Seth Development Project (New Revision 316 MMUS$) 15-Mar-11 11:34

Activity Relationships
Predecessor
Activity ID Successor ID Successor Name Relationshi Lag
Type

Seth First Gas


A1710 A1720 Seth full production & project completion FS 0
Jacket & Piles installation
A2210 A1710 Seth First Gas FS 0
Sealine laying comlpetion
A2220 A1710 Seth First Gas FS 0
Sealine spools, PLEM & SSIV completion
A2230 A1710 Seth First Gas FS 0
Onshore facilities completion
A2240 A1720 Seth full production & project completion FS 0
A2240 A1710 Seth First Gas FS 0
Pre-drilling Seth
A1880 A1710 Seth First Gas FS 0
Deck completion including TSF hookup
A1980 A1710 Seth First Gas FS 0
Deck structure installation and main hookup
A1990 A1710 Seth First Gas FS 0
Sealine basic & detailed engineering (ENPPI WA)
A1290 A1300 Sealine pipes RFQ, receiving offers and TER SS 18
A1290 A3090 Hot Shrinkable Sleeves receiving RFQ, receiving offers and TER SS 74
A1290 A1940 Kamos ring receiving RFQ, receiving offers and TER SS 60
A1290 A2020 Flanges, stud bolts & nuts RFQ, receiving offers and TER SS 60
Onshore detailed engineering (ENPPI WA)
A1500 A2070 Mechanical bulk material PO & receiving @ site SS 150
A1500 A2080 E & I bulk material PO & receiving @ site SS 150
A1500 A2090 Manual valves PO & receiving @ site SS 55
A1500 A2100 ESD/DCS upgrading PO & receiving @ site SS 180
A1500 A2110 Fire fighting and fire & gas detection system PO & receiving @ site SS 180
Platform basic design (1st batch)
A1140 A1150 Jacket, PDT & Piles detailed engineering SS 60
A1140 A1820 Shallow soil survey SS 120
A1140 A2200 Platform basic design (2nd batch) SS 48
A1140 A1110 RFQ & FOA issuance (PRIMARY Jacket, Piles & PDT) FS -50
A1140 A2290 EPC RFQ with 1st batch of basic design FF 0
Sealine concept selection
A1280 A1290 Sealine basic & detailed engineering (ENPPI WA) FS 0
A1280 A2280 Spools basic & detailed engineering (ENPPI WA) FS 0
Onshore basic design
A1460 A1470 El-Gamil plant site survey SS 28
A1460 A1480 LLI by Petrobel (Slug catcher and actuated valves) RFQ FS -45
A1460 A1500 Onshore detailed engineering (ENPPI WA) FS 0
A1460 A1510 Slug catcher PO, manifacturing & receiving @ site FS 0
Platform basic design (2nd batch)
A2200 A2260 PLEM & SSIV SPECs FS -63
A2200 A1380 Deck structure detailed engineering FS 0
A2200 A1150 Jacket, PDT & Piles detailed engineering FS 0
A2200 A1120 RFQ & FOA issuance (PRIMARY Deck) FS 0
A2200 A1130 RFQ & FOA issuance (SECONDARY Jacket, Deck & PRIMARY for Flare) FS 0
A2200 A2270 Platform basic design (Last batch) FS 0
PLEM & SSIV SPECs
A2260 A1390 PLEM & SSIV RFQ and TER FS 0
EPC consortium official presentation
A1020 A2290 EPC RFQ with 1st batch of basic design FS 0
Issuance of Letter of Intent (For early activities)
A1080 A1090 Finalization of the EPC contract terms & detailed SoW & technical FS 0
qualification finalization
Finalization of the EPC contract terms & detailed SoW & technical qualification finalization
A1090 A1100 EPC awarding FS 0
A1090 A1550 Review of basic documents & tech. eval. of Co. free issued TSF & SS LLI SS 0
EPC awarding
A1100 A1380 Deck structure detailed engineering FS -31
A1100 A1800 EPC structural ancillaries material receiving @ site FS 30
A1100 A1780 EPC TSF (Equipment) receiving @ site FS 90
A1100 A1790 EPC E&I bulk material receiving @ site FS 120
A1100 A1860 EPC piping bulk material receiving @ site FS 90
EPC RFQ with 1st batch of basic design
A2290 A1080 Issuance of Letter of Intent (For early activities) FS 0
A2290 A2320 Receiving of EPC offer rev.0 FS 0
Receiving of EPC offer rev.0
A2320 A1090 Finalization of the EPC contract terms & detailed SoW & technical FS 0

