Beruflich Dokumente
Kultur Dokumente
BUILDING SERVICES-‐ II
SREERUPA
DEB
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
Importance of Electrical Services and Its implications on building design
The
function
of
a
building
is
not
limited
to
providing an
enclosure
and
shelter to
the
occupants.
It
also
needs
to
provide
an
environment to
the
occupants
which
will
make
them
comfortable
,
live,
work
and
achieve
to
the
best
of
their
ability
and
encourage
productivity.
The
success
of
a
building
lies
in
the
fact
that
the
building
functions
as
per
the
intent
for
which
it
is
designed.
To
achieve
that
building
services
becomes
very
important.
ELECTRICAL
SERVICES
deals
with
the
following
building
functions
such
as
installation
of
the
high
side
equipments
like
transformers,
DG,
Panels
etc and
distribution
of
power,
lighting
and
other
auxiliary
services.
Electrical
Power
Normal,
standby
and
emergency
power
supply
and
distribution
Lighting
Interior,
exterior
and
emergency
lighting
Extra
low
voltage
systems
Telephone,
data
&
cable
TV
networking
Voltage
(V)– An
electromotive
force
or
"pressure"
that
causes
electrons
to
flow
through
a
conductor
due
to
the
potential
difference
in
charge
between
2
points
and
can
be
compared
to
water
pressure
which
causes
water
to
flow
in
a
pipe.
Voltage is
the
difference
in
charge
between
two
points.
In
other
words,
voltage
is
the
"energy
per
unit
charge”. Measured
in
Volts.
V=
I*
R
where
I
is
current
and
R
is
resistance
Current
(I) — The
flow
of
an
electric
charge
through
a
conductor.
An
electric
current
can
be
compared
to
the
flow
of
water
in
a
pipe.
Current is
the
rate
at
which
electric
charge
flows
past
a
point
in
a
circuit.
Measured
in
amperes.
Power — The
rate
at
which
electrical
energy
is
transferred
by
an
electric
circuit.
Measured
in
Watts.
P=
V*I
Connected
load is
the
sum
of
all
the loads
connected in
the
circuit
irrespective
of
the
fact
that
whether
it
is
being
currently
operated
or
not.
Demand load is the sum of load which is connected to the circuit and is being currently operated.
7/17/17 Terminology 6
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
Maximum
Demand
MD
is
measured
in
Kilowatt
(kW).
It
is
the
highest
level
of electrical
demand
monitored
in
a
particular
period
usually
for
a
month
period.
Load
factor is
defined
as
the
average
load
divided
by
the
peak
load
in
a
specified
time
period. It
is
a
measure
of
variability
of
consumption
or
generation;
a
low
load
factor
indicates
that
load
is
highly
variable,
whereas
consumers
or
generators
with
steady
consumption
or
supply
will
have
a
high
load
factor.
Hence:
•load
factor
=
{ 57200 kWh /
(30 d × 24
hours
per
day
× 436 kW)
}
× 100%
=
18.22%
Source
-‐ Wikipedia
7/17/17 Terminology 7
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
The
demand
factor
is
taken
as
a
time
independent
quantity
where
the
numerator
is
taken
as
the
maximum
demand
in
the
specified
time
period
instead
of
the
averaged
or
instantaneous
demand.
the
possible
This
is
the
peak
in
the load
profile divided
by
the
full
load
of
the
device.
Example:
If
a
residence
has
equipment
which
would
draw
6,000
W
when
all
equipment
was
drawing
a
full
load
draw
a
maximum
of
3,000
W
in
a
specified
time,
then
the
demand
factor
=
3,000
W
/
6,000
W
=
0.5
Diversity
factor (or
simultaneity
factor)
is
a
measure
of
the
probability
that
a
particular
piece
of
equipment
will
turn
on
coincidentally
to
another
piece
of
equipment.
For
aggregate
systems
it
is
defined
as
the ratio of
the
sum
of
the
individual
non-‐coincident
maximum
loads
of
various
subdivisions
of
the
system
to
the
maximum
demand
of
the
complete
system.
7/17/17 Terminology 8
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
The
Power
Factor
is
an
indicator
of
the
quality
of
design
and
management
of
an
electrical
installation.
It
relies
on
two
very
basic
notions:
active
and
apparent
power.
