REVISION
DESCRIPTION DATE ORIGINATOR REVIEWER APPROVER
NO.
1A ISSUED FOR COMMENT 12-Sep-19 VV LHK UM
4 5 6
REVISION
SHEET DESCRIPTION TOTAL PAGE
O1 F1 F2
1 COVER SHEET 1 PAGE X X X
2 REVISION CONTROL PAGE 1 PAGE X X X
3 INDEX SHEET 1 PAGE X X X
4 NOTES SHEET 1 1 PAGE X X X
5 NOTES SHEET 2 1 PAGE X X X
6 NOTES SHEET 3 1 PAGE X X X
7 NOTES SHEET 4 1 PAGE X X X
8 27TIA-501-TX 1 PAGE X X X
9 27TI-502-TX 1 PAGE X X X
10 27TI-503-TX 1 PAGE X X X
11 27TI-504-TX 1 PAGE X X X
12 27TIA-522-TX 1 PAGE X X X
13 27TI-505-TX 1 PAGE X X X
14 27TI-506-TX 1 PAGE X X X
15 27TIC-507-TX 1 PAGE X X X
16 27TIA-508-TX 1 PAGE X X X
17 27TI-509-TX 1 PAGE X X X
18 27TIA-510-TX 1 PAGE X X X
19 27TI-512-TX 1 PAGE X X X
20 27TI-513-TX 1 PAGE X X X
21 27TI-514-TX 1 PAGE X X X
22 27TICA-521-TX 1 PAGE X X X
23 27TI-555-TX 1 PAGE X X X
24 27TIA-531-TX 1 PAGE X
25 27TIA-532-TX 1 PAGE X
26 27TIA-533-TX 1 PAGE X
27 27TIA-534-TX 1 PAGE X
28 SUPPLIER DOCUMENTATION REQUIREMENT 1 1 PAGE X X X
29 SUPPLIER DOCUMENTATION REQUIREMENT 2 1 PAGE X X X
30 DEVIATION LIST 1 PAGE X X X
31 ATTACHMENT 1: TEMPERATURE TRANSMITTER 1 PAGE X X X
PROCESS SPECIFICATION, Rev.F2
DATA SHEET NO.:
DATE
CLIENT: SHELL EASTERN PETROLEUM PTE LTD. SITE: PULAU BUKOM, SINGAPORE 0591-8550-DS-03-0018
4 5 6
GENERAL NOTES
1) TI for skin temperature locate opposite to inlet nozzle.
2) Alternate design conditions are 3.5 bar g / FV @ 190ºC (for steam out purpose)
3) TBA = TO BE ADVISE, VTA = VENDOR TO ADVISE, N/A = NOT APPLICABLE, AMB = AMBIENT,
ATM = ATMOSPHERIC, G.NOTES = GENERAL NOTES, FV = FULL VACUUM.
4) Instrument Transmitters connected to thermocouples shall have automatic compensation for temperature
variations at the cold junction.
5) For RTD, Temperature Transmitters shall be used for signal conversion in the field.
6) For Thermocouples, Temperature Transmitters with zero compensation shall be used for signal conversion in
the field.
7) Temperature transmitters shall be protected from lightning with built-in lightning surge arrestor function.
8) All field electronic instruments shall have an RFI immunity circuit to suppress RF signals.
9) Materials and all electrical components shall be suitable for corrosive atmosphere and tropical climate.
10) Vendor calibration certificate for all instruments and instrument system shall be checked and documented
in accordance with the quality plan. Calibration equipment shall be provided by calibration certificate and
traceable to accredited laboratory. Refer to section 6, DEP 62.10.08.11
11) Remote head housing is supply by others.
12) Vendor to provide model decoding or nomenclature for each product model offered.
13) Vendor to include the recommended spare parts on the quotation.
14) All Transmitters shall have Hermetically sealed electronics.
15) All HART Transmitters shall have following settings.