(c) Primavera Systems, Inc. Page 1 of 7


Seth Development Project (New Revision 316 MMUS$) 15-Mar-11 11:34

Activity Relationships
Predecessor
Activity ID Successor ID Successor Name Relationshi Lag
Type

Deck structure detailed engineering


A1380 A1130 RFQ & FOA issuance (SECONDARY Jacket, Deck & PRIMARY for Flare) SS 0
Mechanical detailed engineering
A1220 A1570 Piping detailed engineering SS 30
Review of basic documents & tech. eval. of Co. free issued TSF & SS LLI
A1550 A1560 Process detailed engineering FS 0
A1550 A1570 Piping detailed engineering FS 0
Process detailed engineering
A1560 A1230 PTB Production manifold procurement & material receiving @ site FF 0
A1560 A1740 PTB Manual & actuated valves procurement & material receiving @ site FF 0
A1560 A1590 Instrumentation detailed engineering SS 15
A1560 A1600 Electrical detailed enigneering SS 15
A1560 A1220 Mechanical detailed engineering SS 23
Piping detailed engineering
A1570 A1860 EPC piping bulk material receiving @ site FF 0
Instrumentation detailed engineering
A1590 A1790 EPC E&I bulk material receiving @ site FF 0
Electrical detailed enigneering
A1600 A1790 EPC E&I bulk material receiving @ site FF 0
EPC project management & procurement follow up (For Platform)
A3070 A2000 Tie-in of 2nd well (Rig assistance for accommodation) FF 0
A3070 A3080 EPC project management & procurement follow up (For Spools) SS 0
EPC project management & procurement follow up (For Spools)
A3080 A2010 Spools sea fastening & transportation FF 0
Dimensional control services (For Platform fabrication)
A1840 A1200 Jacket ready for load out FS 0
Jacket, PDT & Piles detailed engineering
A1150 A3070 EPC project management & procurement follow up (For Platform) SS 0
Shallow soil survey
A1820 A1830 Well site survey (If required) FS 0
A1820 A1150 Jacket, PDT & Piles detailed engineering SS 0
Well site survey (If required)
A1830 A1840 Dimensional control services (For Platform fabrication) FS 0
El-Gamil plant site survey
A1470 A1480 LLI by Petrobel (Slug catcher and actuated valves) RFQ FS 0
Sealine route survey completion
A2250 A1290 Sealine basic & detailed engineering (ENPPI WA) FS 0
A2250 A2280 Spools basic & detailed engineering (ENPPI WA) FS 0
RFQ & FOA issuance (PRIMARY Jacket, Piles & PDT)
A1110 A1160 (PRIMARY Jacket, Piles & PDT) material manifacturing & receiving @ FS 0
fabrication yard
RFQ & FOA issuance (PRIMARY Deck)
A1120 A1130 RFQ & FOA issuance (SECONDARY Jacket, Deck & PRIMARY for Flare) FS 48
A1120 A2300 (PRIMARY Deck) material manifacturing & receiving @ fabrication yard FS 0
RFQ & FOA issuance (SECONDARY Jacket, Deck & PRIMARY for Flare)
A1130 A2310 (SECONDARY Jacket, Deck & PRIMARY for Flare) material manifacturing & FS 0
receiving @ fabrication yard
(PRIMARY Jacket, Piles & PDT) material manifacturing & receiving @ fabrication yard
A1160 A1850 Pre-drilling template fabrication FS -20
A1160 A2390 Piles 1st batch plates rolling & RFS Kattamia Yard SS 142
A1160 A2400 Piles 2nd batch plates rolling & RFS Kattamia Yard FS 0
A1160 A2720 Bottom row fabrication (Row-2) SS 160
(PRIMARY Deck) material manifacturing & receiving @ fabrication yard
A2300 A1240 Fabrication of Cellar Deck & Deck legs FS -40
(SECONDARY Jacket, Deck & PRIMARY for Flare) material manifacturing & receiving @ fabrication yard
A2310 A1240 Fabrication of Cellar Deck & Deck legs FS -80
A2310 A2720 Bottom row fabrication (Row-2) FF -60
EPC structural ancillaries material receiving @ site
A1800 A1200 Jacket ready for load out FF -45
Sealine pipes RFQ, receiving offers and TER
A1300 A1330 Sealine pipes manifacturing & ready for shipment FS 0
A1300 A1340 Sealine pipes commercial evluation & PO FS 0
Sealine pipes manifacturing & ready for shipment
A1330 A1350 Sealine pipes coating, overweighting & anodes application FS 0
A1330 A3110 Large radius bends fabrication (Bending works) FS 0
Sealine pipes commercial evluation & PO
A1340 A1330 Sealine pipes manifacturing & ready for shipment FS 0
Flanges, stud bolts & nuts manifacturing & receiving @ site
A1930 A2500 Sealine laying FS 0
A1930 A1920 Spools fabrication (Non-Metrology Spools) FS 0