The active
power
P
(kW) is
the
real
power
transmitted
to
loads
such
as
motors,
lamps,
heaters,
and
computers.
The
electrical
active
power
is
transformed
into
mechanical
power,
heat
or
light.
The
apparent
power
is
the
basis
for
electrical
equipment
rating.
The Power
Factor λ is
the
ratio
of
the
active
power
P
(kW)
to
the
apparent
power
S
(kVA):
The
load
may
be
a
single
power-‐consuming
item,
or
a
number
of
items
(for
example
an
entire
installation).
The
value
of
power
factor
will
range
from
0
to
1.
Power
factor
0.85
is
good whereas
power
factor
of
0.5
is
poor.
A.C
&
D.C
CURRENT
AC
– Alternating
Current. Electric
current in
which
the
flow
of
electric
charge
periodically
reverses
direction,
whereas
in direct
current (DC,
also dc),
the
flow
of
electric
charge
is
only
in
one
direction.
The
abbreviations AC and DC are
often
used
to
mean
simply alternating and direct. AC is
the
form
in
which
electric
power
is
delivered
to
businesses
and
residences. Source
-‐ Wikipedia
7/17/17 Terminology 9
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
7/17/17 Terminology 10
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
7/17/17 Terminology 11
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
Circuit
-‐ An electric
circuit is
a
path
in
Distribution
board
-‐ Cable
tray
-‐ In
the
electrical
wiring
of
which
electrons
from
a
voltage
or
A distribution
board (also
buildings,
a cable
tray system
is
used
current
source
flow. Electric
current
known
as
panel
board
or
to
support
insulated
electric
cables
flow
in
a
closed
path
is
called
breaker
panel)
is
a
component
used
for
power
distribution
and
an electric
circuit.
The
point
where
of
an
electricity
supply
system
communication.
those
electrons
enter
an electrical
that
divides
an
electrical
power
circuit is
called
the
"source"
of
feed
into
subsidiary
circuits,
electrons. while
providing
a
protective
fuse
or
circuit
breaker
for
each
circuit
in
a
common
enclosure.
7/17/17 Terminology 12
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
Raceway is
used
to
route
wires
through
a
Electrical conduits
refer
to
an electrical
discreet
cable
track
that
will
improve
the
system
used
to
protect
and
provide
route
of
aesthetics
in
just
about
any
room,
and
is
a
electrical
wiring.
Electrical
conduits
are
made
of
great
and
affordable
way
to
conceal
and
metal,
plastic,
or
fiber
and
could
be
rigid
or
protect
cables
in
both
home
or
office. flexible
7/17/17 Terminology 13
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
ELECTRICAL energy is generated in power houses or generating stations.
Electrical energy is generated in – Thermal power plants & Hydel power plants
33kV
/
6.6kV
Substation
33kV
/
6.6kV
Substation BULK
CONSUMER CONSUMER
Generated
electricity
is
distributed
to
the
users
through
transmission
and
distribution
networks
– large
network
of
conductors.
Transmission
system
– System
by
which
Bulk
power
(or
energy)
is
transmitted
from
power
station
to
load
centers
(Large
sub
stations)
Distribution
system
– All
equipments
in
the
Distribution
substation,
overhead
lines,
U/G
cables
radiating
from
the
substation
combined
together
– is
known
as
the
distribution
system.
Distributors – OH lines from which number of consumers are fed by electrical energy at low voltage.
Service
Connections – The
Al
conductors
connecting
the
distributors
with
the
consumer’s
mains
is
known
as
service
connections.
D.C SYSTEM – Distributed at the generated voltage. Not generated beyond 440V.
A.C
SYSTEM
– Voltage
can
be
increased
to
120kV
and
above,
therefore
for
same
amount
of
power
the
current
is
tremendously
reduced.
Transmission
of
electrical
energy
at
a
wide
distance
after
generation
is
possible
with
minimum
copper
losses.
This
is
the
reason
why
A.C
system
of
supply
is
adopted
in
most
countries
world
wide.
Copper
loss is
the
term
often
given
to
heat
produced
by
electrical
currents
in
the
conductors
of
transformer
windings,
or
other
electrical
devices.
Maintenance cost of A.C distributor is low, however initial cost of A.C system is high as compare to the D.C system.
CONDUCTORS
A
substance
that
offers
low
resistance
to
the
flow
of
electric
current
is
a
conductor.
