


cable must be specially designed to protect against moisture, rodents, cable-seeking back-
hoes, and other earth-moving equipment.

Related Glossary Terms


Drag related terms here

Index Find Term


Way Leave

a right of way granted by a landowner, generally in exchange for payment and typically for
purposes such as the erection of telegraph wires or laying of pipes.

Related Glossary Terms


Drag related terms here

Index Find Term

Das könnte Ihnen auch gefallen