(c) Primavera Systems, Inc. Page 2 of 7


Seth Development Project (New Revision 316 MMUS$) 15-Mar-11 11:34

Activity Relationships
Predecessor
Activity ID Successor ID Successor Name Relationshi Lag
Type

Flanges, stud bolts & nuts RFQ, receiving offers and TER
A2020 A1960 Flanges, stud bolts & nuts commercial evluation & PO FS 0
Flanges, stud bolts & nuts commercial evluation & PO
A1960 A1930 Flanges, stud bolts & nuts manifacturing & receiving @ site FS 0
Anodes RFQ, receiving offers and TER
A3130 A3140 Anodes commercial evluation & PO FS 0
Anodes commercial evluation & PO
A3140 A3150 Anodes manifcaturing & receiving @ site FS 0
Anodes manifcaturing & receiving @ site
A3150 A1350 Sealine pipes coating, overweighting & anodes application FS 0
Kamos ring receiving RFQ, receiving offers and TER
A1940 A2540 Spools connection (Spools Nr.3, 4, 5, 6, 7, 8, 9 & 10) FS 0
A1940 A3120 Kamos ring receiving commercial evluation & PO FS 0
Kamos ring manifacturing & receiving @ site
A3100 A2540 Spools connection (Spools Nr.3, 4, 5, 6, 7, 8, 9 & 10) FS 0
Kamos ring receiving commercial evluation & PO
A3120 A3100 Kamos ring manifacturing & receiving @ site FS 0
Hot Shrinkable Sleeves manifacturing & receiving @ site
A1950 A2500 Sealine laying FS 0
Hot Shrinkable Sleeves receiving RFQ, receiving offers and TER
A3090 A2030 Hot Shrinkable Sleeves commercial evluation & PO FS 0
Hot Shrinkable Sleeves commercial evluation & PO
A2030 A1950 Hot Shrinkable Sleeves manifacturing & receiving @ site FS 0
PTB Production manifold procurement & material receiving @ site
A1230 A1650 Equipment installation (Cellar Deck) FS 7
PTB Manual & actuated valves procurement & material receiving @ site
A1740 A1680 Piping fabrication & erection (Main Deck) FF -120
A1740 A1630 Piping fabrication & erection (Cellar Deck) FS -60
PTB E & I module procurement & material receiving @ site
A1750 A1690 Equipment installation (Main Deck) FS 0
PTB Microturbine procurement & material receiving @ site
A1760 A1690 Equipment installation (Main Deck) FS 0
PTB Emergency diesel generator procurement & material receiving @ site
A1770 A1690 Equipment installation (Main Deck) FF -7
EPC TSF (Equipment) receiving @ site
A1780 A1690 Equipment installation (Main Deck) FS -90
EPC E&I bulk material receiving @ site
A1790 A1250 Deck commissioning FS 0
A1790 A2040 E & I works FS -59
EPC piping bulk material receiving @ site
A1860 A1680 Piping fabrication & erection (Main Deck) SS 185
LLI by Petrobel (Slug catcher and actuated valves) RFQ
A1480 A1490 Technical evaluation, direct negotitaion & PO (Slug catcher) FS 0
Technical evaluation, direct negotitaion & PO (Slug catcher)
A1490 A1510 Slug catcher PO, manifacturing & receiving @ site FS 0
Slug catcher PO, manifacturing & receiving @ site
A1510 A1520 Mechanical works FS -75
A1510 A2160 Skids installation FS 0
A1510 A2140 Construction works package negotiation & FOA issuance SS 100
Mechanical bulk material PO & receiving @ site
A2070 A1520 Mechanical works FS 0
E & I bulk material PO & receiving @ site
A2080 A2150 Electrical & instrumentation works FS 0
Manual valves PO & receiving @ site
A2090 A1520 Mechanical works FS 0
ESD/DCS upgrading PO & receiving @ site
A2100 A2150 Electrical & instrumentation works FS 0
Fire fighting and fire & gas detection system PO & receiving @ site
A2110 A2150 Electrical & instrumentation works FS 0
PLEM & SSIV RFQ and TER
A1390 A1430 Issuing PLEM & SSIV PO FS 0
PLEM & SSIV commercial evaluation & LOI
A1410 A1440 PLEM & SSIV manifacturing & receiving @ site FS 0
A1410 A1450 Split tee manifacturing & receiving @ site FS 0
PLEM & SSIV manifacturing & receiving @ site
A1440 A2530 PLEM installation FS 0
A1440 A2520 SSIV installation FS 0
Split tee manifacturing & receiving @ site
A1450 A2500 Sealine laying FS 0