Some
important
conductors
are
Silver,
Copper
,
Aluminium
to
name
a
few.
Properties
of
a
good
conductor
• Low
cost
• Easily
available
in
the
market
• Have
sufficient
tensile
strength
• Joint
should
be
easily
made
&
soldered
• Have
sufficient
mechanical
strength
• Should
not
get
affected
by
changing
atmospheric
conditions
• Flexible
• High
conductivity
&
low
specific
resistance
to
keep
the
electrical
losses
low
Not
covered
with
insulation. Covered
with
insulation.
Used
for
indoor
wiring
Used
in
OH
lines
for
transmission
&
distribution installations
&
UG
distribution
systems.
Copper
Conductor
– best
material
for
conducting
,
Mostly
used
for
commercial
purpose,
its
conductivity
is
approximately
90%
of
that
of
silver,
can
be
exposed
to
all
weather
conditions
,
however
very
expensive
and
frequent
fluctuations
of
price.
Aluminum
– Inferior
to
copper,
60%
conductivity
as
compared
to
copper,
however
second
best
as
conductor,
cheaper
and
lighter
than
copper,
subject
to
less
price
fluctuations.
Conductors
are
made
of
solid
cable
(for
the
smaller
c/s
areas
)
For
the
larger
c/s
areas
a
number
of
smaller
cables
are
twisted
together
to
make
a
larger
cable.
These
are
called
strands.
Insulation
is
a
non-‐conductive
material,
or
a
material
resistant
to
the
flow
of
electric
current.
It
is
often
called
a
dielectric
in
radio
frequency
cables.
Both the safety and effectiveness of the wire depend on its insulation.
Any
conductor
which
is
composed
of
a
conducting
material,
uniform
in
diameter
and
circular
in
cross-‐section
is
called
a
wire.
A
length
of
a
single
insulated
conductor
(solid
or
stranded)
or
two
or
more
such
conductors,
each
provided
with
its
own
insulation
which
are
laid
up
together
is
called
a
cable.
HT
CABLES
A high-‐voltage
cable (HV
cable)
is
a
cable
used
for electric
power
transmission at high
voltage.
A
cable
includes
a
conductor
and
insulation,
and
is
suitable
for
being
run
underground
or
underwater.
This
is
in
contrast
to
an overhead
line,
which
does
not
have
insulation.
High-‐voltage
cables
of
differing
types
have
a
variety
of
applications
7/17/17 HT
Cables 24
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
CORE -‐ One
centre core
or
a
number
of
cores
of
stranded
conductors.
There
may
be
1
core,
2
cores,
3
cores,
3.5
cores
or
4
cores.
BEDDING – Over
metallic
sheath,
a
layer
of
bedding
of
paper
tape
compounded
with
a
fibrous
material.
ARMOURING – Prevents
mechanical
injury
to
the
cable,
consists
of
one
or
two
layers
of
galvanised steel
wires
or
two
layers
of
steel
tape.
SERVING – Over
the
armouring fibrous
material
like
bedding
is
used
which
is
called
serving.
HT
Cables
7/17/17 25
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
LT
CABLES
LT
Cables
are
used
in
the
distribution
of
electricity
at
low
voltage
– upto 1kV.
VOLTAGE
LEVELS
Electricity
is
supplied
to
consumers
through
the
National
Grid
at
a
very high
voltage
to
reduce
energy
losses
during transmission.
Transformers
are
used
to
increase
or
decrease
the voltage of
the
supply.
Electricity
is
charged
in
units.
Most
of
the
world
uses
50 Hz
220
or
230
V
single
phase
400V
3
phase
for
residential
and
light
industrial
services.
In
this
system,
the
primary
distribution
network
supplies
a
few
substations
per
area,
and
the
230
V
power
from
each
substation
is
directly
distributed.
A
live
(hot)
wire
and
neutral
are
connected
to
the
building
for
each
phase
of
three
phase
service.
Single-‐phase
distribution
is
used
where
motor
loads
are
light.
Large
industrial
customers
have
their
own
transformer(s)
with
an
input
from
11
kV
to
220
kV.
Bulk
consumers/
Industries
receive
power
at
approx 6.6kV
where
the
power
is
further
brought
down
to
415V
as
per
the
power
demand.