4 5 6
GENERAL NOTES
DATA SHEET NO.:
DATE
CLIENT: SHELL EASTERN PETROLEUM PTE LTD. SITE: PULAU BUKOM, SINGAPORE 0591-8550-DS-03-0018
4 5 6
HOLDS
1) High Alarm Setting
2) Low Alarm Setting
3) Tag Name assignment for 27TIA-XXX and 27TI-XXX
DATA SHEET NO.:
DATE
CLIENT: SHELL EASTERN PETROLEUM PTE LTD. SITE: PULAU BUKOM, SINGAPORE 0591-8550-DS-03-0018
4 5 6
1 ISBL PEFS:
Wood Dwg No Shell PEFS No.: Rev.
0591-8110-25-0016 B-4.042.891 S1
0591-8110-25-0017 B-4.042.892 S1
0591-8110-25-0019 B-4.042.894 S1
0591-8110-25-0034 B-4.042.921 S1
62 CAUSTIC WASH&LPG
3 Service --- C-2753 OVERHEAD Location/Unit '--- FACILITIES/2750
4 P.E.F.S darws. Number --- 0591-8110-25-0017 63 Zone '--- ZONE 2
5 64 Gas group '--- IIA/IIB
6 Intermediate revison S1 65 Temp category '--- T3
7 66
8 TRANSMITTER: 67 ELECTRONICS:
REMOTE MOUNTED TEMP.TX
68
9 Meter type FOR 3-WIRE RTD Type '--- REMOTE
10 69 Transmission type '--- 2 WIRED
11 70 Supply VDC 24
12 71 Output Signal mA 4-20, HART
13 72
ALUMINIUM EPOXY
73
14 Required repeatabillity % < 1% of span Housing material --- COATED
15 Explosion prot. Cert.transmitter '--- Ex d, IIA/IIB, T3 74 Enclosure case IP 66
16 75 Electrical connections --- SCREW TERMINALS
17 76 Cable entry --- M20 x 1.5
18 77 Output meter '--- YES
19 RANGE: 78
20 Calibrated range °C 0 - 240 79
21 Required Accuracy % 0.25 80
22 Burnout value min/max MA UPSCALE (NOTE3) 81
23 Saturation value min/max MA (NOTE3) 82
24 83
25 84
26 85
27 86
28 87
29 88
30 PROCES DATA 89 SPECIAL REQUIREMENTS
31 Medium/Phase '--- LIGHT HYDROCARBON/ VAPOUR 90
32 91 Validation
33 Operating conditions Min Norm Max 92
34 93
35 Temperature °C - 61-63 - 94
36 95
37 96
38 97
39 98
40 99
41 100
42 101
43 102
44 103
45 104
46 105
47 106 NON-VENDOR RELATED INFO
48 107
49 108
50 109 Grid position '---
51 110 Design code '---
52 111 Shell registration no. '---
53 112 Mesc number '---
54 PURCHASE DATA 113 NOTES
55 Manufacturer '--- Endress & Hauser 114 1. Provide mouting bracket: 304SS suitable for 2" pipe
56 Supplier '--- Endress & Hauser 115 2. Sunshade: SS316 shall be provided
57 Model number '--- TMT162-H22231BBA+NAZ1 116 3. Burnout and Saturation Value as per NAMUR NE 43
58 Serial number '--- TBA 117
59 Item number '--- 118
62 CONDENSATE
3 Service --- LP STEAM FROM A-2751 Location/Unit '--- SYSTEM/2750
4 P.E.F.S darws. Number --- 0591-8110-25-0019 63 Zone '--- ZONE 2
5 64 Gas group '--- IIA/IIB
6 Intermediate revison S1 65 Temp category '--- T3
7 66
8 TRANSMITTER: 67 ELECTRONICS:
REMOTE MOUNTED TEMP.TX
68
9 Meter type FOR 3-WIRE RTD Type '--- REMOTE
10 69 Transmission type '--- 2 WIRED
11 70 Supply VDC 24
12 71 Output Signal mA 4-20, HART
13 72
ALUMINIUM EPOXY
73
14 Required repeatabillity % < 1% of span Housing material --- COATED
15 Explosion prot. Cert.transmitter '--- Ex d, IIA/IIB, T3 74 Enclosure case IP 66
16 75 Electrical connections --- SCREW TERMINALS
17 76 Cable entry --- M20 x 1.5
18 77 Output meter '--- YES
19 RANGE: 78
20 Calibrated range °C 0 - 300 79
21 Required Accuracy % 0.25 80
22 Burnout value min/max MA UPSCALE (NOTE3) 81