(c) Primavera Systems, Inc. Page 3 of 7


Seth Development Project (New Revision 316 MMUS$) 15-Mar-11 11:34

Activity Relationships
Predecessor
Activity ID Successor ID Successor Name Relationshi Lag
Type

Sealine pipes coating, overweighting & anodes application


A1350 A1370 Coated sealine pipes ready for load out FS 0
A1350 A1400 Spools pipes coating, overweighting & anodes application SS 0
Sealine coating RFQ & issuance of FOA
A1360 A1350 Sealine pipes coating, overweighting & anodes application FS 0
Coated sealine pipes ready for load out
A1370 A2490 Coated sealine pipes offshore transportation FS 0
Piles 1st batch plates rolling & RFS Kattamia Yard
A2390 A2450 Piles 1st batch transportation to Maadia yard FS 0
Piles 2nd batch plates rolling & RFS Kattamia Yard
A2400 A2460 Piles 2nd batch transportation to Maadia yard FS 0
Piles 1st batch transportation to Maadia yard
A2450 A2470 Piles assembly at Maadia yard FS 0
Piles 2nd batch transportation to Maadia yard
A2460 A2470 Piles assembly at Maadia yard FF 0
Piles load out and sea fastening
A2350 A2680 Piles & Jacket ancillaries arrival on cargo barge (2nd CB) FS 0
Piles assembly at Maadia yard
A2470 A2350 Piles load out and sea fastening FS 0
Jacket load out & sea fastening
A1190 A2590 Jacket transportation to location on cargo barge (1st CB) FS 0
A1190 A2350 Piles load out and sea fastening FF 0
Jacket ready for load out
A1200 A1190 Jacket load out & sea fastening FS 0
Bottom row fabrication (Row-2)
A2720 A1200 Jacket ready for load out FS 0
A2720 A2990 Top row fabrication & elevation (Row-1) SS 2
A2720 A3000 Plan @ elevation -79000 fabrication & elevation SS 60
A2720 A3060 Plan @ elevation +6400 fabrication & elevation SS 15
A2720 A3050 Plan @ elevation -10600 fabrication & elevation SS 20
A2720 A3020 Plan @ elevation -33400 fabrication & elevation SS 15
A2720 A3010 Plan @ elevation -67000 fabrication & elevation SS 15
Top row fabrication & elevation (Row-1)
A2990 A1200 Jacket ready for load out FS 0
Plan @ elevation -79000 fabrication & elevation
A3000 A1200 Jacket ready for load out FS 0
Plan @ elevation -67000 fabrication & elevation
A3010 A1200 Jacket ready for load out FS 0
Plan @ elevation -33400 fabrication & elevation
A3020 A3030 Lateral plan x-braces fabrication & elevation (Row-A) SS 15
A3020 A1200 Jacket ready for load out FS 0
Lateral plan x-braces fabrication & elevation (Row-A)
A3030 A3040 Lateral plan x-braces fabrication & elevation (Row-B) SS 15
A3030 A1200 Jacket ready for load out FS 0
Lateral plan x-braces fabrication & elevation (Row-B)
A3040 A1200 Jacket ready for load out FS 0
Plan @ elevation -10600 fabrication & elevation
A3050 A1200 Jacket ready for load out FS 0
Plan @ elevation +6400 fabrication & elevation
A3060 A1200 Jacket ready for load out FS 0
Fabrication of Cellar Deck & Deck legs
A1240 A1610 Lifting & installation of Cellar Deck on legs FS 0
A1240 A1620 Supply & fabrication of Vessels SS 0
A1240 A1630 Piping fabrication & erection (Cellar Deck) FS -60
A1240 A1660 Fabrication of Main Deck SS 30
Deck load out & sea fastening
A1260 A2620 Deck installation FS 0
A1260 A2690 Deck & Flare transportation & arrival on carge barge (3rd CB) FS 0
A1260 A2770 HLV arrival to locatrion FS -17
Deck ready for load out
A1270 A1260 Deck load out & sea fastening FS 0
Deck commissioning
A1250 A1270 Deck ready for load out FS 0
Lifting & installation of Cellar Deck on legs
A1610 A1620 Supply & fabrication of Vessels FF 30
A1610 A1630 Piping fabrication & erection (Cellar Deck) FS -120
Supply & fabrication of Vessels
A1620 A1250 Deck commissioning FS 0
Piping fabrication & erection (Cellar Deck)