Consumers
receive
at
230V
single
phase
for
domestic
usage
or
415V
3
phase
for
domestic
and
light
industrial
services.
Voltage,
Nominal
(of
an
Installation)
-‐ Voltage
by
which
an
installation
or
part
of
an
installation
is
designated.
Voltage,
Extra
Low
(ELV)-‐ The
voltage
which
does
not
normally
exceed
50
V.
Voltage,
Low
(LV)
-‐ The
voltage
which
normally
exceeds
50
V
but
does
not
normally
exceed
250
V.
Voltage,
Medium
(MV)
-‐ The
voltage
which
normally
exceeds
250
V
but
does
not
exceed
650
V.
Voltage,
High
(HV)
-‐ The
voltage
which
normally
exceeds
650
V
but
less
than
or
equal
to
33
kV.
Voltage,
Extra
High
(EHV)
-‐ The
voltage,
which
normally
exceeds
33
kV.
Source
-‐ NBC
2016
– Electrical
&
Allied
Installations
SUB
STATION
A
substation
is
essentially
an
assembly
of
apparatus
which
is
installed
to
control
transmission
or
distribution
of
electric
power.
It
transforms
the
characteristics
of
electrical
energy
from
one
form
to
another
i.e form
alternating
current
to
direct
current
and
from
one
voltage
to
another.
The stepping up and stepping down of voltage is done in sub – stations.
Sub
station
7/17/17 29
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
TYPES OF SUBSTATION -‐ ACCORDING TO DESIGN – choice is based on cost & atmospheric conditions
OUTDOOR
SUBSTATIONS
a. Foundation
mounted
– Transmission
substations
• These
substations
are
located
outside
city
limits
&
requires
good
access
for
heavy
transport
• Handles
large
block
of
electrical
energy
– several
hundred
thousand
kVA
• Saves
on
building
cost
but
large
site
areas
required
,
more
maintenance
and
also
adequate
clearance
all
around
for
maintenance
• >
=
132kV
– outdoor
construction
is
universal
7/17/17 Substation 30
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
OUTDOOR
SUBSTATIONS
b. Pole
mounted
– Distribution
substations
Substation
7/17/17 31
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
INDOOR SUBSTATIONS
Substation
7/17/17 32
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
The
layout
of
the
electrical
substation
shall
follow
the
following
sequence
of
spaces
based
on
the
flow
of
electric
power
7/17/17 Substation 33
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
7/17/17 RMU 34
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
METERING PANELS
Metering
panels
are
located
after
the
RMU
to
record
the
energy
consumption
of
the
owner/
consumer.
It
is
located
so
that
it
gives
easy
access
to
the
owner
and
the
Electric
supply
Company’s
representative
to
record
the
electrical
units
consumed.
HT
Meter
is
located
at
the
substation
for
large
installations
at
11KV.
LT
Meter
is
located
at
consumer’s
end.
• Single
phase
(230
Volts)connections
for
Upto &
below
5KW
• 3
Phase
connections
(415
Volts)
for
above
5KW.
HT PANELS
HT
panel
takes
the
inputs
from
the
Metering
panel
and
the
output
goes
out
to
the
number
of
transformers.
7/17/17 HT
Panels 36
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
TRANSFORMERS
Transformers
are
used
for
step
up
and
step
down
of
voltage
for
easier
transmission
of
electric
current
from
the
generating
station
to
the
user
point.
7/17/17 Transformers 38
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
GENERATORS
Diesel
Generators
(D.G)
provides
back
up
to
E.B
power.
LT PANELS
7/17/17 LT
Panels 40
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
7/17/17 41
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
OVERHEAD CABLES
UNDERGROUND CABLES
Underground
cables
• Add
to
the
aesthetics
&
safety
• Important
for
road
crossings
• Care
should
be
taken
that
UG
cables
are
located
far
away
from
the
UG
waterlines.
• Overhead
lines
aren't
the
only
way
of
bringing
power
to
homes.
• When
low-‐voltage
lines
are
underground
but
transformers
and
medium-‐voltage
lines
are
overhead,
this
is
called
a
hybrid overhead/underground distribution
system.
• When
the
system
is entirely
underground,
the
medium-‐voltage
lines
are
also
buried,
while
transformers
are
mounted
on
ground-‐level
pads.
• The
latter
system
is
more
common
in
densely
populated
areas
and
in
housing
developments.