23 Saturation value min/max MA (NOTE3) 82
24 83
25 84
26 85
27 86
28 87
29 88
30 PROCES DATA 89 SPECIAL REQUIREMENTS
31 Medium/Phase '--- LP STEAM / VAPOUR 90
32 91 Validation
33 Operating conditions Min Norm Max 92
34 93
35 Temperature °C 130 155 160 94
36 95
37 96
38 97
39 98
40 99
41 100
42 101
43 102
44 103
45 104
46 105
47 106 NON-VENDOR RELATED INFO
48 107
49 108
50 109 Grid position '---
51 110 Design code '---
52 111 Shell registration no. '---
53 112 Mesc number '---
54 PURCHASE DATA 113 NOTES
55 Manufacturer '--- Endress & Hauser 114 1. Provide mouting bracket: 304SS suitable for 2" pipe
56 Supplier '--- Endress & Hauser 115 2. Sunshade: SS316 shall be provided
57 Model number '--- TMT162-H22231BBA+NAZ1 116 3. Burnout and Saturation Value as per NAMUR NE 43
58 Serial number '--- TBA 117
59 Item number '--- 118
4 5 6
This Supplier Documentation Requirements is in conjunction with the FW Standard “General Notes for
Requisitions”, document no. 0605-8820-GN-00-0001, defines the scope of documentation for all Supplier Documents
SUPPLIER shall include the supply of all Documentation to define the Equipment supplied for the purposes of:
•Integration into the Plant Design
•Design Code Compliance
•Regulatory Authority Approval
•Installation, Operation and Maintenance
4 5 6
NOTES FOR SUPPLIER DOCUMENT SUBMISSION TABLE
1) Documents for review shall be submitted via e-procurement process. No hard copy is required to be submitted
2) Documents shall be submitted in accordance with a DUE DATE CODE as follows
A2 DOCUMENT TIMING
A2.1.1 WITH QUOTE
Q Documents shall be submitted with the Quotation.
A2.1.2 FOR REVIEW
Documents shall be submitted in accordance with a DUE DATE CODE as follows
An : n weeks after order placement (normally n=3)
Bn=3 : n weeks after receipt of PURCHASER information (normally n=3)
Dn : n weeks after equipment dispatch (normally n=2)
E : As information becomes available
F : 1 month prior to equipment dispatch and one copy with equipment
G : at Final Inspection
A2.1.3 DATA BOOKS
VDB : n weeks after order placement (normally n=3)
Supplier may specifically note that the MR has total 3nos of WBS as listed at below:
WBS01= ISBL
WBS02= OSBL
WBS03= COMMON AREAS
Each WBS represents different unit/sections of the plant.
During document approval process supplier may combine documents of similar category (i.e Sizing
/ GAD /Reports etc), mentioned above, for all WBS (01 to 03) as single set / document
for XXXX/FWAPL approval
Approved documents/Certified Final documents are to be inserted in the Vendor Data Books as per
VDB index. These documents must be stamped and signed by the WOOD responsible engineer as
Code 4 or 5, as defined in the General Notes
Project requires that supplier provides separate VDB & CD for each WBS (01 to 03).
CD shall be structured for easy navigation to all documents listed in VDB index via use of bookmarks
/ links
The data book shall include 4 sets of hardcopy and 2 sets of electronics copy (CD ROM) for each
WBS (01 to 03).