(c) Primavera Systems, Inc. Page 4 of 7


Seth Development Project (New Revision 316 MMUS$) 15-Mar-11 11:34

Activity Relationships
Predecessor
Activity ID Successor ID Successor Name Relationshi Lag
Type

A1630 A1680 Piping fabrication & erection (Main Deck) SS 0


Equipment installation (Cellar Deck)
A1650 A1670 Hydrotest & re-instatement (Cellar Deck) FS 0
Fabrication of Main Deck
A1660 A1670 Hydrotest & re-instatement (Cellar Deck) FS 0
A1660 A1680 Piping fabrication & erection (Main Deck) FS -60
Hydrotest & re-instatement (Cellar Deck)
A1670 A1270 Deck ready for load out FS 0
A1670 A1250 Deck commissioning FS 0
Piping fabrication & erection (Main Deck)
A1680 A1690 Equipment installation (Main Deck) FS -90
Equipment installation (Main Deck)
A1690 A1700 Hydrotest & re-instatement (Main Deck) SS 14
Hydrotest & re-instatement (Main Deck)
A1700 A1270 Deck ready for load out FS 0
A1700 A1250 Deck commissioning FS 0
E & I works
A2040 A1250 Deck commissioning FS 0
Pre-drilling template fabrication
A1850 A2360 Pre-drilling template load out and sea fastening FS 0
Pre-drilling template load out and sea fastening
A2360 A2370 Pre-drilling template ready for sail out FS 0
Pre-drilling template ready for sail out
A2370 A1870 Pre-drilling template transportation from maadia yard FS 0
Mechanical works
A1520 A1530 Onshore facilities commissioning FF 7
Onshore facilities commissioning
A1530 A2240 Onshore facilities completion FS 0
Site preparation works
A2120 A2130 Foundation works FS 0
A2120 A2150 Electrical & instrumentation works FS 0
A2120 A1520 Mechanical works FS 0
Foundation works
A2130 A2160 Skids installation FS 15
A2130 A2150 Electrical & instrumentation works FS 15
A2130 A1520 Mechanical works FS 0
Electrical & instrumentation works
A2150 A1530 Onshore facilities commissioning FS 0
Skids installation
A2160 A1530 Onshore facilities commissioning FS 0
Construction works package negotiation & FOA issuance
A2140 A2710 Site handing over FS 14
Site handing over
A2710 A2120 Site preparation works FS 0
Spools fabrication (Non-Metrology Spools)
A1920 A2010 Spools sea fastening & transportation SS 7
Spools sea fastening & transportation
A2010 A2540 Spools connection (Spools Nr.3, 4, 5, 6, 7, 8, 9 & 10) FS 1
Large radius bends fabrication (Bending works)
A3110 A1920 Spools fabrication (Non-Metrology Spools) FS 0
Coated sealine pipes offshore transportation
A2490 A2500 Sealine laying FS 0
A2490 A2480 International DP laying barge arrival @ location FS 0
International DP laying barge arrival @ location
A2480 A2500 Sealine laying FS 0
A2480 A2550 Sealine prelaying survey & crossings preparation (Support vessel) FF -2
Sealine laying
A2500 A2510 Sealine pre-commissioning & hydrotesting FS 0
A2500 A2560 Sealine leak test, dewatering & purging FS 0
A2500 A2540 Spools connection (Spools Nr.3, 4, 5, 6, 7, 8, 9 & 10) FS 0
Sealine pre-commissioning & hydrotesting
A2510 A2520 SSIV installation FS 0
A2510 A2220 Sealine laying comlpetion FS 0
A2510 A2760 Sealine laying DP barge demobilization FS 0
SSIV installation
A2520 A2530 PLEM installation FS 0
A2520 A2230 Sealine spools, PLEM & SSIV completion FS 0
PLEM installation
A2530 A2540 Spools connection (Spools Nr.3, 4, 5, 6, 7, 8, 9 & 10) FS 0