• UG
power
lines
is
gaining
popularity
since
in
addition
to
improving
the
landscape,
undergrounding
protects
electrical
equipment
from
bad
weather
and
vegetation.
• It
also
helps
create
more
open
space
in
neighborhoods.
• Undergrounding
any
distribution
system
is
more
expensive
than
building
overhead
lines,
and
the
decision
is
up
to
municipal
authorities
and
government
7/17/17 45
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
ADVANTAGES
• Repair
– OH
lines
easy
to
repair
over
UG
cables
• Fault
location
easier
in
OH
lines
compared
to
UG
lines
• Initial
cost
is
lower
for
OH
lines
compared
to
UG
lines
• Due
to
more
spacing
between
the
conductors
the
charging
current
is
less
in
OH
System
compared
to
UG
system
• Jointing
is
comparatively
easier
in
OH
system
compared
to
UG
system.
DISADVANTAGES
• Maintenance
cost
is
more
in
OH
system
compared
to
UG
system
since
there
are
more
faults.
• UG
cables
are
safer
for
the
public
since
they
are
buried
in
the
ground.
• OH
systems
affect
the
aesthetics
,
whereas
the
UG
system
is
not
visible.
• Lightning
&
Thunder
affect
the
OH
system.
• Surges
are
absorbed
by
the
metallic
sheath
of
UG
cables.
• OH
lines
are
prone
to
accidents.
• OH
lines
see
more
voltage
drop
• OH
lines
affect
telecommunication
lines.
7/17/17 46
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
• IS RULES
7/17/17 Codes 47
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
Specific
regulations
to
be
adhered
to
in
the
supply
and
use
of
electrical
energy
had
been
laid
down
by
the
Indian
Electricity
Act,
1910
and
the
Indian
Electricity
Rules,
1956
framed
thereunder.
However,
a
need
was
felt
to
elaborate
upon
these
regulations
since
the
agencies
involved
have
varied
practices
in
view
of
their
diverse
interests
and
different
accessibility
levels
to
technological
developments.
In
order
to
rationalize
these
practices,
India’s
first
National
Electrical
Code,
formulated
in
1985,
was
a
compendium
of
several
well
established
codes
of
practice
which
provided
assistance
on
economic
selection,
installation
and
maintenance
of
electrical
equipment
employed
in
the
usage
of
electrical
energy.
The
code
complemented
and
elaborated
on
the
Indian
Electricity
Rules,
1956
for
the
ease
of
application
by
the
system
engineers
by
recommending
the
best
practices
for
electrical
installations
in
a
consolidated
form
in
order
to
provide
for
unified
practices
and
procedures
along
with
consideration
for
safety
and
economic
usage
of
energy
in
the
design,
execution,
inspection
and
maintenance
of
electrical
installations
of
various
locations.
IS RULES
IS
(Indian
Standards)
or
BIS(Bureau
of
Indian
Standards)
codes
are
the
Codes
and
standards
formulated
by
BIS
for
various
kinds
of
items
and
aspects
of
electrical
works
like
-‐ electrical
appliances,
equipments
etc.
• describing
the
material
specifications
,
• storage
requirement,
• method
of
installation
&
fixing
,
• Mode
of
measurement
• testing
and
commissioning
and
is
the
governing
standards
for
all
electrical
works.
7/17/17 IS
Rules 51
15
ARC
5.3
ELECTRICAL
SERVICES
&
ILLUMINATION
In the year 1999, Karnataka embarked on a major Reform of the power sector. As a first step, Karnataka Electricity Board
(KEB) was dissolved and in its place, the Karnataka Power Transmission Corporation Limited (KPTCL) was incorporated.
This was followed by the constitution of Karnataka Electricity Regulatory Commission (KERC) in November 1999.In the
next phase of the Reform Process, the transmission and distribution business managed by KPTCL were unbundled in
June 2002. Four new distribution companies were formed to distribute power in Karnataka.
Bangalore Electricity Supply Company Limited (BESCOM) has taken over the responsibility from KPTCL for the
distribution of electricity in 8 districts and commenced its operations from 1st June 2002.
CEIG
Guidelines
deal
with
Clearance
and
safety
with
a
stress
on
the
local
state
electricity
supply
guidelines.
It
is
drawn
by
state
and
ratifies
and
gives
approval
for
installations.