DATA SHEET NO.:
DATE
CLIENT: SHELL EASTERN PETROLEUM PTE LTD. SITE: PULAU BUKOM, SINGAPORE 0591-8550-DS-03-0018
4 5 6
DEVIATIONS LIST
SUPPLIER shall list all deviations to the Material Requisition and reference documents that are included in the
requisition. SUPPLIER’s quotation is deemed to comply with all requirements except those are brought out
in the deviation list
SUPPLIER’s scope of work and supply shall fully comply with the requirements of this requisition except for the
deviations listed in the following table
Note, SUPPLIER shall propose alternatives and/or the impact, cost and delivery, to comply with the
requirements of the material requisition and associated documents for each deviation tabled
4 5 6
ATTACHMENT 1: TEMPERATURE TRANSMITTER PROCESS SPECIFICATION, Rev.F2 (20 PAGES)
FWAPPL NO: 1-PD-0591
DESIGN FROM: Guswandhi CLIENT: Shell Eastern Petroleum (Pte) Ltd.
INSTRUCTION DEPT: Process INSTRUCTION NO: 0591-DI-PRS-024 Area:
DATE 15-Feb-20 SHEET 1 OF 1
DEVELOPMENT
CLIENT REQUEST ENGINEERING: VENDOR INPUT PROCESS MODIFICATION
MODIFICATION
DISTRIBUTION TO: NAME INFO ACT DISTRIBUTION TO: NAME INFO ACT
CIVIL PROCESS
RO BE FILLED IN BY
SUBJECT: Temperature Transmitter Process Specification Rev F2 and Thermowell Process Specification Rev F1
Decsription: Please find the Process Input for the above said instruments in the attachment. Please discuss in case of any clarification.
SIGNATURE
DCAF Control ID :
Equipment Tag ID :
Page : Page 1 of 23
REVISION
DESCRIPTION DATE ORIGINATOR REVIEWER APPROVER
NO.
O1 Issued for Comment 15-Aug-19 Sivamanickam Jaya Guswandhi
F1 Issued for Final 21-Oct-19 Sivamanickam Jaya Guswandhi
F2 Issued for Final 15-Feb-20 Guswandhi
TEMPERATURE TRANSMITTER PROCESS
SPECIFICATION
CUSTOMERS NAME: SHELL EASTERN PETROLEUM PTE LTD PROJECT No: 1-PD-0591 E
LOCATION: PULAU BUKOM, SINGAPORE UNIT No: 2750
PROJECT TITLE: LPG-4 TREATER PROJECT DOCUMENT CAT.-CLASS 1
REV O1 F1 F2 DOCUMENT No. 0591-8110-PS-0017
DATE 15-Aug-19 21-Oct-19 15-Feb-20 SHEET 3 OF 21
ORIG. BY Sivamanickam Sivamanickam Guswandhi DOCUMENT SEQUENCE No.
APP. BY Guswandhi Guswandhi
NOTES:
1. TI for skin temperature locate opposite to inlet nozzle.
2 Alternate design conditions are 3.5 bar g / FV @ 190ºC (for steam out purpose)
HOLDS:
1. Deleted.
2. Deleted.
3. Deleted.
SHEET 3 of 18
FWEL.2068/18-2 Rev.0 BASE : Instrument datasheet - Control Valve.xls PROJECT SPECIFIC :
DATA SHEET FOR TEMPERATURE TRANSMITTERS contr.job no: 0591E
Rev Units Units
1 GENERAL: --- 60 GENERAL
2 Tag number --- 27-TIA-501 61 Plant '--- SHELL EASTERN PETROLEUM
3 Service --- Lean ADIP 62 Location/Unit '--- PULAU BUKOM
4 P.E.F.S darws. Number --- 0591-8110-25-0016 63 Zone '---
5 64 Gas group '---
6 Intermediate revison R1 65 Temp category '---
7 66
8 TRANSMITTER: 67 ELECTRONICE:
9 Meter type 68 Type '---
10 69 Transmission type '---
11 70 Supply VDC
12 71 Output Signal MA
13 72
14 Required repeatabillity % 73 Housing material ---
15 Explosion prot. Cert.transmitter '--- 74 Enclosure case IP
16 75 Electrical connections ---
17 76 Cable entry ---
18 77 output meter '---
19 RANGE: 78
20 Calibrated range 79
21 Required Accuracy % 80
22 Burnout value min/max MA 81
23 Saturation value min/max MA 82
24 83
25 84
26 85
27 86
28 87
29 88
30 PROCES DATA 89 SPECIAL REQUIREMENTS
31 Medium/Phase '--- Lean ADIP / Liquid 90
32 91 Validation
33 Operating conditions Min Norm Max 92
34 93
35 Temperature °C - 45 94
36 95
37 Density kg/m3 1018 96
38 Viscosity cP 1.819 - 1.836 97
39 98
40 Design Pressure (Note 2) barg 42 / FV 99
41 Design Temperature (Note 2) °C -29 / 120 100
42 101
43 High Alarm °C 52 102
44 103
45 104
46 105
47 106 NON-VENDOR RELATED INFO
48 107
49 108
50 109 Grid position '---
51 110 Design code '---
52 111 Shell registration no. '---
53 112 Mesc number '---
54 PURCHASE DATA 113 REMARKS
55 Manufacturer '--- 114
56 Supplier '--- 115
57 Model number '--- 116
58 Serial number '--- 117
59 Item number '--- 118
DCAF Control ID :
Equipment Tag ID :
Page : Page 1 of 10
REVISION
DESCRIPTION DATE ORIGINATOR REVIEWER APPROVER
NO.