(c) Primavera Systems, Inc. Page 5 of 7


Seth Development Project (New Revision 316 MMUS$) 15-Mar-11 11:34

Activity Relationships
Predecessor
Activity ID Successor ID Successor Name Relationshi Lag
Type

A2530 A2230 Sealine spools, PLEM & SSIV completion FS 0


Spools connection (Spools Nr.3, 4, 5, 6, 7, 8, 9 & 10)
A2540 A2560 Sealine leak test, dewatering & purging FS 0
A2540 A2230 Sealine spools, PLEM & SSIV completion FS 0
Sealine leak test, dewatering & purging
A2560 A2340 Project Cost Contingencies FS 0
A2560 A2230 Sealine spools, PLEM & SSIV completion FS 0
A2560 A2740 Multi-purpose DP vessel demobilization FS 0
Multi-purpose DP vessel arrival for offshore works
A2570 A2520 SSIV installation FS 0
Sealine prelaying survey & crossings preparation (Support vessel)
A2550 A2500 Sealine laying FS 0
Sealine laying DP barge demobilization
A2760 A2570 Multi-purpose DP vessel arrival for offshore works FS 1
HLV positioning & preparation for the activities
A2580 A2600 Jacket installation FS 0
A2580 A2590 Jacket transportation to location on cargo barge (1st CB) FS -2
Jacket transportation to location on cargo barge (1st CB)
A2590 A2600 Jacket installation FS 0
Jacket installation
A2600 A2610 Piles & Jacket ancillaries installation FS 0
A2600 A2680 Piles & Jacket ancillaries arrival on cargo barge (2nd CB) FF 0
Piles & Jacket ancillaries installation
A2610 A2210 Jacket & Piles installation FS 0
A2610 A2690 Deck & Flare transportation & arrival on carge barge (3rd CB) FS 0
Deck installation
A2620 A2630 Helideck installation FS 0
Helideck installation
A2630 A2640 Flare installation FS 0
Flare installation
A2640 A2660 Main structural hook up FS 0
Umbilical laying (With HLV or another multi-purpose DP)
A2650 A2670 Final tie-in spools for startup field setup (With HLV or multi-purpose DP) FS 0
Main structural hook up
A2660 A1990 Deck structure installation and main hookup FS 0
A2660 A2650 Umbilical laying (With HLV or another multi-purpose DP) FS 0
Final tie-in spools for startup field setup (With HLV or multi-purpose DP)
A2670 A2780 Accommodation barge arrival to location & mobilization FS 0
A2670 A2800 HLV demob & area free for Rig entrance FS 0
Piles & Jacket ancillaries arrival on cargo barge (2nd CB)
A2680 A2610 Piles & Jacket ancillaries installation FS 0
Deck & Flare transportation & arrival on carge barge (3rd CB)
A2690 A2620 Deck installation FS 0
A2690 A2640 Flare installation FS 0
TSF final offshore hook up and commissioing + ENI estimate HQ costs
A2700 A1710 Seth First Gas FS 0
A2700 A1980 Deck completion including TSF hookup FS 0
A2700 A2750 Tie-in of 1st well FS 0
A2700 A1900 Re-entry and completion of 1st well (Seth West Shallow) FF 0
Accommodation barge release & demobilization
A2730 A1720 Seth full production & project completion FS 0
Tie-in of 2nd well (Rig assistance for accommodation)
A2000 A1720 Seth full production & project completion FS 0
Tie-in of 1st well
A2750 A1710 Seth First Gas FS 0
A2750 A2790 Main power generation commissioning (Microturbine) FS 0
Pre-drilling template installation
A1640 A1730 Pre-drilling activities FS 0
Pre-drilling activities
A1730 A1900 Re-entry and completion of 1st well (Seth West Shallow) FS 0
A1730 A1880 Pre-drilling Seth FS 0
Offshore drilling rig arrival to location & positioning
A1810 A1640 Pre-drilling template installation FS 0
A1810 A1870 Pre-drilling template transportation from maadia yard FF 0
Pre-drilling template transportation from maadia yard
A1870 A1640 Pre-drilling template installation FF 0
Drilling rig arrival to location & positioning
A1890 A1900 Re-entry and completion of 1st well (Seth West Shallow) FS 0
A1890 A2780 Accommodation barge arrival to location & mobilization FS 0