O1 Issued for Comment 15-Aug-19 Sivamanickam Jaya Guswandhi
F1 Issued for Final 15-Feb-20 Guswandhi
THERMOWELL PROCESS SPECIFICATION
CUSTOMERS NAME: SHELL EASTERN PETROLEUM PTE LTD PROJECT No: 1-PD-0591 E
LOCATION: PULAU BUKOM, SINGAPORE UNIT No: 2750
PROJECT TITLE: LPG-4 TREATER PROJECT DOCUMENT CAT.-CLASS 1
REV O1 F1 DOCUMENT No. 0591-8110-PS-0020
DATE 15-Aug-19 15-Feb-20 SHEET 3 OF 10
ORIG. BY Sivamanickam Guswandhi DOCUMENT SEQUENCE No.
APP. BY Guswandhi
NOTES:
1. Alternate design conditions are 3.5 barg/FV @190°C ( for steam out purpose)
HOLDS:
1. Deleted
2. Deleted
SHEET 3 of 8
FWEL.2068/18-2 Rev.0 BASE : Instrument datasheet - Control Valve.xls PROJECT SPECIFIC :
DATA SHEET FOR THERMOWELLS contr.job no: 0591E
Rev Units Units
1 GENERAL: --- 60 GENERAL
2 Tag number --- 27-TW-552 61 Plant '--- SHELL EASTERN PETROLEUM
3 Service --- Cooling Water Return from E-2754 62 Location/Unit '--- PULAU BUKOM
4 P.E.F.S darws. Number --- 0591-8110-25-0019 63
5 64
F1 6 Intermediate revison R2 65
7 66
8 THERMOWELL: 67
9 Construction type --- 68
10 69
11 Process connection --- 70
12 Size DN 71
13 Rating LBS 72
14 Flange finish 73
15 74
16 Welded construction 75
17 Stem material --- 76
18 Flange material --- 77
19 78
20 Forged construction 79
21 Material 80
22 81
23 Bore diameter mm 82
24 Standard length "L" mm 83
25 SIPM standard dwg --- 84
26 85
27 86
28 87
29 88
30 PROCES DATA 89 SPECIAL REQUIREMENTS
31 Medium/Phase '--- Cooling Water / Liquid 90
32 91 NACE requirements '---
33 Operating conditions 92
34 93
35 Design Pressure Barg 10 94 Material certificate '---
36 Design temperature min/max °C 65 95
37 96
38 Fluid velocity m/s 1.9 97
39 98
40 Operating Temperature °C 42 99
F1 41 Operating pressure Barg 0.9 100
42 101
43 Density kg/m3 995 102
44 Viscosity cP 0.63 103
45 104
46 105
47 106 NON-VENDOR RELATED INFO
48 107
49 108
50 109 Grid position '---
51 110 Design code '---
52 111 Shell registration no. '---
53 112 Mesc number '---
54 PURCHASE DATA 113 REMARKS
55 Manufacturer '--- 114
56 Supplier '--- 115
57 Model number '--- 116
58 Serial number '--- 117