(c) Primavera Systems, Inc. Page 6 of 7


Seth Development Project (New Revision 316 MMUS$) 15-Mar-11 11:34

Activity Relationships
Predecessor
Activity ID Successor ID Successor Name Relationshi Lag
Type

Re-entry and completion of 1st well (Seth West Shallow)


A1900 A2750 Tie-in of 1st well FS 0
A1900 A1970 Re-entry and completion of 2nd well (Seth West Deep) FS 0
Re-entry and completion of 2nd well (Seth West Deep)
A1970 A2000 Tie-in of 2nd well (Rig assistance for accommodation) FS 0
Platform basic design (Last batch)
A2270 A1230 PTB Production manifold procurement & material receiving @ site FS 29
A2270 A1740 PTB Manual & actuated valves procurement & material receiving @ site FS 29
A2270 A1750 PTB E & I module procurement & material receiving @ site FS 29
A2270 A1760 PTB Microturbine procurement & material receiving @ site FS 19
A2270 A1770 PTB Emergency diesel generator procurement & material receiving @ site FS 28
Spools pipes coating, overweighting & anodes application
A1400 A1920 Spools fabrication (Non-Metrology Spools) FS 2
Multi-purpose DP vessel demobilization
A2740 A1720 Seth full production & project completion FS 0
HLV arrival to locatrion
A2770 A2580 HLV positioning & preparation for the activities FS 1
Accommodation barge arrival to location & mobilization
A2780 A2700 TSF final offshore hook up and commissioing + ENI estimate HQ costs FS 0
Main power generation commissioning (Microturbine)
A2790 A2730 Accommodation barge release & demobilization FS 0
HLV demob & area free for Rig entrance
A2800 A1890 Drilling rig arrival to location & positioning FS -1
Spools basic & detailed engineering (ENPPI WA)
A2280 A1300 Sealine pipes RFQ, receiving offers and TER SS 180
A2280 A1940 Kamos ring receiving RFQ, receiving offers and TER SS 60
A2280 A2020 Flanges, stud bolts & nuts RFQ, receiving offers and TER SS 60
A2280 A3090 Hot Shrinkable Sleeves receiving RFQ, receiving offers and TER SS 74

(c) Primavera Systems, Inc. Page 7 of 7